Conference PaperPDF Available

COMPARISON OF EVOLUTIONS OF INTERNAL EROSION IN HOMOGENEOUS EARTH-FILL DAMS BUILT WITH MEDIUM SAND AND CLAY MIXTURE WHEN THE SEEPAGE IS AT UPPER- MIDDLE OR AT UPPER-CORNER PART OF THE DAM

Authors:

Abstract and Figures

One of the most significant reasons for earth-fill dam failures is internal erosion resulting from piping. This research was carried out as a part of a project supported financially by the Scientific and Technological Research Council of Turkey (TÜBİTAK). This paper involves the comparison of the experimental findings related to two different scenarios to look into the breach process and to provide the data allowing the realization of more realistic numerical analyses. A circular tunnel of 2 cm diameter located 6 cm below the dam crest was created to induce the seepage. The experiments were conducted at Hydraulics Laboratory of Civil Engineering Department within İzmir University of Economics. The homogeneous earth-fill dams having a height of 0.60 m and a bottom width of 2 m were built in a flume 1.00 m wide, 0.81 m high and 5.44 m long. Some common soil mechanics tests were carried out before the dam was built. The dam bodies were constructed by using a mixture of 15 % clay and 85 % medium sand. High-precision cameras were used to record the temporal development of the breach resulting from the piping. The pump flow rate was measured by a magnetic flowmeter and the flow rate values outgoing from the breach were determined from the continuity equation. Gauss area formula was used to obtain the time-varied values of the breach areas. The temporal changes of water depth in the channel were also recorded. The so obtained experimental findings are presented and commented.
Content may be subject to copyright.
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
357
COMPARISON OF EVOLUTIONS OF INTERNAL EROSION IN HOMOGENEOUS EARTH-FILL
DAMS BUILT WITH MEDIUM SAND AND CLAY MIXTURE WHEN THE SEEPAGE IS AT UPPER-
MIDDLE OR AT UPPER-CORNER PART OF THE DAM
Prof. Dr. Mehmet Şükrü Güney, Ar. Gör. Merve Okan, Ar. Gör. Emre Dumlu, Yiğit Kalyoncu
ORCID: 0000-0003-1441-4784, 0000-0001-6095-2992, 0000-0003-4311-3040, 0000-0002-5955-963X
1sukru.guney@ieu.edu.tr, 2 merve.okan@ieu.edu.tr, 3emre@ncche.olemiss.edu,
4yigit.k@std.izmirekonomi.edu.tr
1,2,4 İzmir University of Economics, Faculty of Engineering, Civil Engineering Department, İzmir, Turkey
3 The University of Mississippi, National Center for Computational
Hydroscience and Engineering, Oxford, USA
Abstract
One of the most significant reasons for earth-fill dam failures is internal erosion resulting from piping. This
research was carried out as a part of a project supported financially by the Scientific and Technological
Research Council of Turkey (TÜBİTAK). This paper involves the comparison of the experimental findings
related to two different scenarios to look into the breach process and to provide the data allowing the realization
of more realistic numerical analyses. A circular tunnel of 2 cm diameter located 6 cm below the dam crest was
created to induce the seepage. The experiments were conducted at Hydraulics Laboratory of Civil Engineering
Department within İzmir University of Economics. The homogeneous earth-fill dams having a height of 0.60 m
and a bottom width of 2 m were built in a flume 1.00 m wide, 0.81 m high and 5.44 m long. Some common soil
mechanics tests were carried out before the dam was built. The dam bodies were constructed by using a
mixture of 15 % clay and 85 % medium sand. High-precision cameras were used to record the temporal
development of the breach resulting from the piping. The pump flow rate was measured by a magnetic
flowmeter and the flow rate values outgoing from the breach were determined from the continuity equation.
Gauss area formula was used to obtain the time-varied values of the breach areas. The temporal changes of
water depth in the channel were also recorded. The so obtained experimental findings are presented and
commented.
Keywords: Earth-fill dam; Homogeneous dam; Piping; Breach development; Discharge from breach.
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
358
ORTA DERECELİ KUM VE KİL KARIŞIMI İLE İNŞA EDİLEN HOMOJEN TOPRAK DOLGU
BARAJLARDA SIZMANIN ÜST-ORTA VEYA ÜST-KÖŞEDE OLMASI DURUMLARINDA OLUŞAN
İÇSEL EROZYONLARIN KARŞILAŞTIRILMASI
Özet
Toprak dolgu baraj yıkılmalarının en önemli nedenlerinden biri borulanmadan kaynaklanan içsel erozyondur.
Bu araştırma, Türkiye Bilimsel ve Teknolojik Araştırma Kurumu (TÜBİTAK) tarafından desteklenen 119M609
nolu projenin bir bölümü olarak gerçekleştirilmiştir. Bu çalışma, gediğin gelişme sürecini incelemek ve sayısal
analizler için daha gerçekçi veri sağlamak amacıyla oluşturulan farklı senaryolardan iki tanesi ile ilgili deneysel
bulguların karşılaştırmasını içermektedir. Sızma, baraj kretinin 6 cm aşağısında 2 cm çaplı tünel oluşturularak
başlatılmıştır. Deneyler İzmir Ekonomi Üniversitesi İnşaat Mühendisliği Bölümü Hidrolik Laboratuvarı’nda
gerçekleştirilmiştir. Taban genişliği 2 m ve yüksekliği 0,60 m olan homojen toprak dolgu barajlar 1.00 m
genişliğinde, 0.81 m yüksekliğinde ve 5.44 m uzunluğunda bir kanalda inşa edilmiştir. Baraj inşa edilmeden
evvel gerekli bazı zemin mekaniği deneyleri gerçekleştirilmiştir. Baraj gövdeleri %15 kil ve %85 orta dereceli
kumdan oluşan karışım kullanılarak inşa edilmiştir. Borulanmadan kaynaklanan gediğin zamana bağlı
gelişimini kaydetmek için yüksek hassasiyetli kameralar kullanılmıştır. Pompa debisi bir manyetik debimetre ile
ölçülmüş ve gedikten çıkan debi değerleri süreklilik denklemi kullanılarak belirlenmiştir. Gedik alanlarının
zamana bağlı değişimini elde etmek için Gauss alan formülü kullanılmıştır. Kanaldaki su derinliğinin zamansal
değişimleri de kaydedilmiştir. Elde edilen deneysel bulgular sunulmakta ve yorumlanmaktadır.
Anahtar Kelimeler: Toprak dolgulu baraj; Homojen baraj; Borulanma; Gedik gelişimi; Gedikten çıkan debi.
INTRODUCTION
Piping is a significant issue for earth-fill dam failures. In earthen constructions, especially in earth levees
and dams, soil erosion may originate through the foundation, the embankment, or from the embankment to the
foundation. Phases of this type of erosion include: a) initiation and continuation of erosion, b) progression to
form a pipe and c) formation of a breach (Fell et al., 2003). When investigating the failure of an embankment
dam experimentally and numerically, the evolution of the breach caused by the piping is a crucial factor. In the
literature, there have been many researches on dam failures, particularly those caused by overtopping, but there
have not been as many studies on dam failures caused by piping because it is difficult to investigate erosion and
conduct controlled experiments (Chen et al., 2019; Greco et al., 2008; Sharif et al., 2015). A two-dimensional
depth-averaged (2DH) numerical model was used by Greco et al. (2008) to simulate the development of a
breach in an earth-fill dam. According to Chen et al. (2019), 3541 dam breach accidents occurred between 1954
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
359
and 2018, and more than 30% of them resulted from piping. Sharif et al. (2015) built dams with varied
compaction rates in a laboratory flume, and then used image processing technique to assess depth, area, and
volume change due to erosion during the piping progress. Numerous researchers who do numerical studies
make simple assumptions about properties of breach and water flow through it. According to Morris et al.
(2008) more realistic techniques are needed regarding the breach mechanism, as well as the breach shape and
flow through the breach.
In the scope of the project 119M609, supported financially by the Scientific and Technological Research
Council of Turkey (TÜBİTAK), it is aimed to carry out the piping experiments on homogeneous earth fill dams
and also earthen dams with clay core. These experiments were performed with different scenarios according to
the dam type and the location of the weak zone. Some of the experimental findings were presented in different
scientific meetings (M. Sukru Guney et al., 2023; Mehmet Sukru Guney, Dumlu, Okan, & Tayfur, 2022;
Mehmet Sukru Guney, Dumlu, Okan, Bor, et al., 2022; Mehmet Sukru Guney, Okan, et al., 2022). In addition
to these submitted papers, two master theses were also prepared and submitted (Dumlu, 2022; Okan, 2022).
This paper involves the experimental results concerning the evolution of dam failure due to the seepage
in the case of two scenarios corresponding to the dam bodies constructed with medium sand-clay mixture
having D50 = 0.30 mm. The objective of this research is to conduct experiments to investigate the development
of dam failure resulted from the seepage in homogenous earth-fill dams to provide insights into the breach
mechanism and data to the relevant researchers who deal with numerical analyses and emergency action plans.
EXPERIMENTAL PROCEDURE
The dam was constructed in a rectangular flume 1.00 m wide, 0.81 m high, and 5.44 m long (Figure 1).
The bottom of the flume consists of sheet metal whereas its sides are made of tempered glass for the purpose of
obtaining good records from the cameras located at different locations. The lower channel serves as water
supplying container. The upper channel which is at the upstream part of the dam corresponds to the dam
reservoir. A pump equipped with a check-valve and regulating valve was used to provide water circulation in
the closed system.
The details of the characteristics of dams are given in Table 1. The dams were designed and constructed
with side slopes of 1 vertical to 1.5 horizontal. In both of the scenarios, a circular groove of 2 cm diameter,
aligned from upstream to downstream was created at 54 cm from the bottom of the homogeneous dam bodies,
in order to initiate the formation of the breach. While initial groove was located at the middle of dam body in
the upper-middle case, it was located at the corner of the dam body in the upper-corner case.
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
360
Figure 1: Experimental set-up.
Table 1: Details of the characteristics of dams.
Height (cm)
60
Bottom width (cm)
200
Crest width (cm)
20
Length (cm)
96
Side Slopes (Vertical:Horizontal)
1:1.5
Initial groove shape
Circular d= 2 cm
Dam type
Homogeneous
Before building the dam, some common soil mechanics experiments were conducted. 85 % medium
sand and 15 % clay were used to prepare the soil mixture of the dam body. Wet sieve and hydrometer analyses
were conducted to obtain the grain size distribution of the soil mixture.
The particle size distribution of the mixture is given in Figure 2a. According to this figure; D10=0.006
mm, D30= 0.075 mm, D50= 0.3 mm, and D60= 0.4 mm. The coefficients of uniformity and curvature were found
as Cu =66.7 and Cc =2.34, respectively. The soil was classified as Clayey Sand with a corresponding symbol
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
361
SC according to Unified Soil Classification System. The specific gravity for the mixture was 2.63. Specific
gravity for the soil passing No.200 sieve was obtained as 2.72. According to the consolidation test results, the
compression index (Cc), recompression index (Cr) and swelling index (Cs) were found to be as 0.100, 0.009 and
0.007, respectively. The permeability of the mixture was found as k= 4.66x10-4 cm/s from the falling head
permeability test. From the direct shear test, it was found that the soil mixture has a cohesion value of 15.33
kPa and an internal friction of 33.93.
Proctor test was performed to obtain the maximum dry unit weight and the optimum water content
(Figure 2b). From Figure 2b, ϒdry,max= 1.8 g/cm3 and wopt = 12.5 %. In the experiments, the energy was reduced
by 50 % in order to facilitate the occurrence of piping. Hence, the number of blows applied for each layer for
proctor test was 13 instead of 25.
(a) (b)
Figure 2: Grain size distribution and dry density-water content relationship.
In the experiments, the bulk density of 2 g/cm3 was satisfied for each layer. Before the compaction, each
layer was 14 cm thick and after the compaction it was reduced to 10 cm.
Figure 3 shows some construction stages of the dam bodies.
(a) (b) (c)
Figure 3: Some construction stages: a) Spreading out of the mixture, b) Compacting, c) After compaction of the
second layer
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
362
During the compaction, the mixture was spread out evenly and compacted by using a plate and proctor
hammer. At the end of the construction, the L-shaped molds were removed and the excessive soil materials
were carefully trimmed by using a trowel.
A magnetic flowmeter was used to measure the flow rate. Six cameras were placed at different locations
to monitor the experiment and record the evolution of the dam failure. An electromagnetic sensor was utilized
to adjust the water level so that the pump starts and stops at pre-determined water depths in the channel.
EXPERIMENTAL FINDINGS
Figures 4, and 5 show the time-varied breach shapes as obtained by the cameras placed at downstream of
the dam, in the case of upper-middle and upper-corner, respectively. The time t=0 is the time at which the
initiation of the seepage occurs at downstream face.
(a) (b) (c) (d)
Figure 4: The temporal development of the breach at downstream in the case of the seepage at upper-middle a)
t=0, b) t= 127 s, c) t= 254 s, d) t= 380 s.
(a) (b) (c) (d)
Figure 5: The temporal development of the breach at downstream in the case of the seepage at upper-corner a)
t=0, b) t= 167 s, c) t=334 s, d) t=500 s.
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
363
Figures 6 and 7 show the time-varied breach shapes as obtained by the cameras placed at upstream of the
dam, in the case of upper-middle and upper-corner, respectively. The time t=0 is the time at which the initiation
of the seepage occurs at downstream face
(a) (b) (c) (d)
Figure 6: The temporal development of the breach at upstream in the case of the seepage at upper-middle a) t=0,
b) t=127 s c) t=254 s, d) t=380 s.
(a) (b) (c) (d)
Figure 7: The temporal development of the breach at upstream in the case of the seepage at upper-corner a) t=0,
b) t=400s, c) t= 800 s, d) t=1200 s.
Camera recordings were used to obtain the water depth values in the channel. The images recorded by
the upstream and downstream cameras were examined in order to assess the breach's geometry and determine
the change in its shape. The boundary coordinates of the breaches at the downstream and upstream sides were
obtained at Get-data Graph Digitizer 2.26 software along with the scaling of the images derived from the
records corresponding to a certain period. The temporal total breach areas were calculated by Gauss Area
formula. The discharge of water outgoing from the breach was determined by using the continuity equation Eq.
(1):

(1)
where  is the flow rate delivered by the pump,  is the discharge from the breach,  is the
storage in the dam reservoir during the time interval . The temporal water depths in the channel for different
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
364
scenarios are given in Figure 8a. The temporal discharges outgoing from the breach calculated by using Eq. (1)
for different scenarios are given in Figure 8b.
(a) (b)
Figure 8: a) The temporal water depths in the reservoir and b) time-varied discharge outgoing from the breach
for different scenarios.
The temporal variations of the total breach area at downstream and upstream are shown in Figure 9a and
9b, respectively. The comparative experimental findings are given in Table 2.
(a) (b)
Figure 9: Temporal variations of the total breach area a) at downstream and b) at upstream for different
scenarios.
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
365
Table 2: Comparison of the experimental findings for different scenarios.
Scenario number
Upper-middle
Upper-corner
Max. flow rate Qmax (L/s)
8.3
3.6
tQ= time to reach Qmax (s)
245
325
Max. breach area at downstream Bdmax (cm2)
2379
733
td=time to reach Bdmax (s)
370
1080
Max. breach area at upstream Bumax (cm2)
3129
1792
tu=time to reach Bumax (s)
520
1950
The graphs of the curves Q/Qmax = f(t/tQ), Bd/Bdmax = f(t/td) and Bu/Bumax = f(t/tu) are given in Figs 10a,
10b and 10c, respectively. Q, Bd and Bu denote time-dependent values of the discharge, the breach area at
downstream and breach area at upstream, respectively.
(a) (b) (c)
Figure 10: Graphs of the curves a) Q/Qmax = f(t/tQ), b) Bd/Bdmax = f(t/td) and c) Bu/Bdmax = f(t/tu).
RESULTS AND CONCLUSIONS
In all scenarios, the erosion started at downstream, developed and continued inward toward upstream.
As expected, the peak flow rates were found to be very small in the case of seepage located at the upper
parts of the dam. This finding was due to the small value of the initial water head over the breach causing small
flow velocities and a delay in the time of occurrence of the peak flow rates.
1. BİLSEL INTERNATIONAL GORDİON SCIENCE RESEARCHES CONGRESS, 29-30 SEPTEMBER 2023
https://bilselkongreleri.com/
366
The smallest breach areas were found in the case of the seepage at the upper-corner because of the
existence of the flume side preventing the development of the breach.
ACKNOWLEDGEMENTS
The authors thank the Scientific and Technological Research Council of Turkey (TUBITAK) for
supporting financially this study through the project 119M609.
REFERENCES
Chen, S. shui, Zhong, Q. ming, & Shen, G. ze. (2019). Numerical modeling of earthen dam breach due to piping failure.
Water Science and Engineering, 12(3), 169178. https://doi.org/10.1016/j.wse.2019.08.001
Dumlu, E. (2022). Experimental and Numerical Investigation of the Evolution of Piping and Resulting Breach in Earth-
fill Dams. M.Sc. Thesis, İzmir Institute of Technology.
Fell, R., Wan, C. H., & Foster, M. (2003). Progress report on methods for estimating the probability of failure of
embankment dams by internal erosion and piping.
Greco, M., Pontillo, M., Iervolino, M., & Leopardi, A. (2008). 2DH numerical simulation of breach evolution in an earth
dam. River-Flow2008, 1, 661667.
Guney, M. Sukru, Dumlu, E., & Okan, M. (2023). Experimental Study of the Evolution of the Breach and the Discharge
through the Breach resulting from Piping due to Seepage at the Mid-part of Earthfill Dam. International Journal of
Structural and Civil Engineering Research, 12(2), 4351.
Guney, Mehmet Sukru, Dumlu, E., Okan, M., Bor, A., Aklik, P., & Tayfur, G. (2022). Experimental Study of the
Evolution of the Breach and the Discharge through the Breach Resulting from Piping due to Seepage at the Earth-
Fill Dam Bottom. 7th International Conference on Civil Structural and Transportation Engineering (ICCSTE’22)
Niagara Falls, Canada June 05-07, 2022, July, 115-1-115118. https://doi.org/10.11159/iccste22.215
Guney, Mehmet Sukru, Dumlu, E., Okan, M., & Tayfur, G. (2022). Experimental Study of Breach Evolution and
Discharge Through Breach Resulting from Piping due to Seepage at the Upper Corner of in an Earth-Fill Dam. In S.
Elci & G. Bombar (Eds.), 14th International Conference on Hydroscience & Engineering (ICHE 2022) MAY 26-27,
2022 (Issue May, pp. 99109). https://doi.org/10.11159/iccste22.215
Guney, Mehmet Sukru, Okan, M., Dumlu, E., Bor, A., Aklık, P., & Tayfur, G. (2022). Experimental Study of the
Evolution of the Breach and the Discharge Through the Breach Resulting from Piping due to Seepage at the Earth-
Fill Dam Top. In M. Ortega-Sánchez (Ed.), 39th IAHR World Congress 19-24 June 2022 (Issue June, pp. 2735
2743). https://doi.org/10.3850/IAHR-39WC2521711920221298
Morris, M., Hassan, M., Kortenhaus, A., Geisenhainer, P., Visser, P., & Zhu, Y. (2008). Modelling breach initiation and
growth. Flood Risk Management: Research and Practice, 581591. https://doi.org/10.1201/9780203883020.ch67
Okan, M. (2022). Experimental and Numerical Investigation of Piping in Uniform Embankment Dam with Weak Layer at
the Upper Region. M.Sc. Thesis, İzmir Institute of Technology.
Sharif, Y. A., Elkholy, M., Hanif Chaudhry, M., & Imran, J. (2015). Experimental Study on the Piping Erosion Process in
Earthen Embankments. Journal of Hydraulic Engineering, 141(7), 04015012. https://doi.org/10.1061/(asce)hy.1943-
7900.0001019
ResearchGate has not been able to resolve any citations for this publication.
Thesis
Full-text available
From the past to nowadays, earth-fill dams have been built thanks to their advantages, however, piping is a problem that earth-fill dams can experience and then fail. While there are many studies about the overtopping failures of the dams, there are not too many surveys about dam failures due to piping. Dams having a height of 0.6 m, a bottom width of 2 m, and a crest width of 0.20 m were built in a channel of 1 m wide, 0.81 m high and 6.14 m long. 3 different scenarios have been created and the evolution of dam failure resulting from seepage at the dam was recorded by six cameras located at different locations. In the closed system, water was pumped from the lower reservoir to the upper channel. The dam was constructed by using a mixture consisting of 85 % sand and 15 % clay. A circular tunnel with a diameter of 2 cm was created at the middle or corner of the dam according to the scenario and at 6 cm below the dam crest. The breach areas at different time instants at upstream and downstream sides are determined by using the Gauss Area calculation method and by image processing, and then it has been found that methods give close values to each other. Breach discharge and time-varied velocity values were determined by using the continuity equation. Empirical relations were intended to be derived for the breach flow rate and empirical relations represented in the literature were trialed by using experimental findings.
Article
Full-text available
One of the main factors that leads to earth-fill dam failures is the internal erosion, commonly referred to as piping. Regarding the geometry of the breach and the discharge of water flowing through the breach, many researchers working with numerical analyses in this field make some simplified assumptions. This study was carried out as a part of the project supported by the Turkish Council for Scientific and Technological Research (TUBITAK) and it includes experimental research with the goal of supplying the data required to carry out numerical analysis using more realistic approaches. A dam with a height of 65 cm, a bottom width of 200 cm and a crest width of 5 cm was built in a flume 1 m wide, 0.81 m high and 6.14 m long. Before the construction of the dam, some common soil mechanics tests were carried out. The dam was constructed by using a mixture consisting of 85 % fine sand and 15% clay. In order to generate the formation of the breach, a square shaped rock salt layer of 2 cm side lying from upstream to downstream was placed at 28 cm from the bottom of the dam body. The progression of the dam failure was captured by six cameras located at different locations. Gauss Area formula was applied to determine the time-varied breach areas at upstream and downstream sides. The discharge of water through the breach and average flow velocity were determined by using the continuity equation. The changes in water depth in the channel were also recorded. The experimental findings continue to be compared with numerical results obtained from the software PLAXIS 3D.
Thesis
Full-text available
Earth-fill dams have been constructed for decades by compacting natural soil materials near the dam site. Piping is of the most important causes of their failure. In the scope of this thesis, 2 m in length homogenous earth-fill dams were constructed in a rectangular flume in the laboratory of the Izmir University of Economics. The experimental and numerical investigations on a breach by generating piping were realized with different weak zone scenarios. Three experiments were performed by placing a weak layer cross-section 5x5 cm2 at the dam bottom center. One scenario was performed by locating a weak layer of 2x2 cm2, 28 cm above the bottom. Temporal breach areas and the breach-wetted areas are evaluated on scaled screenshots by using Gauss’s area formulation. The Temporal breach discharges were calculated from the continuity equation. Furthermore, finite element analyses on the breaching of homogenous earth-fill dams in different scenarios were performed by comparing the hydraulic gradient with the critical value. In addition to the bottom and middle scenarios, two upper scenarios were also modeled. The water depths were used for each scenario to represent the experimental conditions, and some approaches were made for the weak zones. To simulate the breach mechanism with different loops, a python algorithm was integrated with the Jupyter console. As a result of the simulations, it has been observed that the findings obtained by simulations were in accord with the experimental studies, and the dams were exposed to backward piping starting from downstream towards upstream.
Conference Paper
Full-text available
Piping is one of the main problems which threatens stability of earth-fill dams. Realistic approaches are needed for breach mechanism as well as breach geometry and flow. The aim of this study is to realize experiments to provide data needed to perform numerical analyses by making more realistic assumptions. Dam having a height of 0.6 m, a bottom width of 2 m and a crest width of 0.20 m is built in a channel of 1 m wide, 0.81 m high and 6.14 m long. Evolution of dam failure resulting from seepage at upper corner of the dam is recorded by six cameras located at different locations. The time-varied of breach areas at upstream and downstream sides are determined by applying the Gauss Area functions. Discharge of water through the breach and average outflow velocity are determined by using the continuity equation.
Conference Paper
Full-text available
Internal erosion, also known as piping, is one of the most important causes of earth-fill dam breaks. Many researchers dealing with numerical analyses in this area make some simplified assumptions about the shape of the breach and the discharge of water flowing through the breach. This study was conducted in the scope of the project supported financially by the Scientific and Technological Research Council of Turkey and it consists of experimental study which aims to provide data needed to perform numerical analyses with more realistic approaches. A dam with a height of 0.6 m, a bottom width of 2 m and a crest width of 0.20 m was built in a flume 1 m wide, 0.81 m high and 6.14 m long. Before the construction of the dam, some common soil mechanics tests were carried out. The dam was constructed by using a mixture consisting of 85 % sand and 15 % clay. A circular tunnel with a diameter of 2 cm was created along the centerline at 6 cm below the dam crest. In the closed system, water was pumped from the lower reservoir to the upper channel. Six cameras located at different locations recorded the evolution of the dam failure. Gauss Area formula was applied to determine the time-varied of the breach areas at upstream and downstream sides. The discharge of water through the breach and average flow velocity were determined by using the continuity equation. The changes in water depth in the channel were also recorded.
Conference Paper
Full-text available
Piping is one of the main causes of the earth-fill dam failures. Most of the researchers realizing numerical analyses make some simplified assumptions concerning the shape of the breach and the discharge of water flowing through the breach. The aim of this study is to realize experiments to provide data needed to perform numerical analyses by making more realistic assumptions. The dam having a height of 0.6 m, a bottom width of 2 m and a crest width of 0.20 m is built in a channel 1 m wide, 0.81 m high and 6.14 m long. The evolution of the breach and the discharge through the breach resulting from piping due to seepage at the earth-fill dam bottom was investigated experimentally. The evolution of the dam failure is recorded by six cameras located at different locations. The time-varied of the breach areas at upstream and downstream sides are determined by applying the Gauss Area functions. The discharge of water through the breach and average outflow velocity are determined by using the continuity equation.
Article
Full-text available
Based on model tests of earthen dam breach due to piping failure, a numerical model was developed. A key difference from previous research is the assumption that the cross-section of the pipe channel is an arch, with a rectangle at the bottom and a semicircle at the top before the collapse of the pipe roof, rather than a rectangular or circular cross-section. A shear stress-based erosion rate formula was utilized, and the arched pipe tunnel was assumed to enlarge along its length and width until the overlying soil could no longer maintain stability. Orifice flow and open channel flow were adopted to calculate the breach flow discharge for pressure and free surface flows, respectively. The collapse of the pipe roof was determined by comparing the weight of the overlying soil and the cohesion of the soil on the two sidewalls of the pipe. After the collapse, overtopping failure dominated, and the limit equilibrium method was adopted to estimate the stability of the breach slope when the water flow overtopped. In addition, incomplete and base erosion, as well as one- and two-sided breaches were taken into account. The USDA-ARS-HERU model test P1, with detailed measured data, was used as a case study, and two artificially filled earthen dam failure cases were studied to verify the model. Feedback analysis demonstrates that the proposed model can provide satisfactory results for modeling the breach flow discharge and breach development process. Sensitivity analysis shows that the soil erodibility and initial piping position significantly affect the prediction of the breach flow discharge. Furthermore, a comparison with a well-known numerical model shows that the proposed model performs better than the NWS BREACH model. Keywords: Earthen dam, Piping failure, Overtopping failure, Breach flow, Numerical modeling, Sensitivity analysis
Article
Experimental results on the piping erosion process in an earthen embankment emplaced in a laboratory flume are reported in this paper along with the details of the experimental set-up and procedures. A mixture of sand, silt, and clay with different compaction rates is used for constructing the embankment. An image processing technique is successfully applied to track the erosion process from both side-looking and bottom-up views. The paper discusses changes in the depth, area, and volume of erosion during the piping phenomenon in a model embankment using a visual technique. The results show that increasing compaction of the construction layers significantly increases the time required for erosion but has little effect on the final-average depth of erosion. The ratio of the average depth of erosion to the average bottom width of piping is close to one at different time intervals. Exponential equations to estimate the depth of erosion, side area of the piping zone, and volume of eroded material are presented. Two approaches are investigated to estimate the volume: the approach based on the processing of images from both the side-view and bottom-view gives more accurate results than that based on processing the side-view.
Progress report on methods for estimating the probability of failure of embankment dams by internal erosion and piping
  • R Fell
  • C H Wan
  • M Foster
Fell, R., Wan, C. H., & Foster, M. (2003). Progress report on methods for estimating the probability of failure of embankment dams by internal erosion and piping.