Risk Management Practices in Nigeria Construction Sector and Impact on Project Performance

Authors:

Abstract and Figures

The construction industry in every nation is essential to the growth of the economy and its development. The industry is characterized by complex projects, unpredictable variables, and is dependent on many different stakeholders, which subject projects in this sector to a variety of risks that can have a significant impact on project delivery. Risks in construction projects in Nigeria can lead to cost overruns, schedules not being met, and low quality of the project. The concept of risk management involves the management of identified risks which reduces the likelihood of their occurrence and the consequences of adverse risks. A project may be delivered or deemed successful, but not meet the project performance objectives. The Nigerian construction industry has undergone incredible growth and progress; however, there have been numerous challenges that have prevented project performance, such as a lack of expertise, knowledge gaps, and a drought of experienced personnel. The study examines the various risk management practices and their impact on construction project performance. Project performance implies that the project objectives are met in terms of cost, schedule, and quality. A survey research method was adopted using a questionnaire as the primary instrument for data collection on a five-point Likert scale. The questionnaire was designed to collect data relating to risk management's impact on project performance. The questionnaires were also designed to collect data on risk identification as a risk management practice and its impact on project performance. A total of 85 questionnaires were administered and analyzed. The results from the study indicate a strong relationship between risk management practices and project performance.
Content may be subject to copyright.
Journal of Science & Technology
By The Science Brigade (Publishing) Group 69
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Risk Management Practices in Nigeria Construction Sector and Impact
on Project Performance
By Olaitan Oyekunle
Project Management & Educational Administration, University of Northampton, Northampton, UK
DOI: 10.55662/JST.2024.5204
Abstract
The construction industry in every nation is essential to the growth of the economy and its
development. The industry is characterized by complex projects, unpredictable variables, and
is dependent on many different stakeholders, which subject projects in this sector to a variety
of risks that can have a significant impact on project delivery. Risks in construction projects in
Nigeria can lead to cost overruns, schedules not being met, and low quality of the project. The
concept of risk management involves the management of identified risks which reduces the
likelihood of their occurrence and the consequences of adverse risks. A project may be
delivered or deemed successful, but not meet the project performance objectives. The Nigerian
construction industry has undergone incredible growth and progress; however, there have
been numerous challenges that have prevented project performance, such as a lack of
expertise, knowledge gaps, and a drought of experienced personnel. The study examines the
various risk management practices and their impact on construction project performance.
Project performance implies that the project objectives are met in terms of cost, schedule, and
quality. A survey research method was adopted using a questionnaire as the primary
instrument for data collection on a five-point Likert scale. The questionnaire was designed to
collect data relating to risk management’s impact on project performance. The questionnaires
were also designed to collect data on risk identification as a risk management practice and its
impact on project performance. A total of 85 questionnaires were administered and analyzed.
The results from the study indicate a strong relationship between risk management practices
and project performance.
Journal of Science & Technology
By The Science Brigade (Publishing) Group 70
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Keywords: Risk Management, Project Performance, Risk Identification, Risk Assessment,
mitigation strategies, and Construction Sector.
1.0 Introduction
The construction industry in every nation is essential to the growth of the economy and its
development (Okolie et al., 2020). The industry is characterized by complex projects,
unpredictable variables, and is dependent on many different stakeholders, which subject
projects in this sector to a variety of risks that can have a significant impact on project delivery
(Luo et al., 2017). In Nigeria, the significance of effective risk management practices in the
construction industry is more crucial than ever, considering the nation’s rapidly urbanizing
and expanding infrastructure (Muhammed et al., 2015).
Risk can be defined as an unanticipated occurrence or situation that could have an impact on
the project's goals beneficially or detrimentally (George, 2020). Risks are also unknowns that
might or might not happen, but if they do occur and there is no strategy to deal with them,
they can complicate work on the project and jeopardize the success of the project (George,
2020). Recognizing risk in a construction assessing their implications and finding solutions
and remediations to these identified risks is a core concept of risk management (Bayraktar,
2020).
In project management, the incorporation of a robust risk management strategy is vital for
successful project delivery (Petrovic, 2017). Risk management encompasses a series of actions
aimed at increasing the likelihood and positive outcomes of beneficial risks while
simultaneously reducing the likelihood and impact of adverse risks. (PMI, 2018).
Additionally, the successful completion of a project is closely tied to the effectiveness of
project risk management. Unaddressed risks have the potential to deviate projects from their
initial objectives (PMI, 2018). In this context, one of the most important fields of expertise is
risk management. Risk management is a methodical approach that makes it possible to
comprehend and effectively manage both specific risk incidents and total risk (APM, 2019). It
would be difficult for the management team to maximize the project's outcome without the
use of efficient risk management (APM, 2019).
Journal of Science & Technology
By The Science Brigade (Publishing) Group 71
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Due to their high complexity and susceptibility to numerous risks, construction projects have
a substantial impact on project performance (Assaad et al., 2020). Factors such as capacity
strategy, risk management, and logistical difficulties plague the construction sector (Akinosho
et al., 2020). Furthermore, these factors frequently lead to design flaws, completion backlogs,
excessive costs, and disagreements over contract terms (Akinosho et al., 2020). In all these, the
construction sector is poised for significant transformation. The research by Akinosho et al
(2020) supports the fact that there are substantial deviations in large asset-class projects where
costs can soar up to 80% above the initial budget and time requirements can extend by 20%
beyond the planned schedule. Only a few companies complete the projects they undertake
(Akinosho et al., 2020). Despite the prevalent issue of projects exceeding cost and schedule
expectations, merely 28% of companies employ project performance techniques to improve
their performance (PMI, 2017).
Measuring the performance and success of a project are distinct factors, as a project can be
deemed successful without meeting its performance parameters (Venczel et al., 2021). In this
context, Unegbu et al. (2022) found in their research that project performance measures such
as cost, time, and quality are standards that determine construction project outcomes. The
concept of the iron triangle is one of the most widely utilized standards for judging the
successful outcome of a project in terms of the project performance measures of cost, time,
and quality (Unegbu et al., 2022). Another method of assessing the performance measures of
a construction project can also be carried out in terms of the unit costs of materials, the speed
at which the project is delivered, time and cost increases, as well as other quality metrics
(Konchar and Sanvido, 1999).
The goal of this paper is to study the impact of risk management practices on project
performance in the Nigerian construction industry, with a focus on risk identification as one
of the risk management practices. This study aims to advance knowledge of how effective risk
management might influence project results by carefully examining the state of risk
management approaches, their adoption, and their impact. The paper aims to identify
patterns, trends, and best practices that may be used to strengthen risk management methods
by examining quantitative data.
Journal of Science & Technology
By The Science Brigade (Publishing) Group 72
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
2.0 Methodology
The research methodology, according to Sileyew (2019), describes the process the research
must follow to establish an objective and present all findings derived from the data gathered
throughout the research period. Lewis (2015), in his research, also supported the description,
as he stated that it is an approach that defines the steps and techniques used to analyze and
gather information on a particular research topic, as well as how the results are reported in
detail. This section is divided into 4 sections to cover the research design, sampling strategy,
target population, data collection and analysis, and ethical considerations. Serpell et al. (2015)
stated that one of the biggest challenges currently facing the construction industry centers
around how construction companies and stakeholders manage risk and the strategies these
companies adopt to ensure continuous improvement in risk management, as this affects the
performance metrics of meeting budgets, schedules, and quality (Alsulamy et al., 2012; Serpell
et al., 2015). The research emphasizes the need to understand the specific relationship between
risk identification as a risk management practice and construction project performance in the
Nigerian construction sector, as discussed in the literature review.
2.1 Research Design
This research will utilize a quantitative research design with structured questionnaires as the
primary instrument for data collection. This method was selected as the opinions of the
respondents regarding several variable categories are required by the study to establish the
variables' relevance and arrangement (Unegbu et al., 2022). Quantitative information on
important project performance metrics, such as cost overruns, schedule delays, and quality
alterations, will also be gathered through the survey (Alsulamy et al., 2012).
The purpose of the surveys is to collect quantitative information on risk management
practices, with a particular focus on risk identification and mitigation strategies, as well as
how these practices are being applied in the Nigerian construction industry (Ugwu et al.,
2019). Structured questionnaires were designed for this survey as they are intended to get
targeted and precise details regarding the research problem (Aithal and Aithal, 2020). A Likert
scale survey was employed in this research to evaluate the dependent variable of project
performance and the independent variable of risk identification as a risk management practice
Journal of Science & Technology
By The Science Brigade (Publishing) Group 73
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
(Al-Shibly et al., 2013). A four-page questionnaire was developed for the research, which is
divided into two sections. Section A conveys the respondent’s personal information, role, and
experience in the construction industry. Section B focuses on the impact of risk identification
on project performance, planned budgets, project scheduled time, and quality of project
delivery. Using this methodology, the study seeks to offer a comprehensive and nuanced
understanding of the condition of risk management techniques, with a focus on risk
identification and how they affect project performance in the construction industry in Nigeria.
Descriptive research was used in this research (Ajayi et al., 2022). Regression and correlation
analysis are two statistical techniques that will be used to examine the quantitative data
gathered to find patterns and links between various risk management strategies and project
performance results (Ajayi et al, 2022). With the use of the quantitative approach in this study,
a comprehensive and multifaceted understanding of risk management practices and their
effects on project performance in Nigeria's construction sector would be possible.
2.2 Sampling Strategy
Sampling involves the process of selecting a group of people from a group of people or
organizations to approximate the traits of the entire group (Singh and Masku, et al. 2014). This
research study will involve the use of random and purposeful sampling methods. Purposeful
sampling methods involve picking and choosing any number of people who are particularly
proficient with the subject matter (Palinkas et al., 2015). A random sampling technique will
also be employed to choose a representative sample of construction projects from various
areas for the quantitative phase. Calculations of statistical power will be used to establish the
sample size to guarantee the validity and reliability of the study results. The target population
for this survey would be selected from construction companies operating in the cities of Abuja
(FCT) and Lagos in Nigeria. Abuja was selected due to the concentration of construction
companies grouped into multinationals, locals, and small-scale companies, as well as the
ongoing construction works being carried out to boost urban influx into the city (Kadiri et al.,
2014). Abuja is also the seat of power for the Federal Government of Nigeria, where major
decisions on the development of the country are taken (Elaigwu, 2006). Lagos, the former
capital of Nigeria, was selected for this research due to the heavy investments by both
Journal of Science & Technology
By The Science Brigade (Publishing) Group 74
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
government and private entities in building and urban renewal projects (Hamukoma et al.,
2019). The population would consist of construction professionals in these companies,
including managing directors, construction managers, project managers, and construction
experts, with the concentration being mostly those with at least 5 years of experience in the
construction industry (Ajayi et al., 2022). Referencing Kululanga and Kuocha (2010), a total
of 84 questionnaires would be administered. More so, the companies will consist of
multinational as well as local construction companies (Kadiri et al., 2014).
2.3 Data Collection and Analysis
The process of gathering data will be meticulously organized and carried out to guarantee the
accuracy and legitimacy of the information. Standardized survey procedures will be used for
the quantitative phase, and the data gathered will be arranged in a manner that allows for
concise evaluation. Considering the intricacy of the construction sector and the unique
obstacles encountered in Nigeria, a comprehensive plan for data collection and analysis is
required to achieve incisive and thorough outcomes. Primary data collection methods will be
utilized in this study. Primary data collection methods include the use of structured
questionnaires (Nayak and Narayan, 2019). The data collection will be conducted using the
Joint Information Systems Committee (JISC) online surveys (JISC, 2023). Survey questions will
be uploaded using the JISC online survey platform and distributed via a link generated on the
platform to the identified respondents. In addition to the collection of responses, the data will
be exported and analyzed using standard analysis methods.
2.4 Ethical Considerations
Ethical considerations will be crucial in this research to safeguard the privacy of the
participants and confidentiality (Thompson et al., 2021). Abrar and Sidik (2019) stated that
researchers must take ethical considerations into account to limit harm, uphold respondents'
privacy, and advance compassion. The risks involved in this research for the participants will
be their exposure and privacy in terms of their responses to the survey. Every participant will
be asked for their informed consent before any data is shared, and their personal information
Journal of Science & Technology
By The Science Brigade (Publishing) Group 75
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
will be kept anonymous. The questionnaires will contain relevant information about the
research being carried out, including the objectives, dissertation purpose, and confidentiality
of their responses. To maintain the study's ethical integrity and legitimacy, it will conform to
the standards and guidelines established by the University of Northampton. Data collection
in this research shall be carried out using Joint Information Systems Committee (JISC) online
surveys. JISC provides a safe platform for data collection and storage as they are ISO 27001
certified for data security and comply with the EU General Data Protection Regulation
(GDPR) (JISC, 2023).
3.0 Results and Discussion
3.1 Response Rate
This section focuses on the participant response rate and demographic features of the
participants based on the survey questionnaires for this research. The response rate in this
research study indicates that out of the potential participants approached, 85 responded to
the survey on assessing the impact of risk management practices on project performance in
the Nigerian construction industry. Table 1 illustrates the distribution of participants based
on their roles in the construction industry and their years of experience.
Table 1. Distribution of Participants
Role
Frequency Count
Percentage (%)
Project Manger
32
39.0
Contractor
18
21.0
Construction Engineer
11
13.0
Supervisor
20
24.0
Planning Engineer
4
5.0
Total
85
100.0
Experience
Less than 5 years
18
21.0
5-10 years
35
41.0
10-15 years
29
34.0
20-25 years
3
4
Above 25 years
0
0.0
Total
85
100.0
Journal of Science & Technology
By The Science Brigade (Publishing) Group 76
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
3.1.1 Distribution of participants based on roles
From the data collected from the survey as illustrated in Table 1, 32 participants (39.0%) are
project managers, 18 participants (21.0%) are contractors, 11 participants (13.0%) are
construction engineers, 20 participants (24.0%) are supervisors, and 4 participants (5.0%) are
planning engineers. These percentages demonstrate the varying representation of roles within
the respondent pool. For instance, project managers comprise the largest segment, followed
by supervisors, while planning engineers have the smallest representation. The demographic
information also includes the participants' years of experience within the industry, although
this information is not explicitly provided in the table. To further buttress the response rate,
this distribution may have implications for the study findings and interpretations. For
instance, the higher representation of project managers might mean that the perspectives or
experiences shared in the survey could be more skewed towards managerial insights,
potentially influencing the perceived impact of risk management practices on project
performance. Similarly, the smaller representation of planning engineers might limit the
depth of insights from this particular role. However, the lower response rate from planning
engineers signifies a limitation. Nevertheless, it remains crucial to comprehend how diverse
roles and experiences within the construction industry could potentially influence perceptions
and outcomes concerning risk management practices and project performance in Nigeria. This
limitation does not diminish the significance of exploring the impact of these variables on the
industry.
3.1.2 Distribution of participants based on years of experience
Similarly in Table 1, the distribution of participants in the survey based on their years of
experience in the construction industry shows that 18 participants (21.0%) had less than 5
years of experience, 35 participants (41.0%) had 5 to 10 years of experience, 29 participants
(34.0%) had 10 to 15 years of experience, 3 participants (4.0%) had 20 to 25 years of experience.,
and finally none had more than 25 years of experience. This breakdown showcases the varying
levels of experience among the respondents. Most participants possess between 5 and 10 years
of experience, constituting the largest segment, followed by those with 10 to 15 years of
experience. However, there is a notably smaller representation of individuals with 20 to 25
years of experience, and no respondents reported having more than 25 years of experience in
the construction industry. This distribution illuminates the composition of the participant
Journal of Science & Technology
By The Science Brigade (Publishing) Group 77
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
pool concerning their tenure in the construction field, which is essential when considering
how different experience levels might influence their perspectives on risk management
practices and project performance in the Nigerian construction sector.
3.2 Risk Identification and Analysis of the Current Risk Management Practices in the Nigerian
Construction Sector.
Figure 2 illustrates the awareness levels of employees regarding risks and risk management
practices across different hierarchical tiers within the organization.
Figure 2: Awareness Levels of Employees Regarding Risks and Risk Management Practices
Figure 2 shows a 73% awareness rating for top management, 69% for middle management,
63% for skilled workers level, and 28% for semi-skilled workers’ level. This depiction
showcases varying levels of awareness among different employee categories within the
organizational structure. Top and middle management exhibit higher awareness levels
compared to skilled and semi-skilled workers. Such disparities in awareness across
hierarchical levels could significantly impact the implementation and effectiveness of risk
management practices within the organization.
3.2.1 Assessment of risk identification as a feasible risk management practice for planning stages in
construction projects
Table 2 analyzes risk identification as a feasible risk management practice for planning
stages in construction projects based on the survey conducted.
Journal of Science & Technology
By The Science Brigade (Publishing) Group 78
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Role
Mean
SD
RII
F
Sig.
Project Manager
4.03
1.402
0.806
Contractor
4.11
1.278
0.822
Construction Engineer
4.09
1.578
0.818
0.650
0.663
Supervisor
4.05
1.433
0.810
Planning Engineer
4.75
0.500
0.950
4.07
1.370
0.814
Table 2. Risk Identification as a Feasible Risk Management Practice for Planning Stages of
Construction Projects
Table 2 discloses the mean ratings given by different stakeholders (roles) regarding the
feasibility of risk identification as a risk management practice during the planning stages of
construction projects. The planning engineer had the highest mean score of 4.75, suggesting
that planning engineers rated risk identification as highly feasible compared to other roles in
the construction project. Similarly, contractor, construction engineer, project manager, and
supervisor mean scores range from 4.03 to 4.11, indicating a moderately high perception of
feasibility for risk identification as a risk management practice during the planning stages.
The standard deviation of the planning engineer shows a remarkably low SD of 0.500,
signifying high agreement among planning engineers regarding the feasibility of risk
identification during the planning stages, more so among the contractor, construction
engineer, project manager, and supervisor; these stakeholders have SD values ranging from
1.278 to 1.578, indicating slightly more variability in perceptions compared to the planning
engineer.
The analysis of the RII provides a percentage-based representation of importance among the
stakeholder groups. The planning engineer RII value of 0.950 indicates the highest relative
importance among the roles, suggesting that planning engineers' opinions significantly
contribute to the overall perceived feasibility of risk identification. Similarly, the contractor,
Journal of Science & Technology
By The Science Brigade (Publishing) Group 79
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
construction engineer, project manager, and supervisor had RII values ranging from 0.806 to
0.822, suggesting a relatively lower but still substantial contribution to the overall perception.
Finally, the ANOVA test for statistically significant differences in mean ratings among
different stakeholder groups revealed df (degrees of freedom) with (5, 80) indicating that there
were 5 groups (roles) across responses. The F-value of 0.650 indicates the ratio of the variance
between group means to the variance within groups. Hence, the lower F-value suggests that
the differences between group means are relatively small compared to the variation within
each group. Finally, the p-value obtained from the ANOVA test is 0.663, which is higher than
the common significance level of 0.05. This suggests that there isn't sufficient evidence to reject
the null hypothesis, indicating no significant difference in perceptions regarding the
feasibility of risk identification among the stakeholder groups.
In summary, while planning engineers rated risk identification as highly feasible during the
planning stages, all stakeholder groups generally perceived it as feasible, with no statistically
significant differences among their perceptions.
3.2.2 Types of risk identification techniques utilized in construction projects
Table 3 showcases the mean scores, standard deviations, Relative Importance Index (RII), and
rankings for different types of risk identification techniques utilized in construction projects.
Table 3. Types of Risk Identification Techniques Utilized in Construction Projects
Role
Mean
SD
RII
rank
Brainstorming
0.67
0.471
0.788
1st
Delphi Techniques
0.23
0.425
0.271
6th
Interview or Expert Opinion
0.60
0.492
0.706
3rd
Checklist
0.36
0.483
0.424
5th
Project Documentation Review
0.65
0.479
0.765
2nd
Past experience
0.6
0.492
0.706
3rd
Swot Analysis
0.47
0.502
0.553
4th
Journal of Science & Technology
By The Science Brigade (Publishing) Group 80
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Table 3 reveals that the brainstorming technique received the highest mean score of 0.67,
indicating that respondents considered brainstorming as the most effective or commonly used
risk identification technique in construction projects, with an RII of 0.788, indicating the
highest relative importance among the techniques based on the scale used. Followed by the
project documentation review, which obtained a mean score of 0.65, ranking closely after
brainstorming with an RII of 0.765, indicating substantial importance and is also highly
utilized or perceived as effective. Subsequently, interview or expert opinion and past
experience techniques received mean scores of 0.60, suggesting they are similarly perceived
as effective with an RII of 0.706. SWOT Analysis techniques received low mean scores of 0.47,
indicating average perceived effectiveness or utilization compared to others with 0.553.
Finally, checklist and Delphi techniques received the lowest mean scores of 0.36 and 0.23,
respectively, suggesting they are perceived as less utilized or less effective compared to other
techniques with RII values of 0.424 and 0.271, respectively). This indicates a lower relative
importance compared to others.
The brainstorming, project documentation review, interview or expert opinion, and past
experience techniques have SD values ranging from 0.471 to 0.492, indicating a moderate
agreement among respondents regarding their effectiveness or utilization. While checklist,
SWOT analysis, and Delphi techniques have SD values ranging from 0.425 to 0.502, suggesting
slightly more variability in perceptions among respondents. The ranking depicts the order of
perceived effectiveness or utilization of the risk identification techniques as assessed by the
respondents. Brainstorming ranks first, followed closely by Project Documentation Review
(2nd), Interview or Expert Opinion and Past Experience (tied for 3rd), SWOT Analysis (4th),
Checklist (5th), and Delphi Techniques (6th).
From the foregoing, brainstorming, project documentation review, interview or expert
opinion, and past experience are perceived as the most commonly used or effective risk
identification techniques in construction projects. Checklist, SWOT analysis, and Delphi
techniques are perceived as less utilized or less effective compared to others based on
respondents' ratings. There's relatively moderate agreement among respondents regarding
the effectiveness or utilization of these techniques, with some variability in perceptions
Journal of Science & Technology
By The Science Brigade (Publishing) Group 81
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
observed for certain methods. Acknowledging the effectiveness of these techniques aligns
with a comprehensive risk management approach (Tepeli, 2023). As brainstorming and expert
opinions were highly rated, organizations should encourage leadership support for
collaborative risk identification sessions. This is consistent with the literature emphasizing the
role of leadership commitment in risk management success (Ubani et al., 2015). The lower
ratings for techniques like Delphi and SWOT analysis may indicate a need for training or
familiarization with these methods. Organizations should consider providing training to
ensure diverse techniques are employed effectively (Kadiri et al., 2014). Hence, the findings
affirm the importance of collaborative techniques and effective risk management practices in
the construction industry. The study echoes the literature's emphasis on proactive risk
identification, providing practical insights for project managers and stakeholders. However,
further exploration into the specific factors influencing technique preferences and familiarity
could enhance the understanding of risk management dynamics in construction projects.
3.2.3 Utilization of risk management practices in risk identification in construction projects
Figure 3 below illustrates the results of the survey regarding the distribution of responses
concerning the effective utilization of risk management practices in identifying risks in
Nigerian construction projects.
Figure 3: Effective Utilization of Risk Management Practices in the Identification of Risks
in Construction Projects
Journal of Science & Technology
By The Science Brigade (Publishing) Group 82
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Figure 3 reveals that 32 responses (37.6%) state that it is highly effective, 37 responses (43.5%)
perceive that it is quite effective, 8 responses (9.4%) believed it is moderately effective, seven
responses (8.2%) agree it slightly effective, and one response (1.2%) perceive it not to be
effective. This distribution showcases how respondents rated the effectiveness of using risk
management practices for identifying risks in construction projects in Nigeria. Most
respondents perceive the utilization of these practices as highly or quite effective, with fewer
indicating moderate, slight, or no effectiveness in this regard. This finding aligns with existing
literature (Obondi, 2022), which highlights the importance of collaborative approaches like
brainstorming in identifying diverse risks. Additionally, project documentation review,
interviews, and past experience were also perceived as effective, emphasizing the significance
of historical data and expert insights (Tepeli, 2023). The preference for brainstorming
resonates with King (2016) emphasis on collaborative methods. The acknowledgment of
project documentation and expert opinions aligns with Tepeli (2023) recommendations for
comprehensive risk identification.
3.3 Impact of Risk Management Practices on Project Performance in the Nigerian
Construction Sector
The results from the survey regarding the impact of risk management practices on project
performance in the Nigerian construction sector are depicted in Table 4. The parameters
surrounding performance in the survey focus on cost, schedule, and quality of delivery.
Table 4. Effects of Risk Management Practices on Project Performance (Cost, Schedule, and
Delivery Quality
Factors
Mean
SD
RII
Rank
Risk identification * construction project
Performance
Cost
4.29
0.919
0.858
3rd
Schedule
4.33
0.86
0.866
2nd
Quality of Delivery
4.40
0.885
0.880
1st
Project failures * inefficient risk
Cost Overruns
3.88
1.192
0.776
2nd
Schedule
3.83
1.19
0.766
3rd
Journal of Science & Technology
By The Science Brigade (Publishing) Group 83
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Quality of Delivery
3.99
1.173
0.798
1st
Effective risk management practices contribute to
the overall performance of construction projects in
Nigeria
Time
4.22
1.142
0.844
2nd
Cost
4.27
1.142
0.854
1st
Quality of Delivery
4.1
1.284
0.820
3rd
Effective risk management practices contribute to the overall performance of construction
projects in Nigeria
On risk identification in construction project performance, the mean score for the impact of
risk identification on project cost is 4.29, with a standard deviation of 0.919. This places it as
the 3rd-ranked factor in terms of impact on cost. The Relative Importance Index (RII) is 0.858,
indicating a substantial impact. The mean score for the impact of risk identification on the
project schedule is 4.33, with a standard deviation of 0.86. It ranks 2nd in terms of impact on
schedule, and the RII is 0.866, signifying a considerable impact. The mean score for the impact
of risk identification on the quality of project delivery is 4.40, with a standard deviation of
0.885. It ranks 1st in terms of impact on quality, and the RII is 0.880, indicating the highest
impact among the factors considered.
Similarly, on project failures in inefficient risk management, the mean score for the impact of
inefficient risk management on cost overruns is 3.88, with a standard deviation of 1.192. It
ranks 2nd in terms of impact on cost overruns, and the RII is 0.776, indicating a significant
impact. The mean score for the impact of inefficient risk management on the project schedule
is 3.83, with a standard deviation of 1.19. It ranks 3rd in terms of impact on schedule, and the
RII is 0.766, signifying a notable impact. The mean score for the impact of inefficient risk
management on the quality of project delivery is 3.99, with a standard deviation of 1.173. It
ranks 1st in terms of impact on quality, and the RII is 0.798, indicating the highest impact
among the factors considered.
Regarding the overall impact of effective risk management practices on project performance,
the mean score for the overall impact of effective risk management practices on project time
is 4.22, with a standard deviation of 1.142. It ranks 2nd in terms of impact on time, and the RII
is 0.844, suggesting a considerable impact. The mean score for the overall impact of effective
Journal of Science & Technology
By The Science Brigade (Publishing) Group 84
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
risk management practices on project cost is 4.27, with a standard deviation of 1.142. It ranks
first in terms of impact on cost, and the RII is 0.854, indicating the highest impact among the
factors considered. The mean score for the overall impact of effective risk management
practices on project delivery is 4.1, with a standard deviation of 1.284. It ranks 3rd in terms of
impact on delivery, and the RII is 0.820, signifying a notable impact. These findings support
existing literature that emphasizes the significance of risk identification in cost and schedule
management (Luskova & Dvorak, (2019). Identifying risks early allows for effective planning
and mitigation, reducing the likelihood of cost overruns and schedule delays. Mhetre et al.
(2016) stress the importance of risk management in achieving project quality, while Okolie et
al. (2020) emphasize its role in cost and schedule management. The results align with these
assertions, emphasizing the multi-faceted impact of risk identification.
In summary, the results suggest that effective risk management practices, particularly in the
identification of risks, significantly influence project performance in terms of cost, schedule,
and quality of delivery. The impact of these practices is most pronounced in enhancing the
quality of project delivery, followed by schedule and cost management. The results
underscore the significance of implementing resilient risk management strategies to achieve
favorable results in construction projects within Nigeria.
Table 5. Influence of Effective Risk Management Practices on Construction Project
Performance
Factors
Mean
SD
Efficient risk management practices reduce the likelihood of risks in
construction projects’ lifecycle
4.05
0.63
Construction projects are more likely to fail in Nigeria if risk
management practices are not effectively utilized
4.20
1.34
Risk identification is an important aspect of the construction project
lifecycle
4.33
0.87
Proper and effective risk identification can mitigate project failure
(cost overruns, not meeting time schedules, and non-adherence to
project quality
4.12
1.04
Average
4.18
0.97
Journal of Science & Technology
By The Science Brigade (Publishing) Group 85
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
The analysis presented in Table 5 provides valuable insights into stakeholders' perceptions
regarding the importance of risk management practices in the context of construction projects
in Nigeria. Notably, the mean scores and standard deviations reveal the degree of influence
attributed to specific statements. The statement asserting that "Efficient risk management
practices reduce the likelihood of risks in construction projects’ life cycle" receives a mean
score of 4.05, indicating a moderate level of influence and highlighting the perceived
significance of efficient risk management in mitigating risks. Similarly, the statement asserting
that "Construction projects are more likely to fail in Nigeria if risk management practices are
not effectively utilized" obtains a substantial mean score of 4.20, underlining the widespread
recognition among stakeholders that effective risk management is pivotal in preventing
project failures.
The statement affirming that "Risk identification is an important aspect in the construction
project lifecycle" receives a high mean score of 4.33, emphasizing the paramount importance
of identifying and managing risks throughout the project's life. Additionally, the statement
proposing that "Proper and effective risk identification can mitigate project failure (cost
overruns, not meeting time schedules, and non-adherence to project quality)" attains a mean
score of 4.12, reinforcing the perceived role of robust risk identification in averting various
dimensions of project failure. The overall findings underscore stakeholders' strong belief in
the crucial role of effective risk identification and management practices in ensuring the
success and resilience of construction projects in Nigeria.
The statement suggesting that construction projects are more likely to fail in Nigeria without
effective risk management practices received a substantial mean score. This underscores the
significance of robust risk management in preventing project failures. While the statement on
mitigating project failure through proper risk identification ranked slightly lower, it still
received a notable mean score and RII, indicating the perceived importance of risk
identification in averting project failures. The statement on the reduction of the likelihood of
risks through efficient risk management practices received a moderate level of influence,
ranking 4th among the factors considered.
In essence, the findings confirm the vital importance of effective risk management practices,
specifically in the identification of risks, in shaping the performance of construction projects
Journal of Science & Technology
By The Science Brigade (Publishing) Group 86
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
in Nigeria.The findings underscore the importance of proactive risk management in
mitigating project failures and enhancing overall project success.
Table 6. Univariate Test on Influence of Risk Management Practices on Project
Performance Metrics (Cost, Schedule, and Delivery Quality)
Source
Type III Sum of
Squares
Df
Mean
Square
F
Sig.
Corrected Model
51.14a
2
25.57
9.53
.000
Intercept
11.000
1
11.000
3.903
.000
Risk identification and the overall performance
10.064
1
10.064
1.712
.003
Risk identification and alignment with planned
project budgets.
13.170
1
13.170
1.756
.008
Risk identification and the adherence to
technical specifications in construction projects
12.363
1
12.363
1.545
.007
Risk identification and the capacity to adhere to
project delivery quality
11.371
1
11.371
1.707
.000
Error
10.718
81
Table 6 presents the results of a univariate test examining the impact of risk identification on
various aspects of construction project performance in Nigeria. The corrected model in the
univariate analysis is a statistical model that has been adjusted to consider the simultaneous
effects of multiple variables, providing a more accurate assessment of the relationship
between the independent variables (risk identification) and the dependent variable (overall
performance of construction projects) while accounting for other relevant factors. The
corrected model had type III sum of squares, value (51.14) which represents the variation in
the dependent variable (for instance overall performance of construction projects) that can be
attributed to the independent variables (risk management practice) in the model while
accounting for the influence of other variables. The number of degrees of freedom associated
with the corrected model (2 in this case). The mean square-like is Type III sum of squares
Journal of Science & Technology
By The Science Brigade (Publishing) Group 87
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
divided by its degrees of freedom (25.57). Moreover the F-statistic (9.53) tests revealed the
overall significance of the model, evaluating whether there is a significant relationship
between the independent variables (risk identification practices) and the dependent variable
(overall performance). The p-value (0.000) associated with the F-statistic indicates the
probability of obtaining the observed results if the null hypothesis (no relationship between
variables) is true.
Similarly, the intercept represents the baseline value of the dependent variable when all
predictors (risk identification variables) are zero. The type III sum of squares: had shown the
amount of variability (11.000) in the dependent variable that can be attributed to the intercept
term. The degrees of freedom associated with the intercept (1 in this case), with mean square
(11.000). The F-statistic (3.903) that the model with the intercept term is significantly better
than a model without it at a p-value (0.000)
Hence, both the corrected model and intercept are statistically significant, indicating that risk
identification variables play a significant role in explaining variations in the overall
performance of construction projects. The intercept signifies a baseline level of performance
when risk identification factors are at their minimum. These results enhance the overall
validity and reliability of the model in capturing the relationship between risk identification
and project performance.
The study interprets the findings with respect to the stated hypotheses as follows:
H1: There is a significant impact between the extent of risk identification and the overall
performance of construction projects in Nigeria.
The analysis type III sum of squares, revealed the amount of variation in the overall
performance of construction projects that can be attributed to the extent of risk identification
to be 10.064, with 1 degree of freedom, indicating that one predictor variable (risk
identification extent) is being considered. The mean square provides an average measure of
the explained variability of type III sum of squares (10.064). The F-value of 1.712 is a ratio of
variances, testing whether the variability in overall performance explained by risk
identification is significantly greater than what would be expected by chance. The p-value of
0.003 is less than the commonly used significance level of 0.05.
Journal of Science & Technology
By The Science Brigade (Publishing) Group 88
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
The Type III Sum of Squares and associated F-statistic suggest that risk identification explains
a certain amount of variability in overall project performance. The low p-value (0.003 < 0.05)
indicates that the observed relationship is statistically significant. There is strong evidence to
accept the hypothesis (H1) that there is a significant impact between the extent of risk
identification and the overall performance of construction projects in Nigeria. The mean
square provides an average measure of the impact of risk identification on overall
performance. This finding resonates with previous studies emphasizing the crucial role of risk
management in ensuring technical compliance (Imoni et al., 2023).
In the context of overall performance, this analysis specifically focuses on the contribution of
risk identification extent. It suggests that the extent to which risks are identified has a
statistically significant impact on the overall success of construction projects in Nigeria. The
findings support the idea that a thorough process of risk identification positively influences
the overall performance of construction projects. Projects that identify and assess risks more
comprehensively are likely to have better overall outcomes.
H2: There is a significant impact between the level of risk identification and the alignment
with planned project budgets.
The result of hypothesis II revealed a type III sum of squares of 13.170 variation in the
alignment with planned project budgets that can be attributed to the level of risk
identification. 1 degree of freedom, indicating that one predictor variable (level of risk
identification) is being considered. The mean square is the Type III Sum of Squares divided
by its degrees of freedom, providing an average measure of the explained variability which is
still 13.170. The F-value of 1.756 tested whether the variability in budget alignment explained
by risk identification is significantly greater than what would be expected by chance, and the
p-value of 0.008 is less than the commonly used significance level of 0.05.
The Type III Sum of Squares and associated F-statistic suggest that risk identification explains
a certain amount of variability in the alignment with planned project budgets. The low p-
value (0.008) indicates that the observed relationship is statistically significant. There is strong
evidence to accept the hypothesis (H2) that there is significant impact between the level of risk
identification and the alignment with planned project budgets in Nigeria. The Mean Square
Journal of Science & Technology
By The Science Brigade (Publishing) Group 89
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
provides an average measure of the impact of risk identification on budget alignment. The
findings suggest that the level of risk identification has a statistically significant impact on the
alignment of projects with planned budgets. This implies that projects with a higher level of
risk identification are more likely to adhere to their planned budgets. The link between risk
identification and project budget alignment can be explained by considering how identifying
and assessing risks comprehensively can lead to better anticipation and mitigation of potential
budgetary challenges. For example, if risks are accurately identified, contingency plans can be
developed, and resources can be allocated more effectively, reducing the likelihood of budget
overruns. The results support the notion that a higher level of attention to risk identification
positively influences the alignment of projects with planned budgets. This finding resonates
with established literature, particularly emphasizing the intrinsic relationship between risk
management and project quality (Bayraktar, 2020).
H3: There is a significant impact between the effectiveness of risk identification and the
adherence to technical specifications in construction projects.
On the third hypothesis, considering the type III sum of squares revealing the amount of
variation in the adherence to technical specifications in construction projects that can be
attributed to the effectiveness of risk identification to be 12.363. 1 degree of freedom,
indicating that one predictor variable (effectiveness of risk identification) is being considered.
This is the Type III Sum of Squares divided by its degrees of freedom, providing an average
measure of the explained variability to still be maintained at 12.363. The F-value of 1.545 is a
ratio of variances, testing whether the variability in adherence to technical specifications
explained by the effectiveness of risk identification is significantly greater than what would
be expected by chance with the p-value of 0.007 less than the commonly used significance
level of 0.05.
The Type III Sum of Squares and associated F-statistic suggest that the effectiveness of risk
identification explains a certain amount of variability in the adherence to technical
specifications in construction projects. The low p-value (0.007) indicates that the observed
relationship is statistically significant. There is strong evidence to accept the hypothesis (H3)
that there is significant impact between the effectiveness of risk identification and the
Journal of Science & Technology
By The Science Brigade (Publishing) Group 90
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
adherence to technical specifications in construction projects in Nigeria. The Mean Square
provides an average measure of the impact of the effectiveness of risk identification on
adherence to technical specifications.
The findings suggest that the effectiveness of risk identification has a statistically significant
impact on the adherence to technical specifications in construction projects. This implies that
projects with more effective risk identification are more likely to adhere to technical
requirements. This aligns with previous research emphasizing the financial implications of
effective risk management (Nayak et al., 2019), suggesting that projects with comprehensive
risk identification processes are better equipped to align with budgetary constraints.The link
between risk identification and adherence to technical specifications can be explained by
considering how identifying and managing risks effectively can lead to better planning and
execution of technical aspects. For example, if potential risks to technical specifications are
identified early, appropriate measures can be taken to mitigate these risks, ensuring better
adherence to specifications. Thus, the results support the idea that the effectiveness of risk
identification positively influences the adherence to technical specifications in construction
projects.
H4: There is a significant impact between the effectiveness of risk identification and the
capacity of construction projects to adhere to project delivery quality.
Finally, on H4, the type III sum of squares expressed the variation in the capacity of
construction projects to adhere to project delivery quality to be 11.371, which can be attributed
to the effectiveness of risk identification. 1 degree of freedom, indicating that one predictor
variable (effectiveness of risk identification) is being considered. The mean square is also
maintained as the Type III Sum of Squares since the degree of freedom is 1. The F-value of
1.707 is a ratio of variances, testing whether the variability in the capacity of construction
projects to adhere to project delivery quality explained by the effectiveness of risk
identification is significantly greater than what would be expected by chance. The p-value of
0.000 is less than the commonly used significance level of 0.05.
The Type III Sum of Squares and associated F-statistic suggest that the effectiveness of risk
identification explains a certain amount of variability in the capacity of construction projects
Journal of Science & Technology
By The Science Brigade (Publishing) Group 91
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
to adhere to project delivery quality. The very low p-value (0.000) indicates that the observed
relationship is highly statistically significant. There is strong evidence to accept the hypothesis
(H4) that there is no significant impact between the effectiveness of risk identification and the
capacity of construction projects to adhere to project delivery quality in Nigeria. The Mean
Square provides an average measure of the impact of the effectiveness of risk identification
on the capacity to adhere to project delivery quality.
The findings suggest that the effectiveness of risk identification has a highly significant impact
on the capacity of construction projects to adhere to project delivery quality. This aligns with
literature emphasizing the relationship between risk management and project quality
(Obondi, 2022), suggesting that projects with efficient risk identification processes
demonstrate a higher capacity to maintain quality standards throughout the delivery phase.
This implies that projects with more effective risk identification are more likely to maintain
high-quality standards in project delivery. The link between risk identification and project
delivery quality can be explained by considering how identifying and managing risks
effectively can lead to better planning, resource allocation, and execution, reducing the
likelihood of issues that may compromise project delivery quality. The results strongly
support the idea that the effectiveness of risk identification positively influences the capacity
of construction projects to adhere to project delivery quality.
The results of the univariate test strongly support all four hypotheses. There is a statistically
significant impact between the extent or effectiveness of risk identification and various aspects
of construction project performance, including overall performance, alignment with project
budgets, adherence to technical specifications, and capacity to adhere to project delivery
quality. These findings highlight the crucial role of effective risk identification in influencing
different facets of construction project success in Nigeria. The study elucidates the
multifaceted influence of risk identification on distinct dimensions of construction project
performance. In terms of "Overall Performance," encompassing a comprehensive evaluation
of project success, the analysis establishes a statistically supported connection between the
extent of risk identification and a project's holistic achievements, including time efficiency and
stakeholder satisfaction. "Budget Alignment" scrutinizes a project's financial discipli ne,
revealing that a higher level of risk identification correlates with improved adherence to
Journal of Science & Technology
By The Science Brigade (Publishing) Group 92
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
planned budgets, underscoring the fiscal prudence associated with thorough risk
management practices. The dimension of "Adherence to Technical Specifications" emphasizes
that effective risk identification enhances a project's ability to conform to prescribed technical
standards, ensuring the maintenance of technical integrity throughout the project lifecycle.
Lastly, the "Capacity to Adhere to Project Delivery Quality" highlights the critical impact of
risk identification on a project's capability to uphold high-quality standards, emphasizing the
pivotal role of meticulous risk identification in guaranteeing the quality of the final project
deliverable. Overall, the study underscores how strategic risk identification positively shapes
diverse aspects of construction project performance. This finding resonates with existing
literature highlighting the importance of knowledge and awareness in successful risk
management (Okolie, 2022). The construction industry's dynamic nature demands continuous
learning and adaptation, and addressing these knowledge gaps is crucial for effective risk
identification and mitigation
4.4 Primary Obstacles and Issues Encountered by Construction Projects in Nigeria
Regarding the Efficient Implementation of Risk Management Practices.
Figure 4 presents the primary obstacles and issues experienced in the Nigerian construction
sector, disrupting the effective utilization of risk management techniques.
Journal of Science & Technology
By The Science Brigade (Publishing) Group 93
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Figure 4: Challenges and Problems of Nigerian Construction Projects Affecting Effective
Utilization of Risk Management Practices
Figure 4 provides insights into the key challenges and problems that construction projects
encounter when implementing efficient risk management techniques. Most respondents
(61.2%) identified knowledge gaps as a key challenge in implementing efficient risk
management techniques. This suggests that there is a perceived deficiency in understanding
or awareness of risk management practices within construction projects. A significant
proportion of respondents (63.5%) pointed to the level of expertise as a challenge. This
indicates that there may be concerns about the competency and skill levels of individuals
involved in the application of efficient risk management techniques. The highest percentage
of respondents (71.8%) highlighted insufficient adherence to operational standards as a
critical challenge. This suggests that there may be issues related to compliance and consistency
in applying established operational standards in the context of risk management practices.
This finding is consistent with the literature emphasizing the importance of standardization
in risk management (Petrovic, 2017). Inconsistent application of operational standards can
undermine the effectiveness of risk management practices and result in project uncertainties.
The identified challenges align with existing literature, emphasizing the importance of
knowledge, expertise, and adherence to standards in effective risk management (Egwunatum
et al., 2022). The data collectively underscores the importance of addressing knowledge gaps,
enhancing expertise levels, and promoting adherence to operational standards as essential
strategies for overcoming challenges in implementing efficient risk management techniques
in construction projects. Addressing these issues could potentially contribute to more effective
and successful risk management practices within the construction industry.
4. Conclusion and Recommendations
Conclusion
The study has provided a comprehensive analysis of various facets of risk management in the
Nigerian construction sector, offering valuable insights into the awareness, perception,
challenges, and impacts of risk management practices. The awareness levels across
hierarchical tiers emphasize the importance of organizational understanding for effective risk
Journal of Science & Technology
By The Science Brigade (Publishing) Group 94
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
management. Top and middle management exhibit higher awareness levels, underscoring the
significance of leadership commitment. This finding underscores the necessity for targeted
awareness programs for skilled and semi-skilled workers to improve overall risk management
effectiveness. Moreso study delves into perspectives on risk identification techniques,
revealing planning engineers' strong belief in the feasibility of risk identification during
planning stages, acknowledges the overrepresentation of project managers, and suggests
future research exploring specific challenges faced by planning engineers, enhancing their
involvement in risk management processes.
The evaluation of risk identification techniques indicates the perceived effectiveness of
collaborative methods like brainstorming, project documentation review, interviews, and
experience. These findings provide practical guidance for integrating effective risk
identification techniques into construction projects. The positive perceptions regarding the
effectiveness of risk management practices align with the literature emphasizing the role of
robust risk management in enhancing project outcomes. The study contributes to existing
literature by offering empirical evidence on the multi-dimensional impact of risk management
on project performance. Notably, the highest mean score for quality underscores the
importance of risk identification in ensuring the quality of project delivery.
The univariate test findings confirm the significant impact of risk identification on various
aspects of construction project performance. These results contribute empirical evidence to
theoretical claims, reinforcing the pivotal role of effective risk identification in project success.
The study highlights the need for targeted awareness programs, training, and leadership
commitment to address identified challenges and optimize risk management practices. The
study contributes significantly to the understanding of risk management practices in the
Nigerian construction sector. The identified challenges, perceptions, and impacts provide a
foundation for further research and practical implementation. By addressing the outlined
suggestions and recommendations, stakeholders can enhance risk management practices,
ultimately improving the success rates of construction projects in Nigeria.
Recommendations
Journal of Science & Technology
By The Science Brigade (Publishing) Group 95
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Organizations in the construction industry stand to benefit from a series of recommendations
derived from the study's insightful findings. Firstly, adopting comprehensive risk
identification practices that encompass techniques such as brainstorming, project
documentation review, interviews, and experiential insights is paramount. Encouraging
leadership support for collaborative risk identification sessions is essential to fostering diverse
perspectives and ensuring a thorough understanding of potential risks. Secondly, the study
underscores the critical role of leadership commitment to risk management. Establishing a
culture of commitment at all levels of the organization, with active support and participation
from top and middle management, is crucial for effective risk management initiatives.
Thirdly, recognizing the dynamic nature of the construction industry, organizations should
implement continuous improvement programs.
These programs should address knowledge gaps, enhance expertise, and promote adherence
to operational standards, thereby facilitating adaptability in a constantly evolving
environment. Additionally, a proactive risk management approach is emphasized,
highlighting the significance of early risk identification and mitigation to prevent project
failures and enhance overall project success. Looking ahead, there is a need for future research
to ensure more balanced representation across various roles within the construction industry,
promoting a comprehensive understanding of risk management perspectives. Targeted
outreach to underrepresented roles, such as planning engineers, is recommended to capture
a broader spectrum of insights.
Moreover, recognizing the limited participation of planning engineers, further research
should explore specific challenges and opportunities for enhancing their engagement in risk
management processes. Understanding their unique perspective can contribute to more
inclusive and effective risk management strategies. Lastly, to address the identified
challenges, including knowledge gaps and expertise concerns, tailored training programs are
recommended. Construction organizations and industry associations are encouraged to
invest in training initiatives that ensure a well-informed and skilled workforce capable of
effective risk management. Overall, these recommendations provide a holistic approach to
bolstering risk management practices in the construction industry and fostering long-term
success.
Journal of Science & Technology
By The Science Brigade (Publishing) Group 96
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
References
Abrar, M. and Sidik, E. J. (2019) Analyzing ethical considerations and research methods in
children research. Journal of Education and Learning (EduLearn). 13(2), PP. 184-193.
Available from:
http://edulearn.intelektual.org/index.php/EduLearn/article/viewFile/6516/6905
[Accessed 15 November 2023].
Aithal, A. and Aithal, P. S. (2020). Development and validation of survey questionnaire &
experimental data a systematical review-based statistical approach. International Journal
of Management, Technology, and Social Sciences (IJMTS). 5(2), pp. 233-251. Available from:
https://mpra.ub.uni-muenchen.de/104830/1/mpra_paper_104830.pdf [Accessed 15
November 2023].
Ajayi, A. A., Oyeyipo, O., Apete, L. A. and Dahunsi, O. S. (2022) Evaluation of Corporate
Social Responsibility of Construction Companies in Lagos State, Nigeria. Journal of
Multidisciplinary Engineering Science and Technology (JMEST). 9(2), pp. 15092-15101.
Available from: https://www.researchgate.net/profile/Akeem-
Ajayi/publication/358912145_Evaluation_of_Corporate_Social_Responsibility_of_Construct
ion_Companies_in_Lagos_State_Nigeria/links/621d18f5b1bace0083a2ff73/Evaluation-of-
Corporate-Social-Responsibility-of-Construction-Companies-in-Lagos-State-Nigeria.pdf.
[Accessed 30 November 2023].
Akinosho, T. D., Oyedele, L. O., Bilal, M., Ajayi, A. O., Delgado, M. D., Akinade, O. O. and
Ahmed, A. A. (2020) Deep learning in the construction industry: A review of present status
and future innovations. Journal of Building Engineering. 32 (101827), pp. 1-14. Available
from https://doi.org/10.1016/j.jobe.2020.101827 [Accessed 28 August 2023].
Al-Shibly, H. H., Louzi, B. M. and Hiassat, M. A. (2013). The impact of risk management on
construction projects success from the employees perspective. Interdisciplinary journal of
contemporary research in business. 5(4), pp. 12-43. Available from:
https://www.researchgate.net/publication/269168693_The_impact_of_risk_management_o
n_construction_projects_success_from_the_employees_perspective [Accessed 15 November
2023].
Journal of Science & Technology
By The Science Brigade (Publishing) Group 97
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Alsulamy, S, Wamuziri, S and Taylor, M (2012) Evaluation of key metrics for measurement
of project performance. In: Procs 28th Annual Association of Researchers in Construction
Management (ARCOM) Conference, Edinburgh, 2012. UK: ARCOM, pp. 1101-1110.
Available from: https://www.arcom.ac.uk/-docs/proceedings/ar2012-1101-
1110_Alsulamy_Wamuziri_Taylor.pdf [Accessed 29 November 2023].
Assaad, R., El-Adaway, I. H. and Abotaleb, I. S. (2020). Predicting project performance in the
construction industry. Journal of Construction Engineering and Management, 146(5), pp. 1-
22. Available from: https://www.researchgate.net/profile/Rayan-H-
Assaad/publication/339497565_Predicting_Project_Performance_in_the_Construction_Indu
stry/links/62166bd4b15a6a210163dc4d/Predicting-Project-Performance-in-the-
Construction-Industry.pdf [Accessed 6 October 2023].
Association for Project Management (APM). (2019). APM Body of Knowledge. 7th ed.
Buckinghamshire: APM.
Bayraktar, O. Y. (2020) Risk management in construction sector. World Journal of Advanced
Research and Reviews. 8(2), pp. 237-243. Available from:
https://doi.org/10.30574/wjarr.2020.8.2.0433 [Accessed 24 August 2023].
Egwunatum, S. I., Anumudu, A. C., Eze, E. C. and Awodele, I. A. (2022) Total quality
management (TQM) implementation in the Nigerian construction industry. Engineering,
Construction and Architectural Management. 29(1), pp. 354-382. Available from:
https://www.researchgate.net/profile/Samuel-
Egwunatum/publication/350480753_Total_quality_management_TQM_implementation_in
_the_Nigerian_construction_industry/links/60951ce5458515d3150066a7/Total-quality-
management-TQM-implementation-in-the-Nigerian-construction-industry.pdf [Accessed 23
September 2023].
Elaigwu, J. I. (2006) The Federal Republic of Nigeria [Online]. Available from:
http://www.forumfed.org/libdocs/Global_Dialogue/Book_2/BK2-C08-ng-Elaigwu-en.pdf
[Accessed 30 November 2023].
George, C. (2020) The Essence of Risk Identification in Project Risk Management: An
Overview. International Journal of Science and Research (IJSR). 9(2), pp. 1553-1557.
Journal of Science & Technology
By The Science Brigade (Publishing) Group 98
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Available from:
https://www.researchgate.net/publication/339593332_The_Essence_of_Risk_Identification
_in_Project_Risk_Management_An_Overview#:~:text=Risks%20are%20uncertainties%2C%2
0that%20may,not%20be%20treated%20with%20levity [Accessed 24 August 2023].
Hamukoma, N., Doyle, N., Calburn, S. and Davis, D. (2019) Lagos: Is it Possible to Fix
Africa’s Largest City?. Discussion Paper no. 3. Johannesburg: The Brenthurst Foundation,
pp. 1-23. Available from:
https://www.thebrenthurstfoundation.org/downloads/discussion-paper-03-2019-lagos-is-
it-possible-to-fix-africa-s-largest-city-.pdf [Accessed 30 November 2023].
Imoni, S., Akande, E. O., Jiya, V. H., Onuzulike, C. and Tiza, M. T. (2023) A Comprehensive
Review of Engineering, Procurement, and Construction in Nigeria. Journal of Management
Studies and Development. 2(03), pp. 226-249. Available from:
https://journal.iistr.org/index.php/JMSD/article/download/382/295 [Accessed 13
October 2023].
Joint Information Systems Committee (JISC) (2023) Online Surveys [Online]. Available from:
https://beta.jisc.ac.uk/online-surveys [Accessed 30 November 2023].
Kadiri, Z. O., Nden, T., Avre, G. K., Oladipo, T. O., Edom, A., Samuel, P. O. and Ananso, G.
N. (2014) Causes and effects of accidents on construction sites (a case study of some selected
construction firms in Abuja FCT Nigeria). IOSR Journal of Mechanical and Civil
Engineering. 11(5), pp. 66-72. Available from:
https://www.academia.edu/download/34668741/J011516672.pdf [Accessed 29 November
2023].
King, S. (2016) Assumption Analysis. Project Management Institute (PMI) (Online).
Available from: https://www.projectmanagement.com/articles/324232/Assumptions-
Analysis [Accessed 9 October 2023].
Konchar, M. and Sanvido, V. (1999). Comparison of US project delivery systems. Journal of
construction engineering and management. 124(6), pp. 435-444.
Lewis, S. (2015) Qualitative inquiry and research design: Choosing among five approaches.
Health promotion practice. 16(4), pp. 473-475.
Journal of Science & Technology
By The Science Brigade (Publishing) Group 99
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Luo, L., He, Q., Jaselskis, E. J. and Xie, J., (2017) Construction project complexity: Research
trends and implications. Journal of construction engineering and management. 143(7), pp. 1-
10. Available from https://doi.org/10.1061/(ASCE)CO.1943-7862.0001306 [Accessed 24
August 2023].
Luskova, M. and Dvorak, Z. (2019) Applying risk management process in critical
infrastructure protection. Interdisciplinary Description of Complex Systems. 17(1-A), PP. 7-
12. Available from: https://hrcak.srce.hr/file/319087 [Accessed 19 August 2023].
Mhetre, K., Konnur, B. A. and Landage, A. B. (2016) Risk management in construction
industry. International Journal of Engineering Research. 5(1), pp. 153-155. Available from:
https://d1wqtxts1xzle7.cloudfront.net/45216108/153-155_NCICE-078-
libre.pdf?1461991189=&response-content-
disposition=inline%3B+filename%3DRisk_Management_in_Construction_Industry.pdf&Ex
pires=1695126031&Signature=aJV0HWZyySMpls8bF8yrHslV6m0i6s2X2E~7ctUTqEbuxcLU
A~ysTyFFq9E4mDt6R3cHLMx7S2I2mGty8xiAALDBzJz~~9PDhxpPW4qnsykMgLHxZXX8F
UHvIHkIHq7~oTn3PGTptyu-P9zIp8wTi9NKKzw0BIzevTSFrQ73J7oIc5dsk-
fZLFuYekjJq98qomZBqzwUcnPUXBDxetw04QpJgnrjdF9Z0Gp6W3NJpp6aGQSdeJQo6vkQg
vv7dbCVoR9t9p-
dBXUuNxSlCjIrwMcNRBxpE3ItWqvxgggIrWA9pCORWbvL6BVdMgNR9lYRmU0IdoAuh7
KeDqW26HJwVw__&Key-Pair-Id=APKAJLOHF5GGSLRBV4ZA [Accessed 16 August
2023].
Muhammed, S. N., Sabiu, N. and Khalil, M. S. (2015) An overview of urbanization and its
challenges on sustainable development in Nigeria. Dutse Journal of Pure and Applied
Sciences. 1(1), pp. 19-29. Available from:
https://www.researchgate.net/publication/318876748_AN_OVERVIEW_OF_URBANIZAT
ION_AND_ITS_CHALLENGES_ON_SUSTAINABLE_DEVELOPMENT_IN_NIGERIA
[Accessed 24 August 2023].
Nayak, M. S. and Narayan, K. A. (2019). Strengths and weaknesses of online surveys. IOSR
Journal of Humanities and Social Sciences (IOSR-JHSS). 6(7), pp. 31-38. Available from:
https://www.researchgate.net/profile/Mudavath-
Nayak/publication/333207786_Strengths_and_Weakness_of_Online_Surveys/links/61176e
Journal of Science & Technology
By The Science Brigade (Publishing) Group 100
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
5a0c2bfa282a42253b/Strengths-and-Weakness-of-Online-Surveys.pdf [Accessed 30
November 2023].
Obondi, K. (2022) The utilization of project risk monitoring and control practices and their
relationship with project success in construction projects. Journal of Project Management.
7(1), pp. 35-52. Available from: http://m.growingscience.com/jpm/Vol7/jpm_2021_16.pdf
[Accessed 12 November 2023].
Okolie, K. C., Ezeokoli, F. O. and Fadumo, D. O. (2020) Positioning the Nigerian
Construction Industry and Desiderata for Global Competitiveness in the 21st Century.
Journal of Engineering Research and and Reports. 14(2), pp. 20-31. Available from:
https://doi.org/10.9734/jerr/2020/v14i217120 [Accessed 24 August 2023].
Palinkas, L. A., Horwitz, S. M., Green, C. A., Wisdom, J. P., Duan, N. and Hoagwood, K.
(2015) Purposeful sampling for qualitative data collection and analysis in mixed method
implementation research. Administration and policy in mental health and mental health
services research. 42(5), pp. 533-544. Available from:
https://www.ncbi.nlm.nih.gov/pmc/articles/PMC4012002/ [Accessed 10 November 2023].
Petrovic, D. (2017) Risk management in construction projects: A knowledge management
perspective from Swedish contractors. Masters. Royal Institute of Technology. (Online).
Available from: https://www.diva-portal.org/smash/get/diva2:1150372/FULLTEXT01.pdf
[Accessed 26 August 2023].
Project Management Institute (PMI). (2018) A guide to the Project Management Body of
Knowledge (PMBOK guide) (6th ed). [Online]. Available from:
https://vuthedudotorg.files.wordpress.com/2019/11/a-guide-to-the-pmbok-6e.pdf
[Accessed 29 August 2023].
Serpell, A., Ferrada, X., Rubio, L. and Arauzo, S. (2015). Evaluating risk management
practices in construction organizations. Procedia-Social and Behavioral Sciences. 194(), pp.
201-210. Available from:
https://www.sciencedirect.com/science/article/pii/S1877042815036149/pdf?md5=e25b473
9bb2a7051bd27ae3e90ad4596&pid=1-s2.0-S1877042815036149-main.pdf [Accessed 29
November 2023].
Journal of Science & Technology
By The Science Brigade (Publishing) Group 101
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
Sileyew, K. J. (2020) Research Design and Methodology. In: Abu-Taieh, E., El Mouatasim, A.
and H. Al Hadid, I. (eds.) Cyberspace. Available from:
http://dx.doi.org/10.5772/intechopen.85731 [Accessed 14 November 2023].
Singh, A. S. and Masuku, M. B. (2014) Sampling techniques & determination of sample size
in applied statistics research: An overview. International Journal of economics, commerce
and management. 2(11), pp. 1-22. Available from:
https://www.academia.edu/download/65225177/21131_IJECM.pdf [Accessed 16
November 2023].
Tepeli, E. (2023) Why stakeholder involvement is important for risk management? Project
Management Institute (PMI) (Online). Available from:
https://www.projectmanagement.com/blog-post/73832/why-stakeholder-involvement-is-
important-for-risk-management-#_=_ [Accessed 19 August 2023].
Thompson, A., Stringfellow, L., Maclean, M. and Nazzal, A. (2021) Ethical considerations
and challenges for using digital ethnography to research vulnerable populations. Journal of
Business Research. 124(2), pp. 676-683. Available from:
https://ore.exeter.ac.uk/repository/bitstream/handle/10871/120310/JBR%20Ethics%20Ma
nuscript%20with%20author%20details%20.pdf?sequence=2 [Accessed 30 November 2023].
Ubani, E. C., Amade, B., Okorocha, K. A. and Agwu, F. (2015) Project risk management
issues in the Nigerian construction industry. International Journal of Engineering and
Technical Research (IJETR). 3(1), pp. 217-232. Available from:
https://www.academia.edu/11154035/Project_Risk_Management_Issues_in_the_Nigerian_
Construction_Industry [Accessed 24 August 2023].
Ugwu, M. C., Temidayo O. O. and Clinton O. A. (2019) Evaluation of risk management
practice in the Nigeria construction industry. In: Modular and Offsite Construction Summit,
Alberta, 2019. Canada: University of Alberta, pp. 373-380. Available from: https://napier-
repository.worktribe.com/preview/2883801/MOC_2019_Paper_84.pdf [Accessed 30
November 2023].
Unegbu, H. C. O., Yawas, D. S. and Dan-Asabe, B. (2022) An investigation of the relationship
between project performance measures and project management practices of construction
Journal of Science & Technology
By The Science Brigade (Publishing) Group 102
JOURNAL OF SCIENCE & TECHNOLOGY
Volume 5 Issue 2 ISSN 2582-6921
Bi-Monthly Edition | March April 2024
This work is licensed under CC BY-NC-SA 4.0. View complete license here
projects for the construction industry in Nigeria. Journal of King Saud University-
Engineering Sciences. 34(4), pp. 240-249. Available at:
https://www.sciencedirect.com/science/article/pii/S1018363920303226 [Accessed 15
November 2022].
Venczel, T. B., Berényi, L. and Hriczó, K. (2021) Project management success factors. Journal
of Physics Conference Series. 1935(012005), pp. 1-9. Available from:
https://iopscience.iop.org/article/10.1088/1742-6596/1935/1/012005/pdf [Accessed
August 23, 2023].
... CI is susceptible to risks due to the involvement of complex and uncertain activities that may affect construction project scope, budget, and timely achievement (Hassan et al., 2023, quoting Pinto et al., 2011. Despite the inclusion of health and safety and environmental sustainability as factors for determining success (Zhao, 2024) and other scholars and clients, the iron triangle of quality, cost and time (Oyekunle, 2024citing Unegbu et al., 2022 are the long-ago established parameters, and still very valid, for measuring project success at construction stage. The 100% achievement/attainment of these parameters is only possible with the complete absence or elimination of all risks. ...
... The study found that RM is not dealt with in a systematic, deliberate and continuous manner, but in an ad-hoc manner. This is despite the suggested guide by APM (2019) cited in Oyekunle (2024) that RM be a methodical approach; without which is the eminent resultant difficulty of maximising (positive) project's outcomes. Bahamid et al. (2022) studied the RM practices and knowledge in Yemen construction industry, but also concluded that risk was not managed systematically. ...
Article
Full-text available
Purpose: The purpose of this study is to examine the prevailing risk management practices in building construction project delivery within the Nigerian construction industry, considering its significance in economic value creation, employment generation, and GDP contribution. Design/methodology/approach: Quantitative data were obtained through questionnaire survey. Purposive sampling was adopted and data was collected using close ended questionnaire that were self-administered. 117 questionnaires were distributed and 61 were received, filled and used for the analysis. Descriptive statistics was used to analyse the data collected using statistical package for social science (SPSS V29). Respondents were chosen from one construction firm each classified under the highest building construction class. Findings: The study revealed that risk management in construction projects is not systematically, deliberately, proactively, or continuously implemented. Instead, risks are addressed in an ad hoc manner, deviating from internationally recognised risk management standards/best practices. This highlights weaknesses within project management practices in Nigeria. Research limitations/Implications: Limitations of this research include the focus on a specific segment of the construction industry in Nigeria and the reliance on data from Building construction firms, which may not fully represent the entire industry. However, the implications of these findings underscore the need for enhanced risk management practices in construction project delivery to ensure value for money. Practical implications: The study suggests that project managers within construction firms in Nigeria would benefit from comprehensive training and knowledge in internationally recognised systematic risk management practices. Implementing such practices could lead to better project outcomes and increased efficiency in resource utilisation. Originality/value: This study contributes to the existing literature by shedding light on the current state of risk management practices in the Nigerian construction industry. By highlighting the deficiencies and advocating for improved risk management methodologies, the research emphasises the importance of aligning project management practices with international standards to enhance project success and economic development.
... Furst (2019) and Oyedele, Jaiyeoba & Fadeyi (2012) highlight that the current challenges in achieving quality standards result in significant inefficiencies in the utilization of resources such as time, money and others during project execution. These of factors of budget, duration, and craftsmanship as averred by Oyekunle, (2024), Tunji-Olayeni et al. (2016) and Aibinu & Jagboro, (2002) critically influence the performance of construction endeavours. ...
Research
Full-text available
The study examines the impact of Total Quality Management (TQM) on construction project performance in the Eti-Osa Local Government Area, Lagos State, Nigeria. It evaluates six practices from the Malcolm Baldrige National Quality Award (MBNQA) framework: Leadership, Strategic Planning, Customer Focus, Workforce Focus, Operation Focus, and Measurement, Analysis, and Knowledge Management. The results show that all six MBNQA practices positively impacted project performance, indicating that TQM significantly influences project outcomes. The study offers practical recommendations for construction firms and practitioners to better understand the link between TQM and project performance.
Article
Full-text available
Risk monitoring and control is often poorly implemented in construction projects because of a failure to monitor and manage identified risks. Construction companies experience significant losses due to project managers' lack of project risk monitoring and control in construction projects. Most studies have concentrated on risk identification, risk assessment, and risk analysis processes while neglecting crucial risk management processes of risk control, risk monitoring, and risk response. The lack of research on these three crucial processes highlights a gap in the literature concerning how these processes can increase the delivery of successful projects. The purpose of this study was to examine whether the utilization of project risk monitoring and control practices was related to project success in construction projects in the United States. An electronic survey instrument was used to collect data from a sample of 50 construction project managers in the Dallas-Fort Worth area in the state of Texas, in the United States. Spearman rho correlation analysis was used to examine the relationship between project risk monitoring and control practices and project success. The results of this study indicated that all project risk monitoring and control practices, including risk reassessment, risk audits, contingency reserves analysis, and risk status meetings, were significantly and positively related to project success in construction projects. One of the recommendations presented in this study was that future research should conduct the same study in developing countries to see if the study's findings remain the same and generalizable. The study concluded that construction organizations should regularly consider the importance and usage of project risk monitoring and control practices and apply them to improve the success rate of a project.
Article
Full-text available
This study focuses on the challenges and prospects of engineering procurement in Nigeria. The research examines the existing literature on engineering procurement practices, identifies gaps in knowledge, and explores potential areas for improvement. Through a comprehensive review, key findings emerge, highlighting limited research specific to engineering procurement in Nigeria and a lack of empirical studies on project performance and outcomes. Moreover, the literature review reveals a need for more research on engineering procurement projects' socioeconomic and environmental impacts. The implications of these findings underscore the need for targeted research, enhanced data collection, and monitoring mechanisms to evaluate project performance accurately. Additionally, the study emphasises the importance of considering the broader socioeconomic and environmental implications for sustainable development. Overall, this study serves as a foundation for advancing the understanding of engineering procurement in Nigeria and offers insights for policy-makers, researchers, and practitioners in the field.
Article
Full-text available
The construction industry had been foot-dragging in the improvement of its socio-environmental development. In addressing this issue, there is a need to examine the corporate social responsibility (CSR) of construction companies in the industry. Hence, this study assessed CSR initiatives; and examined factors influencing CSR implementation in the study area. A descriptive research design was adopted in which questionnaires were administered to administrative and executory managers in the construction industry. A total of three hundred and two (302) construction companies were identified and administered copies of the questionnaire for this study. One hundred and four (104) valid copies were completed and returned, representing a response rate of 34%. Percentage distribution, mean score, and spearman's correlation were used to analyse the collected data. The findings of this study indicated that the overall level of implementing CSR initiatives by the surveyed companies is average. Although many of the initiatives were practiced, employees' interests were given more attention over community development and environmental protection. In addition, the study established the vision of the founder, better employee satisfaction, investment attraction, and creating public attention as the key motivating/driving factors influencing CSR implementation. Conversely, the predominant barrier inhibiting the implementation of CSR in the study area is corruption. Lastly, there exists no significant difference between the opinions of the managers surveyed. This study concluded that the implementation of CSR initiatives is not fully embraced and that the most important CSR initiative implemented by the construction companies is more of 'employees interests', which is a social project in nature. In addition, while successfully implementing CSR initiatives by the construction companies surveyed depending on the vision of the founder, better employee satisfaction, and investment attraction, the key inhibiting factor is corruption practices.
Article
Full-text available
Purpose Lack of strict compliance to the principles of total quality management (TQM) by construction organizations has brought about poor quality of the finished building projects. This has been blamed for the incessant structural failure reported in Nigeria. This study appraised TQM implementation in the Nigerian construction industry, with a view to mitigating structural failure rate of construction projects. To achieve this aim, the study aims to assess the practice level of TQM and the factors hindering TQM implementation on construction projects. Design/methodology/approach The study utilized a well-structured questionnaire and convenient sampling method in the gathering and sampling of data among construction professionals in Imo state, Nigeria. Data analyses were done using, frequency, percentage, mean analytics and Pareto analysis. Findings The study revealed that major practice of TQM principles with respect to structural failure rate are purchasing: ensuring the procurement of materials of the specified quality standard, ensuring the use of a quality improvement construction process of the organization, site management responsibility: this entails ensuring quality supervision by the project management leadership and monitoring and control of quality during the construction to guarantee firm observance quality standards. Also, the major factors hindering TQM implementation on construction projects are: inadequacy of the necessary machineries, equipment, tools and facilities for the effective execution of work on construction site; breakdown in communication and information exchange between the management and supervisory teams on site; poor attitudes and strategies toward maintenance of equipment, tools and machines; and absence of prompt salary and incentive payment. It was recommended that construction firms must require the suppliers of construction materials to strictly comply with quality specification evidence in quality certification of delivered materials to mitigate structural failure. Research limitations/implications This study appraised TQM implementation in the construction industry of Nigeria, with emphasis on Imo state. The study underscores the practice level of TQM and the key factors hindering TQM implementation on construction projects. Following the localized geographical limitation of the study area, a similar research in other part/states of Nigeria or even in other developing countries of African is necessary. Practical implications The practices level of TQM and the factors hindering TQM implementation were identified. This will be useful in guiding construction firms, other industry's key stakeholders and regulatory agencies in bringing about a sustainable quality management system for improve profit and value maximization and avoiding incessant structural failure. Originality/value This is one of the few studies that have assessed the practice level of TQM and the factors hindering TQM implementation on construction projects in Nigeria. This study took place in Imo state with records of periodic structural failure and building collapse.
Article
Full-text available
The major requirement of every construction project is meeting client’s need of cost, quality and time. However, the construction industry is overwhelmed with risks more than any other industry due to the fact that they are present in every activity from design to completion. These risks need to be controlled early or face the possibility of cost overruns, time delays and poor quality work leading to displeasure of client and public. Although risk management in construction projects is a very important issue in terms of the firms operating in the construction sector, it has not yet gained clarity and prevalence in our country. Within the scope of this research, the aim of this research is to introduce the risk management system as a concept and to classify the risk in construction projects and to demonstrate the risk management techniques. Risk management system is a cyclic process. In the monitoring and control phase of applied risk responding strategies, some of the risks will be eliminated or reduced, some of unforeseen risks will appear and analysis steps will be realized again. At the end of the project, determination of to what degree project aims and targets have been reached and documentation of risk management system after evaluation regarding to the project will enable the company to use project risk management system more effectively and usefully in the projects undertaken later. Due to construction activities, processes, environment and organization’s structures, construction industry and the clients are broadly in relation with high risk degrees. Therefore, it is highly important for our country’s firms in construction industry to give necessary significance to project risk management idea and system and to consider them as a basic function of the projects for permanence of their enterprise existence.
Article
Full-text available
The construction industry is known to be overwhelmed with resource planning, risk management and logistic challenges which often result in design defects, project delivery delays, cost overruns and contractual disputes. These challenges have instigated research in the application of advanced machine learning algorithms such as deep learning to help with diagnostic and prescriptive analysis of causes and preventive measures. However, the publicity created by tech firms like Google, Facebook and Amazon about Artificial Intelligence and applications to unstructured data is not the end of the field. There abound many applications of deep learning, particularly within the construction sector in areas such as site planning and management, health and safety and construction cost prediction, which are yet to be explored. The overall aim of this article was to review existing studies that have applied deep learning to prevalent construction challenges like structural health monitoring, construction site safety, building occupancy modelling and energy demand prediction. To the best of our knowledge, there is currently no extensive survey of the applications of deep learning techniques within the construction industry. This review would inspire future research into how best to apply image processing, computer vision, natural language processing techniques of deep learning to numerous challenges in the industry. Limitations of deep learning such as the black box challenge, ethics and GDPR, cybersecurity and cost, that can be expected by construction researchers and practitioners when adopting some of these techniques were also discussed.
Article
Full-text available
The research evaluates the drivers toward positioning Nigerian construction industry for global competitiveness in the 21st century. Being a survey research, questionnaires containing information relating to issues and drivers on global competitiveness were administered to selected construction practitioners in Anambra State, Nigeria. Accordingly, a total of 84 questionnaires were administered out of which 80 copies were completed, returned and found useful. This corresponds to a response rate of 95%. Data collected were analyzed and presented using mean score, percentages, relative importance index (RII) and tables. The study found that the identified twelve (12) drivers of global competitiveness were all significant in the study area. However, the most perceived significant drivers for global competitiveness in the study area is labour market efficiency. Also, the study observed that the Nigerian construction industry operates at the level of factor-driven economy. Therefore, the study concluded by recommending that construction firms must find appropriate strategies that would help to improve and strengthen their digital innovation, institutional, technological and infrastructural needs. This will place them in good standing for global competitiveness in the future.
Article
Full-text available
The social technologies of the web permit new techniques of research to emerge, often with novel ethical challenges. One such technique is digital ethnography. While there is a robust literature associated with digital approaches to ethnography, there is a lack of development in how digital ethnography can be used when researching vulnerable populations. This article seeks to clarify these methodological considerations, addressing the role of the researcher, data representation, and the ethical considerations necessary to research vulnerable consumers. We consider the various roles that digital ethnography can play in understanding emerging forms of social order in vulnerable consumer contexts, in generating social knowledge that is nuanced, participative, holistic, and practically orientated. We highlight a selection of the core issues concerning the use, practice and dissemination of digital ethnographic research available to social researchers, and how the incorporation of such methods can invigorate research on vulnerable consumers with new methodological innovations.