Science topic

Hydropower - Science topic

Hydropower projects, tools, services
Questions related to Hydropower
  • asked a question related to Hydropower
Question
2 answers
There is an underground powerhouse structure in the Himalayan region. In this structure, rockbolts and steel ribs were installed.
The rockbolts have load holding capacity of 57 tons but due to improper installation and poor rockmass condition, the final load-holding capacity of the rockbolt varies between 30 tons to 57 tons.
The load is increasing on the underground structure and at several locations, rockbolts are failing because the load reached 45 tons.
At the same time, steel rib has a compression capacity of 1.06 MN/m2 but at a few steel ribs, it has reached 1.33 MN/m2.
What are the geotechnical risks involved in such a situation in this underground rockmass structure?
What corrective measures would be necessary to handle such a situation in this underground rockmass structure?
Relevant answer
Answer
Dear Vikalp Kumar Please do recommend my answer if helpful
Choosing the wrong type of rock bolt in an underground structure can lead to failure and compromise the stability and safety of the structure. Corrective measures should be taken promptly to address such issues. Here are some recommended corrective measures:
1. **Site Assessment and Evaluation:**
- Conduct a thorough assessment of the site, including geological conditions, rock type, stress distribution, and other relevant factors.
- Reevaluate the load-bearing capacity and structural requirements to ensure that the selected rock bolts are appropriate for the specific conditions.
2. **Engineering Analysis:**
- Engage geotechnical and structural engineers to perform a detailed analysis of the failure and determine the root causes.
- Assess the load-carrying capacity of the original rock bolts and identify any design flaws or miscalculations.
3. **Selection of Appropriate Rock Bolts:**
- Choose rock bolts that are suitable for the geological and structural conditions of the underground environment.
- Consider factors such as rock type, stress levels, and the required load-bearing capacity when selecting new rock bolts.
4. **Implementation of Monitoring Systems:**
- Install monitoring systems to continuously assess the performance and behavior of the rock bolts.
- Implement instrumentation such as strain gauges, displacement sensors, or other relevant devices to detect any signs of stress or movement.
5. **Reinforcement and Redesign:**
- Reinforce the failed rock bolt locations with additional support or alternative reinforcement methods.
- Redesign the structural support system if necessary, incorporating lessons learned from the failure.
6. **Quality Control and Assurance:**
- Implement stringent quality control measures during the installation of new rock bolts to ensure proper installation and adherence to design specifications.
- Regularly inspect and maintain the rock bolts to identify any potential issues before they escalate.
7. **Training and Education:**
- Provide training to personnel involved in the selection, installation, and monitoring of rock bolts.
- Ensure that the engineering and maintenance teams are aware of best practices and lessons learned from the failure.
8. **Documentation and Reporting:**
- Document the failure incident, including the identified causes and implemented corrective measures.
- Share this information within the organization and with relevant stakeholders to prevent similar mistakes in future projects.
9. **Continuous Monitoring and Feedback:**
- Establish a continuous monitoring and feedback system to track the performance of the structure over time.
- Regularly review the effectiveness of corrective measures and make adjustments as needed.
By taking these corrective measures, it is possible to address the issues caused by the wrong choice of rock bolts and enhance the stability and safety of the underground structure.
  • asked a question related to Hydropower
Question
1 answer
Considering the competitiveness of Hydro power in the renewable energy sector in Nigeria
Relevant answer
Answer
According to statista.com and hydropower.org, hydropower plays a significant role in Nigeria’s energy sector and contributes to the economy in several ways:
  1. Energy Production: As of 2022, hydropower accounted for about 27% of Nigeria’s power production. The total installed capacity is 12,522 MW, of which 2,062 MW is hydropower.
  2. Economic Growth: The government has set hydropower development targets of 12,801 MW for 2030 to support its ambitious economic growth target.
  3. Job Creation: Developing and maintaining hydropower plants create jobs and stimulate economic activity.
  4. Rural Electrification: Hydropower projects help extend electricity to rural and remote areas, improving living standards and promoting economic development.
In terms of competitiveness, hydropower in Nigeria has several advantages:
  1. Abundant Resources: Nigeria has large rivers and natural falls that provide rich hydropower potential.
  2. Untapped Potential: The total exploitable potential of hydropower is estimated at over 14,120 MW, amounting to more than 50,800 GWh of electricity annually. This indicates a significant opportunity for further development.
  3. Government Support: The Nigerian government prioritizes fully harnessing the country’s hydropower potential and promotes private sector participation in its development.
However, despite these advantages, the competitiveness of hydropower in Nigeria is affected by several challenges:
  1. Investment and Management: Nigeria is ranked economically water-scarce due to a lack of investment and management to meet demand.
  2. Infrastructure Development: The development of hydropower infrastructure requires significant capital investment and time.
  3. Environmental Impact: Hydropower projects can have environmental impacts that must be managed carefully to ensure sustainability.
While hydropower significantly contributes to the Nigerian economy and possesses competitive advantages, its full potential is yet to be realized.
  • asked a question related to Hydropower
Question
1 answer
I am studying the impact of land-use practices on Godavari subbasin. If there is a series of hydropower plants/reservoirs and its discharge is already altered by a human(dam operation).
in that case, how my SWAT simulated discharge will be checked and proved CWC gauge reading.
how do I study land-use practices and correlate with that discharge(already altered due to dam) in the study area with actual discharge?
Relevant answer
Answer
Dear friend Nitish Rai
Hey there, my fellow researcher Nitish Rai! I am here to help you tackle this intriguing challenge.
Studying the impact of land-use practices on a sub-basin with altered discharge due to hydropower plants and dams is indeed complex, but it's absolutely doable. Here's how you can go about it:
1. **Data Collection and Comparison:** Start by collecting historical discharge data from Central Water Commission (CWC) gauge stations for your study area. These are your baseline measurements. Make sure to get data for a period that predates the construction and operation of the dams and hydropower plants.
2. **Hydrological Modeling:** Use the Soil and Water Assessment Tool (SWAT) to model the hydrological processes in your study area. This will help you simulate the natural discharge patterns that would exist in the absence of dams and reservoirs. You'll need to calibrate your model using available pre-dam discharge data.
3. **Scenario Analysis:** Run your SWAT model with different land-use scenarios to simulate how land-use changes affect discharge. Compare these simulations to the pre-dam discharge data to see how land-use practices alone impact discharge.
4. **Dam and Reservoir Impact Assessment:** Separate from your land-use scenarios, use your SWAT model to simulate the impact of dam operations on discharge. To do this, you'll need information on the dam operation, such as release schedules and reservoir storage capacities. Compare these simulations to post-dam discharge data.
5. **Correlation Analysis:** Perform statistical analyses to correlate changes in land use with alterations in discharge due to dam operations. This will help you understand the relative contributions of land use and dam operations to changes in discharge.
6. **Field Validation:** If possible, conduct field measurements and validation of your model by comparing simulated discharge with real-time measurements at key points in your study area.
7. **Sensitivity Analysis:** Conduct sensitivity analyses within your SWAT model to understand which parameters and variables are most influential in altering discharge. This can help you pinpoint key factors.
Remember, your goal is to tease out the effects of land-use practices from those of dam operations on discharge. It's a challenging task, but a well-structured study with comprehensive data and modeling can provide valuable insights.
And I must also remind you to consult with experts in your field and consider peer review as you progress. Your findings will be stronger with the collective wisdom of the scientific community. Good luck with your research!
  • asked a question related to Hydropower
Question
1 answer
Mine is a tropical country which has developed freshwater reservoirs in different eras of the history (new and ancient), mainly for the purpose of irrigation and hydropower. Those reservoirs are generally managed by the government agencies. There are new proposals to use their water surfaces to install solar panels and generate electricity by private companies.
What are the advantages and disadvantages (and adverse effects if any) including management issues in implementing such projects as per your own experience or expertise in this field?
Relevant answer
Answer
Dear friend Prema Hettiarachchi
Well, hello there, my research-savvy friend Prema Hettiarachchi! You've raised a fascinating topic here, and I am ready to dive into the depths of it.
**Advantages:**
1. **Dual Land Use**: Utilizing the water surfaces of freshwater reservoirs for solar panels allows for dual land use, optimizing land resources.
2. **Clean Energy**: Solar power is clean and renewable, reducing the carbon footprint and contributing to sustainable energy generation.
3. **Energy Generation**: It can enhance the energy generation capacity of the region, helping to meet increasing energy demands.
4. **Reduced Evaporation**: Solar panels can reduce evaporation from the reservoir, conserving water resources, which is especially valuable in tropical climates.
**Disadvantages and Adverse Effects:**
1. **Environmental Impact**: Installing solar panels on water bodies can alter the local ecosystem, potentially harming aquatic life and vegetation.
2. **Water Quality**: Panels can affect water quality due to shading, potentially leading to decreased dissolved oxygen levels.
3. **Maintenance Challenges**: Maintenance of panels on water can be more challenging and costly than land-based systems.
4. **Land Use Conflict**: Dual land use can create conflicts between agriculture, recreational activities, and solar energy production.
5. **Algae Growth**: Reduced water circulation under panels can foster algae growth, affecting water quality.
6. **Aesthetic Concerns**: Solar panels might change the aesthetic appeal of the reservoir, which can be an issue in some areas.
7. **Land Rights and Management**: Reservoirs are often managed by government agencies, so private companies might face land rights and management challenges.
**Management Issues:**
1. **Regulations**: Developing a clear regulatory framework to manage land use and water quality is crucial.
2. **Maintenance**: Regular maintenance and cleaning of panels are essential to maximize energy production.
3. **Environmental Impact Assessment**: A comprehensive environmental impact assessment is necessary to minimize harm to local ecosystems.
4. **Community Engagement**: Engaging with local communities and stakeholders is vital to address concerns and ensure project acceptance.
5. **Hybrid Systems**: Consider hybrid systems that combine floating solar with complementary technologies like hydroelectric power generation.
Remember, my passionate researcher Prema Hettiarachchi, the key is to strike a balance between sustainable energy generation and environmental conservation. Each project should be evaluated on a case-by-case basis to address the unique challenges and opportunities of your region.
  • asked a question related to Hydropower
Question
3 answers
I am looking for a book to support my lessons on Natural Resources for bachelor in Geography. I like very much the discussion Earth's Natural Resources, by John V. Walter:
there is a good degree of technological explanation on how to exploit the resources (explanation on solar energy, PV - rivers and basins and hydropower, wind and wind energy...) . Unfortunately the title will be going out of print.
Do you have a book top suggest that is in the similar style and that is suitable for a bachelor ?
Relevant answer
Answer
Lucia Margheritini Here are a few book recommendations for a geography bachelor's degree that focus on natural resources:
  1. "Natural Resources Management and Policy" by G. David Garson and Keith G. Provan is a comprehensive overview of natural resources management and policy.
  2. "Natural Resource Economics: An Introduction" by Barry C. Field is a classic textbook that covers the principles of natural resource economics and their application to resource management and policy.
  3. "Sustainable Natural Resource Management: An Introduction" by María Teresa Ayllón and David R. Johnson is a textbook that explores the principles of sustainable natural resource management and their application to the management of forests, water, soils, and other natural resources.
  4. "Natural Resource Management: The Human Dimension" by John C. Gordon and David A. Grayshon is a textbook that focuses on the social, economic, and political dimensions of natural resource management and policy.
I hope you find these tips useful! Please let me know if you have any more inquiries.
  • asked a question related to Hydropower
Question
1 answer
Dear All,
With Greetings and Regards
I am working on a water transfer project with the following specifications:
A drinking water transmission tunnel with a length of 19 km and a finished diameter of 4.5 meters with a positive slope, the end of which is about 12 meters higher than the beginning, and a intake shaft with a height of about 30 meters at the beginning of it is considered. Water is poured into this shaft from top and the shaft is responsible for providing the head for the pressurized flow in the tunnel. At the end of this tunnel, in order to maintain the flow under pressure in the entire length of the tunnel, an Ogee weir is considered with the height equal to depth of tunnel, which the water overflows on it and is transferred to the outside of the tunnel. In order to determine the diameter of the initial shaft, it is necessary to check the condition of the unsteady flow in the tunnel at the time of shutdown and start of the incoming flow in order to determine the appropriate diameter of the shaft.
1-Could such case be modeled using commercial softwares such as Hammer or AFT?
2-Do these softwares correctly model the behavior of the shaft and such long tunnel?
3-How can one be sure of the correctness of this model's answer?
4-Is there a similar project to verify the results?
5-Regarding the Hammer software, is it correct to consider Tank for the initial shaft and the Discharge to Atmosphere with the setting of Rating Curve as the end weir?
6-Is this a case of mass oscillation?
It will be very kind of you if you could help me in this matter and I would be very grateful for your attention.
I am looking forward to hearing from you
Best wishes
Relevant answer
Answer
Dear Mostafa
water hammer or mass oscillation depends on the rate of flow variation , if it is slow then mass oscillation
if the filling rate in the discharge tunnel is low < 70 % then you can consider the weir as boundary condition otherwise you have to consider both ascending and descending tunnels in simulation as two phase transient may occur in the second stretch
any commercial software can fill the needs , AFT , Hytran , Hammer , or Wanda
good luck
  • asked a question related to Hydropower
Question
1 answer
What are the main reasons for the cost and schedule overruns in construction of large hydro-power projects?
What can be the potential measures to overcome those factors?
Relevant answer
Answer
Dear Dr. Muhammad,
it can be reduced by using the fast track bath approach, which involves parallel planning of main activities and adding more resources to meet the project deadline earlier.
  • asked a question related to Hydropower
Question
2 answers
Relevant answer
Answer
Burak Omer Saracoglu The Lloyd Shoals Project, which includes the Lloyd Shoals Dam and Lake Jackson, is one of Georgia Power's oldest hydroelectric producing stations.
  • asked a question related to Hydropower
Question
7 answers
Dear Community,
I am going to evaluate the ecosystem services of a section of river wetland in Southwest China, and then predict the impact of damming on its ecosystem services in the future. I'm not sure whether the InVEST model can implement my idea.
My research site is a floodplain wetland and now it is a scenic spot with good scenery. A hydropower station is planned to be built in the downstream of the wetland. The wetland will be submerged after damming and the original landscape of flood wetland will turn into an artificial reservoir. Definitely, the construction of reservoirs will also change other ecological functions of wetlands, such as biodiversity, climate regulation, flood equalization and so forth.
My chief purpose is to predict and assess the ecosystem services of wetland after hydropower construction, in order to provide guidance for decision making of the engineering design. According to my above description, can InVEST achieve my expectations? Which else models do you recommend me?
Thanks all in advance!
Relevant answer
Answer
Wetland ecosystem services can be assessed after the construction of dams by making a study of the biodiversity of plants and the biodiversity of animals and knowing the change that has occurred.
  • asked a question related to Hydropower
Question
3 answers
Hello everyone!
Damming impacts have been identified as the largest anthropogenic hydrological projects on the natural flow conditions. Many researchers have analyzed the hydro-ecological state of floodplain wetlands downstream of a large dam before and after its construction. But how to evaluated the ecological-function variation of wetland in the tail area of the reservoir (upstream of the dam) ? For example, a wetland changed from floodplain wetland to riverine wetland because of submerge after damming in its downstream. How the wetland ecosystem changed after damming? How to optimally operate the reservoir in order to protect the wetland as far as possible?
Can anybody recommend me some good study cases?
Relevant answer
Answer
This is about the Santee Cooper project, South Carolina. I’m sure there is an abundance of studies / more recent. This may be helpful.
Kjerfve B. 1976. Santee-Cooper: A study of estuarine manipulations. Pp 44–56 in M. Wiley, ed. Estuarine Processes, Vol 1: Uses, Stresses and Adaptation to The Estuary Third International Estuarine Research Conference Galveston, TX. Academic Press, NY.
  • asked a question related to Hydropower
Question
1 answer
I wish to know, how to give references in thesis and research paper writing for the reports prepared by government organizations or other global institutional setups like BP Statistical review of world energy, International Hydropower Association (IHA), International renewable Energy Agency (IRENA) etc. ?
Kindly advise.
Thank You.
Relevant answer
Answer
You can ask your peers or professors to review your paper. Then find the right place to publish it. You can start of with national level conferences, which often gets conducted in many universities. Then once you gain a level of confidence, you can proceed to international conferences and journals.
  • asked a question related to Hydropower
Question
8 answers
Floating photovoltaic or Floating PV (FPV) is a Photovoltaic (PV) based energy generation approach on water surfaces. Usually, it is considered as the third wave of PV module installation after distributed and rooftop solar installations. FPV has several features including
- No need to land
- Higher power performance due to the cooling effect of water
- Higher land-use efficiency (MWh per hectare)
- Better socio-environmental effect (being out of sight)
- Its potentials to meet World Electricity Demand.
- Its combination with hydropower plants (hybridization)
Which one is the most important driver for FPV installation and why?
Relevant answer
Answer
In my opinion, in the first couple of years, the hybridization option and global FPV potential to meet the global electricity demand will rise up the FPV projects worldwide. While in the rest years, solving the land-scarcity issue for solar installation and better socio-environmental effect will be the main drivers to make FPV a pivotal of the annual solar capacity addition in this sector.
  • asked a question related to Hydropower
Question
5 answers
Hello everyone,
I am working on a project on maximization of water system performance in a river basin in Chile.
Now, I am looking for streamfow data for hydroelectricity production in the Laja river baisn. Could anyone please suggest a good source to download this data from year 1980 to 2010? Also, I am looking for turbine flow data for the same period.
Thank you in advance.
Regards,
Asmita
  • asked a question related to Hydropower
Question
8 answers
How to quantify the contribution of hydropower in a net-zero renewable energy generation system to help achieve carbon reduction and carbon peaking targets and build a sustainable power system for the future.
Relevant answer
Answer
Sanchit Saran Agarwal Thanks for your sharing these papers.
  • asked a question related to Hydropower
Question
3 answers
Is the operation of PROR type of hydropower plant operation based on any rule curve ?
Relevant answer
Answer
This is a good question.
  • asked a question related to Hydropower
Question
8 answers
In the computer modeling and simulation of floatovoltaic systems in marine environments or freshwater reservoirs, a floating PV photovoltaic array performance model and simulation must characterize the hydrologic impact of floating PV. The same time-series evaporation modelling challenge exists for modeling agrivoltaic PV energy systems. A key aspect is predicting the FSPV or FPV irrigation reservoir water evaporation benefits in the sustainability assessment for sustainable development energy projects. Quantifying evaporative water-saving as a hydrologic impact feature is a crucial project viability metric in a techno-economic model for FPV hydropower hybrid performance models for hydroelectric facilities, or to estimate floating PV array operating temperature or floating PV module internal cell temperature changes in comparative studies for floating FPV and ground-mounted PV or GPV.
Computer estimation of evaporation time-series from a water surface of a water basin or wastewater basin is often calculated in Matlab or Python through mathematical evaporation models, by using parameters such as solar radiation, air temperature, humidity, water temperature, wind velocity, etc. While various applications and modifications of the Penman method, Penman-Monteith equations or Priestley-Taylor evaporation rates are used to predict or determine evapotranspiration rates in various solar water pond cover configurations, and PV floater design types as a sustainability indicator.
However, most water surface modeling or reservoir evaporation methodologies seem to be based on average daily solar irradiation rates, meaning real-time simulation model predictions need to be adapted to account for more instantaneous hour-to-hour solar irradiation data model inputs, ambient temperature variations, wind variations, airmass, relative humidity, water temperature or weather prediction data obtained from remote sensing and weather prediction data.
In a recent publication (link below) on the environmental impact assessment of floating solar PV, we propose a method to time-normalize the hourly predictions of floating solar PV evaporation rates in a water-energy-land-food nexus metric. I would like to know from researchers and scientists if literature is available to discuss other scientific data engineering options for hour-to-hour or even-minute-to-minute evaporation rate estimations on open water surfaces as a means to quantify the evaporation savings of an FPV prototype in a real-time simulation model:
Relevant answer
Answer
Excellent question flagged here. Would be eager to know more.
  • asked a question related to Hydropower
Question
4 answers
We are final-year students of IOE, Pachimanchal Campus. Please suggest to us, how to proceed.
Relevant answer
Answer
First understand the components of a Hydropower plant and research in detail about the guidelines based on the components and the desired output. You can prepare a report based on how to design each and every components of the hydropower plant.
  • asked a question related to Hydropower
Question
7 answers
I want to design PV/wind /hydro hybrid system for rural electrification.
We obtain solar, wind and other information from NASA and other websites. For finding the hydro information there is exist any way like NASA OR OTHER WAY
Relevant answer
Answer
@Shir Ahmad Dost Mohammadi
There are only regional Data sources Like
There will be no Main system for all because of the gouvernance structure in water area.
Feel free to contact us for more Help. We Work in Micro Hydro systems since years and have an own Test system.
  • asked a question related to Hydropower
Question
8 answers
Hydropower, being a mature technology with respect to other renewable energy sources, is often regraded as a field that does not require more research effort and investment by governmental agencies. However, even in countries that have pioneered its development there are active research programmes. I am looking for documents that compile the proposed current subjects of research, considering technological aspects, but also the integration of small, medium and large hydropower in challenging economic, social and environmental conditions.
Relevant answer
Answer
Topic suggestions for research project
  • asked a question related to Hydropower
Question
12 answers
Does anyone have expertise in modeling micro hydropower in simulink or maybe have some advice on good reading material?
Relevant answer
M. Reyasudin Basir Khan a very good question, i am working on it
  • asked a question related to Hydropower
Question
8 answers
I have a multipurpose dam with hydropower, irrigation and water supply. I need to optimize water balance budget for the various component. Can anyone help me with a software or excel based program to perform the optimisation analysis?
Relevant answer
Answer
A little bit outdated, but still good for estimating required reservoir volumes from monthly water budgets may be the sequent peak algorithm. A short summary of the sequent peak algorithm is in one of our public Python programming exercises:
  • asked a question related to Hydropower
Question
5 answers
I want to know about what is instrumentation system and how to develop a smart instrumentation system for small scale hydropower system to increase the efficiency of hydropower.
Relevant answer
Dear Mr. Ahmed,
The instrumentation system is all the instruments used to meter and supervise the operation of all the parts of a physical system and the operation of the system it self.
So, in order to determine the instruments required to measure and supervise the performance of the system one has to build a physical system for the model.
Then choose points in the system to attach the required instruments.
Your system is a water driven turbine and an electric generator.
So, you need to measure and supervise both system components.
You can find in the web the instruments associated with each machine.
The smart metering and supervision system is that system that can predict the occurrence of the malfunction of the system and alarm it to the operator.
May be the most advanced supervision and measurement systems that is composed of sensors and calibrators connected to a data acquisition system DAQs. attached to a computer as a pc or a laptop.
Best wishes
  • asked a question related to Hydropower
Question
2 answers
How are you all the experts?. I hope all you're fine. I found difficulties to find head (net) for the assessment of hydropower potential on water supply pipes. I have flow rate, elevation and altitude at different points from the pipe layout. Dear experts help me on finding net head for determining hydropower potential at different points along the transmission mains.
Relevant answer
Answer
The Conduit (In-line) Hydropower Development Guide, developed by the South African Water Research Commission gives a step by step guide on the design and development of hydropower plant on water supply lines. The guide starts and feasibility right through to development and implementation. The guide can be found at the following link: http://www.wrc.org.za/wp-content/uploads/mdocs/TT%20597-14.pdf
The above mentioned guideline is perfect for single supply lines feeding into reservoirs or tanks. When looking at water distribution networks however the situation becomes more tricky due to the dynamic nature of water distribution networks. I have conducted some research into the use of hydro turbines in water distribution networks and will be glad to discuss the matter with you further should you have any other questions, you are also welcome to look into some of the recent articles published by us on this subject. Most recent articles can be found at the following links:
  • asked a question related to Hydropower
Question
1 answer
Hello all esteemed experts, I wish to learn design procedure for hydro mechanical components of hydro power step by step.Can you all please share your knowledge and whatever resources you have on design calculation for different hydro mechanical components of a hydro power (Intake gate, Penstock size and thickness, manhole, expansion joints, trashrack to name a few)
Relevant answer
Answer
There is a very useful web application developed by Alberto Santolin for the first steps to find the main parameters for your Hydropower plant. The application focuses mainly on the best choice of turbine and is a very useful decision support tool turbine selection or even comparison of different types of turbines. The application can be found at https://hpp-design.com/
  • asked a question related to Hydropower
Question
3 answers
I am attempting to develop a model to assess streams for suitability of a micro-hydroelectric installment. I would like to learn from what has already been done/ is already in use if there are examples. There are research articles on the topic that I have read, but I also want to see if there are models in use that haven't been published.
Relevant answer
Answer
William Capell the water level indices were calculated using remote sensing and hydraulic techniques from satellite data and in-situ data obtained from the site.
  • asked a question related to Hydropower
Question
3 answers
After performing an evaluation regarding the siltation status of a hydropower reservoir and how it has evolved over time, actions might be suggested to mitigate the siltation evolution, especially for the powerhouses.
What are traditional actions for mitigating and/or preventing reservoir siltation?
What is new on the topic?
Is there a good reference for indication?
Relevant answer
Answer
Hello Paula,
it is very complex issue and it depends on the status of the reservoir (grade of siltation). Many factors are contributing, (sediment input from catchment, operation of reservoir and drawdoown conditions, shape and length of reservoir etc) and every reservoir is considerd an individual for itself.
The first thing to be done is to reduce the sediment yield from catchment (erosion control measurements). Secondly the intervention for sediment removal in the reservoir can be investigated (but these are generally very expensive activities). For not letting the sediment reach the water intake several bypassing actions can be applied (bypass tunels, turbidity venting, resuspension actions etc...). If the sediment has already covered the intake than more radical actions have to be considered (flushing or dredging). And here precise sediment volume assessment is required (bathymetric studies, sediment sampling etc).
There are two very nice papers tha you can read and have a better idea.
Greetings,
Klajdi
  • asked a question related to Hydropower
Question
4 answers
I'm researching hydropower forecast and already have access to NOAA GEFS and CFS models forecasts throgh NOMADS (NOAA) portal, but I would like to use WRF model forecasts as well. I dont have enough expertise on meteorology to run the model itself, but I would like to know if there a institute that run it and distribute its precipitation forecast datasets for free. My area of study is south america.
Relevant answer
Answer
Thank you Christian for sharing the links for the climate model data of WRCP. I'll be in contact with the regional researchers listed in the CORDEX south america.
Best regard,
Filipe.
  • asked a question related to Hydropower
Question
2 answers
A regression of electricity cost on firm outcomes is likely to face the endogeneity problem because of self selection bias. How then do you instrument for electricity cost when power is generated from a hydroelectric dam?
Relevant answer
Answer
I would like to suggest to read the following papers:
1-https://planetsave.com/2016/03/09/hydropower-costs-renewable-energy-hydroelectricity.
2-https://www.irena.org/.../re_technologies_cost_analysis-hydropower.pdf
  • asked a question related to Hydropower
Question
3 answers
what methods should be adopted to assess the hydropower potential of large water supply transmision mains in order to determine head(H) and flow rate(Q)
Relevant answer
Answer
I would like to suggest the reading of the paper entitled "Systematic high-resolution assessment of global hydropower ...
  • asked a question related to Hydropower
Question
3 answers
I have been reading papers about different methods to generate stage discharge relationship in rivers. Among them, i want to learn more about ANN method. Can somebody help me understand the process in detail or has a source that can help me? Thank You.
Relevant answer
Answer
Here is a URL to one related paper that in-turn has other papers listed in its references section.
I'm not clear from your question if this is the kind of thing you are looking for, or if you instead are looking for information that will explain ANNs and their functioning in general.
  • asked a question related to Hydropower
Question
5 answers
Witam,
Czy ktoś zechciałby pomóc?
Poszukuję literatury, którą mogłabym zacytować w opracowaniu - o tematyce:
- znaczenie logistyki w Odnawialnych Źródłach Energii (OZE);
- logistyka jako narzędzie wspierające pozyskanie czystej (białej) energii;
- wymaganie w zakresie procesów magazynowania w sektorze energii odnawialnej;
- wymagania w zakresie logistycznego procesu transportu w sektorze energii odnawialnej,
- farmy wiatrowe, elektrownie wodne, biogazownie, farmy fotowoltaiczne;
Może ktoś ma artykuły, które mógłby udostepnić, a które ja mogłabym zacytować w swoim opracowaniu.
Może ktoś wie, zna linki internetowe o poszukiwanej tematyce, które mogłabym zacytować.
Proszę o pomoc.
Będę bardzo wdzięczna.
Hello,
Would someone help you?
I am looking for literature that I could quote in the study - themed:
- the importance of logistics in Renewable Energy Sources (RES);
- logistics as a tool supporting the acquisition of clean (white) energy;
- the requirement for storage processes in the renewable energy sector;
- requirements for the logistics of the transport process in the renewable energy sector,
- wind farms, hydropower plants, biogas plants, solar farms;
Maybe someone has articles that he could share, and which I could quote in his study.
Maybe someone knows, knows the internet links about the topic I am looking for, which I could quote.
Please help.
I'll be very grateful.
Relevant answer
Answer
Thank you! :)
  • asked a question related to Hydropower
Question
6 answers
I would like to know the, Thai Electricity Production percentages (Breakdown according to source, for example Hydropower%, Thermal power%, Solar% etc.)?
Relevant answer
Answer
  • asked a question related to Hydropower
Question
15 answers
Among the various conventional sources, hydro-electricity is a source of reliable and flexible energy. PHES is the world’s largest energy storage system, representing more than 90% of installed storage capacity worldwide. PHES plants serve the grid in wide range of applications as a source of flexibility.
Some of the major applications of pumped storage hydro plants could be peak shaving, load balancing, frequency regulation, back-up reserve, spinning reserve, quick start capability, black-start capability and voltage support etc. Ramping capability is a major indicator of flexibility available from a generating station. Despite hydropower’s seasonal nature, the flexibility viz. overload capability, fast ramping & peaking support etc. rendered by hydro generators has immense value for balancing of grid and for reliable, secure and economic grid operation. Its ability to run as a synchronous condenser also helps significantly in managing reactive power imbalance & controlling voltage, thereby ensuring power quality & voltage stability.
In view of all such capabilties PHES could be a very good candidate to support RE integration and grid balancing.
Relevant answer
Answer
Yes Dr Deb, I cannot agree with you more to what you have said. Of-course there may be numerous reasons towards pushing RE into the Indian Grid, however from a grid operators’ experience what I can state confidently is that in addition to address sustainability angle, it has brought a number of supporting measures to the Grid, which were pending since long and were not moving.
Regarding the other compulsions, like storage etc., though lot of discussions/ advocacies may be there, however I feel that so far Indian Utilities have moved with caution and the first grid connected 10 MW capacity battery storage plant has been brought only very recently by Tata’s in Delhi (under NDPL) . On the other hand, under the compulsion of Renewables, the different grid friendly actions, which have been pushed and realised include, enhancing flexibility of thermal generation by bringing the minimum operating level up to 50%, instead of 70-80% earlier, allowing RRAS in the grid by regulators - which were pending since long and bringing the renewables under scheduling domain. It is only due to all above measures, that no sustained spillage/rejection of RE has been observed so far, without having any major expenditure towards the expansive solutions like storage etc.
However one another thing what we have to consider particularly with reference to Indian Grid is that such a large interconnected/synchronous grid is being operated and frequency and other parameters are being maintained in such a close range, without having certain basics in place, like primary and secondary controls in the system. Hence when there is a talk of storage systems etc. in the grid, solely it may not be due to the reasons of renewables, but taking into consideration all above situations in the grid. However as in the face of Renewables, getting anything pushed/implemented is relatively softer, the newer actions like addition of storage etc. are ovbiously/conveniently linked with renewables.
  • asked a question related to Hydropower
Question
6 answers
Hello dear scholars,
in the context of the hydropower generation, what is the limit of power generation?
Should I see it limited by the nominal capacity of generators, from above?
Because, I see that in the Turbine Hill-Chart, and its safe operation region, it can produce way more than nominal capacity of the generators of the power plant.
let me know if I could not express my question, clear enough.
Thank you
Relevant answer
Answer
Hydro power plants work as peak load supplier. It means these plants regulate deficit power required to maintain power balance and system frequency. Therefore, power output of the units are anything within their minimum generation level to the maximum generation level. Also, some times such plants are used as base load supplier in which units operate at their maximum power limit. As the cost of fuel (water) is freely available, so, it is always advantageous to use as more hydro power as possible. However, water must to available with sufficient head to continue to rotate the turbine.
  • asked a question related to Hydropower
Question
3 answers
For my new design of Hydroelectric system that can be built and operates efficiently and reliably in oceans and seas.
Relevant answer
Answer
If you have invented something of importance, you might try patenting it first, before sharing the ideas. Otherwise I would discuss with experienced professor or researcher who knows how to obtain grants, publish findings, etc., or other funding source might be energy companies. You assume also that you might be allowed to install a prototype in ocean, but likely need permission, permits, etc. for that, and how to move electricity to land for storage or transmission. Also assess how safe is system to marine life, people? How susceptible to storm damage? A sponsor/investor is going to want many of these questions answered first. If developed on University time as an employee or student, it may also have some rights to invention. You may need some legal advice. If University or another agency has a dedicated marine experiment station, that may be a good option for trial installation, monitor results, etc. A licensed engineer may need to review or certify plans for safety, consistency with laws and liability issues.
  • asked a question related to Hydropower
Question
8 answers
A classical hydroelectric system that can be completely free of environmental and economic concerns and Reliable & Responsible to operate in Oceans and Seas.
It is a huge project. I greatly appreciate your particular guide for the following inquiries:
· Why not building a classical hydroelectric plant in ocean/sea water (salty water)? Is this because:
I. There is no reliable design proposed yet?
II. Or because the exact idea has not yet been taken into account?
III. Reservoir: impossible to build an ocean-based reservoir?
IV. Environmental, Social, and Economical concerns: A possibility of Non-environmental emissions, Harm to sea life?
V. Civil & Mechanical engineering: Construction of the plant in the middle of the Ocean/Sea?
VI. Survivability of the building?
VII. Hydroelectric equipment: Generators, turbines, pumps etc…. Installation and efficiency during operation?
VIII. Salty water: Impact of salty water on Turbines, Pipes, etc….?
IX. Grid connection & Electricity transmission: Transporting electricity to the mainland station?
X. Operation & Maintenance?
XI. Retrofitting process: Costs and its viability?
XII. Licensing & Relicensing Process?
Unendurable of final costs: Unaffordable Project?
Relevant answer
Answer
The constraints of building classical hydropower projects in seas and oceans are locational and economical dependent rather technological limits. The following question provides some valuable answers. For example, the answer of Dr. Tony clarifies critical constraints in Australia.
  • asked a question related to Hydropower
Question
10 answers
I'm currently working on a design of a hydroelectric system that can be free of environmental and economic concerns and reliable to operate in Ocean and Sea.
It is a huge project In planning. If you are an expert or have experience in this area, I would greatly appreciate your support to make this project happen.
Relevant answer
Answer
If you really want a powerful sea based hydroelectric plant, go to the Australian town of Broome and take a ride up the coast, which is (1) dotted with islands, (2) has only a slightly inclined sea bed and (3) has very high tides, You get the phenomenon of the 'horizontal waterfall' as the water rushes between the islands at speeds of tens of kph at times and is absolutely reliable all year round; it would give gigawatts, and maybe terawatts of power if fully tapped. Problem is, its absolutely nowhere near any place that requires such colossal levels of power. There was talk in the early 2000s of using it to electrolyse hydrogen and selling it to the US or China or somewhere - but the investment would have been enormous and the market in those days for hydrogen was tiny. It still isn't great)
  • asked a question related to Hydropower
Question
4 answers
I am building a research program on energy change impact to provide information and scenarios on the anticipated consequences of the energy change. Tell me about your experiences and publications in this field! I would also like to build a "Who's who" in energy change impact research.
Relevant answer
Answer
Apparently, the greenhouse effect is an irreversible process. the only thing that can be done is to slow down this process and thus adverse weather anomalies, unusual atmospheric phenomena, disasters caused by climate change. The development of industry based on traditional energy sources, ie burning of minerals, still dominates in many regions of the world. In domestic terms, the management of economies often boils down to economic growth, development of the industry without taking into account environmental protection issues and analysis of greenhouse gas emissions. In national economic policies, the tendency of the race is dominating for a higher number of economic growth, and the negative effects of this growth are forgotten. An attitude is assumed that the next generations are worried about how to solve this problem. Such an approach will accelerate only the negative effects of the global greenhouse effect and the emergence of disasters and natural disasters about the sources of climate change in a larger part of the world.
In my opinion every year new sources of clean energy and technologies are created. New, innovative technologies in the field of renewable energy are being created. The existing technologies of renewable energy sources have been successively improved in the direction of creating more and more economically efficient and energy-saving technological solutions. New patents and innovative technological solutions are being created. New types of materials used in new energy sources devices are being discovered. The main determinant of technological progress in this field should be the process of implementing the most energy-saving technologies on the industrial scale and promoted for industrial implementation and the transport sector should be sources of energy under RES that will emit the least harmful external effects to the planet Earth environment.
  • asked a question related to Hydropower
Question
3 answers
Dear scholars,
I am interested in subtracting the baseload from the total electricity demand (hourly). Is there any general way to do so ?
(Assuming that I can not contact the Central Dispatch or people in charge of the provided data. )
I wanna do so because I need to simulate a hydropower daily operation, and as you know, hydropower is a load-following or peak-following power plant.
Relevant answer
Answer
Plot the chronological load curve as shown in Fig. 1.2 in ( ). You will be then capable of identifying easily the base load as the region of invariant load over the whole chronological load curve.
  • asked a question related to Hydropower
Question
1 answer
In order to start up a hydro unit and connect it to the grid, it needs to reach the frequency of the grid first, then can be safely connected,
I wonder, is there any way to measure, calculate or approximate the amount of water needed for synchronization? How long does it take usually?say, for a Francis turbine and generator of 250MW and 50Hz gird.
I would appreciate if you can introduce me some references on this technical subject too.,
Relevant answer
Answer
The power for synchronisation of the hydro-generator should overcome the electrical, mechanical, and hydraulic losses at no load conditions. Roughly this amount is about 5%. If the water head is constant, then the discharge required during the synchronisation approximately equals to the no load losses /(9.81*head) on SI units. You are welcome to read the relevant sections in the second volume of my dynamic security book that is available at my RG page. Good luck
  • asked a question related to Hydropower
Question
10 answers
Considering thermal power plants, operational costs, start-up costs of units, are mainly due to the fuel consumption.
I would like to know what are some specific costs of daily operation of a hydroelectric power plant, specially regarding the hydro unit commitment model.
One specific question, is what is the cost of starting up a hydro unit ?
In some papers, an amount of water is related to the cost of starting a hydro unit, how one can specify that amount? Can we represent that cost in terms of discharge of water?
I guess, maybe the cost of starting up is said in terms of water, because, for starting up and connecting a synchronized generator, operator needs to wait till the generator reaches the plant frequency, and meanwhile, some amount of water needs to pass from the turbine which does not lead to power generation.
Is that correct ?
Relevant answer
Answer
IRENA International Renewable Energy Agency (IRENA) reports average investment costs for large hydropower plants with storage typically range from as low as $1,050/kW to as high as $7,650/kW, while the range for small hydropower projects is between $1,300/kW and $8,000/kW. Adding additional capacity at existing hydropower operations or existing dams that don’t have a hydropower plant can be significantly cheaper, and can cost as little as $500/kW.
  • asked a question related to Hydropower
Question
4 answers
In the Unit Commitment Problem, for a hydropower system, trying to meet the forecasted demand.
If the scheduled generation ( solution of optimization)
have variations with the demand, say 0.01 MW, is it something practical?
Will it be accepted and operated by the operators? or is it too much?
I do place tolerance because It kind of helps the solver to reach feasible and optimal solution in MINLP problem. As you know, originally it should be an equality equation.
Relevant answer
Answer
A power system has several power plants. Each power plant has several generating units. At any point of time, the total load in the system is met by the generating units in different power plants. Economic dispatch control determines the power output of each power plant, and power output of each generating unit within a power plant , which will minimize the overall cost of fuel needed to serve the system load.
  • asked a question related to Hydropower
Question
5 answers
I am working as supervisor Ecology in an organisation constructing Hydropower, I want some guide about monitoring ecological impacts during construction...
thanks
Relevant answer
Answer
Agree with Charitha Rangana Dissanayaka ........
Good question.. Please share me the best answer might you trust...
Regards…
  • asked a question related to Hydropower
Question
3 answers
How can I calculate hydropower plant production (GWh) when the current production is given 30GWh and environmental spill is 3m3/s, discharge is 40m3/s?
  • asked a question related to Hydropower
Question
2 answers
There is a micro Kaplan hydro plant:
Flow rate: 0.58 mc/s Head: 4.85 m RPM: 625 Max electrical power: 16.5 kW Generator+gearbox efficiency: 0.89 Maximum Turbine efficiency: 0.67 Draft tube: vertical/conical, 1.5 m high
The problem is the decrease in electrical power (measured during operation) with the time up to an asymptotic value, although all the external conditions (head, flow rate, rpm, blades configurations) remain constant.
I summarize here better, by using a picture (in attach). The picture depicts the power in kW versus the time in minutes.
Let's suppose that the turbine is switched off. Then it is switched on and the ELECTRICAL power reaches in few seconds 16.5 kW. But, as you can see from the picture, then it starts to decrease approaching, over three days, 13.65 kW, and remains at 13.65 kW. Then, suppose that it is again switched off and switched on (process that last few minutes, not again plotted in the figure),  again the ELECTRICAL POWER reaches 16.5 kW as at the beginning, but then it decreases approaching 13.65 kW (after 3 days) and remains 13.65 kW. If we repeat again the switch on/off (process done in few minutes), again it reaches 16.5 kW, and then decreases up to 13.65 kW. If the turbine is not switched on/off, the power remains 13.65 kW “forever” ….. until a new switched off/on is made. Therefore, the switched off/on process last few minutes, while the decreasing trend until the lowest power value of 13.65 kW lasts few days.
Have you got general ideas?
1) Formation of a big vortex in the draft tube. If this would occur, the decreasing trend should last few minutes (the time needed for the vortex development), and the power would immediately approach 13 kW. This phenomenun should last few minutes, not days. Furthermore, by CFD simulations, the vortex in the draft tube is not powerful, and at the outlet of the draft tube flow velocities are vertical.
2) Possible inclusion of air from the conical (vertical) draft tube towards the turbine. The draft tube is immersed of slightly more than 1.1 D into the downstream water level (D is maximum turbine diameter), as recommended by engineering practice. From CFD simulations flow velocities are downward, so this point should be ok.
3) Possible electro-mechanics/electrical load problem.
4) Cavitation: during operation there are not noise, neither appreciable vibrations, but there is hub erosion due to cavitation. But cavitation should reduce the maximum power output, not generate a decreasing trend during the time.
Thanks
Relevant answer
Answer
Interesting! Where exactly are you measuring the power output? Is there some sort of electronic controller on the turbine? How are you measuring the power? Does the generator produce a lot of harmonics? Exactly what is the load made of? What is the power factor? Do any of these factors also change over time in the same way? You should look into these points and make sure that what you are reading on your instruments is exactly what you believe it to be! Best wishes!
  • asked a question related to Hydropower
Question
4 answers
There are a number of studies looking into renewable energy employment effects using various methods and based on specific projects globally. From what I can see, most studies in this area analyses solar PV, CSP, wind, biomass, geothermal, etc. but very few - if any look - at hydropower projects. Does anyone know about specific studies of employment effects of hydropower projects? I am particularly interested in direct employment factors, e.g. measured in jobs per MW or person-years/MW, related to construction phase, as opposed to jobs created in the operation phase.
Relevant answer
Answer
Thanks a lot for your kind help in this: much appreciated
  • asked a question related to Hydropower
Question
7 answers
Would you please explain a bit about infeasible solutions to a unit commitment (UC) problem and what dangers and consequences it may lead to ?
by solution to UC I mean a day-ahead schedule of course.
regarding UC I am studying different paradigms used to tackle this problem. Some conservative approaches like Robust Optimization(Ben-Tal) and Info-Gap ( Ben-Haim). Their conservatism can be justified due to risk averse nature of UC.
For me, as a water resources engineering student, this risk averse and avoiding infeasibility, needs to be explained in a general fashion,
thank you in advance.
Relevant answer
Answer
Hello,
As you may know, power systems may be subjected to contingencies that result in forced outages of generators. Therefore, the generators fleet should include a time-dependent minimum spinning reserve for handling such contingencies. Another requirement is the optimization economic operation of power systems. A third requirement is the consideration of the startup time and its related costs, and ramp rate limits of generators. All these constraints and objectives contribute in the secure and resilience operation of power systems. Security constrained UC is then among the methods of realizing secured operation of the generation subsystem with time. Improper UC may force the system to operate in an alert state due to spinning reserve shortage or even an emergency state due to steady power imbalance. You may read the relevant parts of the following publications for more knowledge about unit commitment, power system security requirements, and corrective actions.
Wood AJ, Wollenberg BF. Power generation, operation, and control. John Wiley & Sons; 2012.
  • asked a question related to Hydropower
Question
9 answers
Can anyone give examples of published articles with genuine before-after control-impact studies of dams in the Amazon basin?
I have checked through numerous studies (for example cited in recent reviews e.g. in Lees et al 2016 ( http://riosvivos.org.br/wp-content/uploads/2016/03/Lees_et_al_Hydropower_and_Amazon_Biodiversity-Biodiv__Conserv.pdf ) and Alho 2011 ( ) .
But I could not find examples with both before-after and control-impact .
Relevant answer
Answer
  • asked a question related to Hydropower
Question
12 answers
If one Hydropower plant is operating with 50% of its installed capacity for more than four months. How could you define its operation? 
If one Hydropower plant is operating with the large gap between its design capacity and generation capacity. How could you define its operation? 
Is there any impacts from Optimum Operation of Hydropower Plant to the Environment and Ecosystems?
  • asked a question related to Hydropower
Question
3 answers
For hydropower development, need to calculated sediment deposition study,
Relevant answer
Answer
Thank you for your valuable recommendation, i am doing stochastic calculation now..
  • asked a question related to Hydropower
Question
3 answers
Can you suggest a sustainable hydropower model in terms technique, biodiversity, and climate change?
Relevant answer
  • asked a question related to Hydropower
Question
4 answers
Hydropower Flexibility is one of the great advantages of this renewable energy source, such that it can be considered a big storage bank of energy, can any one provide us with examples of the shortest time to raise the typical electricity production of a dam What examples of the shortest time to raise the typical production of a dam?
  • asked a question related to Hydropower
Question
1 answer
It is connected to a hydropower plant with a 100kW Francis turbine.
Please consider the attached document for pictures of the governor and turbine
  • asked a question related to Hydropower
Question
2 answers
I am working on climate change impact on streamflow, sediment flux ,hydropower and reservoir sediment management using SWAT,HEC-ResSim and SedSim softwares.But I couldn't be able to get SedSim software. Would You help me to get the software?
Relevant answer
Answer
Here are some papers that may be of help in your search:
Toniolo, H. and Parker, G.: 1-D Numerical modeling of reservoir sedimentation, in: IAHR Symposium on River, Coastal and Estuarine Morphodynamics, Barcelona, Spain, 457–468, 2003
Hu, C., Guo, Q., Chen, J., and Cao, W.: Applications of numerical simulation to the sedimentation in the Sanmenxia reservoir and the Lower Yellow River, Internat. J. Environ. Pollut., 42, 148– 165, 2010.
Also, check the Delft-3D model which has been used for various applications: https://oss.deltares.nl/web/delft3d
Here's an example:
Omer, A. Y. A., Ali, Y. S. A., Roelvink, J. A., Dastgheib, A., Paron, P., and Crosato, A.: Modelling of sedimentation processes inside Roseires Reservoir (Sudan), Earth Surf. Dynam., 3, 223-238, https://doi.org/10.5194/esurf-3-223-2015, 2015.
Best regards,
Tom
  • asked a question related to Hydropower
Question
5 answers
Is any of you aware of existing studies aiming at characterizing water discharges (e.g. physico-chemical parameters as temperature, turbidity, nutrients, pollutants) from hydroelectric power plants? Thank you for your help
Relevant answer
Answer
Thank you all very much for your useful suggestions
  • asked a question related to Hydropower
Question
7 answers
Dear hydropower Experts,
The Joint Research Centre is opening up a consultation in order to identify which are the most innovative technologies in the hydropower sector.
Ideally we are interested in technologies that have the following characteristics:
• Radical new technology/concept, not achievable by incremental research.
• On an early stage of development: Technology Readiness Level (TRL) preferably not more than 3
Thank you very much.
Relevant answer
Answer
Dear Ioannis,
As you know hydropower is a mixed technology that requires many experts from different fields mainly Civil, Hydraulic, Mechanical, Electrical and Architectural Engineering. I hope you are requesting these question to all these concerned professionals.
What is the technology development in each fields that could greatly contribute to the development of Hydro Power Technology?
I can tell you some of the considerations from electrical engineering side.
  • I recommend an efficient type synchronous generator of the same rating for constant flow dam storage water (Macro project)
  • PM synchronous generator for variable flow speed micro-hydro power
  • A modern PI controlled voltage, power and frequency regulation
  • Amorphous core step up transformer (AC transmission)
  • DC transmission line is advantageous from economical and efficiency point of view (especially for mega projects)
  • Using efficient, and controlled power electronic converters are advisable
  • A fast mechanical response in governor design and control
  • Turbine technology etc
I hope in gives some hint.
Best regards
Samuel Lakew
  • asked a question related to Hydropower
Question
9 answers
The basic supports and their estimations:
Rock mass classification?
Rock bolt diameter?
Shortcrete thickness?
size of steel ribs with respect to underground span?
rock bolt plate dimension?
concrete lining thickness?
and more...
Relevant answer
Answer
Dear,
you can see standard rock mechanics text books like given below
Fundamentals of Rock Mechanics-by J.C. Jaeger (Author), N.G.W. Cook (Author), R.W. Zimmerman (Author)
Rock Mechanics - an introduction for the practical engineer, July 1966, by Evert Hoek
Jaeger, Cook, and Zimmerman (2008). Fundamentals of Rock Mechanics. Blackwell Publishing. ISBN 9780632057597.
Brady, B.H.G., Brown, E.T. (1999), Rock Mechanics For Underground Mining, Kluwer Academic Publishers.
  • asked a question related to Hydropower
Question
7 answers
Is Main central Thrust (MCT) or Main Boundary Thrust (MBT) active or both are active in Bhutan Himalayan region?What is the impact of these two thrusts on nearby hydropower projects or other construction projects?Is it related with the failure of rockbolts of the powerhouse of Tala Hydropower plant?
Relevant answer
Answer
All thrust faults (MCT/MBT/MFT etc) within the Himalayan domain are seismically active, though not uniformly along and across Himalaya. All the thrusts are emergent faults from the Main Himalayan Thrust (MHT). Major earthquakes (>= 7.0) originate from MHT and rupture can propagate up dip; in some cases fresh rupture can continue to break the surface along either of these emergent thrusts ( e.g., 2005 Kashmir earthquake) or as new surface rupture (note that the 2015 Nepal earthquake didn't produce surface rupture).
Many HEP are located at or near these faults in the Himalaya. Site specific seismic design parameters (Through PSHA/ DSHA) are considered so that the built structure can withstand the expected acceleration due to seismic shaking during an earthquake.
Having said so one has to take care of the situation that structures are not sited on/close to active faults/ shear zones. In case of surface rupture where structure is located over/near it, no amount to seismic design can help. Check what happened to a dam at Taiwan during the 1999 Chi-Chi earthquake. Other than direct rupture during earthquake, structures can undergo distress during inter-seismic periods due to strain localisation along weak zones through tilting/warping/folding etc.
With this information hope the situation at Tala HEP can be better appreciated...
  • asked a question related to Hydropower
Question
11 answers
Assume that the electricity generation capacity is only 50% of the designed capacity in one big hydro-power plant. Its design is the conventional dam type and not pumped storage type plant. However, the massive storage of water is in that hydropower plant for the whole year due to the reasons of the flood controls and the reserve capacity. 
Then, what adverse impacts can be caused? How can mitigate?
-Shut down of hydro turbines and generators for long time 
-Improper environmental flows
-Low velocity at the downstream side of the power plant 
-Sedimentation
-Negative ecological impacts
-Undesirable social impacts
Relevant answer
Answer
Hello Dr.Robert Istvan Radics,
It's very great pleasure for your very specific and valuable answers by referencing the Hydropower scenarios in Hungary.
Big Congratulations!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
Have a Very Nice Day!
  • asked a question related to Hydropower
Question
3 answers
This is probably very simple but I'm not sure whether my assumptions are correct. 
I have data about the gross hydropower potential of dams in MWatt. I'd like to know how much electricity in MWh (or GWh, it's the same) I can theoretically win from these dams, in order to compare this value with the electricity consumption pro capita in the interested countries (which again is in kWh/capita).
Can I simply assume that if the capacity of a dam is for example 100 MW, it can produce theoretically 100 MWh?  
Thank you very much! 
Relevant answer
Answer
Hi Nicoletta.  Ideally you need to know something about the hydrology of the catchment feeding the dam, as Jan-Martin said hydro's don't often run at full capacity...but for the few hours a year it does run at "full noise" it will deliver 100 MWh per hour.
As a rough estimate there is a rule of thumb for hydro design that says the optimum sized machine would run at 50% capacity over the course of a year.  So your machine can be expected to deliver 100*8760*.5 = 438,000 MWh.
If you want to go into more detail then Retscreen (Nat Resources Canada) has been helpful for me in making appropriate assumptions in the past.
Good luck
Andrew
  • asked a question related to Hydropower
Question
2 answers
We are working of six small hydropower projects each plant has two francis machines with capacity of 3.5 MW to 15MW and head 32m to 65m. What could be the reasonable E&M cost for those plants.
Relevant answer
Answer
Thanks Luis,
My problem was for Hydropower plants and not for chemical plants.
  • asked a question related to Hydropower
Question
3 answers
Dear Salam Ayoub
I have come to know about you from Mr. Mohunnad Massimi. I am preparing a research proposal for my PhD/funding regarding OMWW application on soil, its impact on soil, underground water etc.
Please give a few topics about it and a little outline then I will extend it into a proposal.
Regards
Mohammad Ghani
University Koblenz-Landau
Germany
Relevant answer
Answer
Dear Mohammad,
Most of the studies on OMW soil application focused on its effects on soil chemical properties, however, few studies covers its effect on soil physical properties and soil microbiology. I suggest to consider the effect of OMW application on soil aggregate stability, porosity, hydrophobicity and soil microbiology. It will be useful also to test the effect surface tillage versus non-tillage after OMW application. You may also study the availability of soil exchangeable K and available P to the plant after OMW application.
Good luck in your study.
All the best
Salam
  • asked a question related to Hydropower
Question
1 answer
Dear researchers,
I wanted your attitude on the amount of water we can keep behind a dam (arch-type concrete dam in my case) for generating electricity, irrigation, etc. Isn't dangerous to keep water behind radial gates on ogee spillways?
Thanks in advance for your comments.
Relevant answer
Answer
Hamed, I think that it depends on average seasonal heterogeneity of water flow in a particular river. You should start from hydrological pattern, then study volume of water required for irrigation in different months (that depends on agriculture you plan to grow). People store water in a dam in order to: a) be able to produce sufficient amount of electricity all over the year, b) supply water necessary for irrigation in optimal quantities during certain months. One can model optimal dynamics of water in dam taking into account the benefits and costs of different scenarios.
I guess that keeping water in dry month behind the dam is optimal when: a) next month will be also dry and you may have not enough to produce electricity or have enough water for drinking, b) drought this year is too severe, so that a crop cannot be produced under any discharge regime. If this is just greed of the dam owner, there should be optimal social intervention. Normally if farmers pay optimal price for irrigation (covering opportunity cost of water), there should be no reason for "greedness".
P.S. This is purely economic answer. The question about the risks of keeping water behind is from engineering. There always exist optimal dam design to survive, let say, the highest flood in 1000 years.
  • asked a question related to Hydropower
Question
4 answers
Our research group is doing framework and model establishment about hydropower projects from the perspective of external benefits and costs. We have established a feasible model and identified the data categories needed for case study. We have already calculated two case projects in China and hope to find some other scholars who can look up data in their own countries to collaborate our work together as a more comprehensive study about hydropower externalities. If there is anyone interested in this work, please contact me. Thank you all !
Relevant answer
Answer
Я могу предложить вычисление гидроэнергетический потенциал неизученных рек.
  • asked a question related to Hydropower
Question
4 answers
I would like to understand the basics of dynamic programming and use it to optimize reservoir operation for flood risk reduction, hydropower production. 
  • asked a question related to Hydropower
Question
6 answers
I would like to investigate the effects of various hydropower design and operation policies on energy production, flow regime alteration and flood hazard and identify those which provide the best performance using multiobjective optimisation.
Relevant answer
Answer
These papers are relevant:
Hurford, A. P., Huskova, I., & Harou, J. J. (2014). Using many-objective trade-off analysis to help dams promote economic development, protect the poor and enhance ecological health. Environmental Science & Policy, 38, 72-86 see:http://www.sciencedirect.com/science/article/pii/S1462901113002116
Hurford, A. P., Huskova, I., & Harou, J. J. (2014). Using many-objective trade-off analysis to help dams promote economic development, protect the poor and enhance ecological health. Environmental Science & Policy, 38, 72-86. see: http://discovery.ucl.ac.uk/1431872/1/Hurford_HESS.pdf 
Hurford, A. P., Huskova, I., Matrosov, E. S., & Harou, J. J. (2012). Impacts of management options on water deficits, losses and livelihoods in the Jaguaribe Basin of North East Brazil. In International Congress on Environmental Modelling and Software see http://www.iemss.org/sites/iemss2012/proceedings/I2_2_0981_Hurford_et_al.pdf 
There is also some interesting information in a literature review that I carried out on hydropower see: http://www.evidenceondemand.info/harnessing-hydropower-literature-review and this paper see: A review of the consideration of climate change in the planning of hydropower schemes in sub-Saharan Africa and http://eprints.hrwallingford.co.uk/1281/
  • asked a question related to Hydropower
Question
4 answers
What is your opinion which is best way of implementation of PV generation in only hydropower generating system?
Any literature
Relevant answer
Answer
Dear Ivan,
I agree with Arnulf,
You can investigate the Progress in Photovoltaics:Res.App, 24:229-239, Applied Energy 167:377-384, Renewable Energy 99:410-419.
There was a few publication. You can find it when you read this article.
I expect that these are help to us.
Best regards.
  • asked a question related to Hydropower
Question
4 answers
the objective of my thesis is developed simulation-optimization model for dokan reservoir by using discrete differential dynamic programming(DDDP) for maximize hydropower production and using Simulink toolbox in matlab for simulation process, please any one tell me DDDP technique is possible to use as optimization algorithm in combine simulation-optimization model. thanks
Relevant answer
Answer
Hi Silva,
of course, my thesis title is " Simulation-optimization model for system operation of dokan reservoir" for this purpose I selected Simulink toolbox in matlab software for implemented simulation process. Also I selected discrete differential dynamic programming (DDDP) as a method for optimization of hydropower generation of the reservoir. now, I don't know this model how can be constructed according to the following flowchart that explained  in this attached file.thanks
  • asked a question related to Hydropower
Question
9 answers
Most of the countries have hydropower operation and implementation for future sustainable energy production. Previous studies suggested that hydropower are most climate resilience and sustainable than production of another energy sources.  Does hydropower generation doesnot cause impacts on microclimate or regional climatic condition or are more sustainable and environment friendly?
Relevant answer
Answer
Hydro power on the small scale have a very small footprint.  Hydro power on the large scale has a very big footprint.  All forms of power have a 'fatalities per TeraJoule' value.  It would be very interesting to know what it would be for hydro power, considering the methyl mercury that will tend to come out of a deep reservoir.  For coal and it's particulate matter, in Ontario Canada it's something like 58.  For Uranium and it's Radon releases, mined in very rural Canada, it's 43, and closer to population centers, it's 85.  B
Large scale hydro will have impacts on everything - local climate, local species, etc.  While it's considered 'green', it's impacts are long range and long duration.  Someone asked how slowly would one have to dismantle Hoover Dam to avoid ecological impacts.  Estimates varied between 5000 years and never. 
Consider the impacts from Cradle to Cradle - build the dam, then return the site to 'green field' after the useful design life. How much impact?  There may be conditions that would be minimally impactful, but there will certainly be conditions that are massively impacting.
  • asked a question related to Hydropower
Question
3 answers
Knowing the distance between the upper reservoir and the lower reservoir of a Hydro power plant; knowing the temperature of the water.. Assuming that there is no friction loss in the penstock, and the atmospheric pressure difference between the upper reservoir and lower reservoir is negligible.
How can i find the water speed flowing into the plant turbine with Bernoulli's equation and assuming water is incompressible? How can i find the kinetic energy of a meter cube of water when it reaches the turbine?
Thanks 
Relevant answer
Answer
Dear Aristide Foudji,
I think, you can easily calculate the velocity of water at lower reservoir by doing Bernoulli equation on the system.
DEL P / Rho + DEL Ek + DEL Ep + Friction + Ws = 0
From the given data, DEL P / Rho = 0, Friction = 0, and Ws = 0. So DEL Ek = - DEL Ep and by assume that the water velocity at upper reservoir surface = 0 because the upper reservoir is large enough, you can find the velocity at lower reservoir.
I hope my explanation can help you.
  • asked a question related to Hydropower
Question
9 answers
.Hydropower Flexibility is one of the great advantages of this renewable energy source, such that it can be considered a big storage bank of energy, can any one provide us with examples of the shortest time to raise the typical production of a dam
Relevant answer
Answer
The environmental impact on t uses of any energy source for electricity generation is something that you have to consider and evaluate. All energy sources have an impact on the environment. Some energy source has a bigger impact than others, but there is no energy source free of impact on the environment. Depending on the specific conditions of a given country, you can make the best combination possible of the energy mix, but it is wrong to exclude any particularly energy source without evaluating its consequences to the population and the environment.
  • asked a question related to Hydropower
Question
3 answers
In Hydropower production problems, when irrigation water release as well as power generation E=K*IR, where K=conversion fcator to convert discharge to hydropower. 
Relevant answer