Content uploaded by M. Giovannozzi
Author content
All content in this area was uploaded by M. Giovannozzi on Mar 25, 2022
Content may be subject to copyright.
16th March 2022
Future Circular Hadron Collider FCC–hh: Overview and
Status
M. Benedikt 1, A. Chance 3, B. Dalena 3, D. Denisov 2, M. Giovannozzi 1,
J. Gutleber 1, R. Losito 1, M. Mangano 1, T. Raubenheimer 5, W. Riegler 1,
V. Shiltsev 4, D. Schulte 1, D. Tommasini 1, F. Zimmermann 1
1CERN, Esplanade des Particules 1, 1211 Geneva 23, Switzerland
2Brookhaven National Laboratory, Nuclear and Particle Physics, Upton, NY, USA
3Commissariat `a l’´energie atomique et aux ´energies alternatives - Institut de Recherche
sur le lois Fondamentales de l’Univers Saclay (CEA/Irfu Saclay), Gif-sur-Yvette, France
4Fermi National Accelerator Laboratory (FNAL), Batavia, IL, USA
5Stanford National Accelerator Center (SLAC), Menlo Park, CA, USA
ABSTRACT
The Future Circular Collider (FCC) study was launched as a world-wide in-
ternational collaboration hosted by CERN. Its goal is to push the field to the
next energy frontier beyond LHC, increasing by an order of magnitude the mass
of particles that could be directly produced, and decreasing by an order of
magnitude the subatomic distances to be studied. The FCC study covers two
accelerators, namely, an energy-frontier hadron collider (FCC–hh) and a highest
luminosity, high-energy lepton collider (FCC–ee). Both rings are hosted in the
same 100 km tunnel infrastructure, replicating the CERN strategy for LEP and
LHC, i.e. developing a lepton and a hadron ring sharing the same tunnel. This
paper is devoted to the FCC–hh and summarizes the key features of the FCC–hh
accelerator design, performance reach, and underlying technologies. The mater-
ial presented in this paper builds on the conceptual design report published in
2019, and extends it, including also the progress made and the results achieved
since then.
Submitted to the Proceedings of the US Community Study
on the Future of Particle Physics (Snowmass 2021)
1
arXiv:2203.07804v1 [physics.acc-ph] 15 Mar 2022
1 Design overview
1.1 Status
The design of the FCC–hh collider has been presented in a Conceptual Design Report
(CDR) [1], which describes the baseline configuration of the ring (see Section 5and following
for a brief review of the baseline design and of the recent developments). Note that the
discussion presented in the rest of this paper is essentially based on the material collected
in the CDR.
Since the publication of the CDR, substantial progress has been made, in particular in
the domain of ring placement and layout, and the main results are summarized in Section 9.
1.2 Performance matrix
1.2.1 Attainable energy
The target energy of 100 TeV fully relies on the successful development of 16 T, supercon-
ducting magnets, and any failure to meet the target magnetic field will necessarily impact
the final energy of the collider. To mitigate the risk linked to this challenging and new
technology, R&D efforts are needed and accurately detailed in [1]. In this respect, the
experience from HL–LHC will be important.
1.2.2 Attainable luminosity and luminosity integrals
Possible limiting factors for the collider luminosity seem more linked to luminosity integrals
rather than attainable luminosity.
In the case of the LHC, the attainable luminosity has surpassed the nominal one thanks
to several elements. Higher-brightness beams delivered by the injectors boosted the lumin-
osity, while in the LHC ring the excellent optics control, which includes measurement and
correction, together with an optimal use of the available beam aperture, thanks also to the
use of tighter collimators settings [2], provided the final touch. It is worth stressing that
in the LHC, β∗= 30 cm, corresponding to the nominal FCC–hh value, has already been
achieved and surpassed. On the downside, the larger number of quadrupole magnets in the
straight sections of the FCC–hh might challenge the correction algorithms devised so far
for the LHC, and new approaches should be explored. Furthermore, the actual operational
performance with crab cavities is still unknown, but the HL–LHC will provide an ideal
test-bed for getting ready in view of the FCC–hh.
In this respect, attaining the FCC–hh target integrated luminosity might be more chal-
lenging for several reasons. The injector chain will increase in terms of the number of
accelerator rings; the number of magnets (and of active elements in general) in the FCC–hh
lattice will also increase with respect to the LHC or HL–LHC; repairing activities will be
2
challenging, also taking into account the distances to be covered to access the faulty hard-
ware and the large number of components. All these considerations suggest that operational
efficiency might be at risk, and that appropriate mitigation measures should be considered
(e.g. repairing activities carried out by robots).
1.2.3 Injector and driver systems
The baseline option for the FCC–hh ring is to use the LHC injector chain and the LHC
as pre-injector. An alternative consists of replacing the LHC in its role of pre-injector
with a superconducting ring to be installed in the SPS tunnel. The LHC injector chain is,
with no doubt, a key element in the success of the LHC. The increase in its complexity,
with the addition of the LHC, will potentially impact on its reliability. Furthermore, the
various accelerators in the injector chain will have rather different ages, with the Proton
Synchrotron being the oldest ring (it was commissioned in November 1959). This might
have impact on the overall performance and should be properly addressed, e.g. with an
appropriate long-term maintenance programme.
1.2.4 Facility scale
Figure 1shows some of the FCC-hh implementation variants under study, including the LHC
and the SPS accelerators. The large scale of the FCC–hh ring and the related infrastructure,
implies a certain number of risk factors stemming from the civil engineering activities. The
tunneling activities (for the ring tunnel as well as the ancillary tunnels) are comparable
to those of the recently completed Gotthard Base tunnel (total of about 152 km, including
two 57km tunnel tubes) in Switzerland. Nevertheless, the handling of excavation materials
might pose problems. In this respect, mitigation measures have been put in place in terms of
R&D for finding efficient treatment and use of these materials. As far as the infrastructure
on the surface is concerned, possible difficulties might arise because of the regional and
national frameworks in the two Host States that regulate the acceptance of an infrastructure
development project plan. In this respect, close contacts have been established with national
regulatory bodies to mitigate this risk.
1.2.5 Power requirements
The FCC–hh collider complex is expected to require about 580 MW of electrical power,
which could be reduced to about 550 MW with further optimization. Of these 550 MW,
about 70 MW are needed for the injector complex, 70 MW for cooling, ventilation, and
general services. A further 40 MW are consumed by the four physics detectors, and 20MW
are allocated to the data centers for the four experiments. Among all the subsystems, the
highest demand comes from the FCC–hh cryogenics, which requires about 276 MW (about
250 MW after further optimization, to be compared with about 40 MW for the existing
cryoplants of the LHC, with a three times shorter ring circumference), roughly half of which
is needed to extract the ∼5 MW of FCC–hh synchrotron radiation heat load from inside
3
Figure 1: Picture of some of the FCC-hh implementation variants under study, including
the LHC and the SPS accelerators.
the cold arcs. These power requirements were obtained thanks to a careful optimization
of the FCC–hh components, and, in particular, by an optimized beam-screen temperature,
energy-efficient designs, and the use of new energy-saving technologies. Note that losses in
the power transmission corresponding to about 5%-7% of the peak power should be added
to estimate the needed grid power.
In addition to the successful efforts in optimizing the power consumption of the FCC–hh,
attempts to further decrease the power needed are planned. These studies will be essential to
improve the energy efficiency of the collider and thus enhance the public acceptance of this
large-scale facility. The three-pronged strategy, put in place already since the conceptual
design study phase, envisages a reduction of energy consumption, increase of efficiency of
energy use, and the recovery and reuse of energy for other purposes. This strategy will
further be pursued in the next phase of the FCC–hh study.
4
1.3 Challenges
Although the FCC–hh clearly poses a number of possible obstacles in several areas (beam
physics and technology), it builds on the experience of previous operational colliders, such as
LHC and HL–LHC, which ensures the possibility of developing sound mitigation measures
for the various challenges. As an example, it is worth mentioning that the machine design
heavily relies on that of the LHC and HL–LHC, which instills confidence in the projected
performance.
The unprecedented beam energy of 8.3 GJ represents a challenge for all systems devoted
to protecting the hardware integrity of the FCC–hh ring, such as the collimation and dump
systems. Such a challenge translates into beam dynamics challenges, e.g. the optics design
of for the straight sections housing collimation and dump systems, which should satisfy
multiple constraints, such as phase-advance relations, beam aperture constraints, and beam
impedance, just to mention a few. The requirements also bring technological challenges in
several areas, e.g.in terms of materials selected for the collimators jaws, and beam dumps,
but also for the hardware related to the kickers that are used to dump the beams and to
dilute them before interacting with the dump material.
The field quality of the main magnets at injection energy is also an aspect that deserves
particular care, as an insufficient field quality might lead primarily to beam loss and possible
also emittance growth, with a direct impact on machine performance.
The technology upon which the FCC–hh design relies is that of high-field Nb3Sn su-
perconducting magnets. Multiple challenges can be identified, linked to different aspects
of this hardware. For instance, one challenge is the development of the Nb3Sn wire to
sustain the high critical currents needed to achieve the 16 T magnetic field. Such a goal
should be achieved with the constraint that the wire be economically affordable, given the
large-scale production of magnets needed for FCC–hh. An appropriate magnet design is
another challenge, as this goal should be achieved by fulfilling several criteria, such as the
minimization of the amount of superconductor and the field quality at injection energy. The
complexity of this novel hadron collider is such that several other technologies are a key
to implementing the FCC–hh. The most important ones are an efficient and cost-effective
cryogenic refrigeration, superconducting septum magnets, and solid state generators. The
best candidate for better (with respect to the LHC and HL–LHC choice) cryogenic refri-
geration is based on a mixture of neon and helium. Superconducting septum magnets are
essential for a compact and efficient design of the beam-dump system. Modular, scalable,
fast, and affordable high-power switching systems are key components of beam transfer
systems. Solid-state devices, currently not commercially available, offer high-performance
capabilities, which are needed for efficient FCC–hh operation.
These technologies, which are connected with an overall increase of the operation effi-
ciency of accelerator systems, naturally lead to the consideration of environmental aspects
linked to the FCC–hh. Such a large-scale facility has an unavoidable impact on the environ-
ment due to the civil engineering works, radioactive waste, and energy efficiency. Concerning
the first two aspects, CERN has a long experience due to the LEP/LHC experience. Al-
though the FCC–hh scale exceeds by far the LEP/LHC scale, since the beginning of the
5
studies, the respect of the environment and the minimization of the impact on it has been
the main guideline. This criterion is applied not only to the underground infrastructure,
but also to the surface infrastructure, given its direct societal impact. The radioactive waste
management is a delicate aspect, but all means have been put in place to integrate it since
the beginning in the global implementation project. Concerning energy efficiency, it is clear
that this aspect is new and high in the societal opinion; for this reason several options have
been studied and are actively pursued to provide more efficient energy consumption, e.g.
via a new cryogenic system, as well as to recover, whenever possible, energy, which is the
case of the waste heat recovery.
2 Technology requirements
The technological choices presented in the FCC–hh CDR represent feasible options for the
implementation of the hadron collider. The time needed to move from the CDR stage to a
TDR stage allows for carrying out R&D studies to pursue the detailed feasibility assessment
of the various technological items that are comprised in the FCC–hh baseline. A set of so-
called strategic R&D topics have been identified, which are essential prerequisites for the
preparation of a sound technical design.
It is clear that in addition to the several technological challenges, a crucial aspect to
consider and to assess carefully is the large-scale production of the 16 T magnets.
It is worth stressing that a detailed analysis of the possibility to establish partnerships
has been carried out, and a series of universities and research institutes have been identified
as possible partners. Furthermore, whenever possible and appropriate, industrial partners
have been also identified.
The list of the strategic R&D topics is as follows
•16 Tesla superconducting high-field dual aperture accelerator magnet.
•Cost-effective and high-performance Nb3Sn superconducting wire at industrial scale.
•High-temperature superconductors. The integrated project time line allows for the
exploration and development of high-temperature superconductor (HTS) magnet tech-
nology, and of possible hybrid magnets, enabling improved performance, i.e. higher
fields, or higher temperature. HTS options might be more rewarding than Nb3Sn
technology, as they might allow for higher fields, better performance, reduced cost, or
higher operating temperature and for this last aspect, HTS could be game changers.
•Energy efficient, large-scale cryogenic refrigeration plants for temperatures down to
40 K.
•Invar-based cryogenic distribution line.
•Superconducting septum magnet (to be merged with high-power switching elements).
6
•High-speed, high-power switching system for beam transfer elements.
•Decentralized, high-capacity energy storage and release.
•Advanced particle detector technologies.
•Efficient and cost-effective DC power distribution.
•Efficient treatment and use of excavation material.
2.1 High-Field Magnet R&D
The primary technology of the future circular hadron collider, FCC–hh, is the high-field
magnets, and both high-field dipoles and quadrupoles [1] are required, or, possibly, combined-
function magnets [3].
For constructing the accelerator magnets of the present LHC, the Tevatron, RHIC,
and HERA, wires based on Nb-Ti superconductor were used. However, Nb-Ti magnets
are limited to maximum fields of about 8 T, as being operated at the LHC. The HL–LHC
will, for the first time in a collider, deploy some tens of dipole and quadrupole magnets
with a peak field of 11–12 T, based on a new high-field magnet technology using a Nb3Sn
superconductor. The Nb3Sn superconductor holds the promise to approximately double the
magnetic field, from ∼8 T at the LHC to 16 T for the FCC–hh.
Recently, several important milestones were accomplished in the development of high-
field Nb3Sn magnets. At CERN, a block-coil magnet, FRESCA2, with a 100 mm bore,
achieved a world-record field of 14.6 T at 1.9 K [4]. In the US, a Nb3Sn cosine-theta accel-
erator dipole short-model demonstrator with 60 mm aperture [5], reached a similar field, of
14.5 T at 1.9 K [6].
Forces acting on the magnet coils greatly increase with the strength of the magnetic
field, while, at the same time, most higher-field conductors, such as the brittle Nb3Sn, tend
to be more sensitive to pressure. Therefore, force management becomes a key element in
the design of future high-field magnets.
Beside the development of optimized magnet design concepts, such as canted cosine-
theta dipoles [7], higher field can be facilitated by a higher-quality conductor. A Nb3Sn
wire development programme was set up for the FCC [8]. For Nb–Ta–Zr alloys, it could be
demonstrated that an internal oxidation of Zr leads to the refinement of Nb3Sn grains and,
thereby, to an increase of the critical current density [9]. The phase evolution of Nb3Sn wire
during heat treatment is equally under study, as part of the FCC conductor development
programme in collaboration with TVEL, JASTEC, and KEK [10].
Advanced Nb3Sn wires including Artificial Pinning Centers (APCs) developed by two
separate teams (FNAL, Hyper Tech Research Inc., and Ohio State; and NHMFL, FAMU/FSU)
achieved the target critical current density for FCC, of 1500 A/mm2at 16 T [11,12], which
is 50% higher than for the HL–LHC superconductor. The APCs decrease the magnetiza-
tion heat during field ramps, improve the magnet field quality at injection, and reduce the
7
probability of flux jumps [13].
In addition to Nb3Sn wires, also high-temperature superconductors (HTS) are of in-
terest, since they might allow for higher fields, operation at higher temperature, and, ulti-
mately, perhaps even lower cost. In this context, the FCC conductor programme has been
exploring the potential of ReBCO (Rare-earth barium copper oxide) coated conductors
(CCs). In particular, the critical surfaces for the current density, Jc(T , B, θ), of coated con-
ductors from six different manufacturers: American Superconductor Co. (US), Bruker HTS
GmbH (Germany), Fujikura Ltd (Japan), SuNAM Co. Ltd (Korea), SuperOx ZAO (Russia)
and SuperPower Inc. (US) have been studied [14].
Outside the accelerator field, HTS magnet technology could play an important role for
fusion research. A number of companies are developing HTS magnets in view of fusion ap-
plications. One of these companies is Commonwealth Fusion Systems, which, in partnership
with MIT’s Plasma Science and Fusion center, is designing SPARC, a compact net fusion
energy device [15]. The SPARC magnets are based on second generation ReBCO conduct-
ors. Recently, the SPARC team successfully demonstrated a coil with 20 T field [16]. An
interesting view on HTS prospects is presented in a Snowmass 2020 Letter of Interest [17],
according to which the actual material and process costs of HTS tapes are a small fraction
of their current commercial value, and that there is a historical link between manufactured
volume and price [18].
3 Staging options and upgrades
Considerations on possible staging options for the FCC–hh can be made on the basis of
the experience of LHC and HL–LHC. Various types of energy upgrade, from a limited
one (of about 7%, based on the assumed engineering margins of the the various systems
and in particular of the main dipoles) to a major one (of about 93%, the so-called HE–
LHC [19], based on FCC–hh-type main dipoles to be installed in the LHC tunnel) have
been considered, but no one has been retained as an efficient upgrade path. On the other
hand, upgrade of the luminosity has been approved as the route to improve the LHC
performance within the LHC Luminosity Upgrade Project [20]. It is worth noting that the
LHC luminosity upgrade goal is achieved thanks to changes in the LHC ring, leading to a
reduction of β∗, but also to the upgrade of the injectors chain to generate brighter beams
and higher currents [21].
We may, therefore, speculate that an energy upgrade is not a realistic option for FCC–
hh, unless even higher-field magnets, e.g. based on HTS, became available.
Instead, a luminosity upgrade, following the two FCC–hh stages already foreseen, with
an ideal delivery of about 2 or 8 fb−1per day, respectively, could be considered an interesting
option. However, further reducing β∗(the nominal value in the second stage of FCC–hh is
30 cm) does not much increase the integrated luminosity without a higher proton intensity.
Already, as designed, the FCC–hh machine is cycling for about half of the time (with fairly
demanding assumptions on the ramp speed of the injectors, either a slightly modified LHC
8
or a new superconducting SPS), and the protons are burnt off quickly in collision (see
Fig. 4 in [22] and the associated equations). Burning off the protons even more quickly
cannot much raise the integrated luminosity, but will mostly increase the event pile up. On
the other hand, the FCC–hh baseline only considers rather moderate intensities from the
injector of ∼1011 protons per bunch and 0.5 A beam current, which are at least a factor
∼2 below the capabilities of the upgraded LIU/HL–LHC complex.
Brightness of the injected beam is not a critical issue for FCC–hh, since the radiation
damping will anyhow shrink the beam in the collider. Maximum integrated luminosity
could be attained by exploiting the maximum proton rate, bunch intensity, and beam
current available from the CERN LHC complex. However, the beam current in the FCC–hh
rings is limited due to the SR heat load and the associated cryogenics power requirements.
With HTS magnets operating at an elevated temperature, these cryogenics needs would be
relaxed, and a higher beam current might become possible.
Another possible approach would be not to cycle the FCC–hh collider, but to run it at
constant magnetic fields and approximately constant beam current, using a top-up injection
scheme as was successfully implemented for the two B-factories, is in routine use at the
present SuperKEKB, and forms a key ingredient of the future FCC–ee lepton collider. For
the case of FCC–hh, top-up injection requires the installation of a fast ramping 50 TeV full
energy injector, which might become available thanks to advancing magnet technology. To
facilitate the design, the beam current in the top-up injector could be restricted to e.g. 10%
of the collider beam current. Such a top-up injector could increase the integrated luminosity
of the FCC–hh by a significant factor.
Lepton colliders utilize radiation damping to merge injected particles with the stored
beam. If the radiation damping in FCC–hh proved too slow for this purpose, the merging of
injected and stored beams could be accomplished by other methods, e.g., by injection into
nonlinear resonance islands, which are then collapsed [23,24], or, alternatively, by innovative
damping of the injected beam, e.g. through optical stochastic cooling or coherent electron
cooling. So, in short, the use of HTS magnets allowing for higher beam current or the
installation of a novel fast cycling full energy top-up injector would be two plausible paths
to increase the integrated luminosity of FCC–hh by a significant factor.
It is also worth mentioning that heavy-ion collisions are part of the FCC baseline,
although they formally represent an extension with respect to the proton-proton programme.
However, lepton-hadron collisions, the so-called FCC–eh, are not part of the baseline and
would be an appealing upgrade.
Other extensions of the FCC–hh scope could be collisions with isoscalar light ion beams [25],
the realization of a Gamma Factory [26,27,28], and becoming an ingredient of a high-energy
muon collider [29,30,31,32,33,34].
9
4 Synergies with other concepts and/or existing facilities
Clearly, a natural synergy exists between FCC–ee and FCC–hh. Moreover, The FCC–hh
can profit from the experience of LHC/HL–LHC in several aspects. The HL–LHC bases
its luminosity increase upon the use of Nb3Sn quadrupoles for the final focus. Hence, the
experience gained in the design, prototype, construction, test, and operation of the new
triplets will be essential for FCC–hh.
A similar situation occurs in the domain of physics detectors, where the planned upgrade
to cope with the HL–LHC performance will bring the detectors in a new territory, thus
approaching that of the FCC–hh. Hence, also in this domain, FCC–hh can build on the
experience of the HL–LHC.
It is also evident that strong synergy is present between FCC–hh and HL–LHC at the
level of beam dynamics, due to the similarity of some regimes. It is possible to identify, as
areas with similar challenges, optics control in the ring, in general, and in the experimental
insertions, in particular, emittance preservation of high-brightness beams, electron-cloud
effects, beam instabilities, as well as, e.g. machine operation with crab cavities.
Finally, it will be easy to find synergies in the domain of energy efficiency and environ-
mental impact with other projects, as these two aspects are gaining so much focus that will
become essential items for any large-scale facility for physics research.
5 Overview of FCC–hh as presented in the 2019 CDR
The discovery of the Higgs boson, announced exactly ten years ago, brought to completion
the search for the fundamental constituents of matter and interactions that represent the
so-called Standard Model (SM). Several experimental observations require an extension of
the Standard Model. For instance, explanations are needed for the observed abundance of
matter over antimatter, the striking evidence for dark matter, and the non-zero neutrino
masses.
Therefore, a novel research infrastructure, based on a highest-energy hadron collider,
FCC–hh, with a center-of-mass collision energy of 100 TeV and an integrated luminosity
of at least a factor of five larger than the HL–LHC [35,20] is proposed to address the
aforementioned aspects [1,36,37]. The current energy frontier limit for collider experiments
will be extended by almost an order of magnitude, and the mass reach for direct discovery
will achieve several tens of TeV. Under these conditions, for instance, the production of
new particles, whose existence could have emerged from precision measurements during
the preceding e+e−collider phase (FCC–ee), would become possible. An essential task
of this collider will be the accurate measurement of the Higgs self-coupling, as well as the
exploration of the dynamics of electroweak symmetry breaking at the TeV scale, to elucidate
the nature of the electroweak phase transition.
This unique particle collider infrastructure, FCC–hh, will serve the world-wide physics
community for about 25 years. However, it is worth stressing that in combination with the
10
lepton collider [38] as initial stage, the FCC integrated project will provide a research tool
until the end of the 21st century.
The FCC construction project will be carried out in close collaboration with national
institutes, laboratories, and universities world-wide, with a strong participation of industrial
partners. It is worth mentioning that the coordinated preparatory effort is based on a core
of an ever-growing consortium of already more than 145 institutes world-wide.
5.1 Accelerator layout
The FCC–hh [1,36,37] is designed to provide proton–proton collisions with a center-of-mass
energy of 100 TeV and an integrated luminosity of ≈20 ab−1in each of the two primary
experiments for 25 years of operation. The FCC–hh offers a very broad palette of collision
types, as it is envisaged to collide ions with protons and ions with ions. The ring design also
allows one interaction point to be upgraded to electron–proton and electron–ion collisions.
In this case, an additional recirculating, energy-recovery linac will provide the electron beam
that collides with one circulating proton or ion beam. The other experiments can operate
concurrently with hadron collisions.
The FCC–hh will use the existing CERN accelerator complex as the injector facility.
The accelerator chain, consisting of CERN’s Linac4, PS, PSB, SPS, and LHC, could de-
liver beams at 3.3 TeV to the FCC–hh, thanks to transfer lines using 7 T superconducting
magnets that connect the LHC to FCC–hh. This choice also permits the continuation of
CERN’s rich and diverse fixed-target physics programme in parallel with FCC–hh opera-
tions. Limited modifications of the LHC should be implemented, in particular, the ramp
speed can be increased to optimize the filling time of the FCC–hh. Furthermore, reliabil-
ity and availability studies have confirmed that operation can be optimized such that the
FCC–hh collider can achieve its performance goals. However, the power consumption of the
aging LHC cryogenic system is a concern. Note that the required 80%–90% availability of
the injector chain could best be achieved with a new high-energy booster. As an alternative,
direct injection from a new superconducting synchrotron at 1.3 TeV that would replace the
SPS is also being considered. In this case, simpler normal-conducting transfer lines with
magnets operating at 1.8 T are sufficient. For this scenario, more studies on beam stability
in the collider at injection are required.
Key parameters of the collider presented in the CDR are given in Table 5.1. In the
CDR, the circumference of FCC–hh was 97.75km. Recently a placement optimization has
led to a “lowest-risk” layout with a circumference of 91.17 km (also see Section 9and Fig. 4),
comprising four short straight sections of 1.4 km length for the experimental insertions, and
four longer straight sections of about 2.16 km each, that would house, e.g. the radiofrequency
(RF), collimation, and beam extraction systems.
Two high-luminosity experiments are located in the opposite insertions PA and PG,
which ensures the highest luminosity, reduces unwanted beam-beam effects, and is inde-
pendent of the beam-filling pattern. The main experiments are located in 66 m long experi-
mental caverns, sufficient for the detector that has been studied and ensuring that the final
11
focus system can be integrated into the available length of the insertion. Two additional,
lower luminosity experiments are located in the other two experimental insertions.
Table 1: Key FCC–hh baseline parameters from the 2019 CDR [1] compared to LHC and
HL–LHC parameters.
LHC HL–LHC FCC–hh
Initial Nominal
Physics performance and beam parameters
Peak luminosity∗(1034cm−2s−1) 1.0 5.0 5.0<30.0
Optimum average integrated 0.47 2.8 2.2 8
luminosity/day (fb−1)
Assumed turnaround time (h) 5 4
Target turnaround time (h) 2 2
Peak number of inelastic events/crossing 27 135†171 1026
Total/inelastic cross section 111/85 153/108
σproton (mb)
Luminous region RMS length (cm) 5.7
Distance IP to first quadrupole L∗(m) 23 40
Beam parameters
Number of bunches n2808 10400
Bunch spacing (ns) 25 25
Bunch population N(1011) 1.15 2.2 1.0
Nominal transverse normalised 3.75 2.5 2.2
emittance (µm)
Number of IPs contributing to ∆Q3 2 2 + 2 2
Maximum total beam-beam tune shift ∆Q0.01 0.015 0.011 0.03
Beam current (A) 0.58 1.12 0.5
RMS bunch length‡(cm) 7.55 8
β∗(m) 0.55 0.15 1.1 0.3
RMS IP spot size (µm) 16.7 7.1 6.8 3.5
Full crossing angle (µrad) 285 590 104 200§
The regular lattice in the arc consists of 90°FODO cells with a length of about 213 m, six
14 m-long dipoles between quadrupoles, and a dipole filling factor of about 0.8. Therefore,
a dipole field around 16 T is required to maintain the nominal beams on the circular orbit.
The dipoles are based on Nb3Sn, are operated at a temperature of 2 K, and are a key
cost item of the collider. Efforts devoted to increasing the current density in the conductors
to 1500 A/mm2at 4.2 K, were successful [11,12]. Several optimized dipole designs have
been developed in the framework of the EuroCirCol H2020 EC-funded project. The cosine-
∗For the nominal parameters, the peak luminosity is reached during the run.
†The baseline assumes leveled luminosity.
‡The HL–LHC assumes a different longitudinal distribution; the equivalent Gaussian RMS is 9 cm.
§The luminosity reduction due to the crossing angle will be compensated using the crab crossing scheme.
12
theta design has been selected as baseline, because it provided a beneficial reduction of the
amount of superconductor needed for the magnet coils. Several collaboration agreements
are in place with organisations such as the French CEA, the Italian INFN, the Spanish
CIEMAT, and the Swiss PSI, to build short model magnets. It is worth mentioning that
a US DOE Magnet Development Programme is actively working to demonstrate a 15 T
superconducting accelerator magnet and has reached 14.5 T.
As the current plans are that FCC–hh is implemented following FCC–ee in the same
underground infrastructure, the time scale for design and R&D for FCC–hh is of the order
of 30 years. This additional time will be used to develop alternative technologies, such
as magnets based on high-temperature superconductors with a potential significant impact
on the collider parameters, relaxed infrastructure requirements (cryogenics system), and
increased energy efficiency (temperature of magnets and beam screen).
5.2 Luminosity performance
The initial parameters, with a maximum luminosity of 5×1034 cm−2s−1, are planned to be
reached in the first years. Then, a luminosity ramp up will be applied, to reach the nominal
parameters with a luminosity of up to 3 ×1035 cm−2s−1. Correspondingly, the integrated
luminosity per day will increase from 2 fb−1to 8 fb−1. A luminosity of 2 ×1034 cm−2s−1
can be achieved at the two additional experimental insertions, although further studies are
needed to confirm this.
High brightness and high-current beams, with a quality comparable to that of the beams
of the HL–LHC, combined with a small β∗at the collision points ensure the high luminosity.
The parasitic beam-beam interactions are controlled by introducing a finite crossing angle,
whose induced luminosity reduction is compensated by means of crab cavities. Further
improvement of the machine performance might be achieved by using electron lenses and
current carrying wire compensators.
The fast burn-off under nominal conditions prevents from using the beams for collisions
for more than 3.5 h. Hence, the turn-around time, i.e. the time from one luminosity run to
the next one, is a critical parameter to achieve the target integrated luminosity. In theory,
a time of about 2 h is within reach, but to include a sufficient margin, turn-around times
of 5 h and 4 h are assumed for initial and nominal parameters, respectively. Note that an
availability of 70% at flat top for physics operation is assumed for the estimate of the overall
integrated luminosity.
The collider performance can be affected by various beam dynamics effects that can lead
to the development of beam instabilities and quality loss. To fight against these effects a
combination of fast transverse feedback and octupoles is used to stabilize the beam against
parasitic electromagnetic interaction with the beamline components. Electron cloud build-
up, which could render the beam unstable, is suppressed by appropriate hardware design.
The impact of main magnet field imperfections on the beam is mitigated by high-quality
magnet design and the use of corrector magnets.
13
5.3 Technical systems
Many technical systems and operational concepts for FCC–hh can be scaled up from HL–
LHC or can be based on technology demonstrations carried out in the frame of ongoing
R&D projects. Particular technological challenges arise from the higher total energy in the
beam (20 times that of LHC), the much increased collision debris in the experiments (40
times that of HL–LHC), and far higher levels of synchrotron radiation in the arcs (200 times
that of LHC).
The high luminosity and beam energy will produce collision debris with a power of up
to 0.5 MW in the main experiments, with a significant fraction of this lost in the ring close
to the experiment. A sophisticated shielding system, similar to HL–LHC [20], protects
the final focusing triplet, avoids quenches, and reduces the radiation dose. The current
radiation limit of 30 MGy for the magnets, imposed by the resin used, will be reached for
an integrated luminosity of 13ab−1, but it is projected that the improvement of both the
shielding and the radiation hardness of the magnets is possible. Hence, it is likely that the
magnets will not have to be replaced during the entire lifetime of the project.
The robust collimation and beam extraction system protects the machine from the
energy stored in the beam. The design of the collimation system is based on the LHC
system [39,20], however, with a number of improvements. Additional protection has been
added to mitigate losses in the arcs that would otherwise quench magnets. Improved con-
ceptual designs of collimators and dogleg dipoles have been developed to reduce the beam-
induced stress to acceptable levels. Further R&D should aim at gaining margins in the
design to reach comfortable levels.
The extraction system uses a segmented, dual-plane dilution kicker system to distribute
the bunches in a multi-branch spiral on the absorber block. Novel superconducting septa
capable of deflecting the high-energy beams are currently being developed. The system
design is fault tolerant, and the most critical failure mode, erratic firing of a single ex-
traction kicker element, has limited impact thanks to the high granularity of the system.
Investigations of suitable absorber materials including 3D carbon composites and carbon
foams are ongoing in the frame of the HL–LHC project.
The cryogenic system must compensate the continuous heat loads in the arcs of 1.4 W/m
at a temperature below 2 K, and the 30 W/m/aperture due to synchrotron radiation at a
temperature of 50 K, as well as absorbing the transient loads from the magnets ramping.
The system must also be able to fill and cool down the cold mass of the machine in less than
20 days, while avoiding thermal gradients higher than 50 K in the cryomagnet structure.
Furthermore, it must also cope with quenches of the superconducting magnets and be
capable of a fast recovery from such situations that leaves the operational availability of the
collider at an adequate level. The number of active cryogenic components distributed around
the ring is minimized for reasons of simplicity, reliability, and maintenance. Note that
current helium cryogenic refrigeration only reaches efficiencies of about 30% with respect
to an ideal Carnot cycle, which leads to high electrical power consumption. For this reason,
part of the FCC study is to perform R&D on novel refrigeration down to 40 K based on
a neon-helium gas mixture, with the potential to reach efficiencies higher than 40%, thus
14
bringing a reduction of the electrical energy consumption of the cryogenics system by 20%.
The cryogenic beam vacuum system ensures excellent vacuum to limit beam-gas scat-
tering, and protect the magnets from the synchrotron radiation of the high-energy beam,
also efficiently removing the heat. It also avoids beam instabilities due to parasitic beam-
surface interactions and electron cloud effects. Note that the LHC vacuum system design
is not suitable for FCC–hh, hence a novel design has been developed in the scope of the
EuroCirCol H2020-funded project. It is as compact as possible to minimize the magnet
aperture and consequently magnet cost. The beam screen features an anti-chamber and is
copper coated to limit the parasitic interaction with the beam; the shape also reduces the
seeding of the electron cloud by backscattered photons, and additional carbon coating or
laser treatment prevents the build-up. This novel system is operated at 50 K and a proto-
type has been validated experimentally in the KARA synchrotron radiation facility at KIT
(Germany).
The RF system is similar to the one of LHC with an RF frequency of 400 MHz, although
it provides a higher maximum total voltage of 48 MV. The current design uses 24 single-cell
cavities. To adjust the bunch length in the presence of longitudinal damping by synchrotron
radiation, controlled longitudinal emittance blow-up by band-limited RF phase noise is
implemented.
5.4 Ion operation
A first parameter set for ion operation has been developed based on the current injector
performance. If two experiments operate simultaneously for 30 days, one can expect an
integrated luminosity in each of them of 6 pb−1and 18 pb−1for proton-lead ion operation
with initial and nominal parameters, respectively. For lead-ion lead-ion operation 23 nb−1
and 65 nb−1could be expected, although more detailed studies are in progress to address
the key issues in ion production and collimation and to review the luminosity predictions.
6 Civil engineering
As stated above, the FCC–hh collider will be installed in a quasi-circular tunnel composed
of arc segments interleaved with straight sections with an inner diameter of at least 5.5 m
and a circumference of 91.17 km. The internal diameter tunnel is required to house all
necessary equipment for the machine, while providing sufficient space for transport and
ensuring compatibility between FCC–hh and FCC–ee requirements. Figure 2shows the
cross section of the tunnel in a typical arc region, including several ancillary systems and
services required. Furthermore, about 8 km of bypass tunnels, about 18 shafts, 10 large
caverns and 8 new surface sites are part of the infrastructure to be built.
The underground structures should be located as much as possible in the sedimentary
rock of the Geneva basin, known as Molasse (which provides good conditions for tunneling)
and avoid the limestone of the nearby Jura. Moreover, the depth of the tunnel and shafts
15
Figure 2: Cross section of the FCC–hh tunnel of an arc (from [1]). The gray equipment
on the left represents the cryogenic distribution line. A 16 T superconducting magnet is
shown in the middle, mounted on a red support element. An orange transport vehicle with
another superconducting magnet is also shown, in the transport passage.
should be minimized to control the overburden pressure on the underground structures and
to limit the length of service infrastructure. These requirements, along with the constrain
imposed by the connection to the existing accelerator chain through new beam transfer
lines, led to the clear definition of the study boundary, which should be respected by all
possible tunnel layouts considered. A slope of 0.2% in a single plane will be used for the
tunnel to optimize the geology intersected by the tunnel and the depth of the shafts, as
well as to implement a gravity drainage system. The majority of the machine tunnel will
be constructed using tunnel boring machines, while the sector passing through limestone
will be mined.
The CDR study was based on geological data from previous projects and data avail-
able from national services, and based on this knowledge, the civil engineering project is
considered feasible, both in terms of technology and project risk control. It is also clear
that dedicated ground and site investigations are required during the early stage of the pre-
paratory phase to confirm the findings, to provide a comprehensive technical basis for an
optimized placement and as preparation for project planning and implementation processes.
It is worth mentioning that for the access points and their associated surface structures,
the priority has been given to the identification of possible locations that are feasible from
16
socio-urbanistic and environmental perspectives. Even in this case, the technical feasibility
of the construction has been studied and is deemed achievable.
7 Detector considerations
The FCC–hh is both a discovery and a precision measurement machine, with the mass reach
increased with respect to the current LHC by a factor of seven. The much larger cross
sections for SM processes combined with the higher luminosity lead to a significant increase
in measurement precision. This implies that the detector must be capable to measure
multi-TeV jets, leptons and photons from heavy resonances with masses up to 50 TeV, as
well as the known SM processes with high precision, and to be sensitive to a broad range
of BSM signatures at moderate pT. Given the low mass of SM particles compared to
the 100 TeV collision energy, many SM processes feature a significant forward boost while
keeping transverse momentum distributions comparable to LHC energies. Hence, a detector
for 100 TeV must increase the acceptance for precision tracking and calorimetry to |η| ≈ 4,
while retaining the pTthresholds for triggering and reconstruction at levels close to those
of the current LHC detectors. The large number of p–p collisions per bunch crossing, which
leads to the so-called pile-up, imposes stringent criteria on the detector design. Indeed, the
present LHC detectors cope with pile-up up to 60, the HL–LHC will generate values of up
to 200, whereas the expected value of 1000 for the FCC–hh poses a technological challenge.
Novel approaches, specifically in the context of high precision timing detectors, will likely
allow such numbers to be handled efficiently.
Figure 3: Conceptual layout of the FCC–hh reference detector (from [1]). It features an
overall length of 50m and a diameter of 20 m. A central solenoid with 10 m diameter
bore and two forward solenoids with 5m diameter bore provide a 4 T field for momentum
spectroscopy in the entire tracking volume.
Figure 3shows the conceptual FCC–hh reference detector, which serves as a concrete
example for subsystem and physics studies aimed at identifying areas where dedicated R&D
17
efforts are needed. The detector has a diameter of 20 m and a length of 50 m, similar to
the dimensions of the ATLAS detector at the LHC. The central detector, with coverage
of |η|<2.5, houses the tracking, electromagnetic calorimetry, and hadron calorimetry
surrounded by a 4 T solenoid with a bore diameter of 10 m. The required performance for
|η|>2.5 is achieved by displacing the forward parts of the detector away from the interaction
point, along the beam axis. Two forward magnet coils, generating a 4 T solenoid field, with
an inner bore of 5 m provide the required bending power. Within the volume covered by
the solenoids, high-precision momentum spectroscopy up to |η| ≈ 4 and tracking up to
|η| ≈ 6 is ensured. Alternative layouts concerning the magnets of the forward region are
also studied [1].
The tracker is specified to provide better than 20% momentum resolution for pT=
10 TeV/c for heavy Z0type particles, and better than 0.5% momentum resolution at the
multiple scattering limit, at least up to |η|= 3. The tracker cavity has a radius of 1.7 m
with the outermost layer at around 1.6m from the beam, providing the full spectrometer
arm up to |η|= 3. The electromagnetic calorimeter (EMCAL) uses a thickness of around
30 radiation lengths, and together with the hadron calorimeter (HCAL), provides an overall
calorimeter thickness of more than 10.5 nuclear interaction lengths to ensure 98% contain-
ment of high-energy showers and to limit punch-through to the muon system.
The EMCAL is based on liquid argon (LAr) due to its intrinsic radiation hardness. The
barrel HCAL is a scintillating tile calorimeter with steel and Pb absorbers, divided into a
central and two extended barrels. The HCALs for the endcap and forward regions are also
based on LAr. The requirement of calorimetry acceptance up to |η| ≈ 6 translates into an
inner active radius of only 8 cm at a z-distance of 16.6 m from the interaction point. The
EMCAL is specified to have an energy resolution around 10%/√E, while the HCAL around
50%/√Efor single particles. The features of the muon system have a significant impact on
the overall detector design. As nowadays there is little doubt that large-scale silicon trackers
will be core parts of future detectors, the emphasis on standalone muon performance is less
pronounced, and the focus is rather shifted towards the aspects of muon trigger and muon
identification.
In the reference detector, the magnetic field is unshielded, with several positive side
effects that concur to a sensible cost reduction. The unshielded coil can be lowered through
a shaft of 15 m diameter and the detector can be installed in a cavern of 37 m height and
35 m width, similar to the present ATLAS cavern. The magnetic stray field reaches 5 mT
at a radial distance of 50 m from the beamline, so that no relevant stray field leaks in the
service cavern, placed 50m away from the experiment cavern and separated by rock. The
shower and absorption processes inside the forward calorimeter produce a large number
of low-energy neutrons, a significant fraction of which enters the tracker volume. To keep
these neutrons from entering the muon system and the detector cavern, a heavy radiation
shield is placed around the forward solenoid magnets to close the gap between the endcap
and forward calorimeters.
The technologies selected for the various subsystems should stand significant radi-
ation levels. On the first silicon layer at r= 2.5cm the charged-particle rate is around
10 GHz/cm2, and it drops to about 3 MHz/cm2at the outer radius of the tracker, whereas
18
inside the forward EMCAL the number rises to 100 GHz/cm2. The 1 MeV neutron equival-
ent fluence, a key number for long-term damage of silicon sensors and electronics in general,
evaluates to a value of 6 ×1017/cm2for the first silicon layer, beyond a r= 40 cm the num-
ber drops below 1016 /cm2, and in the outer parts of the tracker it is around 5 ×1015/cm2.
This means that technologies used for the HL–LHC detectors are therefore applicable when
r > 40 cm, while novel sensors and readout electronics have to be developed for the inner-
most parts of the tracker.
The charged particle rate in the muon system is dominated by electrons, created from
high energy photons in the MeV range by processes related to thermalization and capture
of neutrons that are produced in hadron showers mainly in the forward region. In the
barrel muon system and the outer endcap muon system, the charged particle rate does not
exceed 500 Hz/cm2, the rate in the inner endcap muon system increases to 10 kHz/cm2, and
to 500 kHz/cm2in the forward muon system, at a distance of 1 m from the beam. These
rates are comparable to those of the muon systems of the current LHC detectors, therefore,
gaseous detectors used in these experiments can be adopted.
8 Cost and schedule
In the FCC integrated project, the FCC–hh is preceded by the lepton collider Higgs, top,
and electroweak factory, FCC–ee. Here, both civil engineering and general technical infra-
structures of the FCC–ee can be fully reused for FCC–hh, thus substantially lowering the
investments for the latter to 17 000 MCHF, according to the CDR estimate [1]. The particle
collider- and injector-related investments amount to 80% of the FCC–hh cost, namely to
about 13 600 MCHF. The major part of this accelerator cost corresponds to the expected
price of the 4700 Nb3Sn 16 T main dipole magnets, totaling 9400 MCHF, for a target cost
of 2 MCHF/magnet. For completeness, we note that in the CDR, the construction cost for
FCC–hh as a single standalone project, i.e. without prior construction of an FCC–ee lepton
collider, was estimated to be about 24 000 MCHF for the entire project.
The FCC–hh operation costs, other than electricity cost, are expected to remain limited,
based on the evolution from LEP to LHC operation today, which shows a steady decrease in
the effort needed to operate, maintain and repair the equipment. The cost-benefit analysis
of the LHC/HL–LHC programme reveals that a research infrastructure project of such
a scale and high-tech level has the potential to generate significant socio-economic value
throughout its lifetime, in particular if the tunnel, surface, and technical infrastructures
from a preceding project have been amortized.
In the integrated FCC project, disassembly of the FCC–ee and subsequent installation of
the FCC–hh take about 8–10 years. The projected duration for the operation of the FCC–
hh facility is 25 years, to complete the currently envisaged proton-proton collision physics
programme. As a combined, “integrated” project, namely FCC–ee followed by FCC–hh,
the FCC covers a total span of at least 70 years, i.e. until the end of the 21st century.
19
9 Progress since the CDR
9.1 Evolution of the baseline layout
Among the several domains of activity that have been pursued since the publication of the
CDR, it is important stressing the intense efforts devoted to placement studies, which refined
the results discussed in [1]. These aim to determine an optimal tunnel layout that could
fulfill the multiple constraints imposed by geological situation, territorial and environmental
aspects. Furthermore, in the frame of FCC–ee studies, it emerged that implementing four
experimental interaction points is an interesting option worth investigating. Beam dynamics
considerations impose a symmetrical positioning of the four experimental points. Hence,
to allow sharing the experimental caverns between FCC–ee and its hadron companion,
the same principle should also be applied to the FCC–hh lattice. The outcome of these
considerations is the new layout shown in Fig. 4. The circumference of the proposed layout
is 91.17 km. The proposed layout has an appealing side effect, namely, only eight access
points are present, with a non-negligible impact on the civil engineering works and costs.
Injection Injection
transfer lines proposed to be
installed inside FCC-hh ring tunnel
Beam dump
Betatron collimation
Momentum
collimation
RF
Figure 4: Sketch of the proposed eight-point FCC–hh layout.
The four experimental points are located in PA, PD, PG, and PJ, respectively. The
length of the straight sections has been revised, following the results of the placement
studies: a short straight section, 1.4 km in length like in the baseline lattice, is used to
house the experimental interaction points; a long straight section, 2.16 km in length, is used
20
to house the key systems. Currently, it is proposed to install the beam dump in PB, the
betatron collimation in PF, the momentum collimation in PH, and the RF system in PL.
These preliminary assignments should be confirmed by detailed studies. Such studies should
also assess the feasibility of the optics required for the various systems, following the sizable
length reduction (from 2.8 km of the CDR baseline version to 2.16 km for the new version).
The total length of the arcs is 76.93 km, and, unlike the baseline configuration, all arcs
have the same length. The reduction of the total arc length implies that the collision energy
falls short of 100 TeV by few TeV, and this is not felt as a hurdle. The FODO cell length
is unchanged.
The rearrangement of the experimental points has an impact on the injection and trans-
fer line design. The configuration inherited from the LHC design, in which the injection is
performed in the same straight section in which the secondary experiments are installed,
has to be dropped as it would lead to very long transfer lines. Therefore, the current view
consists of combining the injection with beam dump (in PB) and with RF (in PL). Then, to
save in tunnel length, it is proposed that the transfer lines run in the FCC–hh ring tunnel
from close to PA until the injection point (see Fig. 4). An additional benefit of this solution
is that the transfer line magnets would be normal-conducting and rather relaxed in terms
of magnetic properties. Integration of the transfer lines in the ring tunnel is being actively
pursued to assess the feasibility of this proposal.
9.2 Alternative configuration
In parallel to the studies for the optimization of the baseline layout, some efforts have been
devoted to the analysis of alternative approaches to the generation of the ring optics. Indeed,
the standard paradigm to collider optics consists in using separate-function magnets, in
particular in the regular arcs, in conjunction with a FODO structure. However, a combined-
function optics might provide interesting features, particularly appealing for an energy-
frontier collider. A combined-function optics has the potential of providing a higher dipole
filling factor, thus opening to interesting optimization paths of the dipole field and beam
energy. Currently, this research has explored the benefits of a combined-function periodic
cell [3]. It also optimized some of the parameters of the cell, such as its length [40], showing
that the combined-function magnet is equally feasible as the baseline magnet. Furthermore,
a complex optics, including arc and dispersion suppressors, can indeed be realized with
combined-function magnets. As a next step, the investigations will consider the various
systems of corrector magnets planned in the baseline FODO cell and optimize them in the
context of a combined-function periodic cell.
10 Conclusions
The FCC–hh baseline comprises a power-saving, low-temperature superconducting magnet
system based on an evolution of the Nb3Sn technology pioneered at the HL–LHC. An energy-
efficient cryogenic refrigeration infrastructure, based on a neon-helium light gas mixture,
21
and a high-reliability and low-loss cryogenic distribution infrastructure are also key elements
of the baseline. Highly segmented kickers, superconducting septa and transfer lines, and
local magnet energy recovery, are other essential components of the proposed FCC–hh
design. Furthermore, technologies that are already being gradually introduced at other
CERN accelerators will be deployed in the FCC–hh. Given the time scale of the FCC
integrated program that allows for around 30 years of R&D for FCC-hh, an increase of
the energy efficiency of a particle collider can be expected thanks to high-temperature
superconductor R&D, carried out in close collaboration with industrial partners. The reuse
of the entire CERN accelerator chain, serving also a concurrent physics programme, is
an essential lever to come to an overall sustainable research infrastructure at the energy
frontier.
The FCC–hh will be a strong motor of economic and societal development in all particip-
ating nations, because of its large-scale and intrinsic character of international fundamental
research infrastructure, combined with tight involvement of industrial partners. Finally, it
is worth stressing the training provided at all education levels by this marvelous scientific
tool.
References
[1] A. Abada, M. Abbrescia, S. AbdusSalam, I. Abdyukhanov, J. Abelleira Fernandez,
A. Abramov et al., FCC–hh: The Hadron Collider: Future Circular Collider
Conceptual Design Report Volume 3. Future Circular Collider,Eur. Phys. J. Spec.
Top. 228 (2019) 755.
[2] N. Fuster-Mart´ınez, R.W. Aßmann, R. Bruce, M. Giovannozzi, P. Hermes,
A. Mereghetti et al., Beam-based aperture measurements with movable collimator jaws
as performance booster of the cern large hadron collider,The European Physical
Journal Plus 137 (2022) 305.
[3] M. Giovannozzi and E. todesco, “Combined-function optics for circular high-energy
hadron colliders.” arXiv:2109.13720 [physics.acc-ph], 2021.
[4] G. Willering et al., Tests of the FRESCA2 100 mm bore Nb3Sn block-coil magnet to a
record field of 14.6 T,IEEE Trans. Appl. Supercond. 29 (2019) 4004906.
[5] A. Zlobin et al., First measurements of magnet quench performance and field quality
of the 15 t nb3sn dipole demonstrator mdpct1, in 2019 North American Particle
Accelerator Conf.(NA-PAC’19), Lansing, MI, USA, September 2-6, 2019,
p. MOPL020, 2019.
[6] US-MDP collaboration, Reassembly and Test of High-Field Nb3Sn Dipole
Demonstrator MDPCT1,IEEE Trans. Appl. Supercond. 31 (2021) 4000506.
[7] S. Caspi, F. Borgnolutti, L. Brouwer, D. Cheng, D. Dietderich, H. Felice et al.,
Canted–cosine–theta magnet (cct)—a concept for high field accelerator magnets,IEEE
transactions on applied superconductivity 24 (2013) 1.
22
[8] A. Ballarino et al., The CERN FCC Conductor Development Program: A Worldwide
Effort for the Future Generation of High-Field Magnets,IEEE Transactions on
Applied Superconductivity 29 (2019) 1.
[9] F. Buta et al., Very high upper critical fields and enhanced critical current densities
in Nb3Sn superconductors based on Nb–Ta–Zr alloys and internal oxidation,Journal
of Physics: Materials 4(2021) 025003.
[10] S.C. Hopkins, A. Baskys, A. Ballarino, J. Lachmann and A. Leineweber, Phase
Evolution During Heat Treatm’ent of Nb3Sn Wires Under Development for the FCC
Study,IEEE Transactions on Applied Superconductivity 31 (2021) 1.
[11] X. Xu, X. Peng, J. Rochester, M. Sumption and M. Tomsic, Achievement of FCC
specification in critical current density for N3Sn superconductors with artificial
pinning centers,arXiv preprint arXiv:1903.08121 (2019) .
[12] S. Balachandran, C. Tarantini, P.J. Lee, F. Kametani, Y.-F. Su, B. Walker et al.,
Beneficial influence of hf and zr additions to nb4at.%ta on the vortex pinning of
nb3sn with and without an o source,Superconductor Science and Technology 32
(2019) 044006.
[13] Xu, X and Sumption, M and Peng, X and Collings, EW, Refinement of Nb3Sn grain
size by the generation of ZrO2precipitates in Nb3Sn wires,Applied Physics Letters
104 (2014) 082602.
[14] C. Senatore, C. Barth, M. Bonura, M. Kulich and G. Mondonico, Field and
temperature scaling of the critical current density in commercial REBCO coated
conductors,Superconductor Science and Technology 29 (2015) 014002.
[15] MIT, SPARC,https://www.psfc.mit.edu/sparc accessed 2021 (2021) .
[16] MIT, MIT News,
https://news.mit.edu/2021/MIT-CFS-major-advance-toward-fusion-energy-0908
accessed 2021 (2021) .
[17] V. Matias and B. Moeckly, Price of 2G HTS Wire: Plenty of Room to Go Down,
2020 Snowmass Letter of Interest (2020) .
[18] M. Koratzinos, Private communication, 2021.
[19] A. Abada, M. Abbrescia, S. AbdusSalam, I. Abdyukhanov, J. Abelleira Fernandez,
A. Abramov et al., HE–LHC: The High-Energy Large Hadron Collider — Future
Circular Collider Conceptual Design Report Volume 4,Eur. Phys. J. Spec. Top. 228
(2019) 1109.
[20] I. B´ejar Alonso, O. Br¨uning, P. Fessia, L. Rossi, L. Tavian and M. Zerlauth,
High-Luminosity Large Hadron Collider (HL–LHC): Technical design report, CERN
Yellow Reports: Monographs, CERN, Geneva (2020), 10.23731/CYRM-2020-0010.
23
[21] H. Damerau, A. Funken, R. Garoby, S. Gilardoni, B. Goddard, K. Hanke et al., LHC
Injectors Upgrade, Technical Design Report, CERN (Dec, 2014),
10.17181/CERN.7NHR.6HGC.
[22] M. Benedikt, D. Schulte and F. Zimmermann, Optimizing integrated luminosity of
future hadron colliders,Phys. Rev. ST Accel. Beams 18 (2015) 101002.
[23] M. Giovannozzi and J. Morel, Principle and analysis of multiturn injection using
stable islands of transverse phase space,Phys. Rev. ST Accel. Beams 10 (2007)
034001.
[24] A. Franchi and M. Giovannozzi, Novel technique for injecting and extracting beams in
a circular hadron accelerator without using septum magnets,Phys. Rev. ST Accel.
Beams 18 (2015) 074001.
[25] M. Krasny, A. Petrenko and W. P laczek, High-luminosity Large Hadron Collider with
laser-cooled isoscalar ion beams,Prog. Part. Nucl. Phys. 114 (2020) 103792.
[26] M.W. Krasny, “The Gamma Factory proposal for CERN.” arXiv:1511.07794
[physics.hep-ex], 2015.
[27] Gamma Factory Study Group collaboration, Gamma Factory Proof-of-Principle
Experiment, Tech. Rep. CERN-SPSC-2019-031, SPSC-I-253, CERN, Geneva (Sep,
2019).
[28] D. Budker, J. Crespo L´opez-Urrutia, A. Derevianko, V. Flambaum, M. Krasny,
A. Petrenko et al., “Atomic physics studies at the Gamma Factory at CERN.”
arXiv:2003.03855 [physics.atom-ph], 2020.
[29] “U.S. Muon Accelerator Program (MAP).” http://map.fnal.gov.
[30] “International Muon Collider Design Study.” https://muoncollider.web.cern.ch/.
[31] R. Palmer and K. Long, eds., Muon Accelerators for Particle Physics (MUON),
vol. 16, IOP Publishing, 2021.
[32] M. Antonelli, M. Boscolo, R. Di Nardo and P. Raimondi, Novel proposal for a low
emittance muon beam using positron beam on target,Nucl. Instrum. Meth. A 807
(2016) 101 [1509.04454].
[33] F. Zimmermann, LHC/FCC-based muon colliders,Journal of Physics: Conference
Series 1067 (2018) 022017.
[34] F. Zimmermann, A. Latina, A. Blondel, M. Antonelli and M. Boscolo, Muon Collider
based on Gamma factory, FCC-ee and Plasma Target,Submitted to IPAC’22 (2022) .
[35] O. Br¨uning and L. Rossi, The High-Luminosity Large Hadron Collider,Nature
Reviews Physics 1(2019) 241.
[36] M. Benedikt and F. Zimmermann, The physics and technology of the Future Circular
Collider,Nature Reviews Physics 1(2019) 238.
24
[37] M. Benedikt, A. Blondel, P. Janot, M. Mangano and F. Zimmermann, Future
Circular Colliders succeeding the LHC,Nature Physics 16 (2020) 402.
[38] A. Abada, M. Abbrescia, S.S. AbdusSalam, I. Abdyukhanov, J. Abelleira Fernandez,
A. Abramov et al., FCC-ee: The lepton collider,The European Physical Journal
Special Topics 228 (2019) 261.
[39] O.S. Br¨uning, P. Collier, P. Lebrun, S. Myers, R. Ostojic, J. Poole et al., LHC Design
Report, CERN Yellow Rep. Monogr., CERN, Geneva (2004),
10.5170/CERN-2004-003-V-1.
[40] M. Giovannozzi, “Considerations on combined-function optics for high-energy storage
rings and colliders.” Submitted for publication in EPJ Tech. Instrum., 2022.
25