Conference PaperPDF Available

Experimental Study of the Evolution of the Breach and the Discharge Through the Breach Resulting from Piping due to Seepage at the Earth-Fill Dam Top

Authors:

Abstract

Internal erosion, also known as piping, is one of the most important causes of earth-fill dam breaks. Many researchers dealing with numerical analyses in this area make some simplified assumptions about the shape of the breach and the discharge of water flowing through the breach. This study was conducted in the scope of the project supported financially by the Scientific and Technological Research Council of Turkey and it consists of experimental study which aims to provide data needed to perform numerical analyses with more realistic approaches. A dam with a height of 0.6 m, a bottom width of 2 m and a crest width of 0.20 m was built in a flume 1 m wide, 0.81 m high and 6.14 m long. Before the construction of the dam, some common soil mechanics tests were carried out. The dam was constructed by using a mixture consisting of 85 % sand and 15 % clay. A circular tunnel with a diameter of 2 cm was created along the centerline at 6 cm below the dam crest. In the closed system, water was pumped from the lower reservoir to the upper channel. Six cameras located at different locations recorded the evolution of the dam failure. Gauss Area formula was applied to determine the time-varied of the breach areas at upstream and downstream sides. The discharge of water through the breach and average flow velocity were determined by using the continuity equation. The changes in water depth in the channel were also recorded.
Proceedings of the 39th IAHR World Congress
19-24 June 2022
Granada, Spain
DOI number
©2022 IAHR. Used with permission / ISSN-L 2521-7119
Experimental Study of the Evolution of the Breach and the Discharge Through the
Breach Resulting from Piping due to Seepage at the Earth-Fill Dam Top
Mehmet Sukru Guney(1), Merve Okan(1), Emre Dumlu(2), Aslı Bor(1), Pelin Aklık(1), Gökmen Tayfur(2)
(1) İzmir University of Economics, İzmir, Turkey,
sukru.guney@ieu.edu.tr, merve.okan@ieu.edu.tr, asli.turkben@ieu.edu.tr, pelin.aklik@ieu.edu.tr
(2) Izmir Institute of Technology, İzmir, Turkey,
emredumlu@iyte.edu.tr, gokmentayfur@iyte.edu.tr
Abstract
Internal erosion, also known as piping, is one of the most important causes of earth-fill dam breaks. Many
researchers dealing with numerical analyses in this area make some simplified assumptions about the shape
of the breach and the discharge of water flowing through the breach. This study was conducted in the scope of
the project supported financially by the Scientific and Technological Research Council of Turkey and it consists
of experimental study which aims to provide data needed to perform numerical analyses with more realistic
approaches. A dam with a height of 0.6 m, a bottom width of 2 m and a crest width of 0.20 m was built in a flume
1 m wide, 0.81 m high and 6.14 m long. Before the construction of the dam, some common soil mechanics tests
were carried out. The dam was constructed by using a mixture consisting of 85 % sand and 15 % clay. A circular
tunnel with a diameter of 2 cm was created along the centerline at 6 cm below the dam crest. In the closed
system, water was pumped from the lower reservoir to the upper channel. Six cameras located at different
locations recorded the evolution of the dam failure. Gauss Area formula was applied to determine the time-
varied of the breach areas at upstream and downstream sides. The discharge of water through the breach and
average flow velocity were determined by using the continuity equation. The changes in water depth in the
channel were also recorded.
Keywords: Earth-fill dam; Piping; Breach geometry; Breach development; Discharge through breach
1. INTRODUCTION
Piping is one of the main problems which threatens the stability of earth-fill dams. Soil erosion can be
experienced in earth structures, especially in earth dams and levees, through embankment, foundation or from
embankment to foundation. This kind of erosion can occur in three stages: a) initiation and continuation of
erosion, b) progression to form a pipe, and c) formation of a breach (Fell et al., 2003). The FP5 IMPACT
(Investigation of Extreme Flood Process and Uncertainty) European project (2001-2004) revealed the
assessment and reduction of risks from extreme flooding caused by natural events or failure of dams and water
defense structures (Zech et. al.,2007). Chen et al. (2019) pointed out that between 1954 and 2018, 3541 dam
breach accidents had occurred and more than 30% of them were due to piping. Sparmos homogenous dam in
Greece is one of the recent examples (Dounias, 2019).
The ICOLD Bulletin B164 (2013) had analyzed the internal erosion of existing dams, levees and dikes, and
their foundations. Greco et al. (2008) used a two-dimensional depth-averaged (2DH) numerical model to
simulate the evolution of a breach in an earth-fill dam. Sharif et al. (2015) constructed a dam in a laboratory
flume by using a mixture of sand, silt, and clay with different compaction rates and examined the changes in the
depth, area, and volume of erosion during the piping evaluation by utilizing an image processing technique.
Most of the researchers realizing numerical analyses make some simplified assumptions concerning shape of
a breach and discharge of water flowing through the breach. Morris et al. (2008) revealed that instead of
simplified approaches, more realistic approaches are required about the breach mechanism as well as the
breach geometry and flow through the breach. Dhiman and Patra (2018) investigated the influence of the soil
properties on the breaching process by performing 13 experiments in the hydraulic engineering laboratory of
National Institute of Technology, Rourkela, India. Further, a multivariable regression was performed using the
test data of 25 embankments to obtain the relationship between the breach parameters and the soil properties.
New nondimensional control variables, such as embankment soil factors, relative compaction effort, relative
particle size, and erodibility, were proposed for developing the relationships. Damme (2020) presented a
process-based breach widening relation for levees constructed of dilatant soils. The process-based relation was
Proceedings of the 39th IAHR World Congress
19-24 June 2022, Granada, Spain
©2022 IAHR. Used with permission / ISSN-L 2521-7119
derived from the weir flow equation and a process-based erosion equation. The breach widening relation can
account for the effects of variations in soil parameters.
The aim of this study is to realize experiments to study the evolution of dam failure resulting from piping
along the centerline at 6 cm below the dam crest of the earth-fill dam.
2. EXPERIMENTAL PROCEDURE
The dam was constructed in a rectangular flume (Figure 1) with a width of 1 m, height of 0.81 m and length
of 6.1 m. At the upper channel of the flume, a homogeneous dam possessing 0.6 m height, 2 m bottom width
and 0.20 m crest width was constructed with the slope at the upstream and downstream sides of 1:1.5. Water
was circulated between the lower reservoir and the upper channel by means of a pump.
Figure 1. Experimental flume.
Some soil mechanics experiments were carried out before building the dam. The soil mixture utilized at the
construction of the dam was prepared by using 85 % sand and 15 % clay. The grain- size distribution of the
mixture obtained from the wet sieve and hydrometer analyses is shown in Figure 2.
Figure 2. Grain size distribution of the dam material.
From Figure 2, some characteristic diameters were obtained as D10= 0.006 mm, D30= 0.057 mm, D50=
0.099 mm, and D60= 0.3 mm. The uniformity coefficient Cu equals 54.5 and the curvature coefficient Cc is
equal to 1.969.
The specific weight of the mixture was found to be as Gs = 2.63, from the test ASTM D854 14.
The permeability of the mixture was found as k= 4.66x10-4 cm/s from the falling head permeability
test.
From the direct shear test, it was found that the soil has a cohesion value of 15.33 kPa and an internal
friction angle of 33.93°.
According to the consolidation test results, the compression index (Cc), recompression index (Cr) and
swelling index (Cs) were found to be as 0.100, 0.009 and 0.007, respectively. The oedometric modulus of
deformation (Eoed) was obtained as 35714 kN/m².
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
0.00050.0050.050.5
Percent Passing, (%)
Diameter (mm)
Proceedings of the 39th IAHR World Congress
19-24 June 2022, Granada, Spain
In order to determine the water content, the standard proctor test (ASTM-698) was executed by applying
13 drops and the so obtained curve is plotted in Figure 3. The reason of applying reduced energy (13 drops
instead of 25) was to increase the probability of the piping occurrence. The maximum dry density and optimum
water content were obtained as ϒdrymax= 1.794 g/cm3 and wopt = 12.5 %. The void ratio (e) was calculated as
0.469.
Figure 3. Dry density - water content relationship.
In Figure 4, some construction stages and completed shape of the dam body are shown. The dam was
constructed at 6 layers, each layer being 10 cm high. After homogeneous placement of the soil material, the
mixture was compacted using a flat plate and a proctor hammer (Figure 4a). When the compaction was
completed, the molds were extracted, and then the sides of the dam were trimmed by using a trowel.
(a) (b)
(c) (d)
Figure 4. Some construction stages: (a) Compacting by Proctor Hammer, (b) After compaction of the first
layer, (c) After compaction of the last layer, (d) final shape.
1.74
1.76
1.78
1.8
10.00 11.25 12.50 13.75 15.00
Dry Density (gr/cm³)
Water Content (%)
Proceedings of the 39th IAHR World Congress
19-24 June 2022, Granada, Spain
©2022 IAHR. Used with permission / ISSN-L 2521-7119
The flow rate was measured by a magnetic flowmeter. The evolution of the dam failure was recorded by
six cameras placed at different locations. In order to adjust the water level, an electromagnetic sensor was
attached which starts and stops the pump when water depths in the channel were 0.540 m and 0.555 m,
respectively.
In order to generate the formation of the breach, a circular hole of 2 cm diameter lying from upstream to
downstream was created at 54 cm from the bottom of the dam body. The experiment was started when the
water in the flume reached this level and passed through the hole.
3. EXPERIMENTAL FINDINGS
The temporal developments of the breach recorded by the cameras located at downstream and upstream
of the dam are given in Figure 5 and Figure 6, respectively. The time t=0 corresponds to the starting of the
seepage.
(a) (b)
(c) (d)
Proceedings of the 39th IAHR World Congress
19-24 June 2022, Granada, Spain
(e) (f)
(g) (h)
Figure 5. The temporal development of the breach at downstream a) t=0, b) t=180, c) t=230 s, d) t=280 s,
e) t=340 s, f) t= 380 s, g) t=410 s, h) t= 570 s
(a) (b)
Proceedings of the 39th IAHR World Congress
19-24 June 2022, Granada, Spain
©2022 IAHR. Used with permission / ISSN-L 2521-7119
(c) (d)
(e) (f)
(g) (h)
Figure 26. The temporal development of the breach at upstream a) t=0, b) t=180, c) t=230 s, d) t=280 s,
e) t=340 s, f) t= 380 s, g) t=410 s, h) t= 570 s
The water depths in the channel were attained from the camera recordings. In order to evaluate the
shape of the breach and survey the changes in its geometry, the upstream and downstream cameras
images were investigated. In order not to work with fisheye images, the videos taken from lateral camera
recording were edited and straightened with Hit-film-Express version 2021.1. Moreover, extra sensitive
solutions were implemented to ensure that the images are completely flat. The images taken from the
records corresponding to a certain time were scaled and the boundary coordinates of the breaches at
downstream and upstream sides were specified at Get-data Graph Digitizer 2.26 software. The surface
areas of the breach developed at different instants were computed by the Gauss Area functions.
The discharge of water through the breach was determined by using the continuity equation:
∆S=(Q
pump
-Q
breach
)∙∆t
[1]
Proceedings of the 39th IAHR World Congress
19-24 June 2022, Granada, Spain
where Qpump is the flow rate delivered by the pump, Qbreach is the discharge through the breach, ∆S is the storage
in the channel during the time interval ∆t.
The average velocity V of the flow through the breach was approximately calculated by using
V=
Q
breach
A
[2]
where A represents wetted area.
The temporal water depths in the channel and discharge through the breach calculated by Eq. [1] are given
in Figure 7 and Figure 8, respectively.
Figure 7. Time-varied water depths in channel.
Figure 8. Time-varied discharge through the breach.
The temporal variations of the breach area at downstream and upstream are shown in the Figure 9.
Figure 9. Temporal variations of the breach area at downstream and upstream.
0
5
10
15
20
25
30
35
40
45
50
55
60
0 100 200 300 400 500 600
Water Level (cm)
Time (s)
0
500
1000
1500
2000
2500
3000
3500
0 100 200 300 400 500 600
Time (s)
Downstream Upstream
Proceedings of the 39th IAHR World Congress
19-24 June 2022, Granada, Spain
©2022 IAHR. Used with permission / ISSN-L 2521-7119
The time dependent wetted area and velocity values obtained by using Eq. [2] at upstream and
downstream are given in Figure 10 and Figure 11, respectively.
(a) (b)
Figure 10. (a) Wetted area and (b) velocity values at upstream
(a) (b)
Figure 11. (a) Wetted area and (b) velocity values at downstream
4. RESULTS AND CONCLUSIONS
In this study, time-varied evolution of the breach resulting from the piping at the top of earth-fill dam was
analyzed. The discharges through the breach corresponding to different instants were calculated using the
continuity equation. The boundary coordinates of the breach surface areas and wet areas of the breach were
obtained by using the Get-Data Graph Digitizer, and the areas at each time were calculated by applying the
Gauss-area function of these obtained coordinates. The time dependent velocity values through the breach
areas were also calculated. During the experiment, the breach initiated on the downstream side and then
evolved towards to upstream side. The maximum discharge through the breach was calculated as Qbreach=8.31
L/s at t=240 s. The maximum breach surface area at the upstream was found to be Aups= 3128.7 cm2 at t=520
s, while at downstream Adown= 2379.3 cm2 at t=370 s and remained unchanged afterwards. The maximum
wetted areas were Awetted-ups=274 cm2 at t=250 s and Awetted-downs=225 cm2 at t=270 s. The maximum velocity
values through the breach were calculated as Vups=51.1 cm/s at t=190 s and Vdown=55.8 cm/s at t=230 s for
upstream and downstream, respectively. The pump was turned off at t=380 s, and then experiment was
terminated.
Proceedings of the 39th IAHR World Congress
19-24 June 2022, Granada, Spain
In addition to the experimental studies, the numerical analysis also continues to be performed by using the
software PLAXIS-3D. It is also aimed to give comments of these experimental findings in the light of the
numerical analysis results during the oral presentation.
5. ACKNOWLEDGEMENTS
The authors thank the Scientific and Technological Research Council of Turkey (TUBITAK) for
supporting financially this study through the project 119M609.
6. REFERENCES
Chen S., Zhong Q., and Shen G. (2019). Numerical modeling of earthen dam breach due to piping failure.
Water Sci. Eng., 12 (3), 169178.
Damme M. (2020). An analytical process-based approach to predicting breach width in levees constructed
from dilatant soils. Natural Hazards, 101, 5985.
Dhiman S. and Patra K. C. (2018). Experimental study of embankment breach based on its soil properties. ISH
J. Hydraul. Eng., no. December, 111, doi: 10.1080/09715010.2018.1474500.
Dounias, G. and Bardanis, M. (2019). The failure of homogeneous dams by internal erosion -The case of
Sparmos Dam, Greece. Sustainable and Safe Dams Around the WorldTournier, Bennett & Bibeau (Eds)
© 2019 Canadian Dam Association, ISBN 978-0-367-33422-2
Fell,R., Wan, C. H. and Foster, M. (2003). Progress report on methods for estimating the probability of failure
of embankment dams by internal erosion and piping. University of New South Wales, Sydney, Australia.
Greco, M., Pontillo, M., Iervolino, M., and Leopardi, A. (2008). 2DH numerical simulation of breach evolution in
an earth dam. River-flow2008, Vol. 1, M. S. Altinakar, M. A. Kökpınar, I. Aydın, S. Çokgör, and S. Kırkgöz,
eds., Kubaba, Ankara, Turkey, 661667.
ICOLD Bulletin No.164. (2013). Internal erosion of existing dams, levees and dikes, and their foundations, Vol
1 & 2
Morris M. W., Hassan M., Kortenhaus A., Geisenhainer P., Visser P., and Zhu Y. (2008). Modeling breach
initiation and growth. Floodrisk, Oxford, UK, 30 September-2 October,2008
Sharif, Y. A., Elkholy, M., Hanif Chaudhry, M. and Imran, J. (2015). Experimental Study on the Piping Erosion
Process in Earthen Embankments. J. Hydraul. Eng., 141 (7), 04015012.
Zech, Y. and Soares-Frazão, S. (2007). Dam-break flow experiments and real-case data. A database from the
European IMPACT research, Journal of Hydraulic Research. 45(1), 5-7, DOI:
10.1080/00221686.2007.9521827
... In the scope of the project TUBITAK 119M609, (Guney et al., 2022b andOkan, 2022) experimented by building a 60 cm in height, 200 cm in length, and 20 cm in crest width dam which has a tunnel of 2 cm diameter located 6 cm below the crest corner to investigate temporal breach developments and the discharge through the breach caused by piping. ...
... During the construction of the earth-fill dam, the bulk density was used as 2 g/cm 3 and in 12.5% optimum water content by the standard proctor test from downstream view (Guney et al., 2022b andOkan, 2022) The experimental processes of the upper-corner scenario for the downstream, right side, and upstream are given in Figure 6.46, respectively. Once the dam geometry was defined, a 2 cm diameter hole was created by using the poly curve at 6 cm below the dam crest corner. ...
... 48. The changes in water level in time for the upper-corner scenario(Guney et al., 2022b andOkan, 2022) The longitudinal one-color scale (green) hydraulic gradient distributions at y=0.98 m together with four cross-sectional views at different time steps are given inFigure 6.49. 49. ...
Thesis
Full-text available
Earth-fill dams have been constructed for decades by compacting natural soil materials near the dam site. Piping is of the most important causes of their failure. In the scope of this thesis, 2 m in length homogenous earth-fill dams were constructed in a rectangular flume in the laboratory of the Izmir University of Economics. The experimental and numerical investigations on a breach by generating piping were realized with different weak zone scenarios. Three experiments were performed by placing a weak layer cross-section 5x5 cm2 at the dam bottom center. One scenario was performed by locating a weak layer of 2x2 cm2, 28 cm above the bottom. Temporal breach areas and the breach-wetted areas are evaluated on scaled screenshots by using Gauss’s area formulation. The Temporal breach discharges were calculated from the continuity equation. Furthermore, finite element analyses on the breaching of homogenous earth-fill dams in different scenarios were performed by comparing the hydraulic gradient with the critical value. In addition to the bottom and middle scenarios, two upper scenarios were also modeled. The water depths were used for each scenario to represent the experimental conditions, and some approaches were made for the weak zones. To simulate the breach mechanism with different loops, a python algorithm was integrated with the Jupyter console. As a result of the simulations, it has been observed that the findings obtained by simulations were in accord with the experimental studies, and the dams were exposed to backward piping starting from downstream towards upstream.
... For the first scenario, a circular tunnel with a diameter of 2 cm was created along the centerline, 6 cm below a homogeneous dam crest whereas in the second one it was located at the upper corner. These scenarios were presented in two different international scientific meetings [14,15]. The experiments were performed by designing and building dam bodies in laboratory flumes with significant dimensions compared to those available in the literature concerning such experiments performed in the laboratory. ...
... The temporal developments of the breach recorded by the cameras located at downstream and upstream of the dam are given in Fig. 5 and Fig. 6, respectively. The time t=0 corresponds to the starting of the seepage [15,19]. As seen in Figures 5 and 6, there was headcut erosion proceeding from downstream to upstream. ...
Article
Full-text available
Piping and overtopping are the most important causes of earth-fill dam failure. Such dams may erode under seepage, causing a reduction in the structural strength. The aim of this study was to investigate the temporal evolution of the breach and flow rate from the breach resulting from the piping in earth-fill dams. The experiments were carried out at Hydraulics Laboratory of Civil Engineering Department within İzmir University of Economics. The dam was constructed by using a mixture consisting of 85 % sand and 15 % fine (low plasticity clay). In the first scenario a circular tunnel with a diameter of 2 cm was created along the centreline at 6 cm below the dam crest whereas in the second one it was located at the upper edge. Six cameras at different locations recorded the evolution of the progress of the breach formation. The pump flow rate was measured by magnetic flow meter, and the continuity equation was used to calculate the flow rate values from the breach. The time-varied values of the total breach areas were determined using the Gauss Area formula. The image processing method was also applied in the determination of the breach areas. The time-dependent changes of water depth in the channel were also recorded. The obtained experimental findings are presented and commented, together with the universal dimensionless curves. The failure of the dams occurred mainly because of the headcut erosion developed from downstream to upstream. When breaching started, the orifice flow was converted to open channel flow where breach bottom behaved like a broad crested weir. In the second scenario, the rigid lateral side considerably influenced the flow rate and the development of the breach. The peak flow rate corresponding to the first scenario was found approximately 2.3 times greater than that of the second one. The maximum values of all the breach parameters were reached earlier in the case of the seepage along the centerline. The ratios between the values corresponding to the first and the second scenarios were found as 3.25 and 1.75 for maximum breach areas at downstream and at upstream sides, respectively. These ratios were 2.44 and 1.37 for the average breach widths at downstream and upstream sides, respectively. A very good agreement was found between the area values obtained from Gauss area method and image processing technique, in both scenarios. This fact demonstrated that either of these two approaches can be used to determine the time-dependent breach areas. These experimental findings provide the opportunities for the calibration and validation of the numerical models used in the relevant numerical investigations. This study also offers guidance for the strategies concerning emergency action plans related to the failure of homogeneous earth-fill dams when the piping starts at upper part of the homogeneous earth-fill dams.
... The average velocity of the flow outgoing from the breach was approximately calculated by using The temporal developments of the breach recorded by the cameras located at downstream and upstream of the dam are given in Fig. 4 and Fig. 5, respectively. The time t=0 corresponds to the starting of the seepage (Guney et al. 2022;Okan 2022). The temporal water depths in the channel and discharge outgoing from the breach downstream calculated from Eq. 2 are given in Fig. 6. ...
Conference Paper
Full-text available
Piping is one of the most important causes of earth-fill dam failure. Such dams may erode under seepage, causing a reduction in the structural strength. This study is a part of the project TUBITAK 119M609 supported financially by the Scientific and Technological Research Council of Turkey. The aim of this project is to investigate the temporal evolution of the breach and flow rate from the breach resulting from the piping in earth-fill dams. The experiments were carried out at Hydraulics Laboratory of Civil Engineering Department within İzmir University of Economics. The experiments were performed on both homogeneous and clay cored earthen dams constructed by using a mixture consisting of 85 % sand and 15 % clay. In the first scenario a circular tunnel with a diameter of 2 cm was created along the centerline, 6 cm below a homogeneous dam crest. In the second scenario, an earthen dam with clay core having a weak layer at the top was tested. Six cameras located at different locations recorded the evolution of the progress of the breach formation. The pump flow rate was measured by a magnetic flow meter and the flow rate values from the breach were determined from the continuity equation. The time-varied values of the total and wetted breach areas were determined by using the Gauss Area formula. The velocity values were calculated by dividing the flow rates to the wetted areas. The time-dependent changes of water depth in the channel were also recorded. The so-obtained experimental findings are presented and interpreted.
... When applying gray thresholding, a threshold value is determined, with which the original pixel value of a gray level image is compared. The temporal evolution of the breach resulting from seepage at upper part of a homogeneous earthfill dam was studied experimentally in the scope of the project TUBITAK 119M609 whose details are presented in Guney et al., (2022) and Okan, (2022). In this paper, the breach areas determined at different instants at upstream and downstream sides by Gauss area formula and the image processing technique are compared. ...
Conference Paper
Full-text available
Piping is one of the most important causes of earth-fill dam failure. This study investigates the temporal evolution of the breach resulting from the piping in earth-fill dams by means of the image processing technique. The experiments were performed on dams constructed from a mixture of 85 % sand and 15 % clay. A circular tunnel with a diameter of 2 cm was created along the centerline at 6 cm below a homogeneous dam crest to initiate the piping process. The image processing technique was used to determine the time-varied values of breach areas, and these values were compared with those obtained from Gauss area formula. A very satisfactory accordance was found between the results obtained from these two approaches.
Article
In this study, time-dependent finite element analyses of the breaching process in two homogenous earth-fill dams were performed using the finite element method. Breaching was initiated at the middle and corner sections of the upper part of the dam bodies. The numerical results were compared with the findings of the experiments realized on dams 60 cm high, 2 m wide at bottom, 20 cm wide at crest with 1 V:1.5H side slopes at upstream and downstream faces. This numerical study combines time-dependent hydraulic gradient distributions and groundwater flows to assess breach areas, velocities, and flow rates. A Python algorithm was integrated with the Jupyter console, allowing the simulation of the breach mechanism in multiple runs to determine breach parameters. Both numerical and experimental analyses revealed that the dams were exposed to backward erosion, starting at the downstream side of the dam and progressing inward. The compatibility between experimental and numerical results was sought by means of the parameters RMSE, MAE and the statistical performance of the numerical approach was evaluated by using RSR, NSE, and PBIAS. A fairly good agreement was obtained between the experimental and numerical results.
Conference Paper
Full-text available
One of the most prominent failure reasons for earth-fill dams is internal erosion resulting from piping. This failure mode may cause irreversible weakened structural integrity, loss of properties, and even loss of lives. Therefore, it is important to understand the breaching process due to piping by providing reliable data for the decision-makers in case of emergency. This study was supported by the Scientific and Technological Research Council of Turkey with project number 119M609 and involves experimental investigation on piping under three different weak zone scenarios to examine the breach process and provide the data for more realistic numerical evaluations. The experiments were conducted in the hydraulic laboratory of Izmir University of Economics and Dokuz Eylul University. The initiation of piping was triggered from seepage in weak layers at the bottom, middle, and upper parts, along the centerline of homogenous earth-fill dams in a rectangular flume. As a result of the experiments, the magnitude of the peak discharges and their durations as well as the eroded breach areas were found to be affected by the locations of the seepage and initial water heads acting on the weak zones. Also, in the experiments, at the beginning of the breaching, initial cascading surface flow resulted in sheet and rill erosion.
Conference Paper
Full-text available
One of the most significant reasons for earth-fill dam failures is internal erosion resulting from piping. This research was carried out as a part of a project supported financially by the Scientific and Technological Research Council of Turkey (TÜBİTAK). This paper involves the comparison of the experimental findings related to two different scenarios to look into the breach process and to provide the data allowing the realization of more realistic numerical analyses. A circular tunnel of 2 cm diameter located 6 cm below the dam crest was created to induce the seepage. The experiments were conducted at Hydraulics Laboratory of Civil Engineering Department within İzmir University of Economics. The homogeneous earth-fill dams having a height of 0.60 m and a bottom width of 2 m were built in a flume 1.00 m wide, 0.81 m high and 5.44 m long. Some common soil mechanics tests were carried out before the dam was built. The dam bodies were constructed by using a mixture of 15 % clay and 85 % medium sand. High-precision cameras were used to record the temporal development of the breach resulting from the piping. The pump flow rate was measured by a magnetic flowmeter and the flow rate values outgoing from the breach were determined from the continuity equation. Gauss area formula was used to obtain the time-varied values of the breach areas. The temporal changes of water depth in the channel were also recorded. The so obtained experimental findings are presented and commented.
Article
Full-text available
An accurate prediction of the breach widening rate after the onset of a levee failure is essential for flood risk assessments. Current state-of-the-art analytical breach growth relations are empirical in nature. The large variety in loading conditions, levee design, and levee construction material, combined with the limited amount of accurate measurements of breach growth, make the development of accurate empirical breach growth relations challenging. In this paper, a process-based breach widening relation is presented for levees constructed of dilatant soils. The process-based relation is derived from the weir flow equation and a process-based erosion equation. The breach widening relation can account for the effects of variations in soil parameters. For those cases for which soil parameters are unknown, a calibrated catch-all-coefficient is provided. The relation is benchmarked against the state-of-the-art empirical breach growth relation used in the Netherlands and validated against data on historical levee failures and experimental data.
Article
Full-text available
Based on model tests of earthen dam breach due to piping failure, a numerical model was developed. A key difference from previous research is the assumption that the cross-section of the pipe channel is an arch, with a rectangle at the bottom and a semicircle at the top before the collapse of the pipe roof, rather than a rectangular or circular cross-section. A shear stress-based erosion rate formula was utilized, and the arched pipe tunnel was assumed to enlarge along its length and width until the overlying soil could no longer maintain stability. Orifice flow and open channel flow were adopted to calculate the breach flow discharge for pressure and free surface flows, respectively. The collapse of the pipe roof was determined by comparing the weight of the overlying soil and the cohesion of the soil on the two sidewalls of the pipe. After the collapse, overtopping failure dominated, and the limit equilibrium method was adopted to estimate the stability of the breach slope when the water flow overtopped. In addition, incomplete and base erosion, as well as one- and two-sided breaches were taken into account. The USDA-ARS-HERU model test P1, with detailed measured data, was used as a case study, and two artificially filled earthen dam failure cases were studied to verify the model. Feedback analysis demonstrates that the proposed model can provide satisfactory results for modeling the breach flow discharge and breach development process. Sensitivity analysis shows that the soil erodibility and initial piping position significantly affect the prediction of the breach flow discharge. Furthermore, a comparison with a well-known numerical model shows that the proposed model performs better than the NWS BREACH model. Keywords: Earthen dam, Piping failure, Overtopping failure, Breach flow, Numerical modeling, Sensitivity analysis
Article
Understanding of the phenomenon of embankment breach via overtopping is complex but essential for forecasting the flood inundation map and developing an emergency action plan. Case studies of embankment failures caused by overtopping indicate that apart from hydraulic forces, the influence of the soil properties also plays a crucial role in the formation of the breach. The influence of the soil properties on the breaching process was investigated by performing 13 experiments in the hydraulic engineering laboratory of National Institute of Technology, Rourkela, India. The data obtained from the overtopping failure of these embankments are analyzed and presented in this article. Further, a multivariable regression was performed using the test data of 25 embankments to obtain the relationship between the breach parameters and the soil properties (control variables). New nondimensional control variables, such as embankment soil factors, relative compaction effort, relative particle size, and erodibility, were proposed for developing the relationships. An attempt is made here to understand the influence of these control variables on the dam breach that is not reported so far.
Article
Experimental results on the piping erosion process in an earthen embankment emplaced in a laboratory flume are reported in this paper along with the details of the experimental set-up and procedures. A mixture of sand, silt, and clay with different compaction rates is used for constructing the embankment. An image processing technique is successfully applied to track the erosion process from both side-looking and bottom-up views. The paper discusses changes in the depth, area, and volume of erosion during the piping phenomenon in a model embankment using a visual technique. The results show that increasing compaction of the construction layers significantly increases the time required for erosion but has little effect on the final-average depth of erosion. The ratio of the average depth of erosion to the average bottom width of piping is close to one at different time intervals. Exponential equations to estimate the depth of erosion, side area of the piping zone, and volume of eroded material are presented. Two approaches are investigated to estimate the volume: the approach based on the processing of images from both the side-view and bottom-view gives more accurate results than that based on processing the side-view.
Article
The FP5 IMPACT (Investigation of Extreme Flood Processes and Uncertainty) European project (2001-2004) addressed the assessment and reduction of risks from extreme flooding caused by natural events or the failure of dams and flood defence structures. Research has been undertaken through a combination of laboratory physical modelling, field data collection, field testing, theoretical studies and numerical simulations. This special issue of the JHR aims at disseminating the fantastic database issued from those laboratory works and field observations. The present paper summarises the various types of available data and how to use the database included in the attached DVD-ROM.
The failure of homogeneous dams by internal erosion -The case of Sparmos Dam
  • G Dounias
  • M Bardanis
Dounias, G. and Bardanis, M. (2019). The failure of homogeneous dams by internal erosion -The case of Sparmos Dam, Greece. Sustainable and Safe Dams Around the World -Tournier, Bennett & Bibeau (Eds) © 2019 Canadian Dam Association, ISBN 978-0-367-33422-2
Progress report on methods for estimating the probability of failure of embankment dams by internal erosion and piping
  • R Fell
  • C H Wan
  • M Foster
Fell,R., Wan, C. H. and Foster, M. (2003). Progress report on methods for estimating the probability of failure of embankment dams by internal erosion and piping. University of New South Wales, Sydney, Australia.
2DH numerical simulation of breach evolution in an earth dam
  • M Greco
  • M Pontillo
  • M Iervolino
  • A Leopardi
Greco, M., Pontillo, M., Iervolino, M., and Leopardi, A. (2008). 2DH numerical simulation of breach evolution in an earth dam. River-flow2008, Vol. 1, M. S. Altinakar, M. A. Kökpınar, I. Aydın, S. Çokgör, and S. Kırkgöz, eds., Kubaba, Ankara, Turkey, 661-667.