Periodica Polytechnica Civil Engineering
The Technical Specifications of D.12/H. of Hungarian StateRailways specifies that a continuously welded rail track can be constructed through a bridge without being inter-rupted if the expansion length of the bridge is not longer than 40 m. If the expansion length of a bridge is greater than 40 m, the continuously welded rail should normally be interrupted; a rail expansion joint has to be constructed. The goal of this research is to provide technical solutions of track structureson bridges so a continuously welded rail can be constructed through the bridge from an earthwork without interruption, so rail expansion joints can be omitted.