The article first describes characteristics of major infrastructure projects. Second, it documents a much neglected topic in economics: that ex ante estimates of costs and benefits are often very different from actual ex post costs and benefits. For large infrastructure projects the consequences are cost overruns, benefit shortfalls, and the systematic underestimation of risks. Third, implications for cost–benefit analysis are described, including that such analysis is not to be trusted for major infrastructure projects. Fourth, the article uncovers the causes of this state of affairs in terms of perverse incentives that encourage promoters to underestimate costs and overestimate benefits in the business cases for their projects. But the projects that are made to look best on paper are the projects that amass the highest cost overruns and benefit shortfalls in reality. The article depicts this situation as ‘survival of the unfittest’. Fifth, the article sets out to explain how the problem may be solved, with a view to arriving at more efficient and more democratic projects, and avoiding the scandals that often accompany major infrastructure investments. Finally, the article identifies current trends in major infrastructure development. It is argued that a rapid increase in stimulus spending, combined with more investments in emerging economies, combined with more spending on information technology is catapulting infrastructure investment from the frying pan into the fire.
Content may be subject to copyright.
Oxford Review of Economic Policy, Volume 25, Number 3, 2009, pp.344–367
Survival of the unfittest: why the worst
infrastructure gets built—and what we can
do about it
Bent Flyvbjerg
Abstract The article first describes characteristics of major infrastructure projects. Second, it documents
a much neglected topic in economics: that ex ante estimates of costs and benefits are often very different
from actual ex post costs and benefits. For large infrastructure projects the consequences are cost overruns,
benefit shortfalls, and the systematic underestimation of risks. Third, implications for cost–benefit analysis
are described, including that such analysis is not to be trusted for major infrastructure projects. Fourth, the
article uncovers the causes of this state of affairs in terms of perverse incentives that encourage promoters
to underestimate costs and overestimate benefits in the business cases for their projects. But the projects that
are made to look best on paper are the projects that amass the highest cost overruns and benefit shortfalls
in reality. The article depicts this situation as ‘survival of the unfittest’. Fifth, the article sets out to explain
how the problem may be solved, with a view to arriving at more efficient and more democratic projects, and
avoiding the scandals that often accompany major infrastructure investments. Finally, the article identifies
current trends in major infrastructure development. It is argued that a rapid increase in stimulus spending,
combined with more investments in emerging economies, combined with more spending on information
technology is catapulting infrastructure investment from the frying pan into the fire.
Key words: infrastructure, cost overruns, benefit shortfalls, cost–benefit analysis, optimism bias, agency
issues, reference class forecasting
JEL classification: H43, H54, R42
I. Introduction
In mid-2008, The Economist called current spending on infrastructure the ‘biggest investment
boom in history’ (The Economist, 7 June 2008, p. 80). Spending was the largest it had ever
been as a share of world GDP. When the fiscal crisis deepened and became global during the
autumn to winter of 2008–9, this could have ended the infrastructure boom, as banks and
capital funds radically cut back on their lending. But the opposite appears to have happened.
Sa¨
ıd Business School, University of Oxford, e-mail: bent.flyvbjerg@sbs.ox.ac.uk
Part of the research for this paper was carried out while the author was professor at Aalborg University, Denmark
and Delft University of Technology, the Netherlands.
doi: 10.1093/oxrep/grp024
CThe Author 2009. Published by Oxford University Press.
For permissions please e-mail: journals.permissions@oxfordjournals.org
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 345
Reductions in private funds have been offset by hundreds of billions of public dollars for
stimulus spending. Heads of state, led by US president Barach Obama and China Premier
Wen Jiabao, have singled out investment in infrastructure as a key means to create jobs and
keep the economy from slumping. China was first mover when its State Council, in November
2008, passed a $586 billion stimulus plan, mainly for investment in infrastructure. In February
2009 the USA followed suit, with Congress passing President Obama’s $787 billion new New
Deal. India has a $475 billion plan, and the UK, Germany, France, and many other nations
have made similar arrangements.
With so much money in the pipeline—and with the health of the global economy riding on
the success of infrastructure investment—the efficiency of infrastructure delivery is particu-
larly important at present. If done right the investment boom could become a boon, because
infrastructure investment is appealing in many ways: it creates and sustains employment;
there is a large element of domestic inputs relative to imports; it improves productivity and
competitiveness by lowering producer costs; it benefits consumers through higher-quality ser-
vices; and it improves the environment when infrastructures that are environmentally sound
substitute for infrastructures that are not (Helm, 2008, p. 1).
But there is a big ‘if’ here. Because if done wrong the thrust may become a bust, with
boondoggles worse than any seen yet, weakening the economy instead of improving it. Unfor-
tunately the conventional way of delivering major infrastructure shows a dismal performance
record. In what follows, I document the record, explain why it is so poor, and finally describe
measures that may help current stimulus spending become effective, instead of adding to the
financial and economic failures that litter the field of infrastructure investment.
But first, let’s see what the characteristics of major infrastructure are.
II. Characteristics of major infrastructure
Major infrastructure projects generally have the following characteristics.1
rSuch projects are inherently risky owing to long planning horizons and complex inter-
faces.
rTechnology and design are often non-standard.
rDecision-making, planning, and management are typically multi-actor processes with
conflicting interests.
rOften there is ‘lock in’ or ‘capture’ of a certain project concept at an early stage, leaving
analysis of alternatives weak or absent.
rThe project scope or ambition level will typically change significantly over time.
rStatistical evidence shows that such unplanned events are often unaccounted for, leaving
budget and time contingencies sorely inadequate.
rAs a consequence, misinformation about costs, benefits, and risks is the norm through-
out project development and decision-making, including in the business case.
rThe result is cost overruns and/or benefit shortfalls during project implementation.
1By ‘major projects’ I here mean the most expensive projects that are built in the world today, typically at costs
per project from around a hundred million to several billion dollars.
346 Bent Flyvbjerg
Table 1: Inaccuracy of transportation project cost estimates by type of project, in constant prices
Type of project No. of cases Avg. cost overrun % Standard deviation
Rail 58 44.7 38.4
Bridges and tunnels 33 33.8 62.4
Road 167 20.4 29.9
Cost overruns in the order of 50 per cent in real terms are common for major infrastructure,
and overruns above 100 per cent are not uncommon. Demand and benefit forecasts that are
wrong by 20–70 per cent compared with actual development are common.
Table 1 shows more detailed cost data for transportation infrastructure projects. Trans-
portation is used as an example here and elsewhere in the article because the best data exist
for transportation and because there is not enough space to present data for all project types.
It should be mentioned, however, that comparative research shows that the problems identi-
fied for transportation apply to a wide range of other project types including ICT systems,
buildings, aerospace projects, defence, mega-events such as the Olympics and the World
Cup, water projects, dams, power plants, oil and gas extraction projects, mining, large-scale
manufacturing, big science, and urban and regional development projects (Flyvbjerg et al.,
2003, pp. 18–19; Altshuler and Luberoff, 2003; Priemus et al., 2008; Flyvbjerg et al., 2002,
p. 286; Flyvbjerg, 2005a).
The dataset in Table 1 shows cost overrun in 258 projects in 20 nations on five continents.
All projects for which data were obtainable were included in the study.2For rail, average cost
overrun is 44.7 per cent measured in constant prices from the build decision. For bridges and
tunnels, the equivalent figure is 33.8 per cent, and for roads 20.4 per cent. The difference in
cost overrun between the three project types is statistically significant (Flyvbjerg et al., 2002).
The large standard deviations shown in Table 1 are as interesting as the large average cost
overruns. The size of the standard deviations demonstrates that uncertainty and risk regarding
cost overruns in infrastructure are large, indeed.
The following key observations pertain to cost overruns in transportation infrastructure
projects:
rnine out of 10 projects have cost overrun;
roverrun is found across the 20 nations and five continents covered by the study;
roverrun is constant for the 70-year period covered by the study; cost estimates have not
improved over time.
Table 2 shows the inaccuracy of travel demand forecasts for rail and road infrastructure. The
demand study covers 208 projects in 14 nations on five continents. All projects for which data
2The data are from the largest database of its kind. All costs are construction costs measured in constant prices.
Cost overrun, also sometimes called ‘cost increase’ or ‘cost escalation’, is measured according to international
convention as actual outturn costs minus estimated costs in percentage of estimated costs. Actual costs are defined
as real, accounted construction costs determined at the time of project completion. Estimated costs are defined as
budgeted, or forecasted, construction costs at the time of the decision to build. For reasons explained in Flyvbjerg
et al. (2002) the figures for cost overrun presented here must be considered conservative. Ideally financing costs,
operating costs, and maintenance costs would also be included in a study of costs. It is difficult, however, to find valid,
reliable, and comparable data on these types of costs across large numbers of projects. For details on methodology,
see Flyvbjerg et al. (2002).
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 347
Table 2: Inaccuracy in forecasts of rail passenger and road vehicle traffic
Type of project No. of cases Avg. inaccuracy % Standard deviation
Rail 25 51.4 28.1
Road 183 9.5 44.3
were obtainable were included in the study.3For rail, actual passenger traffic is 51.4 per cent
lower than estimated traffic on average. This is equivalent to an average overestimate in rail
passenger forecasts of no less than 105.6 per cent. The result is large benefit shortfalls for
rail. For roads, actual vehicle traffic is on average 9.5 per cent higher than forecasted traffic.
We see that rail passenger forecasts are biased, whereas this is less the case for road traffic
forecasts. The difference between rail and road is statistically significant at a high level.
Again the standard deviations are large, indicating that forecasting errors vary widely across
projects (Flyvbjerg et al., 2005; Flyvbjerg, 2005b).
The following observations hold for traffic demand forecasts:
r84 per cent of rail passenger forecasts are wrong by more than ±20 per cent;
rnine out of 10 rail projects have overestimated traffic;
r50 per cent of road traffic forecasts are wrong by more than ±20 per cent;
rthe number of roads with overestimated and the number with underestimated traffic is
about the same;
rinaccuracy in traffic forecasts is found in the 14 nations and five continents covered by
the study;
rinaccuracy is constant for the 30-year period covered by the study; forecasts have not
improved over time.
We conclude that if techniques and skills for arriving at accurate cost and traffic forecasts
have improved over time, these improvements have not resulted in an increase in the accuracy
of forecasts.
We also conclude that cost overruns and benefit shortfalls are a problem because: (i) they
lead to a Pareto-inefficient allocation of resources, i.e. waste; (ii) they lead to delays and
further cost overruns and benefit shortfalls; (iii) they destabilize project management; and
(iv) the problem is getting bigger, because projects get bigger.
III. Implications for cost–benefit analysis
Cost–benefit analyses and social and environmental impact assessments are typically at the
core of documentation and decision-making for major infrastructure projects. Such analyses
are based on cost and traffic forecasts like those described above. But if we combine the data
in Tables 1 and 2, we see that for rail an average cost overrun of 44.7 per cent combines
3Followinginter national convention, inaccuracy is measured as actual traffic minus estimated trafficin percentage
of estimated traffic. Rail traffic is measured as number of passengers; road traffic as number of vehicles. The base
year for estimated traffic is the year of decision to build. The forecasting year is the first full year of operations. Two
statistical outliers are not included here. For details on methodology, see Flyvbjerg (2005b).
348 Bent Flyvbjerg
with an average traffic shortfall of 51.4 per cent.4For roads, an average cost overrun of
20.4 per cent combines with a fifty–fifty chance that traffic is also wrong by more than
20 per cent. With errors and biases of such magnitude in the forecasts that form a basis for
cost–benefit analyses, such analyses will also, with a high degree of certainty, be strongly
misleading. ‘Garbage in, garbage out’, as the saying goes.
As a case in point, consider the Channel tunnel, the longest underwater rail tunnel in
Europe, connecting France and the UK. This project was sold as highly beneficial both
financially and economically. At the initial public offering, Eurotunnel, the private owner of
the tunnel, lured investors by telling them that 10 per cent ‘would be a reasonable allowance
for the possible impact of unforeseen circumstances on construction costs’.5In fact, costs
went 80 per cent over budget for construction and 140 per cent for financing, measured in real
terms from the decision date. Revenues have been half of those forecasted. As a consequence
the project has proved non-viable, with an internal rate of return on the investment that
is negative, at –14.5 per cent. However convenient for the users of the service—who are
heavily subsidized—the Channel tunnel detracts from the economy instead of adding to it.
An economic and financial ex post evaluation of the project, which systematically compared
actual with forecasted costs and benefits, concluded that ‘the British Economy would have
been better off had the Tunnel never been constructed’ (Anguera, 2006, p. 291).
But perhaps the Channel tunnel was just a piece of bad luck? Perhaps the next similar
project did better? Not so. The next major tunnel was the Danish Great Belt rail tunnel, the
second-longest underwater rail tunnel in Europe, opened 3 years after the Channel tunnel.
Here construction cost overrun was 120 per cent in real terms, and the project proved non-
viable even before it opened. Only by cross-subsidizing the tunnel with revenues from a
nearby motorway bridge was it possible to pay for the tunnel. Danish legislators—and the
government and the EU Commission—are officially against cross-subsidies. But in this case
they were happy and quick to use the remedy to sweep a major embarrassment under the
carpet: the fact that actual benefits would never come even close to covering actual costs
for the tunnel, although taxpayers had been told the exact opposite when they were asked to
underwrite the billion-dollar debt of the project.
The Channel and Great Belt tunnels are both examples of a phenomenon I focus on below:
‘survival of the unfittest’. From an economic point of view the projects should never have been
built, at least not in the form they were. They survived because benefit–cost ratios presented
to investors and legislators were hugely inflated, deliberately or not. The UK, France, and
Denmark are rich countries and can afford to build financial and economic disasters like this.
But it is important to understand that countries do not become rich by doing so. They do so
when they have become rich.
It is easy to make long lists of projects with similar cost and/or benefit problems (Flyvbjerg,
2005a). To mention only a few, in America Boston’s Big Dig, LA’s subway, San Francisco’s
Bay Bridge, Denver’s new International Airport, and the New Woodrow Wilson Bridge in
Washington, DC come to mind, not to speak of the rebuilding of Iraq. In Britain, the London
Tube public–private partnership, the West Coast Main Line upgrade, the Railtrack fiscal
collapse, the Millennium Dome, the Scottish parliament building, the Humber Bridge, and
the cost overruns on the 2012 London Olympics have been major boondoggles. Other nations,
and even cities, have their own long lists of underperforming projects.
4For each of 12 urban rail projects, we have data for both cost overrun and traffic shortfall. For these projects
average cost overrun is 40.3 per cent; average traffic shortfall is 47.8 per cent.
5Quoted from ‘Under Water Over Budget,’ The Economist, 7 October 1989, 37–8.
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 349
This does not show the uselessness of cost–benefit analysis as such, needless to say. But
if informed decisions are the goal, then conventional ex ante cost–benefit analysis must be
supplemented with empirical ex post risk analysis focused on documented uncertainties in
the estimates of costs and benefits that enter into cost–benefit analysis. For a given major
infrastructure project, this would constitute a kind of empirical due diligence of its cost–
benefit analysis, something that is rarely carried out today.
Given the data presented above, a key recommendation for decision-makers, investors,
and voters who care about what Williams (1998) calls ‘honest numbers’ is that they should
not trust the budgets, patronage forecasts, and cost–benefit analyses produced by promoters
of major infrastructure projects. Independent studies should be carried out and, again, such
studies should be strong on empirically based risk assessment. Until now it has been difficult
or impossible to carry out such assessments, because empirically grounded and statistically
valid figures of risk did not exist. With the study documented above, this has changed and
empirical risk assessment and management has begun (Flyvbjerg, 2006). In addition to sound
data, institutional checks and balances that would enforce accountability in actors towards
risk are also necessary, as we will see below.
In economics, large inaccuracies in forecasting have recently led to discussions of the
necessity of ‘firing the forecaster’ (Akerlof and Shiller, 2009, p. 146). Below, I argue that this
may be letting forecasters off too easily. Some forecasts are so grossly misrepresented that
we need to consider not only firing the forecasters but suing them, too—perhaps even having
afewservetime.
IV. Explaining cost overruns and benefit shortfalls
Three main types of explanation exist that claim to account for cost overruns and benefit
shortfalls in major infrastructure projects: technical, psychological, and political-economic.
Technical explanations account for cost overruns and benefit shortfalls in terms of imperfect
forecasting techniques, inadequate data, honest mistakes, inherent problems in predicting the
future, lack of experience on the part of forecasters, etc. This is the most common type of
explanation of inaccuracy in forecasts (Ascher, 1978; Morris and Hough, 1987; Wachs, 1990;
Flyvbjerg et al., 2002, 2005). Technical error may be reduced or eliminated by developing
better forecasting models, better data, and more experienced forecasters, according to this
explanation.
Psychological explanations account for cost overruns and benefit shortfalls in terms of
what psychologists call the planning fallacy and optimism bias. Such explanations have been
developed by Kahneman and Tversky (1979); Kahneman and Lovallo (1993), and Lovallo
and Kahneman (2003). In the grip of the planning fallacy, managers make decisions based
on delusional optimism rather than on a rational weighting of gains, losses, and probabilities.
They overestimate benefits and underestimate costs. They involuntarily spin scenarios of
success and overlook the potential for mistakes and miscalculations. As a result, managers
pursue initiatives that are unlikely to come in on budget or on time, or to deliver the expected
returns. Over-optimism can be traced to cognitive biases, that is, errors in the way the mind
processes information. These biases are thought to be ubiquitous, but their effects can be
tempered by simple reality checks, thus reducing the odds that people and organizations will
rush blindly into unprofitable investments of money and time.
350 Bent Flyvbjerg
Political-economic explanations see project planners and promoters as deliberately and
strategically overestimating benefits and underestimating costs when forecasting the outcomes
of projects. They do this in order to increase the likelihood that it is their projects, and not the
competition’s, that gain approval and funding. Political-economic explanations have been set
forth by Flyvbjerg et al. (2002, 2005) and Wachs (1989, 1990). According to such explanations
planners and promoters purposely spin scenarios of success and gloss over the potential for
failure. Again, this results in the pursuit of ventures that are unlikely to come in on budget
or on time, or to deliver the promised benefits. Strategic misrepresentation can be traced to
agency problems and political and organizational pressures—for instance, competition for
scarce funds or jockeying for position—and it is rational in this sense.6If we now define a
lie in the conventional fashion as making a statement intended to deceive others (Bok, 1979,
p. 14; Cliffe et al., 2000, p. 3), we see that deliberate misrepresentation of costs and benefits
is lying, and we arrive at one of the most basic explanations of lying that exists: lying pays
off or, at least, political and economic agents believe it does. Where there is political pressure
there is misrepresentation and lying, according to this explanation, but misrepresentation and
lying can be moderated by measures of accountability.
How well does each of the three explanations of forecasting inaccuracy—technical, psycho-
logical, and political-economic—account for the data on cost overruns and benefit shortfalls
presented earlier? This is the question to be answered below.
Technical explanations have, as mentioned, gained widespread credence among forecasters
and project managers (Ascher, 1978; Flyvbjerg et al., 2002, 2005). It turns out, however, that
such credence could mainly be upheld because, until now, samples have been too small to
allow tests by statistical methods. The data presented above, which come from the first large-
sample study in the field, lead us to reject technical explanations of forecasting inaccuracy.
Such explanations do not fit the data well. First, if misleading forecasts were truly caused by
technical inadequacies, simple mistakes, and inherent problems with predicting the future, we
would expect a less biased distribution of errors in forecasts around zero. In fact, we have found
with high statistical significance that for four out of five distributions of forecasting errors,
the distributions have a mean statistically different from zero. Only the data for inaccuracy in
road traffic forecasts have a statistical distribution that seems to fit with explanations in terms
of technical forecasting error. Second, if imperfect techniques, inadequate data, and lack of
experience were the main explanations of inaccuracies, we would expect an improvement
in accuracy over time, since in a professional setting errors and their sources would be
recognized and addressed through the refinement of data collection, forecasting methods, etc.
Substantial resources have, in fact, been spent over several decades on improving data and
methods. Still our data show that this has had no effect on the accuracy of forecasts. Technical
factors, therefore, do not appear to explain the data. It is not so-called forecasting ‘errors’
or their causes that need explaining. It is the fact that, in a large majority of cases, costs
are underestimated and benefits overestimated. We may agree with proponents of technical
explanations that it is, for example, impossible to predict for the individual project exactly
which geological, environmental, or safety problems will appear and make costs soar. But
we maintain that it is possible to predict the risk, based on experience from other projects,
that some such problems will haunt a project and how this will affect costs. We also maintain
6For an interpretation of strategic misrepresentation in terms of agency problems and rent-seeking behaviour,
see Flyvbjerg et al. (2009).
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 351
that such risk can and should be accounted for in forecasts of costs, but typically is not. For
technical explanations to be valid, they would have to explain why forecasts are so consistent
in ignoring cost and benefit risks over time, location, and project type.
Psychological explanations better fit the data. The existence of optimism bias in managers
and promoters would result in actual costs being higher and actual benefits lower than those
forecasted. Consequently, the existence of optimism bias would be able to account, in whole
or in part, for the peculiar bias found in most of our data. Interestingly, however, when
you ask forecasters about causes for forecasting inaccuracies in actual forecasts, they do
not mention optimism bias as a main cause of inaccuracy (Flyvbjerg et al., 2005, pp. 138–
40). This could of course be because optimism bias is unconscious and thus not reflected
by forecasters. After all, there is a large body of experimental evidence for the existence
of optimism bias (Buehler et al., 1994; Buehler et al., 1997; Newby-Clark et al., 2002).
However, the experimental data are mainly from simple, non-professional settings. This is a
problem for psychological explanations, because it remains an open question whether they
are general and apply beyond such simple settings. Optimism bias would be an important
and credible explanation of underestimated costs and overestimated benefits in infrastructure
forecasting if estimates were produced by inexperienced forecasters, i.e. persons who were
estimating costs and benefits for the first or second time and who were thus inexperienced in
the realities of major infrastructure development and were not drawing on the knowledge and
skills of more experienced colleagues. Such situations may exist and may explain individual
cases of inaccuracy. But, given the fact that in modern society it is a defining characteristic
of professional expertise that it is constantly tested—through scientific analysis, critical
assessment, and peer review—in order to root out bias and error, it seems unlikely that a
whole profession of forecasting experts would continue to make the same mistakes decade
after decade instead of learning from their actions. Learning would result in the reduction,
if not elimination, of optimism bias, which would then result in estimates becoming more
accurate over time. But our data clearly show that this has not happened. The profession
of forecasters would, indeed, have to be an optimistic—and non-professional—group to
keep their optimism bias throughout the 70-year period our study covers for costs, and the
30-year period covered for patronage, and not learn that they were deceiving themselves
and others by underestimating costs and overestimating benefits. This would account for
the data, but is not a credible explanation. Therefore, on the basis of our data, we are led
to reject optimism bias as a primary and single cause of cost underestimation and benefit
overestimation.
Finally, political-economic explanations and strategic misrepresentation account well for
the systematic underestimation of costs and overestimation of benefits found in the data. A
strategic estimate of costs would be low, resulting in cost overrun, whereas a strategic estimate
of benefits would be high, resulting in benefit shortfalls. A key question for explanations in
terms of strategic misrepresentation is whether estimates of costs and benefits are intentionally
biased to serve the interests of promoters in getting projects started. This question raises the
difficult issue of lying. Questions of lying arenotoriously hard to answer, because by definition
a lie consists in making a statement intended to deceive others, and in order to establish
whether lying has taken place, one must therefore know the intentions of actors. For legal,
economic, moral, and other reasons, if promoters and managers have intentionally cooked
estimates of costs and benefits to get a project started, they are unlikely to tell researchers or
others formally that this is the case. Despite such problems, two studies exist that succeeded
in getting forecasters and managers to talk about strategic misrepresentation, one from the
UK (Flyvbjerg and COWI, 2004) and one from the USA (Wachs, 1990).
352 Bent Flyvbjerg
V. Survival of the unfittest
Flyvbjerg and COWI (2004) interviewed public officials, planners, and consultants who
had been involved in the development of large UK transportation infrastructure projects. A
planner with a local transportation authority is typical of how respondents explained the basic
mechanism of cost underestimation:
You will often as a planner know the real costs. You know that the budget is too low
but it is difficult to pass such a message to the counsellors [politicians] and the private
actors. They know that high costs reduce the chances of national funding.
Experienced professionals like the interviewee know that outturn costs will be higher than
estimated costs, but because of political pressure to secure funding for projects they hold
back this knowledge, which is seen as detrimental to the objective of obtaining funding.
Similarly, an interviewee explained the basic mechanism of benefit overestimation:
The system encourages people to focus on the benefits—because until now there has
not been much focus on the quality of risk analysis and the robustness [of projects]. It is
therefore important for project promoters to demonstrate all the benefits, also because
the project promoters know that their project is up against other projects and competing
for scarce resources.
Competition between projects and authorities creates political and organizational pressures
that in turn create an incentive structure that makes it rational for project promoters to
emphasize benefits and de-emphasize costs and risks. A project that looks highly beneficial
on paper is more likely to get funded than one that does not.
Specialized private consultancy companies are typically engaged to help develop project
proposals. In general, the interviewees found that consultants showed high professional
standards and integrity. But interviewees also found that consultants appeared to focus on
justifying projects rather than critically scrutinizing them. A project manager explained:
Most decent consultants will write off obviously bad projects but there is a grey zone
and I think many consultants in reality have an incentive to try to prolong the life of
projects which means to get them through the business case. It is in line with their need
to make a profit.
The consultants interviewed confirmed that appraisals often focused more on benefits than
on costs. But they said this was at the request of clients and that for specific projects discussed
‘there was an incredible rush to see projects realized’.
One typical interviewee saw project approval as ‘passing the test’ and precisely summed
up the rules of the game like this: ‘It’s all about passing the test [of project approval]. You are
in, when you are in. It means that there is so much focus on showing the project at its best at
this stage.’
In sum, the UK study shows that strong interests and strong incentives exist at the project-
approval stage to present projects as favourably as possible—that is, with benefits emphasized
and costs and risks de-emphasized. Local authorities, local developers and land owners, local
labour unions, local politicians, local officials, local MPs, and consultants all stand to benefit
from a project that looks favourable on paper and they have little incentive actively to avoid
bias in estimates of benefits, costs, and risks. National bodies, such as certain parts of the
Department for Transport and the Ministry of Finance who fund and oversee projects, may
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 353
have an interest in more realistic appraisals, but so far they have had little success in achieving
such realism, although the situation may be changing with the initiatives to curb bias set out
in HM Treasury (2003) and UK Department for Transport (2006).
Wachs (1986, 1990) found similar results for transit planning in the USA. Taken together,
the UK and US studies both account well for existing data on cost underestimation and
benefit overestimation. Both studies falsify the notion that in situations with high political
and organizational pressure the underestimation of costs and overestimation of benefits is
caused by non-intentional technical error or optimism bias. Both studies support the view
that in such situations promoters and forecasters intentionally use the following formula in
order to secure approval and funding for their projects:
underestimated costs +overestimated benefits =funding
Using this formula, and thus ‘showing the project at its best’ as one interviewee said above,
results in an inverted Darwinism, i.e the survival of the unfittest. It is not the best projects
that get implemented, but the projects that look best on paper. And the projects that look
best on paper are the projects with the largest cost underestimates and benefit overestimates,
other things being equal. But the larger the cost underestimate on paper, the greater the
cost overrun in practice. And the larger the overestimate of benefits, the greater the benefit
shortfall. Therefore the projects that have been made to look best on paper in this manner
become the worst, or unfittest, projects in reality, in the sense that they are the very projects
that will encounter most problems during construction and operations in terms of the largest
cost overruns, benefit shortfalls, and risks of non-viability. They have been designed like that,
as disasters waiting to happen.
VI. The outside view
When contemplating what project managers can do to help reform come about, we need to
distinguish between two fundamentally different situations: (i) project managers consider it
important to get estimates of costs, benefits, and risks right; and (ii) project managers do
not consider it important to get estimates right, because optimistic estimates are seen as a
necessary means to getting projects started. The first situation is the easier one to deal with
and, here, better methodology will go a long way in improving project management. The
second situation is more difficult, and more common for political projects as we saw above.
Here, better governance with changed incentives is essential in order to reward honesty and
punish deception, where today’s incentives often do the exact opposite.
Thus two main measures of reform are (i) better methods for estimating costs, benefits,
and risks, and (ii) improved governance. Better methods are covered in this section, improved
governance in the next.
If project managers genuinely consider it important to get estimates of costs, benefits,
and risks right, it is recommended they use a promising new method called ‘reference
class forecasting’ to reduce inaccuracy and bias. This method was originally developed to
compensate for the type of cognitive bias in human forecasting that Princeton psychologist
Daniel Kahneman found in his Nobel prize-winning work on bias in economic forecasting
(Kahneman, 1994; Kahneman and Tversky, 1979). Reference class forecasting has proven
more accurate than conventional forecasting. It was used in project management in practice
for the first time in 2004 (Flyvbjerg and COWI, 2004); in 2005 the method was officially
354 Bent Flyvbjerg
endorsed by the American Planning Association (2005); and since then it has been used
by governments and private companies in the UK, the Netherlands, Denmark, Switzerland,
Australia, and South Africa, among others.
For reasons of space, here I present only an outline of the method, based mainly on Lovallo
and Kahneman (2003) and Flyvbjerg (2006). Reference class forecasting consists in taking
a so-called ‘outside view’ on the particular project being forecasted. The outside view is
established on the basis of information from a class of similar projects. The outside view
does not try to forecast the specific uncertain events that will affect the particular project, but
instead places the project in a statistical distribution of outcomes from this class of reference
projects. Reference class forecasting requires the following three steps for the individual
project:
(i) identification of a relevant reference class of past projects. The class must be broad
enough to be statistically meaningful but narrow enough to be truly comparable with
the specific project;
(ii) establishing a probability distribution for the selected reference class. This requires ac-
cess to credible, empirical data for a sufficient number of projects within the reference
class to make statistically meaningful conclusions; and
(iii) comparing the specific project with the reference class distribution, in order to establish
the most likely outcome for the specific project.
Daniel Kahneman relates the following story about curriculum planning to illustrate reference
class forecasting in practice (Lovallo and Kahneman, 2003, p. 61). Some years ago, Kahneman
was involved in a project to develop a curriculum for a new subject area for high schools in
Israel. The project was carried out by a team of academics and teachers. In time, the team
began to discuss how long the project would take to complete. Everyone on the team was
asked to write on a slip of paper the number of months needed to finish and report the project.
The estimates ranged from 18 to 30 months. One of the team members—a distinguished
expert in curriculum development—was then posed a challenge by another team member to
recall as many projects similar to theirs as possible and to think of these projects as they
were in a stage comparable to their project. ‘How long did it take them at that point to reach
completion?’, the expert was asked. After a while he answered, with some discomfort, that not
all the comparable teams he could think of ever did complete their task. About 40 per cent of
them eventually gave up. Of those remaining, the expert could not think of any that completed
their task in less than 7 years, nor of any that took more than ten. The expert was then asked
if he had reason to believe that the present team was more skilled in curriculum development
than the earlier ones had been. The expert said no, he did not see any relevant factor that
distinguished this team favourably from the teams he had been thinking about. His impression
was that the present team was slightly below average in terms of resources and potential. The
wise decision at this point would probably have been for the team to break up, according to
Kahneman. Instead, the members ignored the pessimistic information and proceeded with
the project. They finally completed the project 8 years later, and their efforts went largely
wasted—the resulting curriculum was rarely used.
In this example, the curriculum expert made two forecasts for the same problem and
arrived at very different answers. The first forecast was the inside view; the second was the
outside view, or the reference class forecast. The inside view is the one that the expert and the
other team members adopted. They made forecasts by focusing tightly on the case at hand,
considering its objective, the resources they brought to it, and the obstacles to its completion.
They constructed in their minds scenarios of their coming progress and extrapolated current
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 355
Figure 1: What reference class forecasting does, in statisticians’ language
trends into the future. The resulting forecasts, even the most conservative ones, were overly
optimistic. The outside view is the one provoked by the question to the curriculum expert. It
completely ignored the details of the project at hand, and it involved no attempt at forecasting
the events that would influence the project’s future course. Instead, it examined the experiences
of a class of similar projects, laid out a rough distribution of outcomes for this reference class,
and then positioned the current project in that distribution. The resulting forecast, as it turned
out, was much more accurate.
Figure 1 shows what reference class forecasting does in statisticians’ language. First, refer-
ence class forecasting regresses the best guess of the conventional forecast—here the project
promoters’ forecast, indicated by the darker curve—towards the average of the reference class.
The distribution of outcomes in the reference class is indicated by the lighter curve. Second,
reference class forecasting expands the estimate of interval in the conventional forecast to
the interval of the reference class.
With an example from infrastructure provision, planners in a city preparing to build a
new subway would, first, establish a reference class of comparable projects. This could be
the relevant rail projects from the sample described in Table 1. Through statistical and other
analyses the planners would establish which projects to include in the reference class, i.e.
projects that were, indeed, comparable to the one being planned and to each other. Second,
if the planners were concerned, for example, with getting construction cost estimates right,
they would then establish the distribution of outcomes for the reference class regarding the
accuracy of construction cost forecasts. Figure 2 shows what this distribution looks like for
a reference class relevant to building subways in the UK, developed by Flyvbjerg and COWI
(2004, p. 23) for the UK Department for Transport. Third, the planners would compare their
subway project to the reference class distribution. This would make it clear to the planners that
unless they have reason to believe they are substantially better forecasters and planners than
their colleagues who did the forecasts and planning for projects in the reference class, they
are likely grossly to underestimate construction costs. Finally, planners would then use this
knowledge to adjust their forecasts for more realism. Figure 3 shows what such adjustments
are for the UK situation. More specifically, Figure 3 shows that for a forecast of construction
costs for a rail project, which has been planned in the manner that such projects are usually
planned (i.e. like the projects in the reference class), this forecast would have to be adjusted
upwards by 40 per cent, if investors were willing to accept a risk of cost overrun of 50 per cent.
If investors were willing to accept a risk of overrun of only 10 per cent, the uplift would have
to be 68 per cent. For a rail project initially estimated at, say £4 billion, the uplifts for the
356 Bent Flyvbjerg
Figure 2: Inaccuracy of construction cost forecasts for rail projects in reference class (average
cost increase is indicated for non-UK and UK projects, separately; constant prices)
Source: Flyvbjerg and COWI (2004).
50 and 10 per cent levels of risk of cost overrun would be £1.6 billion and £2.7 billion,
respectively.
The first instance of reference class forecasting in practice was done in 2004 for capital
costs of the proposed Edinburgh Tram Line 2 (Flyvbjerg, 2006). An initial cost estimate
of £320m made by planners was adjusted for optimism bias and acceptable risk, using the
probability distribution in Figure 3. This resulted in a new cost estimate of £400m, including
contingencies to insure against cost overruns at the 80 per cent level, i.e. with a 20 per cent risk
of overrun. If the Scottish Parliament, which was underwriting the investment, were willing
to accept a risk of overrun of 50 per cent, then the cost estimate including contingencies could
be lowered to £357m. Insurance is expensive, here as elsewhere, and the marginal cost of
insurance against cost overruns increases as the level of acceptable risk decreases, as seen in
Figure 3. Since the Edinburgh Tram, many other infrastructure projects have been subjected
to reference class forecasting, Crossrail in London being the most expensive at a cost of
£16 billion ($23 billion).
The contrast between inside and outside views has been confirmed by systematic research
(Gilovich et al., 2002). The research shows that when people are asked simple questions
requiring them to take an outside view, their forecasts become significantly more accurate.
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 357
Figure 3: Required adjustments to cost estimates for UK rail projects as function of the maxi-
mum acceptable level of risk for cost overrun (constant prices)
Source: Flyvbjerg and COWI (2004).
However, most individuals and organizations are inclined to adopt the inside view in planning
major initiatives. This is the conventional and intuitive approach. The traditional way to think
about a complex project is to focus on the project itself and its details, to bring to bear
what one knows about it, paying special attention to its unique or unusual features, trying to
predict the events that will influence its future. The thought of going out and gathering simple
statistics about related cases seldom enters a manager’s mind. This is the case in general,
according to Lovallo and Kahneman (2003, pp. 61–2). And it is certainly the case for cost
and benefit forecasting in large infrastructure projects. Despite the many forecasts my team
and I have reviewed, before the Edinburgh Tram forecast, which is based on our research, we
had not come across a single genuine reference class forecast of costs and benefits. Neither
had Daniel Kahneman, who first conceived the idea of the reference class forecast.
While understandable, managers’ preference for the inside view over the outside view is
unfortunate. When both forecasting methods are applied with equal skill, the outside view is
much more likely to produce a realistic estimate. That is because it bypasses cognitive and
political biases, such as optimism bias and strategic misrepresentation and cuts directly to
outcomes. In the outside view managers and forecasters are not required to make scenarios,
imagine events, or gauge their own and others’ levels of ability and control, so they cannot
get all these things wrong. Surely the outside view, being based on historical precedent, may
fail to predict extreme outcomes, that is, those that lie outside all historical precedents. But
for most projects, the outside view will produce more accurate results. In contrast, a focus on
inside details is the road to inaccuracy.
The comparative advantage of the outside view is most pronounced for non-routine projects,
understood as projects that managers in a certain locale have never attempted before—such as
building an urban rail system in a city for the first time, or launching a completely new product
to the market. It is in the planning of such new efforts that the biases toward optimism and
strategic misrepresentation are likely to be largest. To be sure, choosing the right reference
358 Bent Flyvbjerg
class of comparative past projects becomes more difficult when managers are forecasting
initiatives for which precedents are not easily found, for instance the introduction of new and
unfamiliar technologies. However, many major infrastructure projects are both non-routine
locally and use well-known technologies. Such projects are, therefore, particularly likely to
benefit from the outside view and reference class forecasting.
VII. Getting governance right
In this section we consider the situation where project managers and other influential actors
do not find it important to get estimates of costs, benefits, and risks right and where managers,
therefore, do not help to clarify and mitigate risks but, instead, generate and exacerbate them.
Here project managers are part of the problem, not the solution.
This situation may need some explication, because it may sound to many like an unlikely
state of affairs. After all, it may be agreed that project managers and other professionals in-
volved in major infrastructure provision ought to be interested in being accurate and unbiased
in their work. It is even stated in the Project Management Institute (PMI)’s Code of Ethics and
Professional Conduct (PMI, 2006, pp. 4, 5) that project managers should ‘provide accurate
information in a timely manner’ and they must ‘not engage in or condone behaviour that is
designed to deceive others’. Economists, engineers, planners, and others involved in major
infrastructure provision have similar codes of conduct. But there is a dark side to their work,
which is remarkably underexplored in the literature (Flyvbjerg, 1996).
On the dark side, project managers and planners ‘lie with numbers’. as Wachs (1989) has
aptly put it. They are busy not with getting forecasts and business cases right and following
the PMI Code of Ethics but with getting projects funded and built. And accurate forecasts
are often not an effective means for achieving this objective. Indeed, accurate forecasts may
be counterproductive, whereas biased forecasts may be effective in competing for funds
and securing the go-ahead for a project. ‘The most effective planner,’ says Wachs (1989,
p. 477), ‘is sometimes the one who can cloak advocacy in the guise of scientific or technical
rationality.’ Such advocacy would stand in direct opposition to PMI’s ruling that project
managers should ‘make decisions and take actions based on the best interests of society’
(PMI, 2006, p. 2).
Nevertheless, seemingly rational forecasts that underestimate costs and overestimate ben-
efits have long been an established formula for project approval as we saw above. Forecasting
is here mainly another kind of rent-seeking behaviour, resulting in a make-believe world
of misrepresentation which makes it extremely difficult to decide which projects deserve
undertaking and which do not. The consequence is, as even one of the industry’s own organs,
the Oxford-based Major Projects Association, acknowledges, that too many projects proceed
that should not. One might add that many projects do not proceed that probably should, had
they not lost out to projects with ‘better’ misrepresentation (Flyvbjerg et al., 2002).
In this situation, the question is not so much what project managers can do to reduce
inaccuracy and risk in forecasting, but what others can do to impose on project managers the
checks and balances that would give managers the incentive to stop producing biased forecasts
and begin to work according to their Code of Ethics. The challenge is to change the power
relations that govern forecasting and project development. Better forecasting techniques and
appeals to ethics will not do here; organizational change with a focus on transparency and
accountability is necessary.
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 359
As argued in Flyvbjerg et al. (2003), two basic types of accountability define liberal
democracies: (i) public-sector accountability through transparency and public control; and
(ii) private-sector accountability via competition and the market mechanism. Both types of
accountability may be effective tools to curb misrepresentation in project management and
to promote a culture which acknowledges and deals effectively with risk, especially where
large amounts of taxpayers’ money are at stake and for projects with significant social and
environmental impacts, as is common with major infrastructure projects.
(i) Transparency and public control
In order to achieve accountability through transparency and public control, the following
would be required as practices embedded in the relevant institutions (the full argument for
the measures may be found in Flyvbjerg et al. (2003, chs 9–11)).
rNational-level government should not offer discretionary grants to local agencies for
the sole purpose of building a specific type of project (a.k.a. ‘categorical grants’). Such
grants create perverse incentives. Instead, national government should simply offer
‘block grants’ to local governments, and let local political officials spend the funds
however they choose to, but make sure that every dollar they spend on one type of
project reduces their ability to fund another.
rCost–benefit analysis and other types of ex ante appraisal should be shifted from
promoters to more neutral ground, for instance with the Treasury, in order to reduce
risks of agency problems.
rForecasts and business cases should be made subject to independent peer review. Where
projects involve large amounts of government funds, such review may be carried out
by national or state auditing offices, such as the General Accounting Office in the USA
or the National Audit Office in the UK, who have the independence and expertise to
produce such reviews.
rForecasts should be benchmarked against comparable forecasts, for instance using
reference class forecasting as described in the previous section.
rFor publicly funded projects, forecasts, peer reviews, and benchmarkings should be
made available for public scrutiny, including by the media, as they are produced,
including all relevant documentation.
rPublic hearings, citizen juries, and the like should be organized to allow stakeholders
and civil society to voice criticism and support of forecasts. Knowledge generated in
this way should be integrated in project management and decision-making.
rScientific and professional conferences should be organized where forecasters would
present and defend their forecasts in the face of colleagues’ scrutiny and criticism.
rProjects with inflated benefit–cost ratios should be reconsidered and stopped if recalcu-
lated costs and benefits do not warrant implementation. Projects with realistic estimates
of benefits and costs should be rewarded.
rProfessional and occasionally even criminal penalties should be enforced for managers
and forecasters who consistently and foreseeably produce deceptive forecasts (Garett
and Wachs, 1996).
When I first began suggesting, in lectures for project managers, promoters, and forecasters,
that deception and criminal penalties may be concepts relevant to our professions, I would get
headshakes, sighs, and the occasional boo. Enron and Iraq changed that, almost overnight.
360 Bent Flyvbjerg
Today people listen and the literature has become replete with books and articles that hammer
out the links between lying, forecasting, and management. For instance, a recent book about
risk, the planning fallacy, and strategic misrepresentation bluntly states: ‘Anyone who causes
harm by forecasting should be treated as either a fool or a liar. Some forecasters cause more
damage to society than criminals’ (Taleb, 2007, p. 163).
Law-making has followed suit, most prominently with the 2002 Sarbanes–Oxley Act,
which stipulates up to 20 years in prison for a knowingly false forecast intended to impede,
obstruct, or influence the proper administration of affairs. There is little doubt that penalties
like this influence behaviour. The point is that malpractice in project management should
be taken as seriously as it is in other professions, e.g. medicine and law. Failing to do this
amounts to not taking the profession of project management seriously.
(ii) Competition and market control
In order to achieve accountability via competition and market control, the following would be
required, again as practices that are both embedded in and enforced by the relevant institutions.
rThe decision to go ahead with a major infrastructure project should, where at all
possible, be made contingent on the willingness of private financiers to participate
without a sovereign guarantee for at least one-third of the total capital needs.7This
should be required whether projects pass the market test or not—that is, whether
projects are subsidized or not or provided for social justice reasons or not. Private
lenders, shareholders, and stock-market analysts would produce their own forecasts or
conduct due diligence for existing ones. If they were wrong about the forecasts, they
and their organizations would be hurt. The result would be added pressure to produce
realistic forecasts and reduced risk to the taxpayer.
rForecasters and their organizations must share financial responsibility for covering cost
overruns and benefit shortfalls resulting from misrepresentation and bias in forecasting.
rThe participation of risk capital would not mean that government reduces control of
major infrastructure projects. On the contrary, it means that government can more
effectively play the role it should be playing, namely as the ordinary citizen’s guarantor
for ensuring concerns about safety, environment, risk, and a proper use of public funds.
Whether infrastructure projects are public, private, or public–private, they should be vested
in one and only one project organization with a strong governance framework and strong
contract-writing skills. The project organization may be a company or not, public or private,
or a mixture. What is important is that this organization has the capacity to (i) set up
and negotiate contracts that will effectively safeguard its interests, including in equity risk
allocation, and (ii) enforce accountability vis-`
a-vis contractors, operators, etc. In turn, the
directors of the organization must be held accountable for any cost overruns, benefit shortfalls,
faulty designs, unmitigated risks, etc. that may occur during project planning, implementation,
and operations.
7A sovereign guarantee is a guarantee where government takes on the risk of paying back a loan, even if the
loan was obtained in the private lending market. The lower limit of a one-third share of private risk capital for such
capital to influence accountability effectively is based on practical experience. See more in Flyvbjerg et al. (2003,
pp. 120–3).
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 361
Experience with contract writing is a much-neglected topic, but is particularly important in
developing and managing major infrastructure projects. This is because a fundamental asym-
metry in experience with and resources allocated to contract writing often applies in the client–
contractor relationship for such projects. Clients who decide to do major infrastructure—for
instance, a city council deciding to build a new subway or toll road—do so relatively rarely,
often only once, or never, in the lifetime of the individual city manager and council member.
Learning is therefore impaired for clients, and if you do not know what your interests are,
it is difficult to safeguard them. Contractors, on the other hand, who bid for and build such
projects, do so all the time. Contractors, therefore, typically know much more than clients
about the ins and outs of projects and contracts, including the many risks and pitfalls that
apply, plus which lawyers, bankers, and consultants to hire to safeguard their interests most
effectively. This asymmetry has brought many a client to grief. A possible way to bring
more symmetry into the client–contractor relationship would be for government to establish
a central contract-writing unit at the state or national level, which would be in charge of
negotiating, on behalf of local and other branches of government, the types of major contracts
they do too infrequently to gain real experience. This would concentrate a larger number
of contracts in one place, allowing experience—and the negotiating power that comes with
it—to accumulate.
Fortunately, better governance along the lines described above has recently become stronger
around the world. The Enron scandal and its successors have triggered new legislation and
a war on corporate deception that is spilling over into government with the same objective:
to curb financial waste and promote good governance. Although progress is slow, good
governance is gaining a foothold also in major infrastructure project management.
For example, in 2003 the Treasury of the United Kingdom required, for the first time, that
all ministries develop and implement procedures for major projects that will curb what the
Treasury calls—with true British civility—’optimism bias’. Funding will be unavailable for
projects that do not take into account this bias, and methods have been developed for how
to do this (HM Treasury, 2003; Flyvbjerg and COWI, 2004; UK Department for Transport,
2006). In the Netherlands in 2004, the Parliamentary Committee on Infrastructure Projects
for the first time conducted extensive public hearings to identify measures that will limit
the misinformation about large infrastructure projects given to the Parliament, public, and
media (Tijdelijke Commissie Infrastructuurprojecten, 2004). In Boston, the government has
sued to recoup funds from contractor overcharges for the Big Dig related to cost overruns.
More countries and cities are likely to follow the lead of the UK, the Netherlands, and
Boston in coming years; Switzerland and Denmark are already doing so (Swiss Association
of Road and Transportation Experts, 2006; Danish Ministry for Transport and Energy, 2006,
2008).
Moreover, with private finance in major infrastructure projects on the rise over the past
15–20 years, capital funds and banks are increasingly gaining a say in the project development
and management process. Private capital is no panacea for the ills in major infrastructure
project management, to be sure (Hodge and Greve, 2009). But private investors place their
own funds at risk, as opposed to governments who place the taxpayer’s money at risk. Capital
funds and banks can therefore be observed not to automatically accept at face value the
forecasts of project managers and promoters. Banks typically bring in their own advisers to
do independent forecasts, due diligence, and risk assessments, which is an important step in
the right direction. The false assumption that one forecast or one business case (which is also
a forecast) may contain the truth about a project is problematized. Instead project managers
and promoters are getting used to the healthy fact that different stakeholders have different
362 Bent Flyvbjerg
forecasts and that forecasts are not only products of objective science and engineering but of
negotiation. Why is this more healthy? Because it is more truthful about our ability to predict
the future and about the risks involved.
If the institutions with responsibility for developing and building major infrastructures
continued to implement, embed, and enforce such measures of accountability effectively,
then the misrepresentation in cost, benefit, and risk estimates, which is widespread today,
might be mitigated. If this is not done, misrepresentation is likely to continue, and the
allocation of funds for major infrastructure is likely to continue to be wasteful, unethical, and
sometimes even unlawful.
VIII. Current trends in infrastructure investment
In the introduction to this article, I mentioned that current spending on infrastructure con-
stitutes the biggest investment boom in history, measured as share of world GDP. We also
saw above that, even in the best of times, large infrastructure investments have a dismal
performance record in terms of cost overruns, delays, and benefit shortfalls. Nine out of ten
projects experience cost overrun, and overrun has not diminished for the 70 years for which
we have data, to mention but two grim statistics.
Throwing hundreds of billions of extra stimulus dollars at an underperforming business
that is already at bubble-like investment levels, is therefore highly risky at best. Nevertheless,
this is what China, the USA, and many other countries decided to do with their stimulus
packages in 2008 and 2009. Risks include rampant pork-barrel, fast-tracking, bid-rigging,
local governments pulling their funds out of on-going projects in anticipation of national
funding that may not come or comes late, and projects left unfinished because of cost
overruns on stimulus projects that local government cannot finance. The consequences could
be dire to the economy, and to public trust in the institutions and people who administer
infrastructure spending. Perhaps this is why Macquarie Bank—probably the largest and most
experienced infrastructure investor in the world—began reducing its infrastructure portfolio
in 2009, moving into energy instead.
Add to this that global infrastructure investments are shifting geographically from devel-
oped to emerging economies, where risks of ineffective project delivery are even higher. Over
half of infrastructure investments are now taking place in emerging economies. In the past
5 years, China has spent more on infrastructure in real terms than in the whole of the twentieth
century. In the past 4 years, China has built as many kilometres of high-speed passenger rail
lines as Europe has in two decades. Morgan Stanley predicts that emerging economies will
spend $22 trillion in today’s prices on infrastructure over the next 10 years. Political risks,
risks of corruption, and logistical risks are higher in emerging economies. As a consequence,
risks of cost overruns and benefit shortfalls are also higher. A recent study documented that
the average cost overrun on rail projects—measured in real terms from the decision date
to completion—was 64.6 per cent in emerging economies against 40.8 per cent in North
America and 34.2 per cent in Europe (Flyvbjerg et al., 2002, p. 285). Geography matters to
project performance. The striking shift in infrastructure investments to emerging economies
is therefore placing increased pressure on project delivery.
Finally, information and communication technology (ICT) has fast become a large and
rapidly increasing part of more major infrastructure projects. The consequences are often
devastating, because large ICT projects appear to perform even worse than other major
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 363
Figure 4: Cost overrun in construction projects and IT projects compared.
projects. Recently, a group of ICT experts contacted me to ask how they might learn to
manage cost overruns, delays, etc. in ICT projects ‘as well as in transportation infrastructure
projects’. I laughed out loud because I mistakenly thought they were making a joke. As
mentioned above, the evidence is clear that most major transportation infrastructure projects
perform poorly. But here is another project type, ICT, that apparently performs so much worse
that it can use transportation as a benchmark to be strived for. We did a pilot study, and sure
enough, the ICT experts were right: if a major project is not already messed up, injecting a
good dose of ICT will do the job (see Figure 4).
As if it were not difficult enough to develop, say, a major new airport, we are now developing
airports that depend on major new ICT for their operations, and we pay the price. Hong
Kong international airport is a case in point, with initial ICT hiccups so bad that the whole
Hong Kong economy suffered. Terminal 5 at London Heathrow is another example. An
infrastructure planner recently told me, ‘We know how to build large, expensive tunnels by
now, but we don’t know how to build the ICT safety systems that go into the tunnels; ICT
busts us every time.’
Or take Germany’s Toll Collect, a consortium of DaimlerChrysler, Deutsche Telekom,
and Cofiroute of France responsible for tolling heavy trucks on German motorways for the
federal government. The new tolling system was designed to be a showcase for public–private
partnership in infrastructure management. Tolling was scheduled to start in January 2003.
A year later the project was falling apart. The developers had been too optimistic about the
software that would run the system. The government was losing toll revenues estimated to
total 6.5 billion ($8.6 billion). For lack of funds, all new road projects in Germany and
related public works were put on hold, threatening 70,000 construction jobs. Politicians and
media were calling for prosecution of Toll Collect for deceiving the government. Finally, the
German transport minister cancelled the contract with Toll Collect and gave the company
2 months to come up with a better plan. By the time tolling at last started, several years delayed,
364 Bent Flyvbjerg
‘Toll Collect’ had become a popular byword among Germans used to describe everything
wrong with the national economy. Projects like this will not get us out of the current crisis.
Quite the opposite.
Examples abound and the advice regarding ICT seems obvious: if you are doing ICT as
part of a major project (or as a major project in itself) be sure to get ICT that has been
developed and debugged elsewhere and that has a proven track record in daily use. If you
decide not to follow this advice (which is common) you should be explicit that you are in
essence taking on the development risk of a major new product, which translates into large
and unpredictable risks of delays, cost overruns, and benefit shortfalls. Your set-up for risk
management and contingencies should then duly reflect this (which is uncommon).
And here’s the crunch: not only are clients and managers of major infrastructure projects
rushing headlong into risky ICT investments that are really new product development schemes,
but a rapidly increasing part of these investments are shifting to emerging economies, which
is a source of risk in its own right, as we saw above. Between 2003 and 2008, the share of
ICT spending in emerging economies rose by 60 per cent, from 15 to 24 per cent of global
ICT spending, according to the OECD.
In sum, the following formula captures the current trends in major infrastructure
investment:
(rapid increase in infrastructure spending) +(rapid shift in spending to emerging economies)
+(rapid increase in spending on ICT) =(risk to the third degree of financial and
economic disasters).
Whether stimulus infrastructure spending will improve or worsen the global economy will be
decided by how well we deal with these main trends. Thus the efficiency of project delivery is
both particularly important at present and particularly challenged. The major challenges are
(i) not to lower standards as the project pipeline rapidly expands, (ii) to navigate the particular
risks of doing more projects in emerging economies, and (iii) to harness the bull in a china
shop that is ICT in major projects.
Three main ingredients will help meet the challenges. First, we need honestly to acknowl-
edge that infrastructure investment is no easy fix but is fraught with problems. For this
purpose, President Obama was immensely helpful when at a 2009 White House Fiscal Re-
sponsibility Summit he openly identified ‘the costly overruns, the fraud and abuse, the endless
excuses’ in public procurement as key problems (White House, 2009). The Washington Post
(24 February 2009) rightly called this ‘a dramatic new form of discourse’. Before Obama it
was not comme-il-faut to talk about overruns, deception, and abuse in relation to infrastruc-
ture spending, although they were of epidemic proportions then as now, and the few who did
use such language were ostracized. However, we cannot solve problems we cannot talk about.
So talking is the first step.
Second, we must arrive at a better understanding and better management of the long, fat tails
of financial and economic risks—the abundance of black swans—that apply to infrastructure
investment. Risks have so far been as misunderstood and as mismanaged in infrastructure
investment as in the financial markets, with equally devastating outcomes. Methods and data
for better risk assessment and management were presented above.
Third, incentives need to be put straight, so that bad performance is punished and good
performance rewarded, and not the other way around, which is often the case today. Again,
methods for how to do this were described above.
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 365
IX. Conclusions
This article documents a much neglected topic in economics, namely the fact that ex ante
estimates of ventures’ costs and benefits are often very different from actual ex post costs
and benefits. The article shows that such differences between estimated and actual outcomes
are pronounced for large infrastructure projects, where substantial cost underestimates often
combine with equally significant benefit overestimates, rendering cost–benefit analyses of
projects not only inaccurate but biased.
The cause of biased cost–benefit analyses is found to be perverse incentives that encourage
promoters of infrastructure projects to underestimate costs and overestimate benefits in the
business cases for their projects in order to gain approval and funding. But the projects that
are artificially made to look best in business cases are the projects that generate the highest
cost overruns and benefit shortfalls in reality, resulting in a significant trend for ‘survival of
the unfittest’ for infrastructure projects.
The cure to the problem is enforcing an outside view in the planning of new projects and
employing a method called reference class forecasting, based on Daniel Kahneman’s Nobel
Prize-winning theories of decision-making under uncertainty. However, to be effective such
new methodology must be combined with better governance structures with incentives that
reward accurate estimates of costs and benefits and punish inaccurate ones.
Finally, stimulus spending has recently resulted in extra money and attention for in-
frastructure investing. This is placing increased pressure on project delivery. Stimulus
spending—together with rapidly increasing spending on infrastructure in emerging economies
and on information technology in infrastructure—is driving infrastructure investment from
the frying pan into the fire.
References
Akerlof, G. A., and Shiller, R. J. (2009), Animal Spirits: How Human Psychology Drives the Economy, and
Why It Matters for Global Capitalism, Princeton, NJ, Princeton University Press.
Altshuler, A., and Luberoff, D. (2003), Mega-Projects: The Changing Politics of Urban Public Investment,
Washington, DC, Brookings Institution.
American Planning Association. (2005), ‘JAPA Article Calls on Planners to Help End Inaccuracies in Public
Project Revenue Forecasting’, available at http://www.planning.org/newsreleases/2005/ftp040705.htm,
7 April.
Anguera, R. (2006), ‘The Channel Tunnel: An Ex Post Economic Evaluation,’ Transportation Research Part
A,40, 291–315.
Ascher, W. (1978), Forecasting: An Appraisal for Policy-makers and Planners, Baltimore, MD, Johns Hopkins
University Press.
Bok, S. (1979), Lying: Moral Choice in Public and Private Life, New York, Vintage.
Buehler, R., Griffin, D., and MacDonald, H. (1997), ‘The Role of Motivated Reasoning in Optimistic Time
Predictions’, Personality and Social Psychology Bulletin,23(3), 238–47.
Ross, M. (1994), ‘Exploring the ‘Planning Fallacy’: Why People Underestimate their Task Completion
Times’, Journal of Personality and Social Psychology,67, 366–81.
Cliffe, L., Ramsey, M., and Bartlett, D. (2000), The Politics of Lying: Implications for Democracy, London,
Macmillan.
Danish Ministry for Transport and Energy (2006), Aktstykke om nye budgetteringsprincipper (Act on New
Principles for Budgeting), Aktstykke nr. 16, Finansudvalget, Folketinget, Copenhagen, 24 October.
— (2008), ‘Ny anlægsbudgettering p˚
a Transportministeriets omr˚
ade, herunder om økonomistyringsmodel og
risikoh˚
andtering for anlægsprojekter’, Copenhagen, 18 November.
366 Bent Flyvbjerg
Flyvbjerg, B. (1996), ‘The Dark Side of Planning: Rationality and Realrationalit¨
at’, in S. Mandelbaum, L.
Mazza, and R. Burchell (eds), Explorations in Planning Theory, New Brunswick, NJ, Center for Urban
Policy Research Press, 383–94.
— (2005a), ‘Design by Deception: The Politics of Megaproject Approval’, Harvard Design Magazine,22,
Spring/Summer, 50–9.
— (2005b), ‘Measuring Inaccuracy in Travel Demand Forecasting: Methodological Considerations Regarding
Ramp Up and Sampling’, Transportation Research A,39(6), 522–30.
— (2006), ‘From Nobel Prize to Project Management: Getting Risks Right’, Project Management Journal,
37(3), 5–15.
— COWI (2004), Procedures for Dealing with Optimism Bias in Transport Planning: Guidance Document,
London, Department for Transport.
— Bruzelius, N., and Rothengatter, W. (2003), Megaprojects and Risk: An Anatomy of Ambition, Cambridge,
Cambridge University Press.
— Garbuio, M., and Lovallo, D. (2009), ‘Delusion and Deception in Large Infrastructure Projects: Two Models
for Explaining and Preventing Executive Disaster’, California Management Review,51(2), 170–93.
— Skamris Holm, M. K., and Buhl, S. L. (2002), ‘Underestimating Costs in Public Works Projects: Error or
Lie?’, Journal of the American Planning Association,68(3), 279–95.
— — — (2005), ‘How (In)accurate Are Demand Forecasts in Public Works Projects? The Case of Trans-
portation’, Journal of the American Planning Association,71(2), 131–46.
Garett, M., and Wachs,M. (1996), Transportation Planning on Trial:The Clean Air Act and Travel Forecasting,
Thousand Oaks, CA, Sage.
Gilovich, T., Griffin, D., and Kahneman, D. (eds) (2002), Heuristics and Biases: The Psychology of Intuitive
Judgment, Cambridge, Cambridge University Press.
Helm, D. R. (2008), ‘Time to Invest. Infrastructure, the Credit Crunch and the Recession’, Monthly Com-
mentary, 18 December, www.dieterhelm.co.uk
HM Treasury. (2003), The Green Book: Appraisal and Evaluation in Central Government, Treasury Guidance,
London, The Stationery Office.
Hodge, G. A., and Greve, C. (2009), ‘PPPs: The Passage of Time Permits a Sober Reflection’, Economic
Affairs, March, 33–9.
Kahneman, D. (1994), ‘New Challenges to the Rationality Assumption’, Journal of Institutional and Theo-
retical Economics,150, 18–36.
— Lovallo, D. (1993), ‘Timid Choices and Bold Forecasts: A Cognitive Perspective on Risk Taking’, Man-
agement Science,39, 17–31.
Tversky, A. (1979), ‘Prospect Theory: An Analysis of Decisions under Risk’, Econometrica,47, 313–27.
Lovallo, D., and Kahneman, D. (2003), ‘Delusions of Success: How Optimism Undermines Executives’
Decisions’, Harvard Business Review, July, 56–63.
Morris, P. W. G., and Hough, G. H. (1987), The Anatomy of Major Projects: A Study of the Reality of Project
Management, New York, John Wiley and Sons.
Newby-Clark, I. R., McGregor, I., and Zanna, M. P. (2002), ‘Thinking and Caring about Cognitive Inconsis-
tency: When and for Whom does Attitudinal Ambivalence Feel Uncomfortable?’, Journal of Personality
and Social Psychology,82(2), 157–66.
PMI (2006), Code of Ethics and Professional Conduct, Project Management Institute, accessed 22 January
2009 at http://www.pmi.org/PDF/ap_pmicodeofethics.pdf
Priemus, H., Flyvbjerg, B., and van Wee, B. (eds) (2008), Decision-making On Mega-projects: Cost–Benefit
Analysis, Planning, and Innovation, Cheltenham, UK and Northampton, MA, Edward Elgar.
Swiss Association of Road and Transportation Experts (2006), Kosten-Nutzen-Analysen im Strassenverkehr,
Grundnorm 641820, valid from 1 August, Z ¨
urich, Swiss Association of Road and Transportation Experts.
Taleb, N. N. (2007), The Black Swan: The Impact of the Highly Improbable, London, Penguin.
Tijdelijke Commissie Infrastructuurprojecten (2004), Grote Projecten Uitvergroot: Een Infrastructuur voor
Besluitvorming, The Hague, Tweede Kamer der Staten-Generaal.
UK Department for Transport (2006), Changes to the Policy on Funding Major Projects, London, Department
for Transport.
Wachs, M. (1986), ‘Technique vs Advocacy in Forecasting: A Study of Rail Rapid Transit’, Urban Resources,
4(1), 23–30.
Survival of the unfittest: why the worst infrastructure gets built—and what we can do about it 367
Wachs, M. (1989), ‘When Planners Lie with Numbers’, Journal of the American Planning Association,55(4),
476–9.
— (1990), ‘Ethics and Advocacy in Forecasting for Public Policy’, Business and Professional Ethics Journal,
9(1–2), 141–57.
White House (2009), ‘Remarks by the President and the Vice President at Opening of Fiscal Responsibility
Summit’, 2–23-09, Office of the Press Secretary, 23 February.
Williams, W. (1998), Honest Numbers and Democracy: Social Policy Analysis in the White House, Congress,
and the Federal Agencies, Washington, DC, Georgetown University Press.
... Hydropower projects are thus often exposed to significant cost overruns [4][5][6][7][8]. Cost overruns represent a source of uncertainty in hydropower projects and can cause huge losses that are damaging to its stakeholders [9][10][11][12]. Improving the accuracy of estimated costs for a hydropower project is therefore very important. ...
... It is generally claimed that the underlying root causes of cost overruns and benefit shortfalls are due to one of three factors-technical, psychological and politico-economic [10]. Technical factors most commonly manifest in the form of faulty forecasting techniques, lack of experience of the forecasters, limited data and inability to properly predict future occurrences [10,[20][21][22]. ...
... It is generally claimed that the underlying root causes of cost overruns and benefit shortfalls are due to one of three factors-technical, psychological and politico-economic [10]. Technical factors most commonly manifest in the form of faulty forecasting techniques, lack of experience of the forecasters, limited data and inability to properly predict future occurrences [10,[20][21][22]. ...
Article
This paper investigates the potential effects of the use of reference class forecasting on the World Bank's financing decisions, and quantifies the net economic impact of such decisions in the long run. A set of 57 World Bank-financed hydropower projects constructed between 1975 and 2015 was selected based on data availability. The findings show that reference class forecasting can help reduce net losses by preventing some hydropower projects with negative economic net present values from being executed. However, it also leads to the forfeiture of even larger amounts of net economic benefits by causing the rejection of some projects that are found, from ex-post analysis, to be economically worthwhile. Furthermore, because of the increased ex-ante rejection of projects, the loss of potentially economically positive projects from the portfolio of hydro dam projects is greatly increased. The errors in the estimation of economic net present values of these hydropower projects are highly positively correlated to the errors in the estimation of the benefits and only weakly negatively correlated to the errors in the estimation of costs.
... The scope of these challenges is such that individual scientific disciplines and traditional approaches fall short of addressing them in a thorough manner to unequivocally inform policy (Funtowicz & Ravetz, 1994;Larsen et al., 2016;Hoekstra et al., 2018). Any solution to the challenges facing urban water systems will have manifold uncertainties in projected costs, benefits and risks, and this is especially true when large infrastructures are considered (e.g., see Flyvbjerg, 2009 andCrow-Miller et al., 2017, for a general description of the contentious process of cost-benefits assessments of large infrastructures, and for specific cases, see Berkoff, 2003, Since these conflicts are politically perilous situations, many policymakers seek specialized scientific knowledge that is perceived as neutral and unbiased to serve as the basis of making difficult decisions over controversial issues (Schneider & Ingram, 1997). ...
... Such asymmetry is characterized by hegemonic discourses that privilege technical knowledge as infallible, while other kinds of knowledge are disregarded to understand a socio-environmental problem (Schneider & Ingram, 1997;Wesselink et al., 2013). This may result in what Boelens et al. (2019) denominate 'the manufacture of ignorance', understood as the process of cherry-picking facts and knowledge to further one´s position, while discrediting ex-ante competing knowledge without a thorough debate (see also Flyvbjerg, 2009, Moore et al., 2018. In the case of large infrastructures, governments undertake this process often by invoking scientific evidence (Brugnach et al., 2011), which is often presented a-critically by downplaying the inherent risks and uncertainties (Flyvbjerg, 2009), and by presenting it as the only valid frame to understand socio-environmental problems. ...
... This may result in what Boelens et al. (2019) denominate 'the manufacture of ignorance', understood as the process of cherry-picking facts and knowledge to further one´s position, while discrediting ex-ante competing knowledge without a thorough debate (see also Flyvbjerg, 2009, Moore et al., 2018. In the case of large infrastructures, governments undertake this process often by invoking scientific evidence (Brugnach et al., 2011), which is often presented a-critically by downplaying the inherent risks and uncertainties (Flyvbjerg, 2009), and by presenting it as the only valid frame to understand socio-environmental problems. ...
Thesis
Full-text available
This thesis is about a number of rural communities resisting flooding and the eradication of their ancestry, history and culture by opposing the implementation and imposition of a large dam in rural Mexico that would supply water to two large cities. The importance of this case lies in the unlikely odds of not only resisting a State-led, large-scale infrastructure project for almost two decades, but also building a grassroots movement that grew in extent, scope and scale to advocate for a comprehensive water management transformation in Mexico. The scientific analysis of the conflict and this grassroots movement, informally dubbed ‘Temaca’, contributed to several scientific fields including water conflicts, transition management, science-policy processes, socio-hydrology and transdisciplinary action research. The analysis of the case study shows how politics influences science by defining a limited decision space that can only superficially address the serious water problems of large cities. As a result, cities follow a development pathway that may deepen their water problems in the long term. Therefore, water conflicts and grassroots movements play a crucial role in opening the decision space. This thesis demonstrates that through transdisciplinary action research, scientific knowledge can become actionable and relevant; addressing power asymmetries and finding sound alternative water management solutions that are more equitable and sustainable.
... The rapid transformational advances in technologies, increasing demands from stakeholders, and significant disruptions caused by natural disasters present many challenges for managers responsible for ensuring sustainable capabilities and capacities for their organisations are optimised to create value for all stakeholders. Getting the most out of assets that make up the built environment is becoming a focus in many countries as it is no longer viable just by building their way out of capacity problems or asset underperformance due to poor practices (Flyvbjerg, 2009). A 2013 global study of over 400 case studies by the McKinsey Global Institute identified the $350 billion annual infrastructure gap faced by the world will triple to meet the United Nations Sustainable Development Goals targets in 2030. ...
Conference Paper
Full-text available
A built environment can be considered as a complex system with multiple layers and networked organisations, institutions, and users that collectively create value for all parties involved. The rapid transformational advances in technologies, increasing demands from stakeholders, and significant disruptions caused by natural disasters present many challenges for managers responsible for ensuring sustainable capabilities and capacities for their organisations are maintained to optimise value for all stakeholders. In this study, we look at three perspectives that have emerged in response to such challenges in the strategic asset management literature: (i) the dynamic capabilities paradigm, (ii) a holistic systems approach, and (iii) the business model concept. With few exceptions, these multidisciplinary viewpoints have often been treated separately, leading to several limitations for their application in practice. While complex systems are fundamentally deterministic, successful organisations have created complex adaptive systems that exhibit flexibility and resilience in challenging situations. This article will explore the linkages of these perspectives and suggest a business model design that presents effective enablement of different tangible and intangible resources owned or controlled by an organisation and those in the wider networked environment. This enablement will lead to creating and extending the organisation's capability and capacity using its resource base. This article contributes to asset management literature by using established theories to study a distinctly overlapping body of knowledge that applies to asset management in the built environment that is often absent. It is based on a systematic literature review for AM publications between 2014-2021, including a snowballing technique that led to relevant articles prior to the study period. The findings of this study will form part of an ongoing larger research study on optimising value through enhanced asset management capability for the New Zealand built environment.
... The functioning and relevance of infrastructure has been studied along several perspectives. Studies on infrastructure revolve around topics such as the power mechanisms behind infrastructure provision (Reeves, 2017;Rogelja, 2020) or on infrastructure as wellsprings of (state-)power themselves (Meehan, 2014), on aspects such as repair and maintenance (Graham & Thrift, 2007) or the phenomenon of cost-overruns in large infrastructural projects (Flyvbjerg, 2009), but also on the significance of infrastructural projects for regional, urban or rural development and individual wellbeing more generally (Grimes, 2003;Latham & Layton, 2019;Monstadt & Coutard, 2019;Cowie, Townsend & Salemink, 2020;Humer & Granqvist, 2020). To highlight the interdependence between infrastructure and regional development, Addie et al. (2020) recently came up with the notion of 'infrastructural regionalism'. ...
Article
Full-text available
Infrastructure matters for regional development as well as for the individual wellbeing of people. This not only became painstakingly obvious since the outbreak of the Covid-19 pandemic in early 2020. Thus, the phases of ‘lock-down’ during the pandemic became an eye opener for the condition of infrastructural fundaments of our cities and regions. Debates about systemic infrastructure for maintaining the functioning of our societies and economies – in scientific terms ‘Services of General Interest’ or the ‘Foundational Economy’ – received wide societal and political attention since the outbreak of the pandemic. Yet, already before the outbreak of this most severe global health crisis, discourses in applied social sciences have experienced an ‘infrastructural turn’, putting technical, social and green infrastructures into the centre of attention of social research, theory building and dissemination. This has led to different understandings of ‘infrastructure’ coexisting in academic and professional debates today. This introductory paper to the issue on ‘The Geography and Governance of Infrastructure Provision’ aims at giving an overview of current debates about infrastructure provision in Regional Science and Planning while introducing the six papers included in this theme issue of Europa XXI.
... Infrastructure has been mostly considered as the exclusive preserve of the government and governing institutions (Buhr, 2003), However, it has been shown that private companies are both more efficient and profitable than government-run organisations (Megginson and Netter, 2001). One reason advanced for this is that private investors put their own funds at risk while the government only put taxpayers' funds at risk (Flyvbjerg, 2009). It has also been argued that the provision of material infrastructure should be based on a cost-benefit analysis (Edwards, 1992). ...
... Infrastructure has been mostly considered as the exclusive preserve of the government and governing institutions (Buhr, 2003), However, it has been shown that private companies are both more efficient and profitable than government-run organisations (Megginson and Netter, 2001). One reason advanced for this is that private investors put their own funds at risk while the government only put taxpayers' funds at risk (Flyvbjerg, 2009). It has also been argued that the provision of material infrastructure should be based on a cost-benefit analysis (Edwards, 1992). ...
Article
The race against time to attain the Sustainable Development Goals (SDGs) intensifies, with inequality, poor living conditions, and biodiversity threats still prevalent. Achieving the SDGs is constrained by limited resources that require frugal solutions that are affordable, easy-to-use, ecologically sustainable, and socially inclusive. The role of infrastructure companies developing technologies with a frugal orientation that focus on the 17 SDGs must be at the core of efforts, because sustainable infrastructure is critical to the SGDs. This paper examines how such company-efforts foster the SDGs through the lens of frugal innovation. An exploratory multiple case study methodology was used with a 3-step and 4-dimensional evaluation approach to determine what technologies are fostering the SDGs, and their frugal characteristics. The results show that alternative resource and energy innovations are at the core of how infrastructure companies are promoting sustainability and fostering the SDGs. Most cases cluster around ecological contributions (mainly climate and energy), with sustainability and cost-effectiveness being the common characteristics. Implications for theory and practice are discussed, as well implications for policy-making.
... Valued at $1 billion or above, they are "projects of a significant cost that attract a high level of public attention or political interest because of substantial direct and indirect impacts on the community, environment, and budgets" (Dimitriou et al 2013). Because of their extensive reach and years, if not decades, of planning and appraisal, decision-making, planning, and management typically involve many actors with conflicting interests (Flyvbjerg 2009). Although mega-projects should in theory be delivered within a specified planning or spatial framework, they themselves often change existing frameworks. ...
Thesis
This thesis discusses how financialisation influenced the planning of the Vauxhall Nine Elms Battersea Opportunity Area (VNEBOA) and accompanying Northern Line Extension. The United Kingdom, and London particularly, increasingly adopt financialisation as a method to deliver development and infrastructure, in which speculative real estate investments and the infrastructure it demands are converted into financial products for shareholders of private companies. This research was carried out via desktop review of feasibility studies, promotional materials, business cases, and a number of plans relevant to the VNEBOA, plus 11 interviews with developers, consultants, academics, and public sector employees. It found that in the absence of local and central government funding, local planning authorities entrepreneurialise by providing additional services to developers and maximising land value capture. Developers shape their projects based on the most financially viable schemes but promote them under principles of “placemaking.” Lastly, mega-transport projects financed by the public and funded by the private sector act as public guarantee for private project delivery. These findings support claims that financialisation subjugates the public’s best interest in favour of private profits and limits regulatory autonomy of planning authorities.
... An interviewee in our research described this strategy as "showing the project at its best" (Flyvbjerg et al. 2004: 50). It results in an inverted Darwinism, i.e., "survival of the unfittest" (Flyvbjerg 2009b). It is not the best projects that get implemented like this, but the projects that look best on paper. ...
Preprint
Full-text available
Behavioral science has witnessed an explosion in the number of biases identified by behavioral scientists, to more than 200 at present. This article identifies the 10 most important behavioral biases for project management. First, we argue it is a mistake to equate behavioral bias with cognitive bias, as is common. Cognitive bias is half the story; political bias the other half. Second, we list the top 10 behavioral biases in project management: (1) strategic misrepresentation, (2) optimism bias, (3) uniqueness bias, (4) the planning fallacy, (5) overconfidence bias, (6) hindsight bias, (7) availability bias, (8) the base rate fallacy, (9) anchoring, and (10) escalation of commitment. Each bias is defined, and its impacts on project management are explained, with examples. Third, base rate neglect is identified as a primary reason that projects underperform. This is supported by presentation of the most comprehensive set of base rates that exist in project management scholarship, from 2,062 projects. Finally, recent findings of power law outcomes in project performance are identified as a possible first stage in discovering a general theory of project management, with more fundamental and more scientific explanations of project outcomes than found in conventional theory.
Article
Organizational paradoxes persist. In their persistence, they resist closure; we demonstrate how, by using an exemplary project, that of the construction of the Sydney Opera House. By analyzing paradoxes encountered in the construction of a notable contemporary architectural project, we discuss how dialogical interactions enable options to emerge in the form of responses that were not previously evident. Engaging paradoxes dialogically requires accepting rather than denying contradictions, meaning that rather than resolving them in favor of one pole or the other, the contradictions remain in play. Monologic interactions—favoring dominant and singular voices, rather than producing consensus—repress dissent, leading to conflict, through suppressing paradox.
Chapter
Full-text available
In this chapter, the authors explore what more-than-human approaches can contribute to development research, teaching and practice. The authors believe that this work is timely as development studies and practice have yet to engage with more-than-human insights in any significant way. They first develop the concept of more-than-human development before analysing the challenges it poses to how we conceptualize and approach core development concerns such as community and empowerment. They then reflect on the ramifications of the concept for practice and policy, before finally exploring how to incorporate more-than-human approaches into pedagogy.
Chapter
Full-text available
Niccolò Machiavelli, the founder of modern political and administrative thought, made clear that an understanding of politics requires distinguishing between formal politics and what later, with Ludwig von Rochau, would become known as Realpolitik. No such distinction has been employed in the study of rationality. Yet I will argue that distinguishing between formal rationality and real rationality is as important for the understanding of rationality and planning as the distinction between formal politics and Realpolitik has been for understanding politics.
Article
Full-text available
Some argue that almost no projects, including our most treasured ones, would ever be undertaken if some form of deception about costs and benefits weren‘t involved. The Brooklyn Bridge, for instance, had a cost overrun of 100%, the Sydney Opera House of 1,400%. Had the true costs been known, these architectural wonders may not have been built. Deception is necessary for action—and for exquisite design—according to this argument. By systematic comparison of the Guggenheim Bilbao Museum and the Sydney Opera House, and by examples from dozens of other projects, the article demonstrates how seductive, yet precarious, the argument is.
Book
The global financial crisis has made it painfully clear that powerful psychological forces are imperiling the wealth of nations today. From blind faith in ever-rising housing prices to plummeting confidence in capital markets, "animal spirits" are driving financial events worldwide. In this book, acclaimed economists George Akerlof and Robert Shiller challenge the economic wisdom that got us into this mess, and put forward a bold new vision that will transform economics and restore prosperity. Akerlof and Shiller reassert the necessity of an active government role in economic policymaking by recovering the idea of animal spirits, a term John Maynard Keynes used to describe the gloom and despondence that led to the Great Depression and the changing psychology that accompanied recovery. Like Keynes, Akerlof and Shiller know that managing these animal spirits requires the steady hand of government--simply allowing markets to work won't do it. In rebuilding the case for a more robust, behaviorally informed Keynesianism, they detail the most pervasive effects of animal spirits in contemporary economic life--such as confidence, fear, bad faith, corruption, a concern for fairness, and the stories we tell ourselves about our economic fortunes--and show how Reaganomics, Thatcherism, and the rational expectations revolution failed to account for them.