Operation of Price Adjustment in Construction Projects

Authors:
  • Madhesh University Nepal

Abstract and Figures

The construction industry always faces problems on price fluctuation and adjustment of the price to compensate the cost fluctuation becomes necessary. There is dilemma on which formula of price adjustment to use in construction contracts. Price adjustment affects all the stakeholders i.e. client, consultant and contractor. This research has revealed about the trend of the cost of components of construction i.e. labor, material, fuel, equipment, etc. and compare the different formulas of price adjustment Ten contracts commencing within 2010 A.D to 2019 A.D have been chosen. The formula used in the contracts has been compared with other formulas under same circumstance that original formula was used. The cost of fuel and bitumen cannot be predicted as it is fluctuating with respect to time. PPMO formula for Price Adjustment use NRB index of labor, material and equipment or fuel. Labor index has increased by 44.86 % during June 2015 to June 2019. Material index is fluctuating and has increased by 20.66% and Equipment index by 31.54%. Comparing the price adjustment factor using different formulas it is seen that the value of price adjustment factor using different formulas are different and change with course of time. Thus, it cannot be generalized that which formula could give minimum value of price adjustment. It depends upon condition such as time, index and cost.
Content may be subject to copyright.
1
Operation of Price Adjustment in Construction Projects
Anjay Kumar Mishra*, & P. S. Aithal**
*Post Doctorate Scholar, Srinivas University, India & Associate Professor, Madan Bhandari
Memorial Academy Nepal, Urlabari 3, Morang, Nepal
OrcidID: 0000-0003-2803-4918; Email: anjaymishra2000@gmail.com
**Professor, College of Management & Commerce, Srinivas University, Mangalore, India
OrcidID: 0000-0002-4691-8736; E-mail: psaithal@gmail.com
November 2020
ABSTRACT
The construction industry always faces problems on price fluctuation and adjustment of the price
to compensate the cost fluctuation becomes necessary. There is dilemma on which formula of price
adjustment to use in construction contracts. Price adjustment affects all the stakeholders i.e. client,
consultant and contractor. This research has revealed about the trend of the cost of components of
construction i.e. labor, material, fuel, equipment, etc. and compare the different formulas of price
adjustment Ten contracts commencing within 2010 A.D to 2019 A.D have been chosen. The
formula used in the contracts has been compared with other formulas under same circumstance
that original formula was used. The cost of fuel and bitumen cannot be predicted as it is fluctuating
with respect to time. PPMO formula for Price Adjustment use NRB index of labor, material and
equipment or fuel. Labor index has increased by 44.86 % during June 2015 to June 2019. Material
index is fluctuating and has increased by 20.66% and Equipment index by 31.54%.Comparing the
price adjustment factor using different formulas it is seen that the value of price adjustment factor
using different formulas are different and change with course of time. Thus, it cannot be
generalized that which formula could give minimum value of price adjustment. It depends upon
condition such as time, index and cost.
Keywords: Trend, Price adjustment, Index, Initial completion date, Formulas
1. INTRODUCTION:
Price fluctuations are the outcome of different forces i.e. both national and international bazzar forces,
along with components of the development sector that mainly causes it vulnerable to average cost
fluctuation andbank economic report(Riggs, 2006)[1]. Price fluctuation has become a very obvious trend
in current economic scenario, all over the world. It particularly gets very important in the developing
countries due to the dependency of the country on external factors (MCCartney, 2011) [2]. Market price
fluctuations all levels directly affect contractors. Besides the contractor, the client and the beneficiaries of
construction project also are affected by price fluctuation.Inflation has become an ongoing issue whose
impacts saturate the whole development industry. Contractual workers are confronted with extreme
vulnerability in offering and financing chips away at ventures. Efficiency is influenced on the grounds that
contractual worker can't precisely estimate long haul returns on their ventures and are needed to redirect
important funding to meet asset costs (Mishra and Regmi, 2017) [3]. It is therefore a major concern to know
how the price of different components of construction is fluctuating during various time of a construction
project and know the trend so that we can predict the risk in a more accurate way.
For addressing the adverse effect of price fluctuation price adjustment provision is introduced in most of
the contracts with duration greater than 12 months. According to ‘Price Adjustment Guidance on
Procurement 2018’, there is no single price adjustment formula that encompasses every situation. Different
formulas are applied in contracts of different sizes and for different components. A contract may comprise
one or more currencies of payment. For a contract with price adjustment provisions, at least one price
Electronic copy available at: https://ssrn.com/abstract=3732323
2
adjustment formula should be given for each currency of payment. Agreements for major and complex
works and plant may likewise contain a few areas, every one of which can be recognized commonly, area,
access, timing, or whatever other exceptional attributes which may cause various strategies for
development, staging of the works, or contemplations of cost. General things normal to all pieces of the
works might be gathered as a different segment in the bill of amounts. For such contracts, a different price
adjustment formula with different cost components and weights may be required for each group or section.
So, it is of concern in construction industry to compare the different results that come by applying different
price adjustment formulas and choose the one that minimizes the risk. Generally, FIDIC formula and
PPMO’s formula are used for price adjustment.
Department of roads is one of the major agencies that conducts development activities on contractual basis.
However, progress of individual project in their annual report shows that most of the time, projects are not
completed within planned time, budget and also sometimes within specified quality. Price escalation is
additionally considered as a major issue, which prevents venture progress, since it diminishes the
contractual worker's benefit prompting immense misfortunes leaving venture in a difficult situation. There
is dilemma among project personnel whether to deduct mobilization advance from IPC and calculate the
price adjustment value or not to deduct mobilization advance for calculation of price adjustment.
2. OBJECTIVES:
The main objective of the paperis to analyze the trend of cost of components of construction for
comparingvalue of price adjustment factor of selected contracts using different price adjustment formulas.
3. LITERATURE REVIEW:
3.1 Price Adjustments:
Generally, for the projects funded by Government of Nepal, price adjustment provision is used for contracts
having the duration of 12 months or more. And for donor funded project (ADB), price adjustment
provisions may also be used in consulting and on consulting service contracts, to adjust remuneration rates
for the effects of inflation for contracts with duration of 18 months or more. Bidders will factor in the risk
of price escalation when preparing their bid, depending on the contract specified in the bidding document.
In a fixed-value contract, bidders will factor in the total money related dangers related with value
heightening in their offers.
In a no fixed-value contract, a value change equation is utilized to appraise value acceleration, henceforth;
bidders have the choice to diminish their premium related with dangers of value heightening in their offers
to stay serious.A fixed-price contract may give certainty to budget and simplify contract management.
However, it may lead to other problems since it requires bidders to estimate and bear the financial risks
associated with price escalations. On the off chance that the evaluations are excessively high or functions
don't appear, the borrower will follow through on a lofty cost that may influence the economy and
proficiency of the agreement. In a worst case, it may mean that the bid price is then above budget and may
lead to a reduction in the requirements or rebidding. If the estimates are too low, it may appear as an
abnormally low bid and disrupt contract execution (ADB, 2018) [4].
Value change arrangements incorporate equations intended to address issues, and can shield both the
borrower and temporary workers from value variances. Value change equations permit contractual workers
to offer more practical costs at the hour of offering. Despite concerns that they may lead to budget
uncertainties, price adjustment formulas will estimate the actual cost implications that will be encountered.
They use indexes that can be used for cost projection (ADB, 2018) [4].
3.2 Deciding to Apply Price Adjustments:
This danger of value acceleration is probably going to arise for merchandise contracts with long conveyance
periods, for works contracts with long culmination periods, for major common works contracts, for gets
that contain supplies or wares whose costs vary fundamentally over a brief period, for time sensitive
counseling administrations, for example, development oversight administrations and for because of any
Electronic copy available at: https://ssrn.com/abstract=3732323
3
unordinary conditions in the market being referred to.The longer the delivery or completion period, the
more likely those market prices for components will change. Since the cost of works, for example, depends
directly on the cost components, this will also affect the overall cost of works contracts. ADB thus applies
a general guidance that any contract with a delivery or completion period beyond 18 months should contain
an appropriate price adjustment clause (ADB, 2018) [4].
The price of some components may still vary significantly within time periods shorter than 18 months.
These usually include bitumen, fuel, cement and reinforced steel. Where; the price of such components
fluctuates over short periods of time, it is also appropriate to include a price adjustment clause, whatever
the length of the contract may be (ADB, 2018) [4].
According to ‘Price Adjustment Guidelines 2018, ADB’, price adjustment regulation may not be
compulsory for general supply contracts (i.e. not including components that are usually affected by
escalating or fluctuating prices) with short delivery periods.
The procurement of certain types of hardware where typical business practice expects bidders to submit
firm costs paying little mind to the conveyance time, which may be the case for (a) engineering,
procurement, and construction contracting arrangements; and (b) fixed-price contracts that are common in
projects financed by private sector financiers, who are generally reluctant to accept the risk of cost overruns,
as it increases credit risk rating and reduces financial viability of the project. Contracts for the supply,
installation, and construction of facilities wherein the value of the permanent works represents the major
part of the estimated cost of the contract. All major equipment is usually supplied from fixed production
lines; thus, an experienced manufacturer should be able to mitigate the risk of price fluctuations.
3.3 Price Adjustment formulas:
Price adjustment equations involve fixed or nonadjustable and customizable cost parts. Each cost part has
a coefficient or weight that is determined dependent on its relative incentive to the complete agreement sum
according to the designer's gauge. A value record is utilized to appraise the periodical change of unit cost
of each cost part remembered for the recipe.
The following tables ‘t1’ and ‘t2’ gives examples of price adjustment formulas from the standard bidding
documents (SBD) of the Asian Development Bank (ADB) for goods, works, and plant.
Table 1 : FIDIC Formula for Large Work
SBD Reference [5] Clause Formula
Large Works FIDIC MDB 2010 GCC
13.8
𝑃𝑛
𝐴
𝑏
𝐿𝑛
𝐿𝑜 𝑐
𝐸𝑛
𝐸𝑜 𝑑
𝑀𝑛
𝑀𝑜 ⋯
Where "Pn" is the change multiplier to be applied to the assessed agreement esteem in the important money
of the work did in period "n," this period being a month, except if in any case expressed in the agreement
information. "a" (default esteem is set at 0.15) is a fixed coefficient, expressed in the applicable table of
change information, speaking to the nonadjustable segment in legally binding installments. "b", "c", "d",
… are coefficients speaking to the assessed extent of each cost component identified with the execution of
the works, as expressed in the pertinent table of change information. Such classified cost components might
be characteristic of assets, for example, work, gear, and materials. (a + b + c + d + … = 1) "Ln", "En",
"Mn", … are the current expense records or reference costs for period "n," communicated in the significant
cash of installment, every one of which is pertinent to the important organized cost component on the date
49 days preceding the most recent day of the period (to which the installment declaration relates). "Lo",
"Eo", "Mo", are the base expense files or reference costs, communicated in the important cash of
installment, every one of which is appropriate to the applicable arranged cost component on the base date.
Table 2 : Standard Bidding Document for Small Work
Electronic copy available at: https://ssrn.com/abstract=3732323
4
SBD Reference [5] Clause Formula
Small Works MDB harmonized GCC
54.1
𝑃𝑐
𝐴
𝑐𝐵𝑐
𝐼𝑚𝑐
𝐼𝑐
Where, Pc is the change factor for the bit of the agreement value payable in a particular cash "c." Ac and
Bc are coefficients determined in the specific states of agreement, speaking to the nonadjustable (normally
0.10 to 0.20) and movable segments, separately, of the agreement value payable in that particular money
"c." Ac + Bc = 1. Imc is a merged record winning toward the month's end being invoiced and Ioc is a similar
united file winning 28 days before offer opening for inputs payable; both in the particular money "c." PPMO
uses price adjustment formula as shown in table ‘Table 3’ below :
Table 3 : Standard Bidding Document for Project of More than a Year
SBD Reference [6] Clause Formula
Works with
duration
greater than 12
months.
PPMO GCC
45.1 𝑃𝑛
𝐴
𝑏
𝐿𝑛
𝐿𝑜 𝑐
𝐸𝑛
𝐸𝑜 𝑑
𝑀𝑛
𝑀𝑜 ⋯
Where, Pn is the change factor for the bit of the agreement valuefor the work carried out in the period "n".
"A" "is a constant or the non-adjustable portion of price adjustment factor to be specified in Appendix- to
bid, representing the non-adjustable portion of the contract price"
"b, c, d " " are coefficients or weightages of the order 0.xx (i.e.., fractions having two significant digits) for
each specified element of adjustment in the contract. The sum of a, b, c, d, etc shall be one"
"Lo, Mo, Eo" "are the base date indices for specified (adjustable) elements"
"Ln, Mn, En - " are the current date records of the predetermined (customizable components for the period
"n". Regularly following wellspring of list is applied. Public Entity will pick material Index for everything.
(a) Labor: "Public Salary and Wage Rate Index"- "Development Labor" of Nepal Rastra Bank or rate fixed
by District Rate Fixation Committee
(b) Material:"National Wholesale Price Index" - Construction Materials" of Nepal Rastra Bank
(c) Equipment use: "Public Wholesale Price Index" - "Transport Vehicles and Machinery Goods" of Nepal
Rastra Bank or Fuel Price fixed by Nepal Oil Corporation.
The base costs of the development materials are taken of 30 days before the cutoff time for accommodation
of the offer as cited by the bidder and checked by the business. With the end goal of count of value change,
the ex-manufacturing plant cost of a similar source will be mulled over. HTMA (2010) [7] are found to be
referred by experience engineer for modification in private contract. Hiyassant (2000) [8] has concluded
bid evaluation is significant for price fluctuation decision. Jennings (1996) [9] also highlighted
prequalification and M.T. Banki (2008) [10] focuses on bidding strategy of Iranian construction industry.
3.4 Price Escalation and Adjustment Problems:
Various studies have been conducted in the past about the price adjustment and related topics. Research
study has been done on “Assessment of Price Escalation and Adjustment Problems on Federal Road
Construction Projects, 2013” by Mohommed Gassow Mossa [11].
The objectives of the research were to assess the causes and effects of price escalation, to identify problems
of price escalation adjustment, to assess the present price escalation administration system and to forward
recommendations which can assist in improving the price escalation administration on federal road
construction projects.
Electronic copy available at: https://ssrn.com/abstract=3732323
5
The results showed that: poor estimation, improper planning and/or improper implementation of proper
planning and project schedule changes are identified as major internal causes of price escalation in
Ethiopian federal road construction projects (Mossa, 2013) [11].
Besides, increase in material cost/material price fluctuation, increase in global demand for construction
materials, fluctuation in money exchange rates and limited capacity of material producers are assessed as
major external causes of price escalation in Ethiopian federal road construction projects. Finally, the main
effects of price escalation found in this research are higher project costs, cash flow (project financing)
problem of the projects, delay and dispute among parties (Mossa, 2013) [11].
From the survey; 36%, 20% and 14% of clients, consultants and contractors respectively, showed the
current price escalation administration system (practice) in federal road construction projects as very good.
And it is rated good by 50%, 35% and 36% of clients, consultants and contractors respectively. However,
14% of contractors and 20% consultants believe the current price escalation administration system
(practice) in federal road construction projects as poor (Mossa, 2013) [11].
Consider fluctuation/escalation clauses, consider locally available materials in design, regular cost
monitoring throughout the project and develop program wide contingencies and risk management protocol
are identified as major methods to manage/administer price escalation in Ethiopian federal road
construction projects (Mossa, 2013) [11].
3.5 Market Price Fluctuation Trend:
According to the response of the contractors’ representative who responded to the questionnaire survey, it
can be seen that the degree of predictability of construction material price fluctuation is very low. The result
shows that contractors cannot easily determine how the price of materials behaves in future. Degree of
unpredictability in construction materials price is higher than that of construction labor and Construction
equipment (Mishra & Regmi, 2017) [3]. Occurrence of price fluctuation on construction inputs especially
on construction materials is unpredictable because the construction materials price is increasing and
decreasing for short period of time due to social geographical complexity though on quarterly basis it
consistently increases at a lower rate (Mishra & Regmi, 2017) [3]. It was found that most of the construction
materials and its raw materials are imported which makes the chain longer resulting into high price
fluctuation whereas labors are not having much more options to create their high demand so they want to
grow with the industry resulting into lesser price fluctuation comparatively though the increment is higher
(Mishra & Regmi, 2017) [3].
4. RESEARCH METHODOLOGY:
4.1 Study Area :
This study has focused on the contracts which have the clause of price escalation and have crossed two
years period in construction under ‘Government of Nepal, Department of Roads, Project directorate ADB,
Kathmandu’ and ‘Road Division Butwal, Rupandehi’, Mid-hill Project east sector, Bridge Project Western
Sector No.3 Banke.
Name of organizations taken for study:
1. Department of Roads, Project directorate ADB, Kathmandu.
2. Road Division Butwal, Rupandehi.
3. Mid-hill Project east sector
4. Bridge Project Western Sector No.3 Banke
Contracts under DOR having price adjustment provisions and completing two years period were selected
deliberately. The ten contracts whose base date is within in past ten years are Nepalgunj-Kohalpur Road
Package-1, Nepalgunj-Kohalpur Road Package-2, Bhairahawa-Lumbini-Taulihawa Road Project,
Construction of Prestressed RCC bridge over TinauRiver, Puspalal Midhill Highway Project East Sector,
Design & Build of Rapti Nadi Bridge, Gauri Khola Bridge, Ungrida Khola Bridge Inguriya River Bridge
and Chainpur-Khandbari Road Project.
Electronic copy available at: https://ssrn.com/abstract=3732323
6
4.2 Research Design:
The trend of price adjustment of various components of construction i.e. labor, material, equipment, fuel in
selected contracts of DOR has been analyzed and price adjustment factor of selected contract using different
formulas have been compared. Analytical research design has been used.
4.3 Data Collection:
The secondary data have been collected through the interim payment certificates and contract documents
of the selected contracts of Department of Roads, Project directorate ADB, Kathmandu’, ‘Road Division
Butwal, Rupandehi, ‘Mid-hill Project east sector’ and Bridge Project Western Sector No.3 Banke. It has
also beencollected the data from price index published by NRB. Secondary data have been obtained from
various sources such as ‘Price Adjustment Guidelines of ADB, 2018’, previous thesis on the related topics,
relevant text books regarding price adjustment. FIDIC and PPMO documents, journal’s data from
previously mentioned offices.
4.4 Data Analysis and Presentation of Data:
After collection of data, the data has been classified into different categories. The cost/index of material,
equipment and labor has been separately noted and each of them has been plotted on graph where x-axis is
duration and y-axis are cost/index. The trend of the material, equipment, labor, fuel cost/index varies during
the construction period of each selected contract have been analyzed.
The data has been used to compare the price adjustment factor of selected contract using different formulas.
Each value of price adjustment calculated from the formula mentioned in the price adjustment clause of
contract and the value of price adjustment calculated from formula other than that mentioned in price
adjustment clause has been compared.
5. RESULTS AND DISCUSSION:
5.1 Trend of Cost of Components of Construction on Contracts using FIDIC formula:
FIDIC formula have been used in the contracts namely Nepalgunj-Kohalpur Road Package-1, Nepalgunj-
Kohalpur Road Package-2, Bhairahawa-Lumbini-Taulihawa Road Project and Construction of Prestressed
RCC bridge over Tinau River. The cost of components of construction in each IPC is taken starting from
the base date and graph is plotted.
5.2 Labor Cost Trend:
The cost of labor has been taken from the district rates of the respective district on which the project is
implemented. The graphs below show the actual trend of the cost of labor in the four contracts using FIDIC
formula for price adjustment.
Electronic copy available at: https://ssrn.com/abstract=3732323
7
Fig. 1: Labor Cost trend of Nepalgunj Kohalpur Road Package-1
Similarly, by analyzing the all 4 contracts, it can be seen that the labor cost has increased with respective
to time in every contract. Labor cost has increased by 33.33 % in Nepalgunj-Kohalpur Road Package-1,
21.67% in Nepalgunj-Kohalpur Road Package-2, 29.21%in construction of Prestressed Bridge over Tinau
River and 18.17% in Bhairahawa-Lumbini-Taulihawa Road project up to the last IPC date.
5.3 Fuel Cost Trend:
The cost of fuel has been taken from the district rates of the respective district on which the project is
implemented. The graphs below show the actual trend of the cost of fuel in the four contracts using FIDIC
formula for Price adjustment.
0
50
100
150
200
250
300
350
400
450
10‐Jul‐12
18‐Oct‐12
26‐Jan‐13
06‐May‐13
14‐Aug‐13
22‐Nov‐13
02‐Mar‐14
10‐Jun‐14
18‐Sep‐14
27‐Dec‐14
06‐Apr‐15
15‐Jul‐15
23‐Oct‐15
31‐Jan‐16
10‐May‐16
18‐Aug‐16
26‐Nov‐16
06‐Mar‐17
14‐Jun‐17
22‐Sep‐17
Laborcosttrend
Laborcost
DateofIPC
Electronic copy available at: https://ssrn.com/abstract=3732323
8
Fig. 2; Fuel Cost trend of Nepalgunj Kohalpur Road Package-1
Similarly, by observing the all 4 contracts, it can be seen that the fuel cost has fluctuatedmore with respect
to time. In Nepalgunj-Kohalpur Road Package-1, it can be seen that base value of fuel was 95500/KL in
October 2012 and cost has increased up to 109000/KL in April 2014 and again went on decreasing to
77500/KL in May 2017.The cost of fuel has reduced by 23.22% up to last IPC. In Nepalgunj Road Kohalpur
Package-2, the cost of fuel has increased by 4.71% up to last IPC. In construction of Prestressed RCC bridge
over Tinau River, the cost of fuel has reduced by 5.81% up to last IPC date. In Bhairahawa-Lumbini-
Taulihawa Road Project the cost of fuel has increased by 34.93% upto last IPC date. So, it cannot be
predicted accurately whether the fuel cost increase or decrease in a contract over time.
5.4 Bitumen Cost Trend :
The cost of Bitumen has been taken from the district rates of the respective district on which the project
was implemented. The graphs below show the actual trend of the cost of bitumen in the three contracts
using FIDIC formula for Price adjustment. As bitumen is not used in bridge construction so Tinau River
Bridge has not been considered.
Fig. 3: Bitumen Cost trend of Nepalgunj Kohalpur Road Package-1
Similarly, it can be seen that the bitumen cost has fluctuated with respect to time. In Nepalgunj Road
Kohalpur Package-1, base value of bitumen is Rs 81350, peak valueis 96400 and value at last date of IPC
0
20000
40000
60000
80000
100000
120000
10‐Jul‐12
18‐Oct‐12
26‐Jan‐13
06‐May‐13
14‐Aug‐13
22‐Nov‐13
02‐Mar‐14
10‐Jun‐14
18‐Sep‐14
27‐Dec‐14
06‐Apr‐15
15‐Jul‐15
23‐Oct‐15
31‐Jan‐16
10‐May‐16
18‐Aug‐16
26‐Nov‐16
06‐Mar‐17
14‐Jun‐17
22‐Sep‐17
Fuelcosttrend
Fuelcost/KL
Date ofIPC
0
20000
40000
60000
80000
100000
120000
10‐Jul‐12
18‐Oct‐12
26‐Jan‐13
06‐May‐13
14‐Aug‐13
22‐Nov‐13
02‐Mar‐14
10‐Jun‐14
18‐Sep‐14
27‐Dec‐14
06‐Apr‐15
15‐Jul‐15
23‐Oct‐15
31‐Jan‐16
10‐May‐16
18‐Aug‐16
26‐Nov‐16
06‐Mar‐17
14‐Jun‐17
22‐Sep‐17
BitumencostTrend
Bitumen Cost
Date ofIPC
Electronic copy available at: https://ssrn.com/abstract=3732323
9
is 77900. The cost of bitumen has reduced by 4.24 % up to last IPC. Similarly, in Nepalgunj Road Kohalpur
Package-2, the cost of bitumen has reduced by 7.8 % up to last IPC date. In Bhairahawa-Lumbini-Taulihawa
Road Project the cost of bitumen has increased by 18.13% up to last IPC date. It can be seen that the bitumen
costcannot be predicted in more accurate way.
5.5 Trend of cost of components of construction on Contracts using PPMO formula:
PPMO formula has been used in 5 construction contracts under study. Three inputs labor, material and
equipment index are taken from NRB [12] economic bulletin and publications.The base dates of these
contracts are
Puspalal Midhill Highway Project East Sector: 7 June 2015
Design & Build of Rapti Nadi Bridge: 10 April 2016
Gauri Khola Bridge:12 March 2017
Ungrida Khola Bridge: 7 May 2017
Inguriya River Bridge:12 March 2017
All the contracts study period is before July 2019. So, the trend of labor,material and equipment index from
June 2015 to present has been analyzed to know how the construction input index is changing.
5.6 Labor index Trend:
Labor index is published by NRB [12]. For our study of five contracts using PPMO formula of price
adjustment labor index starting from June 2015 to June 2019has been plotted.
Fig. 4: Labor Index Trend
From the figure 4; it can be seen that labor index has increased every month from June-2015 to June-2019.
Labor index has increased by 44.86 % during four years.
5.7 Material Index Trend:
0.0
100.0
200.0
300.0
400.0
500.0
600.0
Dec‐14 Jul‐15 Jan‐16 Aug‐16 Mar‐17 Sep‐17 Apr‐18 Oct‐18 May‐19 Dec‐19
LaborIndex
Month
LaborIndexTrend
LaborIndex Linear(LaborIndex)
Electronic copy available at: https://ssrn.com/abstract=3732323
10
Material index is published by NRB [12]. For our study of five contracts using PPMO formula of price
adjustment Material index starting from June 2015 to June 2019has been plotted.
Fig. 5: Material Index Trend
From the figure 5, it can be seen that material index has increased from month from June-2015 with value
291.6 to March 2016 with value 299.9 and decreasing up to October 2016 with value 285.9 and then
increased to June-2019 with value 359.47. Material index has increased by 20.66 % during four years.
5.8 Equipment index Trend:
Equipment index is published by NRB [12]. For our study of five contracts using PPMO formula of price
adjustment equipment index starting from June 2015 to June 2019 is plotted.
0
50
100
150
200
250
300
350
400
Dec‐14 Jul‐15 Jan‐16 Aug‐16 Mar‐17 Sep‐17 Apr‐18 Oct‐18 May‐19 Dec‐19
MaterialIndex
Month
Materialindextrend
MaterialIndex Linear(MaterialIndex)
Electronic copy available at: https://ssrn.com/abstract=3732323
11
Fig. 6: Equipment index Trend
From the figure 6, it can be seen that equipment index has increased from month from June-2015 with value
190.1 to October 2018 with value 245.04 and decreasing up to April 2019 with value 239.3 and then
increased up to June-2019 with value 250.07. Equipment index has increased by 31.54 % during last four
years.
5.9 Comparison of Price Adjustment Factor:
Price Adjustment Factor is calculated using different formulas. In Nepalese Construction industry three
formulas of Price Adjustment are under Practice, i.e. FIDIC formula, PPMO formula and Small works
formula. The IPC of each contract is taken and Original Price Adjustment Factor calculated in contract is
compared with other formulas. In our study contracts having price adjustment calculation using FIDIC
formula is compared with PPMO formula and Small works formula. Contracts using PPMO formula is
compared with Small works formula and vice versa.
5.10 Nepalgunj Kohalpur Road Package-1:
Bid Opening date: 11-November-2012
Base Date: 13-October-2012
Original formula used is FIDIC formula: Pfa+b *(ln/l0)+c(Fn/Fo)+d(Bn/Bo)+e(On/Oo)
Where a=0.15, b=0.10, c=0.10, d=0.35, e=0.30
Ln, Fn, Bn, On are the current cost of labor, fuel, bitumen and others index (consumer price index)49 days
before each IPC. Lo, Fo, Bo, Oo are base value of labour, Fuel, Bitumen and Others index (consumer price
index).
Small works formula is Ps=Ac+Bc*(Lmc/Lmo). Where Ac=0.15 and Bc=0.85 Lmc is consolidated
consumer price index at current IPC and Lmo is consolidated consumer price index at base date. From NRB
economic bulletin was taken the value of Lmo for the base date and Lmc for 49 days before IPC date. Lmo
is 180.8 for the base date.
PPMO formula is taken as Pp=a+b*(Ln/Lo)+c*(Mn/Mo)+d*(En/Eo) where Ln, Mn, En are the NRB index
of Labor,Material and Equipment respectively taken 49 days before IPC date and Lo, Mo, Eo are the base
index of Labor,Material and Equipment respectively. Apart from this, the coefficient of b,c and d are not
known. Generally, the limits are set by the employer for the value of b, c and d as
0
50
100
150
200
250
300
Dec‐14 Jul‐15 Jan‐16 Aug‐16 Mar‐17 Sep‐17 Apr‐18 Oct‐18 May‐19 Dec‐19
AxisTitle
Month
Equipmentindextrend
EquipmentIndex Linear(EquipmentIndex) Linear(EquipmentIndex)
Electronic copy available at: https://ssrn.com/abstract=3732323
12
A B C D
0.15 0.15 to 0.25 0.30 to 0.40 0.20 to 0.30
Where the sum of a, b, c and d should be equal to 1.
The value of b, c, d has been chosen with three combinations and calculate the price adjustment factor using
PPMO formula
(i) Pp1 has been calculated using coefficients b=0.25, c=0.40, d=0.20 where coefficient of labor is
Maximum, Material is maximum and Equipment is minimum. In simpler form combination can be denoted
as Lmax, Mmax, Emin
(ii) Pp2 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
(iii) Pp3 has been calculated using coefficients b=0.25, c=0.30, d=0.30 (Lmax, Mmin, Emax)
Table 4: Comparison of Price Adjustment Factor in Nepalgunj Kohalpur Road Package-1
Price
adjustment
FIDIC
Formula
Small
works
formula PPMO formula
Date of IPC
Pf Ps Pp1 Pp2 Pp3
Base value 13-Oct-12 1 1 11 1
IPC 3 30-Jun-13 1.022 1.008 1.000 0.999 1.001
IPC 4 30-Sep-13 1.05 1.04 1.004 1.002 1.004
IPC 5 15-Nov-13 1.113 1.068 1.0235 1.022 1.021
IPC 6 31-Dec-13 1.119 1.083 1.024 1.023 1.022
IPC 7 31-Jan-14 1.119 1.083 1.03 1.027 1.028
IPC 8 28-Feb-14 1.117 1.079 1.032 1.024 1.027
IPC 9 31-Ma
r
-14 1.115 1.072 1.193 1.181 1.15
IPC 10 30-Ap
r
-14 1.121 1.076 1.051 1.039 1.043
IPC 11 31-May-14 1.12 1.085 1.055 1.042 1.046
IPC 12 30-Jun-14 1.124 1.092 1.058 1.046 1.049
IPC 13 20-Aug-14 1.135 1.108 1.0615 1.049 1.053
IPC 14 30-Nov-14 1.132 1.134 1.087 1.07 1.08
IPC 15 31-Dec-14 1.134 1.15 1.094 1.078 1.088
IPC 16 28-Feb-15 1.093 1.146 1.0885 1.069 1.0805
IPC 17 31-Ma
r
-15 1.051 1.136 1.093 1.072 1.085
IPC 18 31-May-15 1.054 1.145 1.100 1.0785 1.091
IPC 19 30-Jun-15 1.055 1.149 1.104 1.081 1.094
IPC 20 31-Aug-15 1.066 1.18 1.1065 1.0835 1.096
IPC 21 31-Oc
t
-15 1.073 1.199 1.1175 1.096 1.109
IPC 22 31-Dec-15 1.078 1.213 1.1395 1.1125 1.1305
Electronic copy available at: https://ssrn.com/abstract=3732323
13
IPC 23 31-Jan-16 1.078 1.254 1.147 1.119 1.139
IPC 24 30-Ap
r
-16 1.094 1.258 1.155 1.128 1.149
IPC 25 15-May-17 1.089 1.254 1.161 1.134 1.155
By application of FIDIC formula the price adjustment has increased by 8.9% up to last IPC, Small works
formula has shown increment up to 25.4%. PPMO formula using coefficients Lmax, Mmax, Emin (Pp1)
has shown increment up to 16.1%, PPMO formula using coefficients Lmin, Mmax, Emax (Pp2) has shown
increment up to 13.4%, PPMO formula using coefficients Lmax, Mmin, Emax (Pp3) has shown increment
up to 15.5%.
Figure 7: Comparison of Price adjustment factor using different formulas in Nepalgunj Kohalpur Road
Package-1
From the figure 7, it can be seen that Price adjustment factor has fluctuated more during time in FIDIC
formula. The reason behind this is the fluctuation in cost of fuel and bitumen.
5.11NepalgunjKohalpur Road Package-2:
Bid Opening date: 11-November-2012 and Base Date: 13-October-2012
By application of FIDIC formula the price adjustment has increased by 1.17% up to last IPC,Small works
formula has shown increment up to11.8%up to last IPC. PPMO formula using coefficients Lmax, Mmax,
Emin (Pp1) has shown increment up to10.1%, PPMO formula using coefficients Lmin, Mmax, Emax (Pp2)
has shown increment up to8.0%, PPMO formula using coefficients Lmax, Mmin, Emax (Pp3) has shown
increment up to9.2%.The reason behind this is the fluctuation in cost of major construction components
fuel and bitumen.
5.12 Bhairahawa-Lumbini-Taulihawa Road Project:
Base Dated on 22-September-2016, by application of FIDIC formula the price adjustment has increased by
11.36% up to last IPC, Small works formula has shown increment of 8.8% up to last IPC. PPMO formula
using coefficients Lmax, Mmax, Emin (Pp1) has shown increment of 16.99%, PPMO formula using
1.089
1.254
1.161
1.134
1.155
0.95
1
1.05
1.1
1.15
1.2
1.25
1.3
10‐Jul‐12
18‐Oct‐12
26‐Jan‐13
06‐May‐13
14‐Aug‐13
22‐Nov‐13
02‐Mar‐14
10‐Jun‐14
18‐Sep‐14
27‐Dec‐14
06‐Apr‐15
15‐Jul‐15
23‐Oct‐15
31‐Jan‐16
10‐May‐16
18‐Aug‐16
26‐Nov‐16
06‐Mar‐17
14‐Jun‐17
22‐Sep‐17
ComparisonofPriceAdjustmentfactorusingdifferent
formulas
Fidicformula SmallworksFormula PPMOformulaPp1
PPMOformulaPp2 PPMOformulaPp3
Price adjustment factor
Electronic copy available at: https://ssrn.com/abstract=3732323
14
coefficients Lmin, Mmax, Emax (Pp2) has shown increment of 16.7%, PPMO formula using coefficients
Lmax, Mmin, Emax (Pp3) has shown increment of 16.18%.
5.13 Construction of Prestressed RCC bridge over Tinau River:
Base Date: 5th-June-2015
Original formula used is FIDIC formula: Pf=A+Bu*(ln/l0) +Bc*(Cn/Co)
+Br*(Rn/Ro)+Bg*(Gn/Go)+Bd*(Fn/Fo)+Bn(On/Oo).The values of coefficient are
A Bu Bc Br Bg Bd Bm
0.15 0.15 0.15 0.20 0.05 0.05 0.25
Ln, Cn, Rn, Gn, Fn, Bn are the current cost of unskilled labor,cement, reinforcement, gabion, fuel, and
others indexconsumer price index) 30 days before each IPC. Lo, Co, Ro, Go, Fo, Bo are the cost of base
date. The value of b, c, d has been chosen with three combinations and calculate the price adjustment factor
using PPMO formula.
(i) Pp1 has been calculated using coefficients b=0.25, c=0.40, d=0.20 where coefficient of labor is
Maximum,Material Maximum and Equipment is minimum. In simpler form combinations have been
denoted as Lmax, Mmax, Emin
(ii) Pp2 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
(iii)Pp3 has been calculated using coefficients b=0.25, c=0.30, d=0.30 (Lmax, Mmin, Emax)
Table 5: Comparison of Price adjustment factor of Prestressed RCC Tinau River Bridge
FIDIC
Formula
Small works
formula PPMO formula
Date of
IPC Pf Ps Pp1 Pp2 Pp3
Base value 5-Jul-15 1.0000 1.0000 1.0000 1.0000 1.0000
IPC 1 23-Mar-16 1.0681 1.0672 1.0449 1.0427 1.0493
IPC 2 29-Jun-16 1.0773 1.0941 1.0497 1.0502 1.0616
IPC 3 30-Sep-16 1.0908 1.1201 1.0760 1.0679 1.0928
IPC 4 28-Jan-17 1.1092 1.1067 1.1009 1.0987 1.1213
IPC 5 28-Ma
r
-17 1.1066 1.0941 1.1031 1.1009 1.1230
IPC 6 19-May-17 1.1400 1.1176 1.1081 1.1050 1.1279
IPC 7 10-Jul-17 1.1395 1.1235 1.1099 1.1059 1.1298
IPC 8 13-Oc
t
-17 1.1545 1.1512 1.1261 1.1245 1.1456
IPC 9 29-Ap
r
-18 1.2177 1.1453 1.1879 1.1801 1.1995
IPC 10 5-Jul-18 1.2177 1.1453 1.1879 1.1801 1.1995
IPC 11 2-Jan-19 1.2177 1.1453 1.1879 1.1801 1.1995
IPC 12 28-Ap
r
-19 1.2177 1.1453 1.1879 1.1801 1.1995
By application of FIDIC formula the price adjustment has increased by 21.77% upto last IPC from base
value, Small works formula has shown increment of 14.53% upto last IPC. PPMO formula using
coefficients Lmax, Mmax, Emin (Pp1) has shown increment of 18.79% from base value, PPMO formula
using coefficients Lmin, Mmax, Emax (Pp2) has shown increment of 18.01%, PPMO formula using
coefficients Lmax, Mmin, Emax (Pp3) has shown increment of 19.95%.
5.14 PUSPALAL (mid-hill) Highway Project:
Electronic copy available at: https://ssrn.com/abstract=3732323
15
Base Date: 7th-June-2015
Original formula used is PPMO formula. PPMO formula is taken as
Pp=a+b*(Ln/Lo)+c*(Mn/Mo)+d*(En/Eo) where Ln, Mn, En are the NRB index of Labor, Material and
Equipment respectively taken 30 days before IPC date and Lo, Mo, Eo are the base index of Labor, Material
and Equipment respectively. Apart from this, the coefficient of b, c and d are not known here in this study.
The limits have been set by the Project for the value of b, c and d as
A B C d
0.15 0.15 to 0.25 0.40 to 0.50 0.20 to 0.25
Original formula “Poriginal” has been calculated using coefficients b=0.20, c=0.45, d=0.20. These
coefficients are proposed by contractor of this project. PPMO formula is compared using different
combinations
(i) Pp1 has been calculated using coefficients b=0.15, c=0.50, d=0.20 (Lmin, Mmax, Emin)
(ii) Pp2 has been calculated using coefficients b=0.25, c=0.40, d=0.20 (Lmax, Mmin, Emin)
(iii) Pp3 has been calculated using coefficients b=0.15, c=0.45, d=0.25 (Lmin, Mmid, Emax)
PPMO formula has been compared with small works formula and expressed in graph of figure 8.
By the PPMO formula using original coefficients the increment of price adjustment factorsup to last IPC is
17.91%. PPMO formula using coefficients Lmin, Mmax, Emin (Pp1) has shown increment of 17.20% from
base value, PPMO formula using coefficients Lmax, Mmin, Emin (Pp2) has shown increment of 18.62%,
PPMO formula using coefficients Lmin, Mmid, Emax (Pp3) has shown increment of 17.81%. By using
SmallWorksformula, the increment of price adjustment factors upto Last IPC is 14.98%.
Fig.8: Comparison of Price adjustment factor in Midhill Highway Project Gauri Khola Bridge along
Sisapur Bhawanipur Road in Rupandehi District
Base Date: 12th-March-2017
1.1498
1.172
1.1862
1.1781
0.98
1
1.02
1.04
1.06
1.08
1.1
1.12
1.14
1.16
1.18
1.2
27‐Dec‐14
06‐Apr‐15
15‐Jul‐15
23‐Oct‐15
31‐Jan‐16
10‐May‐16
18‐Aug‐16
26‐Nov‐16
06‐Mar‐17
14‐Jun‐17
22‐Sep‐17
31‐Dec‐17
10‐Apr‐18
19‐Jul‐18
27‐Oct‐18
04‐Feb‐19
15‐May‐19
23‐Aug‐19
ComparisonofPriceadjustmentfactorusingdifferent
formulas
Smallworksformula PPMOformulaPoriginal PPMOformulaPp1
PPMOformulaPp2 PPMOformulaPp3
Priceadjustmentfactor
Date ofIPC
Electronic copy available at: https://ssrn.com/abstract=3732323
16
Original formula used is PPMO formula.PPMO formula is taken as Pp=a+b*(Ln/Lo) +c*(Mn/Mo)
+d*(En/Eo) where Ln, Mn, En are the NRB index of Labor, Material and Equipment respectively taken 30
days before IPC date and Lo, Mo, Eo are the base index of labor, material and equipment respectively.
Apart from this, the coefficients of b, c and d are not known here in this study. The limits have been set by
the project for the value of b, c and d as
A B C D
0.15 0.15 to 0.25 0.30 to 0.40 0.20 to 0.30
Original formula “Poriginal” has been calculated using coefficients b=0.25, c=0.30, d=0.30 which is
combination of (Lmax, Mmin, Emax). These coefficients have been proposed by contractor of this
project.PPMO formula has been compared using different combinations.
(i) Pp1 has been calculated using coefficients b=0.25, c=0.40, d=0.20 (Lmax, Mmax, Emin)
(ii) Pp2 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
PPMO formula has been compared with small works formula.
Table 6: Comparison of Price adjustment factor in Construction of Bridge over Gauri Khola
Small
works
formula
PPMO formula
Date of IPC Ps Poriginal Pp1 Pp2
Base value 12-Ma
r
-17 1.0000 1.0000 1.0000 1.0000
IPC 1 8-May-18 1.0537 1.0835 1.0939 1.0892
IPC 2 30-Jun-18 1.0597 1.0941 1.1077 1.1032
IPC 3 1-Jan-19 1.0870 1.1172 1.1270 1.1206
IPC 4 19-Apr-19 1.0938 1.1219 1.1307 1.1221
IPC 5 24-May-19 1.1051 1.1272 1.1371 1.1283
IPC 6 5-Jul-19 1.1157 1.1272 1.1371 1.1283
By the PPMO formula using original coefficients (Lmax, Mmin, Emax) the increment of price adjustment
factorsup to last IPC is 12.72%. PPMO formula using coefficients Lmax, Mmax, Emin (Pp1) has shown
increment of 13.71% from base value, PPMO formula using coefficients Lmin, Mmax, Emax (Pp2) has
shown increment of 12.83%. By using Small Works formula, the increment of price adjustment factor upto
Last IPC is 11.57%.
5.15 Ungrida River Bridge at Sainamaina-9 Baikhutti Devapar in Rupandehi District
Base Date: 7th-May-2017
Original formula used is PPMO formula. PPMO formula is taken as Pp=a+b*(Ln/Lo) +c*(Mn/Mo)
+d*(En/Eo) where Ln, Mn, En are the NRB index of Labor, Material and Equipment respectively taken 30
days before IPC date and Lo, Mo, Eo are the base index of Labor, Material and Equipment respectively.
Apart from this, the coefficient of b, c and d are not known here in this study. The limits have been set by
the project for the value of b, c and d as
A
b
C d
0.15 0.15 to 0.25 0.30 to 0.40 0.20 to 0.30
Original formula “Poriginal” has been calculated using coefficients b=0.20, c=0.40, d=0.25. These
coefficientswere proposed by contractor of this project.PPMO formula has been compared using different
combinations.
Electronic copy available at: https://ssrn.com/abstract=3732323
17
(i) Pp1 has been calculated using coefficients b=0.25, c=0.40, d=0.20 (Lmax, Mmax, Emin)
(ii) Pp2 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
(iii) Pp3 has been calculated using coefficients b=0.25, c=0.30, d=0.30 (Lmax, Mmin, Emax)
PPMO formula has been compared with small works formula.
Table 7: Comparative Price adjustment factor in Construction of Ungrida River Bridge
Small works
formula PPMO formula
Date of IPC Ps Poriginal Pp1 Pp2 Pp3
7-May-17 1.0000 1.0000 1.0000 1.0000 1.0000
IPC 1 25-Mar-18 1.0288 1.0777 1.0786 1.0768 1.0713
IPC 2 2-Jul-18 1.0376 1.0889 1.0912 1.0866 1.0809
IPC 3 19-Dec-18 1.0679 1.1195 1.1222 1.1168 1.1126
IPC 4 18-Jan-19 1.0642 1.1192 1.1220 1.1164 1.1124
IPC 5 10-Mar-19 1.0664 1.1213 1.1251 1.1175 1.1167
IPC 6 24-May-19 1.0819 1.1280 1.1320 1.1240 1.1223
IPC 7 12-Jul-19 1.0922 1.1280 1.1320 1.1240 1.1223
By the PPMO formula using original coefficients the increment of price adjustment factorsup to last IPC is
12.80%. PPMO formula using coefficients Lmax, Mmax, Emin (Pp1) has shown increment of 13.20% from
base value, PPMO formula using coefficients Lmin, Mmax, Emax (Pp2) has shown increment of 12.40%.
and using coefficients Lmax, Mmin, Emax (Pp3) showed increment of 12.23%. By using Small works
formula, the increment of price adjustment factor up to Last IPC is 9.22%.
5.16 Inguriya River Bridge along Sainamaina-11 Palpa Laugha Pani Road in Rupandehi District:
Base Date: 12-March-2017
Original formula used is PPMO formula. PPMO formula is taken as Pp=a+b*(Ln/Lo) +c*(Mn/Mo)
+d*(En/Eo) where Ln, Mn, En are the NRB index of labor, material and equipment respectively taken 30
days before IPC date and Lo, Mo, Eo are the base index of Labor, Material and Equipment respectively.
Apart from this, the coefficient of b, c and d are not known in this study. The limits have been set by the
project for the value of b, c and d as
A B C d
0.15 0.15 to 0.25 0.30 to 0.40 0.20 to 0.30
Original formula “Poriginal” was calculated using coefficients b=0.25, c=0.40, d=0.20 (Lmax, Mmax,
Emin) These coefficients are proposed by contractor of this project. PPMO formula was compared using
different combinations.
(i) Pp1 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
(ii) Pp2 has been calculated using coefficients b=0.25, c=0.30, d=0.30 (Lmax, Mmin, Emax)
PPMO formula has been compared with small works formula.
Table 8: Comparison of Price adjustment factor in Construction of Bridge over Inguriya River
Small works
Formula PPMO formula
Date of IPC Ps Poriginal Pp1 Pp2
Base value 12-Ma
r
-17 1.0000 1.0000 1.0000 1.0000
Electronic copy available at: https://ssrn.com/abstract=3732323
18
IPC 1 18-Dec-17 1.0507 1.0332 1.0359 1.0349
IPC 2 11-May-18 1.0567 1.0970 1.0973 1.0906
IPC 3 11-Jul-18 1.0537 1.0939 1.0892 1.0835
IPC 4 17-Jan-19 1.0597 1.1270 1.1206 1.1172
IPC 5 18-Mar-19 1.0870 1.1331 1.1243 1.1233
IPC 6 13-Jul-19 1.0885 1.1371 1.1283 1.1272
By the PPMO formula using original coefficients Lmax, Mmax, Emin the increment of price adjustment
factorup to last IPC is 13.71%. PPMO formula using coefficients Lmin, Mmax, Emax (Pp1) has shown
increment of 12.83% from base value, PPMO formula using coefficients Lmax, Mmin, Emax (Pp2) has
shown increment of 12.72%. and using coefficients Lmax, Mmin, Emax (Pp3) has shown increment of
12.23%. By using SmallWorks formula, the increment of price adjustment factors upto Last IPC is8.85%.
5.17 Design & Build of Rapti Nadi Bridge, Sisniya:
Base Date: 10-April-2016, Original formula used is PPMO formula as
Pp=a+b*(Ln/Lo)+c*(Mn/Mo)+d*(Fn/Fo) where Ln, Mn are the NRB index of Labor, Material and Fn is
the cost of fuel respectively taken 30 days before IPC date and Lo, Mo are the base index of Labor, Material
and Fo is the base value of Fuel respectively. The coefficient of b, c and d are not known. The limits have
been set by the project for the value of b, c and d as
A B C D
0.15 0.15 to 0.25 0.30 to 0.40 0.20 to 0.30
Original formula “Poriginal” has been calculated using coefficients b=0.25, c=0.40, d=0.20 (Lmax, Mmax,
Emin) These coefficients have been proposed by contractor of this project. PPMO formula has been
compared using different combinations.
(i) Pp1 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Fmax)
(ii) Pp2 has been calculated using coefficients b=0.25, c=0.30, d=0.30 (Lmax, Mmin, Fmax).
PPMO formula has been compared with small works formula.
By the PPMO formula using original coefficients Lmax, Mmax, Fmin the increment of price adjustment
factorsup to last IPC is 21.83%. PPMO formula using coefficients Lmin, Mmax, Emax (Pp1) has shown
increment of 21.66% from base value, PPMO formula using coefficients Lmax, Mmin, Emax (Pp2) has
shown increment of 22.57 %. By using Small Works formula, the increment of price adjustment factors up
to Last IPC is 14.22%.
Electronic copy available at: https://ssrn.com/abstract=3732323
19
Fig.9: Comparison of Price adjustment factor at Rapti Nadi Bridge, Sisniya Chainpur Khadbari Road
Project
Base date: 10-May-2011, Original Formula used is Small Works formula as Ps=Ac+Bc*(Lmc/Lmo). Where
Ac=0.15 and Bc=0.85 Lmc is consolidated consumer price index at current IPC and Lmo is consolidated
consumer price index at base date. From NRB economic bulletin the value of Lmo for the base date and
Lmc for 30 days before IPC date has been taken.Small works formula has been compared with PPMO
formula given by Pp=a+b*(Ln/Lo) +c*(Mn/Mo) +d*(En/Eo).
(i) Pp1 has been calculated using coefficients b=0.25, c=0.40, d=0.20 where coefficient of labor is
maximum, material maximum and equipment is minimum. In simpler form combination can be denoted as
Lmax, Mmax, Emin
(ii) Pp2 has been calculated using coefficients b=0.15, c=0.40, d=0.30 (Lmin, Mmax, Emax)
(iii) Pp3 has been calculated using coefficients b=0.25, c=0.30, d=0.30 (Lmax, Mmin, Emax)
By using Small Works formula, the increment of price adjustment factorsup to Last IPC is 31.85%. By the
PPMO formula using coefficients Lmax, Mmax, Emin (Pp1) has shown increment of 25% from base value,
PPMO formula using coefficients Lmin, Mmax, Emax (Pp2) has shown increment of 19.8%, PPMO
formula using coefficients Lmax, Mmin, Emax (Pp3) has shown increment of 23.9%.
5.18 Overall Comparison of price adjustment factor:
Table 9: Overall Comparison of percentage increase in price adjustment factor
% increase in price adjustment factor using different
formulas
1.1422
1.2166
1.2257
0.8000
0.8500
0.9000
0.9500
1.0000
1.0500
1.1000
1.1500
1.2000
1.2500
31‐Jan‐16
10‐May‐16
18‐Aug‐16
26‐Nov‐16
06‐Mar‐17
14‐Jun‐17
22‐Sep‐17
31‐Dec‐17
10‐Apr‐18
19‐Jul‐18
27‐Oct‐18
04‐Feb‐19
15‐May‐19
23‐Aug‐19
01‐Dec‐19
ComparisonofP.Afactorusingdifferentformulas
Smallworksformula PPMOformulaPoriginal
Priceadjustmentfactor
Date ofIPC
Electronic copy available at: https://ssrn.com/abstract=3732323
20
Contract Base
date
Date of
last
IPC
taken
for
study
Formul
a used
in
contrac
t
FIDIC
formu
la
Small
works
formu
la
PPMO formula
Lmax,
Mmin,
Emax
Lmin,
Mmax,
Emax
Lmax,
Mmax,
Emin
Nepalgu
nj-
Kohalpur
Road-1
13-
Oct-
12
15-
May-
17
FIDIC 8.90
%
25.40
% 16% 13.40% 15.50%
Nepalgu
nj-
Kohalpur
Road-2
13-
Oct-
12
1-Oct-
15 FIDIC 1.17
%
11.80
% 10.10% 8.00% 9.20%
Bhairaha
wa-
Lumbini-
Taulihaw
a Road
Projec
22-
Sep-
16
31-Jul-
19 FIDIC 11.36
% 8.80% 16.99% 16.70% 16.18%
Tinau
River
Bridge
5-Jun-
15
28-
Apr-19 FIDIC 21.77
%
14.53
% 18.79% 18.01% 19.95%
Gauri
khola
Bridge
12-
Mar-
17
5-Jul-
19 PPMO - 11.57
% 13.71% 12.83% 12.72
%
Lmid,
Mmax,
Emid
Ungrida
Khola
Bridge
7-
May-
17
12-Jul-
19 PPMO - 9.22% 13.20% 12.40% 12.23% 12.80
%
Inguriya
Khola
Bridge
12-
Mar-
17
13-Jul-
19 PPMO - 8.85% 13.71% 12.83% 12.72%
Rapti
River
Bridge
10-
Apr-
16
9-Jul-
19 PPMO - 14.22
% 21.83% 21.66% 22.57%
Lmid,
Mmid,
Emin
Lmin,
Mid,
Emax
Lmax,
Mmin,
Emin
Lmin,
Mmax,
Emin
Electronic copy available at: https://ssrn.com/abstract=3732323
21
Mid hill
Project
7-Jun-
15
24-
May-
19
PPMO - 14.98
% 17.91% 17.81% 18.62% 17.20
%
Chainpur
-
Khandba
ri Road
Projec
10-
May-
11
1-Sep-
15
Small
works
formul
a
- 31.85
% 25.00% 19.80% 23.90%
From the table 9, It is seen that the contracts whose base date is before 2015, The price adjustment factor
calculated by FIDIC formula is lowest, followed by PPMO formulas and Price adjustment factor obtained
by small works formula is highest. And in the contracts whose base date is after 2015, the price adjustment
factor calculated by FIDIC formula is highest, followed by PPMO formulas and Price adjustment factor
obtained by small works formula is lowest. Thus, it cannot actually be defined which formula gives more
value of price adjustment factor. It depends upon the condition such as time, index and cost.
In PPMO formula if the coefficients are set by the client, the price adjustment factor using coefficients of
labor “Lmax’’is more likely to give higher value of Price Adjustment factor than using “Lmin’’.
6. CONCLUSION:
There are different formulas used in different contracts. In contracts using FIDIC formula, the cost of labor
is increasing with respect to time and it is more predictable that labor cost will increase in future. The cost
of bitumen and fuel are unpredictable as the cost is fluctuating more with respect to time. In contracts using
PPMO formula the index of Labor, Material and Equipment is used. The index of labor increase with time
and it is more predictable than Material and Equipment index as they are fluctuating with respect to time.
Comparing the price adjustment factor using different formulas it can be seen that the value of price
adjustment factor using different formulas are different. Also, it can be seen that during the course of time
the price adjustment factor calculated using different formulas is different.Thus,it cannot be generalized
that which formula could give minimum value of price adjustment. It depends upon the condition such as
time, index and cost. As most of the respondents in our study preferred to use PPMO formula so it is
suggested to use PPMO formula in the construction contracts. In PPMO formula under the limits set by the
client, if the coefficient of labor is chosen maximum it is likely that the price adjustment factor would be
more.
REFERENCES:
[1] Riggs, J., (2006). Material price escalation. Construction briefing.
[2] McCartney, M., (2011). PakistanGrowth, Dependency and crisis. The Lahore Journal of
Economics,16(1), 71-94.
[3] Mishra, A. & Regmi, U., (2017). Effects of Price Fluctuation on the Financial Capacity of "Class A"
Contractors. International Journal of Creative Research Thoughts (IJCRT), 5(4), 1920-1938.
[4] ADB, (2018). Price Adjustment Guidance Note on procurement, s.l.: ADB.
https://www.adb.org/sites/default/files/procurement-price-adjustment.pdf
[5] FIDIC MDB, (2010). Conditions of Contract for Construction, s.l.: Multilateral Development Bank
Harmonised Edition. General conditions.
[6] Public Procurement Act (2007). www.ppmo.gov.np
[7] Highways Term Maintenance Association (HTMA). (2010). Price Adjustment Formulae Indices
(Highways Maintenance) 2010 Series – Guidance Notes. Prepared in association with the Civil
Electronic copy available at: https://ssrn.com/abstract=3732323
22
Engineering Contractors' Association and Building Cost Information Service.
www.mhaweb.org.uk/htm_indices_final_guidance_notes.doc. Accessed 26 May 2020.
[8] Hiyassat, M. (2000). Construction Bid Price Evaluation. Canadian Journal of Civil Engineering, 28(2),
264-270.
[9] Jennings, G. H. E. (1996). Prequalification and Multicriteria Selection-A measure of Contractor's
Opinions. Journal of Construction Engineering Management and Economics, 16(6), 651-660.
[10] Banki, M. T., Esmaeeli, B., & Ravanshadnia, M. (2009). The Assessment of Bidding Strategy of
Iranian construction firm. International Journal of Management Science and Engineering
Management, 4(6), 153-160.
[11] Mossa, M. G. (2013). Assessment of Price Escalation and Adjustment Problems on Federal Road
Construction Projects. 1st ed. Ethopia: s.n.
[12] MOF (2018). Economic Survey, s.l.: s.n.www.mof.gov.np
*********
Electronic copy available at: https://ssrn.com/abstract=3732323
Book
Full-text available
One of the recent research projects I had an opportunity to participate in required me to envision what AI will look like in the next 10 years. It was an interesting activity that gave me a chance to stretch my thinking, but ultimately like all of those predictions about jobs and robots it was no more than an educated guess. What I do know is that today, there are some great opportunities to leverage technology, and some of those technologies have AI within them, extending their capabilities beyond what we’ve seen historically. Every facet of our personal lives is being impacted by these ever-evolving systems and tools, including economically and socially. Work is such a big part of life for the people that companies employ, and if there’s an opportunity to use technology to make that work experience more human to some degree, we should absolutely take it. The book has widely covered employee engagement and E-HRM also in depth. Investing in employee engagement is not merely an HR initiative; it is a strategic imperative for organizations aiming for sustainable growth and success.
Article
Full-text available
Variation orders are common in civil engineering construction projects and serve as significant measurement tools for project efficiency and success. This study focuses on identifying the causes and impacts of variation orders in building projects. Three hotel buildings under construction in Bharatpur were considered for the study. The study population included the client, consultant, and contractor, as they are the major stakeholders in any construction project. Data were collected using a five-point Likert scale and analyzed using the Relative Importance Index (RII) to rank the causes and impacts of variation orders. The study also identified strategies to minimize variation orders. Based on the overall ranking using the RII index, the top three causes of variation orders in building projects at Bharatpur were found to be: Errors and omissions in design (RII = 0.953),Variations in the scope of work by additions, omissions, and alterations of the employer's requirements (RII = 0.937) and Change in design and drawings by the consultant (RII = 0.905) Regarding the impacts of variation orders, the top three identified impacts were: Completion schedule delay, Increase in project cost, Affect on progress. All parties strongly agreed on the ranking of these impacts, as supported by a Kendall's coefficient of concordance value of 0.973. Strategies to minimize variation orders: Fourteen major strategies were identified and analyzed to minimize variation orders. The top three measures, ranked based on overall RII analysis (Kendall's coefficient of 0.812), were: Complete the drawings at the tendering stage (RII = 0.942), All involved parties should plan adequately before works start on-site (RII = 0.937) and Carry out detailed site investigation, including soil investigations, and consider them during the tendering stage (RII = 0.895)
Book
Full-text available
The performance of development projects of a nation largely depends upon construction contract administration operation adopted in the country. Among all projects of the nation , construction seems to be given high priority in developing country. The proposed research based reference book aims to analyse the operation of projects in Nepal with special focus of Infrastructure Construction projects performance. The management aspects for assuring effective Contract Administration in the area of Project Operation under the analysis of the report is assured. Primary and Secondary data followed by literature review helps to get the objective of the research based on collection of published journal articles. On the basis of projects avaibility and issue of the selected project phase , Philosophy and Design of research decided to be applied for further methodological aspects in ex-post facto condition to get solution and new knowledge in the respective Contract Administration of project management. This study reveals the Contract Administration of Projects . The study has covered several aspects under 6 broad sections such as performance, Contract Administration, Planning and Designing, Hazards and Risk, Material Management followed by Features of Sales, Aids and Returns. It is second session of the book, deals with Contract Administration related issues under operation in Project Management of Nepal. This section contains altogether 9 Articles out of which 5 chapters as first Author 2 as single Author and 2 as second Author by the first author of the book. The study signify the policy makers, professionals, officers, engineers, supervisors, workers and other related agencies for the running project and upcoming project's operational problems of construction projects in new way for assuring effective contract administration.
Article
Full-text available
This paper assesses the patterns and trends of price fluctuations and price adjustment practices in RCC T-beam and pre-stressed bridge construction contracts. Using a questionnaire survey, we conducted a descriptive research to document the existing practices. The perceptions of clients and contractors were measured using mean score and standard deviation on issue, followed by a consistency check. We then analysed the major components of price adjustments to identify trends. Price adjustment provisions are planned during the procurement planning and bid preparation stages of procurement cycle, and are used as necessary during the contract implementation stage. These provisions are meant to give protection to the contractor against price escalation. In the absence of any compensation provision in bridge construction contracts, price fluctuation can affect the time, cost and quality parameters of construction projects. This may lead to delays or cancellation of projects, reduced number of bidders, poor quality, problems with cash flow, and loss of interest of stakeholders in the project. The research draws attention to the serious issues of price adjustments among bridge projects to ensure constructability. This is the first attempt to address the issue in bridge contracts of Nepal and can serve as a starting point for further research on this topic.
Article
This paper assesses the patterns and trends of price fluctuations and price adjustment practices in RCC T-beam and prestressed bridge construction contracts. Using a questionnaire survey, we conducted a descriptive research to document the existing practices. The perceptions of clients and contractors were measured using mean score and standard deviation on issue, followed by a consistency check. We then analysed the major components of price adjustments to identify trends. Price adjustment provisions are planned during the procurement planning and bid preparation stages of procurement cycle, and are used as necessary during the contract implementation stage. These provisions are meant to give protection to the contractor against price escalation. In the absence of any compensation provision in bridge construction contracts, price fluctuation can affect the time, cost and quality parameters of construction projects. This may lead to delays or cancellation of projects, reduced number of bidders, poor quality, problems with cash flow, and loss of interest of stakeholders in the project. The research draws attention to the serious issues of price adjustments among bridge projects to ensure constructability. This is the first attempt to address the issue in bridge contracts of Nepal and can serve as a starting point for further research on this topic
Article
Full-text available
The main objective of this study is to identify the origin and causes of variation orders and their impacts in project cost and completion time for developing preventing measures which can be beneficial in upcoming similar projects. The study is conducted in project inside the Tribhuvan University premises, Kathmandu. The primary data were collected from the questionnaire survey and field study. A questionnaire survey was conducted with construction team who are related to the project. For the case study of the project, contract documents were obtained from the related offices which were thoroughly studied to obtain the project related findings about variation orders relating to project cost and completion time. Five ranking linkert scale have been used for ranking the perception based relative importance index of respondents about causes of variation orders. Existence of variation orders inside Tribhuvan University premises, Kathmandu has been noted from the study. 9.85%, 5.99%, 10.37%, 12.32% and 21.02% cost above the contract amount has been incurred at the completion of the projects respectively. Similarly, 26.67%, 83.33%, 12.5%, 20% and 25% time for the successive contract has been increased by the extension of the contract completion time. From the study, main causes of variation orders are known to be change of plan, change of scope, defect of bill of quantities, lack of specified and appropriate competent construction manager and impediment in prompt decision making. Similarly, causes of variation orders impacting project cost are additional work, client financial problems/ delay in payment of bill and change in design. Causes of variation orders impacting project time are change in design, delay in payment and dispute between parties to the contract. The control measures for the variation orders are appointment of project manager to supervise design, preparation of bill of quantities with good estimate and adequate financial planning. The findings of this study will be beneficial for developers, designers and contractors in building projects and also to the Governmental authorities to develop preventing measures to eliminate or reduce variation orders.
Article
Full-text available
The construction industry is facing problem of price fluctuation in all of its inputs. This major problem is spread all over the country and Nepalese contractors are critically affected. The general objective of the research is to investigate the effect of price fluctuation for improving the financial capacity of Nepalese contractors to enhance the performance of the industry. Questionnaire, scheduled and case studies ware used to assess the contractor's perspective. The research result shows that the problem of price fluctuation occurs in an unpredictable manner. At least 27 % price was escalated of the construction inputs. Contractors lose their at least 52 % of the expected profit. Few contractors are planned to address for the future price escalated situation and remaining others are not concerned about the future situation. Price adjustment clause is not favorable for the contractors. The price fluctuation system that is in place is limited to few construction inputs. Moreover, contractors get compensation only for portion of the price increase of inputs. Project delay was found to be one of the major effects of price increase and delay caused by the contractors is affecting them by making them vulnerable to effects of price increase.
Article
Arriving at the final bid price is a critical decision which is mostly done through experience and intuitions. As, many factors affect the final proposed price, no quantified decision processes may lead to irrational low or high proposed prices. Therefore, various attempts have been done to propose systematic models to track and analyze the bidding trends. This paper focuses on the previous trends of the bidding prices to estimate proper bidding cost in the Iranian construction industry The prices might be influenced by external characteristics such as competitors’ policies, the number of tendered projects, the number of contractors competing in the current tender, project characteristics, and the client. The subject of bidding price can be investigated through the client view or the contractor view. This paper attends the second approach. This paper present a quantitative analysis of impact of number of bidders on project bid prices. The study found that increasing the number of bidders will result in decreased project bid prices.
Article
To overcome the disadvantages of the low bid price policy in open competitive contracts, many are advocating the average bid method for bid evaluation. However, as elucidated in this study, this method has some disadvantages. The purpose of this paper is to propose an alternate statistical procedure for bid evaluation. Such procedure applies simplestatistical analysis to identify unrealistically low-priced bids, based on either the t-distribution or the normal distribution of a previously established database of similar bids. In this procedure, the ratio of a contractor's bid to owner cost estimate is used to eliminate the distorting effect of the project size. The unrealistically low-priced contracts are then excluded and the bid with the lowest price among the remaining bids is accepted. The procedure requires establishing a database of previous bids.
Article
Compared to the historical and even contemporary experience of India, Pakistan has long been regarded as a “dependent” economy. Gross domestic product growth in Pakistan is typically argued to be contingent on external factors: trade, financial flows, and the interdependence of asset markets. Beyond the rhetoric, there is only ambiguous and contradictory empirical evidence to support this view. This paper offers a new methodology, that of case studies of growth and stagnation, to test the hypothesis of dependency. The results show that growth in Pakistan is influenced by external factors, but that growth is driven primarily by the dynamics of the domestic economy.
Article
The procurement of a construction contractor normally involves some form of prequalification. The better prequalification regimes adopt a structured multi-criteria approach (i.e. contractor evaluation based on a multiple of factors over and above cost). This research solicits contractors' viewpoints on prequalification, in contrast to earlier works which have tended to present clients' perspectives. Contractors are dissatisfied with the frequency and adequacy of current prequalification regimes. An investigation of the mutual benefits of multi-criteria selection leads to the suggestion that such benefits could be better capitalized upon. Contractors' perceived levels of importance (with respect to selection criteria considered by clients during the selection process) are evaluated and show that, in line with earlier findings, 'cost' is still the predominant selection factor, followed by 'contractor experience' and 'company reputation'. A comparison between contractors' rankings of the selection criteria with similar rankings derived from an earlier survey of clients, finds significant correlation, indicating that contractors agree with clients' importance levels of multi-criteria selection factors.
Material price escalation. Construction briefing
  • J Riggs
Riggs, J., (2006). Material price escalation. Construction briefing.
Price Adjustment Guidance Note on procurement
ADB, (2018). Price Adjustment Guidance Note on procurement, s.l.: ADB. https://www.adb.org/sites/default/files/procurement-price-adjustment.pdf
Conditions of Contract for Construction, s.l.: Multilateral Development Bank Harmonised Edition
  • Fidic Mdb
FIDIC MDB, (2010). Conditions of Contract for Construction, s.l.: Multilateral Development Bank Harmonised Edition. General conditions.
Assessment of Price Escalation and Adjustment Problems on Federal Road Construction Projects
  • M G Mossa
Mossa, M. G. (2013). Assessment of Price Escalation and Adjustment Problems on Federal Road Construction Projects. 1st ed. Ethopia: s.n.
Economic Survey, s.l.: s.n.www.mof.gov.np ********* Electronic copy
  • Mof
MOF (2018). Economic Survey, s.l.: s.n.www.mof.gov.np ********* Electronic copy available at: https://ssrn.com/abstract=3732323