Technical Feasibility Study for Improving the
Implementation Process of a 2MW Hybrid Power
Plant using Operational Research
Anne Emanuelle Varvenczack de Carvalho1, Bárbara Corrêa dos Santos2, Renata Duarte
Mellim3, Luiz Melk de Carvalho4, Rafaela Priscila Cruz Moreira5, Flávio Henrique Batista de
Souza6
Centro Universitario de Belo Horizonte UNIBH
Abstract
The concept of hybrid power plants has driven several studies to optimize the energy generation
process. In Brazil, the focus country of this work, despite having great potential for alternative
energy sources, still concentrates its electric production in hydrographic sources. The main
issue with hydrographic sources relies in their nature, which are inconstant and due to the
evident climate changes, their scenario can be even more aggravated. This article proposes a
study of the application of operational research as a way of improving the implementation
process and choosing a location for a hybrid plant in Brazilian territory. This work presents
quantitative-qualitative analyzes on the subject and a proposal for the implementation of a plant
through the center of gravity technique. The data was provided by a large company in the
energy sector. As a result, the calculation of the optimal point of implementation was obtained,
resulting in a necessary investment of about 38,896,000.00 Brazilian Reais (BRL), with a
payback period of 12 years.
Keywords: Hybrid Power Plants; Technical viability; Energy; Gravity center; Operational
Research.
47
1. Introduction
The negative effects caused by conventional energy production have been widely discussed
since the United Nations Conference on the Human Environment (Stockholm) convened by
the UN in 1972 (ONU, 2021). As the main subsequent event, it can be mention the Kyoto
Protocol signed in 1997, which established goals for the reduction of greenhouse gas emissions
and additional mechanisms for achieving these goals. One of these mechanisms is the Clean
Development Mechanism (CDM), which seeks, through the implementation of project
activities, to reduce GHG (Greenhouse Gas) emissions, or to increase CO2 removal, through
investments in more efficient technologies, replacement of fossil energy sources with
renewables, among other means (Lazaro & Gremaud, 2017).
Non-renewable energy sources, in addition to causing high emission of greenhouse gases, are
also subject to a shortage of raw materials, as occurred in the oil crisis in 1973. Even with these
unfavorable variables, these energy sources still represent the largest part of the world energy
consumption. According to data released in 2020 by the IEA (International Energy Agency,
2020), non-renewable energy sources such as coal and oil represent about 73.8% of the total
consumption, while renewable energy sources represent about 26.2%. In Brazil, hydroelectric
plants are the most significant source of electricity, representing 61.27% of its total (Pereira, et
al., 2017).
According to the National Electric System Operator, the reservoirs of the systems that generate
70% of the energy of the country operates with 19.59% of total capacity, which means that the
country is experiencing the worst water crisis in 91 years (ONS, 2021). These facts cause
greater urgency in the search for more viable alternatives in the energy matrix.
In order to implement it, it is necessary to structure the Project Management, which according
to PMI, is defined as the temporary effort undertaken to create a unique product, service or
result (PMI, 2017). These processes, in addition to generating quantitative-qualitative analysis,
can provide an optimization process, using operational research (OR) as a tool. OR is a
mathematical method composed of statistical and algorithmic models that are used to help in
decision-making tasks (Giordano, Fox, & Horton, 2013).
Thus, the general objective of this article is to propose the analysis of the process of
implantation of an energy plant based on the production of wind-photovoltaic hybrid energy,
in order to present a quantitative-qualitative evaluation with a proposal of mathematical
modeling for optimization of its processes. In this way, the specific objectives are to evaluate
the implementation process, to weave quantitative-qualitative comparative analysis between
conventional plants and hybrid plants, and verify through mathematical modeling and
simulations the possibilities of optimization of the process.
In view of the facts previously mentioned, the work is justified by the risk of an energy crisis
in the country, which requires an alternative energy source, as well as by the growing trend of
clean and renewable energy generation motivated by international agreements.
48
2. Materials and Methods
2.1 Theoretical Foundations
Three concepts were the references of the work: Energy Production, Strategic Financial
Planning and Operational Research.
This work aims to analyze two of the forms of sustainable and renewable energy production,
which are photovoltaic energy and wind energy, and the operation of both together in a hybrid
power plant (Tessaro, 2006; ANEEL, 2021).
• Photovoltaic Energy: photovoltaic energy, also known as solar energy, bases its operation
on silicon photovoltaic cells (Sc) combined with boron, to create positive charges, and with
phosphorus, to create negative charges. When the plates capture solar radiation, the silicon
electrons are excited along with their combinations, resulting in a release of electrons from
the atoms, which generates the direct electric current.
• Wind Energy: wind energy is known for capturing energy by the wind through wind
turbines. Its generation is produced by wind turbines that, from the force of the wind, there
is a movement of the blades, which rotate the rotor inside the nacelle, generating
mechanical energy.
• Hybrid Power Plant: a hybrid power plant is the combination of two or more sources of
energy or power, including forms of storage.
The wind and solar energy can be combined, so that during the day the photovoltaic plant
would produce energy at its peak, while at night the energy produced by the wind would be
responsible for its maximum capacity, using the efficient production of both sources. Another
interesting point of this plant is the reduction of operation and maintenance costs, as there is
the use of the transmission line, as well as the costs of logistics during the project.
To verify the economic viability of a project, it is necessary to prepare a Strategic Financial
Planning aiming at observing what the costs and expenses will be. According to (Freitas &
Rossi, 2021): “Planning is the key to business management. The corporate budget is a financial
plan capable of leading the company to its goals, serving as a control of operations in the short
and long term.”.
The process of implementing strategies requires changes in the organization. Therefore, the
availability of material and financial resources is essential for the strategies to be implemented,
as the lack of resources or delays can become a reason for well-formulated strategies to fail.
Finally, for the optimization of this implementation process, Operational Research (OR) is
implemented, which consists of a mathematical modeling tool that is applied in the resolution
of real problems, helping on the optimal decision-making tasks during the planning and
execution of projects. In summary, it consists of the following steps: formulate the problem,
build the model from the established metrics, obtain the solution, test the result and, finally,
implement, correlating the variables of the problem (Souza, Teixeira, & Simão, 2017).
49
In the present research, more specifically, Linear Programming Problems (LP) were used in
OR analysis, which consists of a method for solving optimization problems, with restrictions
in the objective function that are linear in relation to the control variables. Based on this LP
modeling, the present work uses the Center of Gravity technique, which allows, through the
application of equations 1, 2, 3 and 4, to define a optimal location (Kreyszig, Kreyszig, &
Normington, 2021).
(1)
(2)
(3)
(4)
Where Xx corresponds to the x coordinate (latitude) of the new facility allocation point, Xy
corresponds to the y coordinate (longitude) of the new facility allocation point, xi is the latitude
of the studied point, with i varying from 1 to I, yi is the longitude of the study point, with i
varying from 1 to I, ρi is the density of the point, with i varying from 1 to I, Di corresponds to
the density of each demand point, with i varying from 1 to I, and Ki corresponds to solar
irradiance or wind speed data from point i, with i varying from 1 to I.
The equations (1) and (2) result in the densities of reference points, by multiplying them with
the database for each application. Equation (3) calculates the optimal latitude of x using the
densities of x and y, and, finally, equation (4) calculates the optimal longitude of y using the
densities of x and y.
A few papers in the literature have also addressed this subject of implementing hybrid energy
plants, and they were considered as a reference for the present work.
In the work of (Campos, 2020) it was carried out an analysis of the complementarity of
generation of solar and wind plants and the role of energy storage for hybrid plants. In this
work, the author aimed to optimize the dimensioning and operation of wind and photovoltaic
plants, together with battery-based storage systems, which could increase the dispatchability
of these energy sources.
In (Marozinski, 2018) it was evaluated the generation of a hybrid photovoltaic wind power
plant in the state of Rio Grande do Norte, based on the methodological proposal developed by
Empresa de Pesquisa Energética - EPE.
50
2.2 Methodology
To achieve the proposed objectives, the following steps were analysed: evaluating the strategic
issues of a plant; delimit the OR steps that will be carried out in the research; assess the possible
returns and impacts of the project.
Initially, the location of installation of the hybrid plant will be defined, considering five critical
evaluation points:
1 - incidence of solar radiation between 5.8 and 6.2 kWh/m².
2 - annual average wind speed at 100m height above 8m/s.
3 - flat terrain (Garni & Awasthi, 2017).
4 - tax benefits in the region (Bittencourt, Busch, & Cruz, 2021).
5 - nearby utility substation.
As a reference for this process, the database of the second edition of the Brazilian Atlas of Solar
Energy (2017) was used to define the study sites for the first criterion. For the second criterion,
the CRESESB database - Reference Center for Solar and Wind Energy (Brito, 2008) was used,
which also makes reference to the Brazilian Atlas of Solar and Wind Energy. In the third
criterion, it was necessary to examine the geomorphology map made by the Secretary of State
for Science and Technology and the Environment of Paraíba – SECTMA. For the fourth
criterion, the data from CINEP - Companhia de Desenvolvimento da Paraíba was used as
source. And finally, for the fifth criterion, the data from the Dynamic Map of the SIN, available
on the website of the ONS - National Electric System Operator (ONS, 2021), was analyzed.
For feasibility and financial analyses, data from a large company operating in the market was
used.
After defining the criteria for installing the plant, an OR project is prepared with the objective
of defining the best geographic point in Brazil for the execution of the work, according to the
following steps:
1 - Formulate the problem: hybrid plants must be built at strategic points, aiming at
using their maximum capacity. In this way, the maximum capacity criterion will be
used to find the optimal Brazilian geographic point for the execution of the project.
2 - Build the model from the established metrics: to develop the mathematical model,
it will be necessary to collect geographic coordinates of the best points of incidence of
solar radiation, wind performance, flat terrain, tax benefits and the substations of the
concessionaire.
3 - Get the solution mathematical location modeling through Excel support.
4 – Test the result, assessing whether the chosen geographic point has an average
incidence of solar radiation between 5.8 and 6.2 kWh/m² day, annual average wind
51
speed at 100m height above 8m/s, flat terrain, benefits inspectors in the region and the
nearby substation of the concessionaire.
5 - Evaluate the implementation process.
Such procedures will then undergo an impact assessment. The next step is to prepare a strategic
financial plan, aiming to obtain the best Internal Rate of Return (IRR) for the investor, based
on two topics: WORK and OPERATION AND MAINTENANCE (O&M). At this stage, a
spreadsheet will be presented with the costs and expenses of the project, involving the
following parts:
1 - 1MW wind turbine park.
2 - 1MW photovoltaic generator park, with 3 technologies of photovoltaic panels:
a - Crystalline silicon (c-Si).
b - Microcrystalline amorphous silicon (a-Si/uc-Si).
c - Copper-Indium-Gallium-Selenium (CIGS).
3 - Battery Storage System, with 2 technologies (Ni-Cad and Lithium-ion).
4 - Monitoring and Control Center.
5 - Meteorological station (solarimetric and anemometric).
At the end of the study, to optimize the Implementation Process of a Hybrid Power Plant, an
implementation schedule will be prepared, aiming to execute the project management with
excellence. From these topics, it will be possible to prove the feasibility of the project.
3. Results
From the five evaluation definitions delimited for plant implementation strategies, the
following results were obtained.
3.1 Implementation Definition
According to the first evaluation point, it was outlined through the database provided by Atlas
Solar (2019), that the region under analysis would be the Brazilian Northeast, as it has a higher
incidence of solar rays, with an average daily incidence ranging between 5.6 and 6.2 kWh/m²
in most of its states. Some points such as the coast of Maranhão, regions of the state of Bahia
and João Pessoa are the regions with the highest average in Brazil (6.2MJ/m² day, equivalent
to 2,264 kWh/m² year), as shown in Figure 1.
52
Figure 1: Horizontal irradiation - Brazil
Source: Global Solar Atlas - Solargis, 2019
Regarding the second evaluation point, and considering the data from ETENE - Empresa
Transmissora de Energia do Nordeste - Northeast Energy Transmission Company (Bezerra,
2019), which contains the records of annual average speeds and wind power flows in Brazil, it
is possible to notice that the Northeast region is the most favorable area among the other regions
of the country. This region has the higher rates on the coastal coast and in the offshore perimeter
- where it goes beyond the borders of Brazil, also entering the sea - as shown in Figure 2. High
slope areas are not economically viable for solar energy projects, as they require earthmoving
and landfill works the project. Among the requirements for the implementation of photovoltaic
farms, it is indicated that flat areas are chosen, without the presence of rocks and with a
maximum slope of 10%, as described by the third evaluation point.
According to data on the topography of Brazil released by the second edition of the Brazilian
Atlas of Solar Energy, the central region of the North region, the northern region of the
Northeast region and the coastal coast are the areas with less relief in the country, as illustrated
in the figure 3 (Atlas, 2021). The tax incentives for reducing income tax and non-refundable
surcharges and reinvestment administered by SUDENE (Superintendência do
Desenvolvimento do Nordeste - Superintendence for the Development of the Northeast), are
part of the public policy promoted by the Federal Government with the objective of reducing
economic and social inequalities, throughout the regions by creating development
opportunities (as elected by the fourth evaluation point). In 2019, investments made in
Infrastructure stood out with around BRL (Brazilian Reais) 8.4 billion with 87 requests
53
approved, with emphasis on projects in the energy sector, with BRL 7.4 billion and 55 requests
approved.
Figure 2: Annual average wind speed at 100m height (m/s)
Source: (Bezerra, 2019)
Figure 3: Topography of the Brazilian territory. SRTM v4 data
Source:( Pereira et al.. 2017)
54
Among the tax incentives granted by SUDENE there is the Exemption from IRPJ (Programa
de Inclusão Digital - Digital Inclusion Program), which consists of a 75% reduction in taxes
for new projects.
Electric power plants, whether hydraulic, thermal, wind and photovoltaic, generate energy at
low voltage levels. The energy generated at these voltage levels initially feeds a transformer,
which has the function of raising the generation voltage to levels compatible with the value of
the block of energy generated and the distance to be traveled through a transmission system.
For this reason, it is necessary that the defined area of implantation also have nearby power
substations, which is a set of industrial equipment interconnected with the objectives of
controlling the flow of power, modifying voltages and altering the nature of the electric current,
as well as to ensure the protection of the electrical system.
3.2. Financial Strategic Planning
To assess the economic viability of the project, a financial planning of the project was prepared
based on consultation and studies carried out in a company operating in the market. Such
organization, as mentioned, is a service provider of projects in photovoltaic and wind power
plants. Firstly, a basic budget of the expenses and costs of the hybrid plant installation project
was developed, which is detailed in table 1.
Table 1: Project budget for the hybrid plant
DESCRIPTION
MONTHLY (BRL)
COST CENTER
Company for the elaboration of the electrical/civil project
760.000,00
HUMAN RESOURCES
Project management company
936.000,00
HUMAN RESOURCES
Company to build the wind farm
6.050.000,00
HUMAN RESOURCES
Solar plant installation company
1.750.000,00
HUMAN RESOURCES
Network adequacy company
1.000.000,00
HUMAN RESOURCES
Office supplies
72.000,00
ADMINISTRATIVE COSTS
Vehicle Rental
156.000,00
ADMINISTRATIVE COSTS
4ha plot of land
180.000,00
ADMINISTRATIVE COSTS
Solar panels
2.700.000,00
EQUIPMENT
Metal structures for solar panels
530.000,00
EQUIPMENT
Photovoltaic Inverters
220.000,00
EQUIPMENT
Transformers
130.000,00
EQUIPMENT
10 100kWp wind turbines
16.000.000,00
EQUIPMENT
Electrical infrastructure for wind turbines
2.000.000,00
EQUIPMENT
Central Storage with batteries
6.400.000,00
EQUIPMENT
Weather station
12.000,00
EQUIPMENT
FINAL VALUE
38.896.000,00
Source: (Authors, 2022)
Based on this study, it can be concluded that a total investment of 38,896,000.00 BRL will be
necessary, with 10,496,000.00 BRL reserved for human resources such as service providers,
expenses for project preparation and training of members; 408,000.00 BRL allocated to
administrative expenses such as office supplies, vehicle rental and land where the plant will be
55
installed; 27,992,000.00 BRL reserved for the acquisition of equipment such as photovoltaic
panels, wind turbines, inverters and metallic structures. Based on that, to calculate the rate of
return of the investment, it was considered that the hybrid plant will generate a power of
2.0MWh, under a tariff for the generation of wind and solar park of BRL196.00/MWh.
Considering a period of one year (8,760 hours), the revenue of the plant can be calculated as
follows:
Annual Revenue: 2.0 × 8760 × 196.00 = BRL 3,433,920.00
Considering that in one year the revenue from the hybrid plant is 3,433,920.00 BRL and the
initial investment is R$38,896,000.00, the investment will be returned in 12 years.
3.3. Project management
In order to execute a project with excellence and avoiding the incidence of errors, it is necessary
to prepare a basic schedule. Considering this objective, a 2.0MW hybrid power plant was
prepared based on the information that the operating company provided for the continuity and
proof of this study, as shown in table 2.
Table 2: Schedule for Implementation of the 2.0MW Hybrid Power Plant
Task
DURATION (working days)
1.
HR CONTRACTING
254
2.
TECHNICAL VISIT
252
3.
ENGINEERING
125
Preliminary Projects
38
Civil Project
65
Planning
22
4.
ACQUISITION AND SUPPLY
60
5.
IMPLANTATION
175
Preliminary services
63
Photovoltaic Park
135
Wind Farm
120
Storage
30
6.
CLOSURE AND REPORT
98
Source: (Authors, 2022)
Table 2 shows a sample of activities that add up to more than 60 actions. Thus, the work would
have a duration of 282 working days.
3.4. Mathematical Modeling
To perform the mathematical calculations, it was chosen the Google Sheets tool, aiming at
dynamics, practicality and greater precision compared to conventional calculators. The first
step was to filter the databases (as shown in Table 3), eliminating coordinates that did not meet
one or more restrictions defined in topic 2.2. Then, with the help of the Google tool, tables
were created with the remaining data, and the OR model was developed to find the optimal
result.
56
In the computational model, the center of gravity formula was applied to the database of annual
average solar irradiation (kWh/m²) of the northeastern states, obtaining the coordinates of x as
-7.001944 latitude and y as -35.35127 longitude. In sequence, wind data (m/s) from the
northeast of the country were manipulated, obtaining the results of x -6.193027 latitude and y
-36.239455 longitude. To find the coordinate equivalent to the optimal point for the hybrid
plant, the calculation of the midpoint between the two discovered points was used, with the
final result found: -6.59749 latitude and -35.79536 longitude, as shown in Figure 4.
The optimal point generated by the formula of center of gravity combined with the midpoint,
is located in the city of Cacimba de Dentro in the State of Paraíba, the nearest Substation is
PILÕES II of CHESF - Companhia Hidro Elétrica do São Francisco. The relief of the area
qualifies as a depression with tabular shapes, haracterized by being a monotonous, smooth-
wavy relief.
Table 3: Sample of 10 data Filtered Database for mathematical modeling
LAT (X)
LONG (Y)
V_100m (velo. 100m)
Density Xi
Density Yi
-10.393.936,00
-42.821.646,00
8,000120
-83.152.735,2723
-342.578.306,5975
-3.915.293,00
-38.969.638,00
8,000190
-31.323.087,9057
-311.764.508,2312
-3.166.062,00
-40.754.715,00
8,000470
-25.329.984,0491
-326.056.874,7161
-10.393.936,00
-43.056.524,00
8,000670
-83.158.451,9371
-344.481.039,8711
-11.539.818,00
-4.145.935,00
8,000890
-92.328.814,4380
-33.171.169,8822
-9.336.198,00
-42.023.059,00
8,001010
-74.699.013,5600
-336.226.915,2896
-5.501.899,00
-37.137.586,00
8,001010
-44.020.748,9180
-297.138.196,9619
-5.457.827,00
-37.137.586,00
8,001010
-43.668.128,4053
-297.138.196,9619
-12.156.832,00
-431.035,00
8,001170
-97.268.879,4934
-3.448.784,3110
-3.386.424,00
-42.492.816,00
8,001240
-27.095.591,1658
-339.995.219,0918
Source: (Authors, 2022)
Figure 4: Optimal Point Superimposed on the Wind Database - zoom in and zoom out
Source: (Authors, 2022)
Regarding the fiscal benefit parameter, the region has the Fain - The Paraíba Industrial
Development Support Fund, which has the purpose of granting financial incentives for the
implementation, expansion, revitalization and relocation of industry, granting presumed ICMS
(taxes applied on services) credit with percentages varying between 48% and 74.25%. This
57
variation occurs according to the number of direct jobs generated, volume of investments made,
and the location chosen by the company. In addition to this fund co-managed by CINEP
(Paraiba Development Company - Companhia de Desenvolvimento da Paraíba), there is also
the SUDENE - Superintendence for the Development of the Northeast, which promotes
investments made in projects in the energy sector, among the tax incentives granted by
SUDENE there are a tax reduction of 75% for new projects and tax reinvestments.
4. Conclusion
With the constant creation of new climate goals for Brazil in order to reduce the emission
of greenhouse gases by 50% by 2030 and neutralize carbon emissions by 2050, industries with
clean and renewable energy are gaining notoriety. This work aimed to address possible
improvements in the process of choosing the location and implementation of a hybrid power
plant in northeastern Brazil, considering mainly the potential for generating wind and solar
energy that the region has available. For this case, it was also necessary to understand the
economic feasibility of the project, that is, what would be the Internal Rate of Return (IRR) to
the investment, based on the topics of work, operation and maintenance. As a result, it was
found that the necessary investment would be about 38,896,000.00 BRL, with a payback period
of 12 years.
To validate the optimal point found through the application of the concepts and formula of the
Operational Research, three important parameters were determined, namely: type of land,
substation of the nearby concessionaire and tax benefits of the region. The resulting coordinates
belong to the city of Cacimba de Dentro in the State of Paraíba, which has a land characterized
by a depression with tabular shapes, that represents a monotonous and smooth-wavy relief.
This area corresponds to a suitable region for the installation of the plant, as it does not present
large undulations, thus not requiring large earthworks. The point is located relatively close to
a substation, about 61 km away, being located in the city of Pilões-PB. Finally, the location
also has tax incentives with FAIN - The Paraíba Industrial Development Support Fund granting
presumed ICMS tax credit with percentages ranging from 48% to 74.25%, and SUDENE -
Superintendence for the Development of the Northeast, also granting tax exemption (75%
reduction in tax for new ventures) and tax reinvestments, which ends up enabling the
installation of the hybrid plant. Thus, it is concluded that the optimal point satisfies all the
criteria defined by the authors, and that the results obtained in this work prove the possibility
of using this methodology for studies that require the ideal location for a given enterprise not
necessarily linked to costs.
58
References
Atlas, P. G. (2021, September 06). Portal Global Solar Atlas [Global Solar Atlas Portal]
Retrieved from https://globalsolaratlas.info/support/data-sources
Bezerra, F. D. (2019). Enegia Eólica no Nordeste [Wind Energy in the Northeast] Caderno
Setorial ETENE, Ano 4 N 66.
Brasil, A. N. (2021, September 08). Retrospectiva ANEEL 2020 [ANEEL Retrospective 2020].
Retrieved from ANEEL:
https://www.aneel.gov.br/documents/656877/15495819/Retrospectiva+ANEEL+2020/1
2d3aec4-b714-523e-a3e4-25b838ca2667?version=1.2
Brito, S. d. (2008). Centro de referência para energia solar e eólica [Reference center for solar
and wind energy] CRESESB informe, 3.
Bittencourt, S., Busch, S., Cruz, M. (2017) O Mecanismo de Desenvolvimento Limpo no Brasil
[The Clean Development Mechanism in Brazil.] Available:
http://repositorio.ipea.gov.br/bitstream/11058/9474/1/O%20Mecanismo.pdf
Campos, R. A. (2020). Análise da complementaridade de geração entre usinas solar e eólica e
o papel do armazenamento de energia para usinas híbridas [Analysis of generation
complementarity between solar and wind power plants and the role of energy storage for
hybrid power plants]. Master dissertation. Universidade Federal de Santa Catarina.,
Florianópolis.
Freitas, M., & Rossi, R. (2021, September 20). Planejamento financeiro para um projeto de
empresa de hidroponia de alface Lactusa sativa da variedade brunella.[ Financial
planning for a hydroponics company project of Lactusa sativa lettuce of the brunella
variety] Retrieved from Companhia AlfaCroC:
https://www.encontrohidroponia.com.br/images/site/Anais_Final.pdf#page=95
Garni, H. A., & Awasthi, A. (2017). Solar PV power plant site selection using GISAHP based
approach with application in Saudi Arabia. Applied Enegy, 1225-1240.
Giordano, F. R., Fox, W. P., & Horton, S. B. (2013). A first course in Mathematical modeling.
Boston: M. D. Brooks Cole.
International Energy Agency – IEA (2020). IEA, Key estimated energy demand, CO2 emissions
and investment indicators, 2020 relative to 2019: https://www.iea.org/data-and-
statistics/charts/key-estimated-energy-demand-co2-emissions-and-investment-
indicators-2020-relative-to-2019. Access in: 08 sep 2021.
Kreyszig, E., Kreyszig, H., & Normington, E. J. (2021, September 24). Advanced Engineering
Mathematics. Retrieved from
https://www.bau.edu.jo/UserPortal/UserProfile/PostsAttach/59003_3812_1.pdf
59
Lazaro, L. L., & Gremaud, A. P. (2017). Contribuição para o desenvolvimento sustentável dos
projetos de Mecanismo de desenvolvimento limpo na América Latina [Contribution to the
sustainable development of Clean Development Mechanism projects in Latin America]
O&S (Organizations & Society), 53-72.
Marozinski, R. P. (2018). Avaliação da geração de uma usina híbrida eólico-fotovoltaica no
estado do Rio Grande do Norte [Evaluation of the generation of a hybrid wind-
photovoltaic plant in the state of Rio Grande do Norte] Specialization monography,
Curitiba.
ONS. (2021, September 08). Escassez hídrica. [Water shortage.] Retrieved from Operador
Nacional do Sistema Elétrico 9 National Electric System Operator]:
http://www.ons.org.br/Paginas/Noticias/20210707-escassez-hidrica-2021.aspx
ONU. (2021, September 08). A ONU e o meio ambiente.[The UN and the environment]
Retrieved from Organização das Nações Unidas: https://brasil.un.org/pt-br/91223-onu-e-
o-meio-ambiente
Pereira, E. B., Martins, F. R., Gonçalves, A. R., Costa, R. S., Lima, F. L., Ruther, R., . . . Souza,
J. G. (2017). Atlas Brasileiro de Energia Solar [Brazilian Solar Energy Atlas]. São José
dos Campos: INPE.
PMI. (2017). Project Management Body of Knowledge (PMBOK). Newtown Square: Project
Management Institute: 6 ed.
Sonia Bittencourt, S. B. (2021, September 04). O mecanismo de desenvolvimento limpo no
Brasil. [The clean development mechanism in Brazil] Retrieved from IPEA:
http://repositorio.ipea.gov.br/bitstream/11058/9474/1/O%20Mecanismo.pdf
Souza, F. H., Teixeira, G. A. and Simão, D. R. (2017). Estudo de Caso da Aplicação de
Métodos Lineares para Auxílio no Processo de Tomada de Decisão em uma Indústria de
Laticínios [Case Study of the Application of Linear Methods to Aid in the Decision
Making Process in a Dairy Industry] VII Congresso Brasileiro de Engenharia de
Produção , Ponta Grossa. PR.
Tessaro, A. R. (2006). Desempenho de um painel fotovoltaico acoplado a um rastreador solar
[Performance of a photovoltaic panel coupled to a solar tracker]. Proceeding of the 6
Encontro de Energia no Meio Rural.