One of the key tasks of an investor and a contractor at the stage of planning and implementing construction works is to measure the progress of execution with regard to the planned deadlines and costs. During the execution of construction works, the actual progress of the works may differ significantly from the initial plan, and it is unlikely that the construction project will be implemented entirely according to the planned work and expenditure schedule. In order to monitor the process of deviations of the deadline and the budget of the investment task, several rudimentary methods of planning—as well as the cyclical control of the progress of construction projects—are used. An effective tool for measuring the utilization of the financial outlays of a construction project is the presentation of the planned financial flows on a timeline using a cumulative cost chart, the representation of which is the S-curve. The purpose of this paper is to analyze the course of an sample construction project comparing the planned costs of the scheduled works with the actual costs of the performed works, as well as identifying the reasons leading to the failure to meet the planned deadlines and budget of the project implementation. As part of the research conducted at a construction site of a hotel facility, the authors of this paper analyzed each of the 20-month effects of financial expenditures on construction works that were developed and processed by the Bank Investment Supervision (BIS) over a period of three years (between 2017 and 2019). Based on these results, charts and tables of the scheduled and actual cumulative costs of the completed construction project were prepared, the careful analysis of which enables interesting conclusions to be drawn.
Content may be subject to copyright.
applied
sciences
Article
The S-Curve as a Tool for Planning and Controlling of
Construction Process—Case Study
Jarosław Konior and Mariusz Szóstak *
Department of Building Engineering, Faculty of Civil Engineering, Wroclaw University of Science and
Technology, 50-370 Wrocław, Poland; jaroslaw.konior@pwr.edu.pl
*Correspondence: mariusz.szostak@pwr.edu.pl; Tel.: +48-71-320-23-69
Received: 12 February 2020; Accepted: 13 March 2020; Published: 19 March 2020


Abstract:
One of the key tasks of an investor and a contractor at the stage of planning and implementing
construction works is to measure the progress of execution with regard to the planned deadlines
and costs. During the execution of construction works, the actual progress of the works may dier
significantly from the initial plan, and it is unlikely that the construction project will be implemented
entirely according to the planned work and expenditure schedule. In order to monitor the process of
deviations of the deadline and the budget of the investment task, several rudimentary methods of
planning—as well as the cyclical control of the progress of construction projects—are used. An eective
tool for measuring the utilization of the financial outlays of a construction project is the presentation
of the planned financial flows on a timeline using a cumulative cost chart, the representation of which
is the S-curve. The purpose of this paper is to analyze the course of an sample construction project
comparing the planned costs of the scheduled works with the actual costs of the performed works,
as well as identifying the reasons leading to the failure to meet the planned deadlines and budget
of the project implementation. As part of the research conducted at a construction site of a hotel
facility, the authors of this paper analyzed each of the 20-month eects of financial expenditures on
construction works that were developed and processed by the Bank Investment Supervision (BIS)
over a period of three years (between 2017 and 2019). Based on these results, charts and tables of
the scheduled and actual cumulative costs of the completed construction project were prepared,
the careful analysis of which enables interesting conclusions to be drawn.
Keywords: construction project management; cost; time; Bank Investment Supervision
1. Introduction
Construction project management is a process that includes a number of operations, activities
and decisions that are closely related to a project being executed and that aim to create new, or to
increase, existing fixed assets in order to achieve utility eects [
1
]. The utility eect of the construction
process may be the construction of a new building, or the renovation or modernization of an
existing building. In each construction process, four basic phases are distinguished according to the
definition of the building object life cycle: the programming/planning phase, the implementation
phase, the operation/use/maintenance phase and the phase of decommissioning or demolition [
2
].
Appropriate planning of the entire construction process is a very important operation that has a direct
impact on whether the investment project implementation is successful [3].
The construction industry is characterized by high complexity of the implemented construction
processes. The execution of construction projects is specific and particularly dicult, because each
implementation is a unique, complex and dynamic process that consists of a number of interrelated
subprocesses in which various participants of the investment process are involved [4].
Appl. Sci. 2020,10, 2071; doi:10.3390/app10062071 www.mdpi.com/journal/applsci
Appl. Sci. 2020,10, 2071 2 of 14
Each construction project is exposed to various types of risk [
5
]. The most common risks
associated with the implementation of construction projects include, among others, time risk, cost risk,
work quality risk, construction risk and technological risk [
6
]. The construction risks that occur during
the execution of works can be classified into five categories: people and their safety, budget, cost,
schedule, planning/quality and eciency [7].
During the implementation of construction projects, a common phenomenon is that the planned
budget is exceeded and/or the planned implementation deadlines are not met. This phenomenon
occurs in all countries [
8
,
9
]. Deviations from the plan may arise as a result of changing weather
conditions; changes in the volume of available means of production; untimely deliveries of materials,
machinery and equipment; unprofessional project management; mediocre discipline and organization
of work; delays in making decisions; incorrect decisions; and so on [10].
An important element of appropriately managing the investment process is the thoughtful
planning of construction project costs and the eective control of the progress of works in the area of
incurred investment costs during project implementation. When planning the costs of a construction
project, the cost of construction works must always be correctly determined, and both the direct costs
related to the implementation of works and the indirect costs (i.e., overheads and profit) should be
taken into account [
11
]. Unfortunately, exceeding the planned budget and/or time is a very common
attribute of construction projects, and it is unlikely that a construction investment will be carried out
completely in accordance with the planned work and expenditure schedule [12].
Therefore, it is important to plan the entire investment process, in particular, by developing a
correct Investor’s work and expenditure schedule with specific dates for starting and completing the
project, with appropriate connections between planned tasks, and also with an outline of the specific
duration of the individual tasks and the costs of their implementation. However, it should be borne in
mind that during the implementation of a construction project, the actual progress of works may dier
significantly from the initial plan, and it is therefore also necessary to specify the principles of control
and monitoring for the construction project. Only a properly developed work plan, which includes
optimal working sequences and perfect timing for executing each individual activity, can enhance the
work eciency and enable contractors to fulfill the contract at the lowest cost [13].
An eective tool for measuring the utilization of the financial outlays of a construction project
is the presentation of the planned financial flows on a timeline using a cumulative cost chart,
the representation
of which is the S-curve. The S-curve shows the progress of the investment project
from the beginning of the construction works through to their completion. The cumulative cost chart
for construction projects takes the shape of the letter “S”, hence the name of the curve. The variable
slope of the cost curve indicates the changing progress of works per unit of time [14].
The S-curve is flatter at the beginning and end of the execution of a construction project,
and steeper
in the middle. This is due to the fact that a traditional construction project starts quite slowly. At the
beginning of the construction process, human resources are organized, construction site development is
prepared and simple preparatory works are carried out. After some time, the implementation of work
begins to accelerate. Works are carried out on several working fronts using various working teams.
Contractors start to undertake more and more tasks simultaneously. The mutual implementation
of parallel tasks generates a much greater increase in costs when compared to the initial stage of
implementation [15].
As a result of the continuing research, the classic S-curve method is being expanded and constantly
modified in the following ways: through the use of the least square method and fuzzy S-curve
regression model [
16
,
17
], the use of a polynomial function to generalize the S-curve [
18
], the use of
methods of artificial intelligence [
19
], the use of an S-curve Bayesian model [
20
] or by dividing the entire
duration of a construction project into three periods for the improved accuracy of cost forecasting [
21
]).
The second large group of methods that are used for controlling and monitoring the progress
of the construction project implementation is earned value management. Earned value management
involves the control of the investment task through the cyclical comparison of the actually executed
Appl. Sci. 2020,10, 2071 3 of 14
scope of work with the planned time and cost of implementation [
22
]. Project management that uses
earned value management is a well-known management system that integrates schedule, costs and
technical performance [
23
,
24
]. Earned value management allows cost and schedule deviations as
well as performance indicators, project cost forecasts and schedule durations to be calculated [
25
,
26
].
In literature, there are many studies that present the eective application of earned value management
in real-life construction projects [2730].
Classic earned value management is being expanded and modified by way of, among others,
the introduction of a hybrid methodology based on work packages and logical time analysis [
31
],
the introduction of new parameters (e.g., the Schedule Forecast Indicator (SFI) [
32
]) or by taking into
account of the impact of unplanned time and cost deviations on the financial liquidity of a construction
project [33].
The purpose of this article is to analyze the course of an sample construction project by comparing
the planned costs of the scheduled work with the actual costs of the performed work, and to identify
reasons leading to failures to meet planned deadlines and the budget of the project’s implementation.
The goals of the paper are to demonstrate the reasons for construction project cost overruns and
time delays using a representative case study. Both factors are strongly based on the Earned Value
Method (EVM) approach, using an indicated project budget breakdown and timeline deviations.
In this particular case study the poorly managed project was carried out and the cost spent exceeded
the expected and planned figures by over 50%, which is not uncommon in the Polish investment
process nowadays.
2. Research and Methodology of Measurements
The following documents were analyzed as part of the research conducted: (1) the basic
Investor’s work and expenditure schedule of the construction project, which was developed before the
commencement of works; and (2) a set of information about the actual progress of the construction
process, contained and updated in the monthly reports of the Bank Investment Supervision (BIS) [
34
].
The Investor’s work and expenditure schedule is a document that shows the planned progress of
the project over time, taking into account the planned costs. It was developed at the planning stage of
the construction project.
Information on the actual progress of the construction process was collected as part of the BIS
services during the authors’ own research at the construction site of a hotel facility [
34
]. For non-public
investment tasks that are co-financed by two entities—the Investor and the Bank—a third independent
entity was appointed: the Banking Supervision Inspector, who performed a monitoring and auditing
function. The BIS’s tasks included, among others: preliminary reporting (e.g., verification of
documentation about a construction project such as permits, administrative decisions, the planned
budget, contracts concluded by an Investor, etc.), monthly reporting (e.g., constant monitoring of the
project execution, control of the state of the project implementation, settlement verification, analysis
of loan tranche disbursement conditions, etc.), and final reporting (i.e., final financial analysis of the
project implementation) [35].
In the implementation phase, the Bank Investment Supervision develops documents that enable the
mapping and presentation of the actual progress of the construction process. From the monthly reports
developed by the BIS, information about, among others, the progress of works carried out in individual
implementation periods, the values of works carried out in individual implementation periods and the
values of works carried out cumulatively since the beginning of the works were obtained.
As a result of the performed documentation analysis, a collective data summary was prepared.
It was presented in a two-dimensional table where each subsequent row of the table contained data
on subsequent periods of the construction works. The table distinguished the following information
about the project [33,36]:
the budgeted cost of work scheduled (
BCWS
) determined for each individual examined period
on the basis of the Investor’s work and expenditure schedule;
Appl. Sci. 2020,10, 2071 4 of 14
the cumulative value of the budgeted cost of work scheduled (
CBCWS
) for each single examined
period, calculated as the cumulative value obtained by adding the value of the budgeted cost of
work scheduled from the analyzed period to the value of budgeted cost of work scheduled from
the preceding period, determined on the basis of the Investor’s work and expenditure schedule;
the actual cost of work performed
(ACWP
) determined for each individual examined period on
the basis of BIS reports;
the cumulative value of the actual cost of work performed
(CACWP
) for each examined individual
period, calculated as a cumulative value obtained by adding the value of the actual cost of work
performed from the analyzed period, based on BIS reports, to the value of the actual costs of the
work performed from the preceding period;
the actual percentage advancement of work performed
(AC
), calculated as a ratio of the value of
the cumulative actual cost of work performed to the total actual cost of the construction project;
the planned percentage advancement of work scheduled
(PP)
, calculated as the ratio of the
cumulative value of the budgeted cost of work scheduled to the total budgeted cost of the
construction project;
the actual percentage advancement of work scheduled
(AP
), calculated as the ratio of the value of
the cumulative actual cost of work performed to the total budgeted cost of the construction project;
the actual schedule variance
(ASV
), calculated as the dierence between the actual duration and
the planned duration of the project;
the actual schedule performance indicator
(IASV
), calculated as the ratio of the actual duration of
the construction project to the planned duration of the project;
the at-completion variance
(ACV
), calculated as the dierence between the total actual cost of the
construction project and the total budgeted cost of the construction project;
the performance indicator of the at-completion variance
(IACV
), calculated as the ratio of the total
actual cost of the construction project to the total budgeted cost of the construction project.
3. Case Study
The subject of the analyzed project is the execution of a hotel with an underground garage (one
underground floor), as well as the execution of elements of land development around it. The hotel was
located in a Polish city. The erected building, on the ground floor, had a reception, daytime area, oces
and hotel administration, and also a catering area with a restaurant and kitchen facilities. On floor +1,
there were oce rooms, meeting rooms, conference rooms and sanitary facilities with toilets. On the
levels +2 to +7 there were 200 hotel rooms. The floor space of the building was approximately 8200 m
2
.
The project was carried out according to the general contracting system. The subject of the
contract was an experienced construction company concerned the execution of the “shell & core” state.
This consisted of the implementation of a comprehensive investment project involving the construction
of a hotel with a garage, the execution of land development and the commissioning of the project after
obtaining an occupancy permit. It should be emphasized that the original contract with the General
Contractor did not take into account the finishing of the rooms, and therefore the scope of works in the
finishing part did not include the finishing and equipping of hotel rooms with bathrooms and annexes.
The scope of the commissioned works included the finishing of common parts (e.g., kitchen,
restaurants and catering equipment) without providing the technology as described in the tender
design. In addition to the contract, the equipping of the sanitary facilities, oces, facilities, reception,
fitness area, toilets and technical rooms was required, as well as the provision of the premises’ mobile
equipment. The deadline for the implementation of the subject of the contract was scheduled from
September 2016 to June 2018. A flat-rate remuneration of PLN 36,111,146.13 net +VAT was set for
performing the subject of the contract. Figure 1presents the Investor’s work and expenditure schedule
of the project, including the planned amounts of construction works to be executed.
Appl. Sci. 2020,10, 2071 5 of 14
1
1
Figure 1. Investor’s work and expenditure schedule of the analyzed hotel facility (own elaboration).
The five most important elements of the execution process of the analyzed hotel facility are
described below in the chronological order:
August 2017: The Investor, aiming at a more ecient management of the construction project,
signed an annex extending the scope of works of the General Contractor. It included specialist
works concerning Leadership in Energy and Environmental Design (LEED) certification, additional
fire protection and the execution of power and teletechnical installations in hotel rooms. The value
of remuneration increased by 13.0% when compared to the Investor’s schedule and reached the
level of PLN 40,815,455.00 net.
December 2017: The General Contractor presented, in consultation with the Investor, an updated
work schedule that included subsequent annexes regarding changes in the facility, covering door
joinery, automation and the building façade, among others. It should be emphasized that the
subsequent annexes to the Agreement introduced new elements to its basic scope that were
originally excluded from the scope of the General Contractor. Increasing the scope of the subject of
the contract concerned the finishing of the premises, including the installation of shower trays and
frames in hotel bathrooms. The value of remuneration in December 2017 increased by 17.2% when
compared to the Investor’s schedule and reached the level of PLN 42,313,695.00 net. The deadline
did not change (curve No. 2 in Figure 2).
March 2018: The Investor decided to increase the hotel standard (to four stars), which forced
the introduction of changes resulting from the dierence between the detailed design and the
tender design. The changes concerned, among others, sanitary installations, ventilation, electrical
installations of rooms, automation and wall arrangement. As a consequence, the value of
remuneration increased by 20.8% when compared with the Investor’s schedule, and reached the
level of PLN 43,635,084.50 net. The annex to the contract extended the duration of the execution
until October 2018 (curve No. 3 in Figure 2).
June 2018: Another annex significantly modified the basic scope of the contract with the General
Contractor (as of September 2017). The Investor commissioned the General Contractor an
additional scope of works and, in particular, installations of the residence and public areas
Appl. Sci. 2020,10, 2071 6 of 14
(including the hall), catering and multifunctional rooms, and the execution of finishing works
involving the equipping of the hotel rooms. The value of remuneration increased by 48.1%
when compared to the Investor’s schedule and reached the level of PLN 53,473,979.01 net.
The implementation time was extended until January 2019 (curve No. 4 in Figure 2).
July 2018: Due to the increasing scope of work entrusted to the General Contractor and the
extension of the deadline, it was necessary to agree and sign oanother annex. Therefore,
the value
of remuneration increased by 59.4% when compared to the Investor’s schedule and
reached the level of PLN 57,564,756.03 net without the end date changing (curve No. 5 in Figure 2),
although in October 2018 the investment completion date was extended to February 2019 (curve
No. 6 in Figure 2).
June 2019: final completion of the investment task (i.e., 12 months later than originally planned
(June 2018)). The value of remuneration increased by 62.4% and reached the final value of PLN
58,646, 84.75 net (curve No. 7 in Figure 2).
1
1
Figure 2. Planned and actual cumulative costs of the completed hotel facility (own elaboration).
Table 1summarizes the collected data concerning the completed construction project.
Appl. Sci. 2020,10, 2071 7 of 14
Table 1. Results of measurements and cost analyses of the assessed hotel facility (own elaboration).
No. Period
The Budgeted Cost of
Work Scheduled
According to the Work
and Expenditure Schedule
The Cumulative
Value of the
Budgeted Cost of
Work Scheduled
The Actual
Cost of Work
Performed
The Cumulative
Value of the Actual
Cost of Work
Performed
The Actual
Percentage
Advancement of
Work Performed
The Planned
Percentage
Advancement of
Work Scheduled
The Actual
Percentage
Advancement of
Work Scheduled
BCWS CBCWS ACWP CACWP AC PP AP
(1) (2) (3) (4) (5) (6) (7) (8) (9)
[–] [–] [PLN] [PLN] [PLN] [PLN] [%] [%] [%]
1 Sep.16 743,145.00 743,145.00 743,145.00 743,145.00 1.27 2.06 2.06
2 Oct.16 1,342,960.76 2,086,105.76 1,342,960.76 2,086,105.76 3.56 5.78 5.78
3 Nov.16 1,962,497.14 4,048,602.90 1,962,497.14 4,048,602.90 6.90 11.21 11.21
4 Dec.16 1,786,729.02 5,835,331.92 1,786,729.02 5,835,331.92 9.95 16.16 16.16
5 Jan.17 890,075.82 6,725,407.74 890,075.82 6,725,407.74 11.47 18.62 18.62
6 Feb.17 1,024,911.29 7,750,319.03 1,024,911.28 7,750,319.02 13.22 21.46 21.46
7 Mar.17 1,124,204.85 8,874,523.88 1,124,204.85 8,874,523.87 15.13 24.58 24.58
8 Apr.17 899,863.73 9,774,387.61 899,863.73 9,774,387.60 16.67 27.07 27.07
9 May 17 860,000.82 10,634,388.43 860,000.82 10,634,388.42 18.13 29.45 29.45
10 Jun.17 537,721.00 11,172,109.43 537,721.00 11,172,109.42 19.05 30.94 30.94
11 Jul.17 293,524.63 11,465,634.06 293,524.63 11,465,634.05 19.55 31.75 31.75
12 Aug.17 1,064,465.00 12,530,099.06 1,072,251.29 12,537,885.34 21.38 34.70 34.72
13 Sep.17 1,236,413.52 13,766,512.58 614,825.93 13,152,711.27 22.43 38.12 36.42
14 Oct.17 1,998,683.50 15,765,196.08 1,509,792.56 14,662,503.83 25.00 43.66 40.60
15 Nov.17 2,195,751.00 17,960,947.08 2,231,802.48 16,894,306.31 28.81 49.74 46.78
Appl. Sci. 2020,10, 2071 8 of 14
Table 1. Cont.
No. Period
The Budgeted Cost of
Work Scheduled
According to the Work
and Expenditure Schedule
The Cumulative
Value of the
Budgeted Cost of
Work Scheduled
The Actual
Cost of Work
Performed
The Cumulative
Value of the Actual
Cost of Work
Performed
The Actual
Percentage
Advancement of
Work Performed
The Planned
Percentage
Advancement of
Work Scheduled
The Actual
Percentage
Advancement of
Work Scheduled
BCWS CBCWS ACWP CACWP AC PP AP
16 Dec.17 2,925,234.00 20,886,181.08 2,559,405.11 19,453,711.42 33.17 57.84 53.87
17 Jan.18 3,816,618.00 24,702,799.08 2,644,027.80 22,097,739.22 37.68 68.41 61.19
18 Feb.18 3,825,234.00 28,528,033.08 2,202,625.30 24,300,364.52 41.44 79.00 67.29
19 Mar.18 3,540,993.30 32,069,026.38 2,905,521.47 27,205,885.99 46.39 88.81 75.34
20 Apr.18 2,408,845.75 34,477,872.13 1,947,719.29 29,153,605.28 49.71 95.48 80.73
21 May.18 1,358,443.00 35,836,315.13 1,488,799.77 30,642,405.05 52.25 99.24 84.86
22 Jun.18 274,831.00 36,111,146.13 1,191,291.00 31,833,696.05 54.28 100.00 88.15
23 Jul.18 0.00 36,111,146.13 1,622,583.04 33,456,279.09 57.05 100.00 92.65
24 Aug.18 0.00 36,111,146.13 2,415,758.53 35,872,037.62 61.17 100.00 99.34
25 Sep.18 0.00 36,111,146.13 4,252,403.78 40,124,441.40 68.42 100.00 111.11
26 Oct.18 0.00 36,111,146.13 4,722,806.07 44,847,247.47 76.47 100.00 124.19
27 Nov.18 0.00 36,111,146.13 4,470,580.10 49,317,827.57 84.09 100.00 136.57
28 Dec.18 0.00 36,111,146.13 3,013,286.20 52,331,113.77 89.23 100.00 144.92
29 Jan.19 0.00 36,111,146.13 2,226,044.30 54,557,158.07 93.03 100.00 151.08
30 Feb.19 0.00 36,111,146.13 0.00 54,557,158.07 93.03 100.00 151.08
31 Mar.19 0.00 36,111,146.13 2,014,670.58 56,571,828.65 96.46 100.00 156.66
32 Apr.19 0.00 36,111,146.13 0.00 56,571,828.65 96.46 100.00 156.66
33 May.19 0.00 36,111,146.13 0.00 56,571,828.65 96.46 100.00 156.66
34 Jun.19 0.00 36,111,146.13 2,074,556.10 58,646,384.75 100.00 100.00 162.41
Appl. Sci. 2020,10, 2071 9 of 14
Each subsequent annex to the principal contract (as of September 2016) forced the General
Contractor to develop an updated work and expenditure schedule. The updated schedule that was
used for the implementation of works modified the actual progress of the work performed. Figure 3
shows the variable work progress that resulted from several work and expenditure schedule updates.
2
Figure 3.
Variability in the progress of construction works as a result of updating the work and
expenditure schedule of the hotel facility (own elaboration).
Table 2summarizes information about individual changes in the remuneration and the completion
date of the implemented task.
Table 2. Results of measurements and cost analyses of the assessed hotel facility (own elaboration).
Work and Expenditure
Schedule Duration
Cost of
Construction
Works
Deviation
from
Schedule
Deviation
from
Budget
Schedule
Performance
Indicator
Cost
Performance
Indicator
ASV ACV IASV IACV
(1) (2) (3) (4) (5) (6) (7)
[–] [months] [PLN] [months] [PLN] [–] [–]
Original cost of
construction works 22 36,111,146.13 - - - -
Cost of construction
works in Dec. 2017 22 42,313,695.00 0 6,202,548.87 1.000 1.172
Cost of construction
works in Mar. 2018 26 4, 635,084.50 4 7,523,938.37 1.182 1.208
Cost of construction
works in Jun. 2018 29 53,473,979.01 7
17,362,832.88
1.318 1.481
Cost of construction
works in Jul. 2018 29 57,564,756.03 7
21,453,609.90
1.318 1.594
Cost of construction
works in Nov. 2018 30 57,564,756.03 8
21,453,609.90
1.364 1.594
Final cost of
construction works 34 58,646,384.75 12
22,535,238.62
1.545 1.624
Appl. Sci. 2020,10, 2071 10 of 14
4. Results of the Case Study
The hotel facility was completed in June 2019 after 34 months of work. The final cost of the
construction works amounted to PLN 58,646,000 and therefore was higher by PLN 22,535,000 from the
figure originally assumed (as of September 2016). It should also be noted that the actual date of the
commissioning and commencement of operation of the hotel was 12 months later than the planned
date, resulting in additional financial losses for the Investor.
Analysis of the actual progress of works clearly indicates how much the actual state of
implementation of the project diered from that originally assumed. The original budget of the
investment task was underestimated. The changes that occurred during the implementation of the
project resulted in failure to meet the parameters assumed by the Investor in mid-2016 (i.e., the time
and cost of implementing the project).
The following reasons led to the failure of meeting the planned deadlines and implementation
costs:
A lack of appropriate preparation for the construction project in the investment planning phase.
The Investor planned the cost of implementing the construction project based on prices that were
valid in 2016 and did not take into account increases in prices during the subsequent periods of
implementation, or the financial fluctuations over time determined by discounted techniques.
The Investor’s lack of experience in implementing similar construction projects. The Investor had
carried out in the past several smaller projects, but not from the hotel sector.
Changes in the originally adopted standard of the hotel. The Investor incorrectly analyzed the
market demand for hotel buildings and initially adopted a lower standard for the facility than
required at this location.
Changes in the scope of work of the General Contractor. Subsequent scopes of work required the
General Contractor to develop additional cost estimates and oers, and this took up additional
time. In turn, the increase in the scope of works resulted in a significant increase in employment
at the construction site, especially with regard to specialized subcontractors. The extension of the
implementation time caused an increase in the indirect costs of the General Contractor.
The current situation of the market imbalance in the construction industry. In the analyzed
project period between 2017 and 2019 there were major problems concerning contracting and
subcontracting companies at the initially assumed cost level.
The case study of the analyzed hotel facility enabled the following conclusions to be made
regarding the measurement of deviations in the deadlines and budget of the investment task:
the investment task was completed 12 months later than originally planned;
the schedule performance eciency indicator was equal to 1.545, and therefore the project was
longer than planned by 54.5%;
the final cost of the construction works increased by PLN 22,535,338.62 net when compared to the
original cost;
the cost performance eciency indicator was equal to 1.624, and therefore the project was more
expensive than planned by 62.4%;
analysis of the progress of the hotel facility execution indicates a growing trend of the schedule
and cost performance eciency indicator.
5. Discussion
S-curve provides the basis for monitoring cash flows while planning any construction project.
Unfortunately, there is very little likelihood that a project will proceed completely as planned. Small
deviations between the plan and the reality can be seen as being within the limits of the norm and
usually do not interfere with the purpose. However, greater dierences can hinder the goal and require
Appl. Sci. 2020,10, 2071 11 of 14
a revision to ensure that project objectives are achieved [
12
]. The problems of overruns of a planned
project budget or rescheduled deadlines are widely recognized in many countries [8,9,37,38].
The simplest scheduling methods utilizing the S-curve are assumed to be deterministic, and do
not take into account possible risks and uncertainties. However, there are methods that take into
account the use of stochastic curves in probabilistic monitoring and project prediction as an alternative
to deterministic curves and traditional forecasting methods. For the generation of stochastic cost
curves, a simulation method was adopted based on defining the variability of the duration and the
costs of individual activities in the project [
39
]. The study also used a stochastic model approach to
financial management, taking into account the uncertainty of duration and costs at dierent stages
during the project lifecycle [
40
]. Eective project management requires a reliable knowledge of cash
flows at dierent stages of the project lifecycle. Obtaining this knowledge largely depends on taking
into account the precarious environmental conditions of the project, which can be obtained using the
method of assessing cash flow based on the project schedule [
41
]. Uncertainty and imprecision in
project planning have been included in cash flow calculation methodologies for projects involving
fuzzy activities and/or costs. Cash flow can be represented by the cost area S (as opposed to traditional
S-curves) obtained from a combination of cost curves at dierent risk capability levels. Unfortunately,
according to the authors, the proposed concept of the cost area S, in addition to the need to collect a lot
of data, also requires the use of advanced software [42].
In the presented case analysis there were continuous time and cost deviations due to poor project
management and a lack of application of even the simplest model for monitoring the S-curve. (i.e.,
using the models indicated in this discussion).
The entire analysis of research conducted by the authors of the paper leads to the main conclusion
that the models proposed earlier by various researches of the forecasted S-curve as a rule are not
exactly in line with a real state. Some works are too general and too descriptive [
15
,
23
]. There are
also presented models and methods that are too complicated and thus not very practical or easy to
adopt in planning and managing construction projects [
3
,
11
,
19
,
40
]. In some research, the models
seems to be reasonable, however they have not been tested and verified during construction process
monitoring [
9
,
15
,
41
]. To make things worse, it is hard to find reliable, proven research data based on
solid measures of actually executed construction projects where technical inspections were conducted
on construction sites and what was planned, paid and earned was reviewed. Some of the published
papers that are accessible have relied on questionnaires, analyses of past documents and assumptions
rather than facts [
38
,
39
]. However, there are still some strong construction-based papers that present
a case study of the application of the S-curve regression method to project control of construction
management [17].
One of the authors of the paper represents a strong continuity and solid experience collected
from more than 30 years of engineering and construction [
7
,
35
]. The main value of the described
construction case study is a detailed and systematic analysis of the course of the hotel project that
compares the planned costs of the scheduled work with the actual costs of the performed work, as well
as the identification of the reasons leading to the failure to meet the planned deadlines and budget of
the project’s implementation [
34
]. The paper demonstrates the reasons and the eects of construction
project’s cost overruns and time delays using a representative case study. Both factors were strongly
based on the EVM approach, including an indicated project budget breakdown and timeline deviations.
According to the newly published Project Management Institute briefings [
1
], 70% of construction
projects are completed with overruns of cost and time. This statement is rather frightening but credible,
and the presented case study highlights the state-of-the-art.
6. Summary and Conclusions
Appropriate planning of the investment process is a very important operation with a direct impact
on the successful implementation of a construction project via maintenance of the assumed budget
and project completion deadline, while ensuring a consistent quality of on-going construction work.
Appl. Sci. 2020,10, 2071 12 of 14
Correct planning of cash flows is of key importance for Investors and contractors, preferably taking
into account financial fluctuations over time determined by discounted techniques.
Planning of costs also has a significant impact on the financial liquidity of construction companies.
There is therefore a need to develop simple, fast and eective methods that enable cash flows to
be properly planned and controlled. A very helpful tool for planning, monitoring and controlling
construction projects is the S-curve. Knowledge of the planned and actual course of cumulative financial
expenditures over time and the shape of the S-curve and its deviations permits rational actions to be
taken in order to achieve the intended goal and achieve success in construction project implementation.
Cumulative cost S-curves, due to their uniqueness, are unrepeatable. Each construction project
is unique because it is situated in a dierent location and dierent environment; designed and
implemented by dierent work teams; and carried out using various technical, organizational and
technological solutions. Therefore, it is justified to conduct further research into the course of cash
flows and cost planning. The development of a methodology for planning cumulative cost curves in
construction projects will allow the development of eective methods and verified models for better
planning and utilizing financial expenditures during construction works.
Author Contributions:
Conceptualization, J.K. and M.S.; Methodology, J.K. and M.S.; Formal analysis,
M.S.; Resources, J.K. and M.S.; Writing—Original draft preparation, J.K. and M.S.; Supervision, J.K.; Project
administration, M.S.; All authors have read and agreed to the published version of the manuscript.
Funding: This research received no external funding.
Conflicts of Interest: The authors declare no conflict of interest.
References
1.
Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK GUIDE), 6th ed.;
Project Management Institute (PMI): Newtown Square, PA, USA, 2017.
2.
Plebankiewicz, E.; Zima, K. Wieczorek Damian Life cycle cost modelling of buildings with consideration of
the risk. Arch. Civ. Eng. 2016,62, 149–166.
3.
Kern, A.P.; Formoso, C.T. A model for integrating cost management and production planning and control in
construction. J. Financ. Manag. Prop. Constr. 2006,11, 75–90. [CrossRef]
4.
Hoła, B.; Sawicki, M.; Skibniewski, M. An IT model of a Knowledge Map which supports management in
small and medium-sized companies using selected Polish construction enterprises as an example. J. Civ.
Eng. Manag. 2015,21, 1014–1026. [CrossRef]
5.
Kasprowicz, T. Quantitative Identification of Construction Risk. Arch. Civ. Eng.
2017
,63, 63–75. [CrossRef]
6.
Zavadskas, E.K.; Turskis, Z.; Tamošaitien
˙
e, J. Risk assessment of construction projects. J. Civ. Eng. Manag.
2010,16, 33–46. [CrossRef]
7.
Konior, J. Enterprise’s Risk Assessment of Complex Construction Projects. Arch. Civ. Eng.
2015
,61, 63–74.
[CrossRef]
8.
Makesh, S.; Mathivanan, M. Analysis on causes of delay in building construction. Int. J. Innov. Technol.
Explor. Eng. 2019,8, 335–341.
9.
Rachid, Z.; Toufik, B.; Mohammed, B. Causes of schedule delays in construction projects in Algeria. Int. J.
Constr. Manag. 2019,19, 371–381. [CrossRef]
10.
Poło´nski, M. Management of Construction Investment Process; Wydawnictwo SGGW (in Polish): Warszawa,
Poland, 2018.
11.
Le´sniak, A.; Zima, K. Cost Calculation of Construction Projects Including Sustainability Factors Using the
Case Based Reasoning (CBR) Method. Sustainability 2018,10, 1608. [CrossRef]
12.
Al-Jibouri, S.H. Monitoring systems and their eectiveness for project cost control in construction. Int. J. Proj.
Manag. 2003,21, 145–154. [CrossRef]
13.
Lo, W.; Chen, Y.-T. Optimization of Contractor’s S-Curve. In Proceedings of the 24th International Symposium
on Automation & Robotics in Construction (ISARC 2007), 19–21 September 2007; pp. 417–420. Available
online: https://www.irbnet.de/daten/iconda/CIB11259.pdf (accessed on 18 March 2020).
14.
Chao, L.-C.; Chen, H.-T. Predicting project progress via estimation of S-curve’s key geometric feature values.
Autom. Constr. 2015,57, 33–41. [CrossRef]
Appl. Sci. 2020,10, 2071 13 of 14
15. Cristóbal, J.R.S. The S-curve envelope as a tool for monitoring and control of projects. Procedia Comput. Sci.
2017,121, 756–761. [CrossRef]
16.
Hsieh, T.Y.; Wang, M.H.L.; Chen, C.W.; Chen, C.Y.; Yu, S.E.; Yang, H.C.; Chen, T.H. A new viewpoint of
s-curve regression model and its application to construction management. Int. J. Artif. Intell. Tools
2006
,15,
131–142. [CrossRef]
17.
Hsieh, T.-Y.; Hsiao-Lung Wang, M.; Chen, C.-W. A Case Study of S-Curve Regression Method to Project
Control of Construction Management via T-S Fuzzy Model. J. Mar. Sci. Technol. 2004,12, 209–216.
18.
Chao, L.-C.; Chien, C.-F. Estimating Project S-Curves Using Polynomial Function and Neural Networks.
J. Constr. Eng. Manag. 2009,135, 169–177. [CrossRef]
19.
Chao, L.-C.; Chien, C.-F. A Model for Updating Project S-curve by Using Neural Networks and Matching
Progress. Autom. Constr. 2010,19, 84–91. [CrossRef]
20.
Kim, B.C.; Reinschmidt, K. An S-curve Bayesian model for forecasting probability distributions on project
duration and cost at completion. In Proceedings of the CME 25 Conference of Construction Management
and Economics, Reading, UK, 16–18 July 2007; pp. 1449–1459.
21.
Cheng, Y.M.; Yu, C.H.; Wang, H.T. Short-interval dynamic forecasting for actual S-curve in the construction
phase. J. Constr. Eng. Manag. 2011,137, 933–941. [CrossRef]
22.
Chen, H.L.; Chen, W.T.; Lin, Y.L. Earned value project management: Improving the predictive power of
planned value. Int. J. Proj. Manag. 2016,34, 22–29. [CrossRef]
23.
De Marco, A.; Narbaev, T. Earned value-based performance monitoring of facility construction projects.
J. Facil. Manag. 2013,11, 69–80. [CrossRef]
24.
Dziadosz, A.; Kapli ´nski, O.; Rejment, M. Usefulness and fields of the application of the Earned Value
Management in the implementation of construction projects. Bud. Archit. 2014,13, 357–364.
25.
Waris, M.; Khamidi, M.F.; Idrus, A. The Cost Monitoring of Construction Projects through Earned Value
Analysis. J. Constr. Eng. Proj. Manag. 2012,2, 42–45. [CrossRef]
26.
Bhosekar, S.K.; Vyas, G. Cost Controlling Using Earned Value Analysis in Construction Industries. Int. J.
Eng. Innov. Tech. 2012,1, 324–332.
27.
Vandevoorde, S.; Vanhoucke, M. A comparison of dierent project duration forecasting methods using
earned value metrics. Int. J. Proj. Manag. 2006,24, 289–302. [CrossRef]
28.
Kwon, O.; Kim, S.; Paek, J.; Eom, S.-J. Application of Earned Value in the Korean Construction Industry.
J. Asian Archit. Build. Eng. 2008,7, 69–76. [CrossRef]
29.
Khamidi, M.F.; Ali, W.; Idrus, A. Application of Earned Value Management System on an Infrastructure
Project: A Malaysian Case Study. Int. Conf. Manag. Sci. Eng. 2011,8, 1–5.
30.
Poło´nski, M.; Komendarek, P. Earned value method for operational cost control of civil structure. Quantit.
Meth. Econ. 2011,12, 279–290.
31.
Howes, R. Improving the performance of Earned Value Analysis as a construction project management tool.
Eng. Constr. Archit. Manag. 2000,7, 399–411. [CrossRef]
32.
Czemplik, A. Application of earned value method to progress control of construction projects. Procedia Eng.
2014,91, 424–428. [CrossRef]
33.
Przywara, D.; Rak, A. The time-cost analysis of schedule monitoring using the earned value method.
Tech. Trans. 2017,5, 57–66.
34.
Bauer-Celny, A.; Konior, J.; Sz
ó
stak, M. PM Group Polska sp. z o.o. 2006–2015 and 3EPCM sp. z o.o.
2016–2019, “Initial, Monthly, Close-out Reporting of Bank Investment Supervision”.
35.
Konior, J. Monitoring of Construction Projects Feasibility by Bank Investment Supervision Approach. Civ.
Eng. Archit. 2019,7, 31–35. [CrossRef]
36.
Kozie ´n, E. Application of approximation technique to on-line updating of the actual cost curve in the earned
value method. Czas. Tech. 2017,9, 181–195.
37.
Gardezi, S.S.S.; Manarvi, I.A.; Gardezi, S.J.S. Time Extension Factors in Construction Industry of Pakistan.
Procedia Eng. 2014,77, 196–204. [CrossRef]
38.
Gebrehiwet, T.; Luo, H. Analysis of Delay Impact on Construction Project Based on RII and Correlation
Coecient: Empirical Study. Procedia Eng. 2017,196, 366–374. [CrossRef]
39.
Barraza, G.A.; Back, W.E.; Mata, F. Probabilistic Forecasting of Project Performance Using Stochastic S Curves.
J. Constr. Eng. Manag. 2004,130, 25–32. [CrossRef]
Appl. Sci. 2020,10, 2071 14 of 14
40.
Yao, J.-S.; Chen, M.-S.; Lu, H.-F. A fuzzy stochastic single-period model for cash management. Eur. J. Oper.
Res. 2006,170, 72–90. [CrossRef]
41.
Mohagheghi, V.; Meysam Mousavi, S.; Vahdani, B. An Assessment Method for Project Cash Flow under
Interval-Valued Fuzzy Environment. J. Optim. Ind. Eng. 2017,22, 79–80.
42.
Maravas, A.; Pantouvakis, J.-P. Project cash flow analysis in the presence of uncertainty in activity duration
and cost. Int. J. Proj. Manag. 2012,30, 374–384. [CrossRef]
©
2020 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access
article distributed under the terms and conditions of the Creative Commons Attribution
(CC BY) license (http://creativecommons.org/licenses/by/4.0/).
... The execution of a construction object within the assumed budget and schedule, while at the same time ensuring the quality standard, is a key factor that determines the success of a construction project [1]. This requires the appropriate planning and effective monitoring of each parameter at the successive stages of an investment task [2]. The fundamental issue is the analysis of the time and costs of implementing a project, especially during its construction phase, when 75% -80% of the estimated expenditure on construction works is utilized [3]. ...
... The obtaining of a rational estimate of the S-curve, which reflects reality, before the start of the construction project is important for all participants that are involved in the implementation of the investment project, in particular for the investor and contractors. The S-curve is a helpful tool for the planning, monitoring and control of construction projects [2,13,34,35]. ...
... In order to obtain the most reliable and real estimate of the costs and duration of an investment, analyses should be conducted in accordance with the actual progress of the project. This was done by the authors of the article in several hundred technical and financial inspections at construction sites throughout Poland [2,31]. The estimated actual costs and duration are not reliable in the first period of the project, and they only stabilize with greater accuracy in the second period of the investment process. ...
Article
Full-text available
The purpose of the paper is to analyse and evaluate the course of various construction projects and to compare the planned, incurred and actual costs. Moreover, the authors aim to indicate the basic causes of cost deviations from the earned values, i.e., those that were really performed on a construction site. The data on the development of the original research methodology come from the authors' own experience and professional work involving the providing of Bank Investment Supervision services in the years 2006-2019 on behalf of banks granting investment loans for non-public contracts. The authors of the article collected and processed cost data by conducting monthly direct technical and financial inspections at construction sites of implemented investments. The measurement of the cost and budget of investment tasks was documented in 536 technical and financial reports. A database was built in the form of tables that were prepared for the purpose of value and cumulative analyses of the cost and time of 40 construction projects measured in a monthly cycle from 8 different investment sectors. On their basis, charts of planned / estimated, invoiced / incurred, and actual / earned values of the cumulative costs of the examined construction projects were prepared. The elaborated levels of the amounts of construction that works to be executed were determined using the S-curve. The selected, planned, incurred and actual cost graphs in homogeneous groups, and also earned cost graphs in a diverse group were presented. The conducted studies, which are briefly presented in the article, relate to various construction projects concerning 8 typological research samples. Analyses were carried out in accordance with the methodology of the Earned Value Method (EVM), which enables the actual achieved budgets of various investment tasks to be assessed. Analogies in the arrangement of cumulative cash flow curves were observed within the same groups of buildings, and also between them. Such information is fundamental in terms of controlling and predicting of cost and schedule performances within homogeneous construction sectors. Planning diverse investments budget and timeframe the executives may foresee in measurable way the most probable spend of actual and earned values of managed projects. They can estimate the range of cost and schedule overrun at the construction project completion and set up mitigation actions to minimise the risks of such overrunning.
... The execution of a construction object within the assumed budget and schedule, while at the same time ensuring the quality standard, is a key factor that determines the success of a construction project (Gunduz and Almuajebh 2020). This requires the appropriate planning and effective monitoring of each parameter at the successive stages of an investment task (Konior and Sz ostak 2020b). The fundamental issue is the analysis of the time and costs of implementing a project, especially during its construction phase, when 75% À80% of the estimated expenditure on construction works is utilized (Wang and Hu 2011). ...
... The obtaining of a rational estimate of the S-curve, which reflects reality, before the start of the construction project is important for all participants that are involved in the implementation of the investment project, in particular for the investor and contractors. The S-curve is a helpful tool for the planning, monitoring and control of construction projects (Chao and Chen 2015;Crist obal 2017;Tijani c and Car-Pu si c 2017;Konior and Sz ostak 2020b). ...
Article
The purpose of the paper is to analyse and evaluate the course of various construction projects and to compare the planned, actual and earned costs. The data for the development of the original research methodology come from the authors' own experience and professional work involving the providing of Bank Investment Supervision services documented in 536 BIS reports. On their basis, charts of planned/ estimated, invoiced/actual and performed/earned values of the cumulative costs of the examined construction projects were prepared. The selected BCWS, ACWP, and BCWP graphs of the Earned Value Method curves in 8 homogeneous typological groups were presented. Such information is fundamental in terms of controlling and predicting of cost and schedule performances within homogeneous construction sectors. While planning diverse investments budget and timeframe the executives may foresee in measurable way the most probable spend of actual and earned values of managed projects. They can estimate the range of cost and schedule overrun at the construction project completion and set up miti-gation actions to minimize the risks of such overrunning.
... The S-Curve is the one most commonly used project management tools for cost estimation and productivity assessment (Konior and Szóstak, 2020). The nature of an ERP implementation project results in the progress growing rapidly during the training and configuration phases, more slowly in the testing and conversion phases and reaching an asymptotic maximum when the project goes live (Fig. 1). ...
Article
Full-text available
This research examines how a Constrained Nonlinear programming model for ERP implementation (CNL_ERP) can facilitate Small and medium sized enterprises (SMEs) to deploy resources to address the Critical Success Factors (CSFs) in the pre-implementation phase, and to invest in them during implementation to increase the probability that the implementation will be successful. Applications of CNL_ERP in three case studies demonstrate that the average ERP implementation outcomes outperform the observed results. Using the Generalised Reduced Gradient Method, we developed an ERP implementation strategy realising resource allocation to CSFs. The strategy provides a rich picture of where to concentrate effort in the initial, intermediate and final phases, and is very helpful in enabling an SME to understand the progress of an ERP project and the resources needed. In case there are changes in resources (such as budget, team performance), the model enables SMEs to rank CSFs, and to adjust resources allocations accordingly to achieve the best ERP implementation performance.
... The technique of the S-curve is commonly used for control. However, the traditional method of estimating cost curves based on the schedule is not always accurate, and therefore many alternative empirical models have been suggested as an alternative, e.g. using a polynomial function to generalize S-curves [29][30][31], methods of simulation [32,33], or methods of artificial intelligence [34,35]. The analysis of the literature shows that the S-curve models proposed to date usually differ from reality and are too complicated, and thus not practical in the planning and management of construction projects. ...
Article
Full-text available
The constant increase in the population of cities affects the development of housing. Investors, in their activities related to the profit from the sale of flats, focus on the completion of residential buildings, which must be timely and in accordance with the budget assumptions. Therefore, there is a problem concerning the correct planning of the costs and duration of an investment. The aim of the conducted research was to determine the shape and course of the cost curves for construction projects related to the construction of residential buildings. Based on the analysis of the authors' own studies carried out in a homogeneous research group of 11 residence buildings, an original attempt was made to determine the area of the curve, which indicates the area of correct planning of cumulative costs and the forecasting of their deviations in the financial outlays of construction projects. By knowing the planned cost and duration of a construction project, and by using the proposed 6th degree polynomial, it is possible to determine the planned monthly work and expenditure amounts, and thus correctly plan the investment costs over time. It was proven that the planned work and expenditure advancement of the housing construction sector is greater in the first stage of its implementation when compared to the actual state. The determined 6th degree polynomials describe the regularity that shows that for half of the planned duration of works, the planned work and expenditure advancement is approx. 46%, while the actual advancement is approx. 35%.
... Yield value analysis and control is a powerful technique for analyzing and controlling project performance, as well as acting as a warning sign. The graph S curve and schedule table both illustrate this warning sign [26]. Monitoring time and cost with the help of yield values is advantageous [27]. ...
Article
Full-text available
Controlling how construction work is completed is critical to success. Generally, the result value method is used as the tool. Although this method has been applied to a variety of different types of construction work, the tool has been limited to a single project. This study examines the total value of completed construction work. Because the duration of construction work varies, the researchers refer to the percentage of the plan's duration. The percentages are set at 25%, 30%, and 50%. There have been 17 completed building construction projects between 2017 and 2018. Additionally, a comparison sample of construction work is used. The results of the data processing are pessimistic, most likely, optimistic, and hopeful. Additionally, the expected value is compared to a reference value. The expected values for the percentages of 25%, 30%, and 50% are (-2.425), (1.071), and 50%, respectively (2.275). Indeed, the expected value obtained is not the same as the comparison value. The contractor can prepare the necessary resources by knowing the value of the expected yield at a certain percentage of the duration.
... Knowledge of the planned and actual course of cumulative financial outlays over time, as well as the shape of the S curve and its deviations, allows rational actions to be taken in order to achieve success and the intended goal in the implementation of the investment. The aim of article [8] is to analyse the course of an exemplary construction project, to compare the costs of the planned works with the actual costs of the performed works, as well as to indicate the reasons of failure to meet the planned deadlines and the project's budget. The authors of the article analysed the financial expenditure for the implementation of a construction investment, which were incurred in 20-month cycles. ...
Article
Full-text available
The construction industry is a sector of the economy that is characterized by a large variety of building structures, as well as a large variability in the conditions of their implementation [...]
Article
The aim of the research results presented in the article was to develop a method that enables the analysis and evaluation of deviations at the stage of implementing a construction investment in various construction sectors. The new method was based on the well-known Earned Value Method (EVM). It was assumed that the monitoring of costs and the constant control of the implementation time of construction projects, with the simultaneous analysis of the level of deviations, allows for the consistent management of the investment task. Moreover, it ensures—in the required time—the adoption of appropriate improvement actions, and also enables the quantification of risk during the planning of an investment. The article attempts to prove the validity of the assumption about the necessity of the cyclical verification of the level of deviations in construction projects budget and schedule. Such an approach provides numerous perceptible benefits; such as the precise determination of the size of possible losses; an immediate reaction to risk; and the possibility of making changes at every stage of implementing an investment. On the basis of the analysis of the author’s own research carried out in three research groups of facilities (collective housing; hotels; and commercial and service facilities), an original attempt was made to determine the size of cost and time performance indexes of various investment tasks. The values of these performance indexes were determined, and are presented as quantile images in boxplots.
Article
Full-text available
Purpose Planning phase of a project results to series of crucial decisions which determine the path to objectives achievement. At the same time, in this phase, project encounters the highest level of uncertainty in comparison of all phases of project lifecycle. This paper aims to support early decisions of project based on the progress forecasting. Design/methodology/approach The scope of study is limited to downstream projects of petroleum industry in Iran, and the proposed model is trained and tested based on 75 Iranian completed petroleum projects. First, types of progress curve functions are investigated, and various types are studied and the most appropriate ones are selected through curve fitting. In the next step, using questionnaire, dependent and independent variables are recognized. Finally, using historical data and s-curve generator functions, a fuzzy inference system (ANFIS) based model have been developed to support early phases decision-making processes. Findings Based on the analysis of received questionnaires, six functional criteria in two groups as dependent variables and 25 independent variables, in two groups and four clusters are determined and categorized. Eventually, performance prediction model of a project has been developed by using Adaptive Nero Fuzzy Inference System. Originality/value The main contribution of this study to construction management knowledge is categorizing two groups of variables, which first one defines the project dynamic and the other calculates the key effects on previous one. Also, this investigation improves the current knowledge by analyzing the project system from the dynamic behavior perspective and modeling the defined variables using ANFIS tools.
Article
Full-text available
Abstract: The Earned Value Method allows the prediction of future values of the total cost and duration of the construction project realization, and also it allows the early detection of the collisions between the schedule and the construction project budget. It is more often indicated its usefulness for monitoring and controlling the construction work progress in the time and cost formulation. It is used, in the indirect way, to control the risk in terms of the cost overruns of the construction project realization and in case of the failure to meet the deadline for completion of the construction project. The authors’ goal was not only to indicate the advantages of the method (widely discussed in the literature) but also to indicate some inaccuracies in the application of the Earned Value Method, which may affect the costs forecasting and the date of completion of the construction project. The conclusions are based on the analysis of several construction project realizations. Keywords: control of construction progress, risk, earned value
Article
Full-text available
The Earned Value Method allows the prediction of future values of the total cost and duration of the construction project realization, and also it allows the early detection of the collisions between the schedule and the construction project budget. It is more often indicated its usefulness for monitoring and controlling the construction work progress in the time and cost formulation. It is used, in the indirect way, to control the risk in terms of the cost overruns of the construction project realization and in case of the failure to meet the deadline for completion of the construction project. The authors’ goal was not only to indicate the advantages of the method (widely discussed in the literature) but also to indicate some inaccuracies in the application of the Earned Value Method, which may affect the costs forecasting and the date of completion of the construction project. The conclusions are based on the analysis of several construction project realizations. Keywords: control of construction progress, risk, earned value
Article
Full-text available
Technical, financial and organisational feasibility study methods in compliance with a Bank Investment Supervision requirements have been presented. Methodology of construction project appraisal for financing and execution professional preparation have been laid out – technical documentation, arrangements, realisation. Analysis and assessment of Bank Investment Supervision consisted of Project Execution Plan, geotechnical and environmental conditions, permit design, agreements and decision impacts of local authorities, engineering contract for construction works, project insurance and performance bonds, schedule of execution tasks and their costs, payment plan, investment budget and project economical effectiveness, scope of monthly construction works execution assessed by Earned Value Method approach, significant risks measurable assessment and handover procedure of construction project. Engineering, Project and Construction Management (EPCM) approach to investment process and solid, consequent, regular construction projects monitoring executed by professional Banking Supervision Inspector make possible to minimise any faults of inappropriate financing of construction projects.
Article
Full-text available
The idea of sustainable development and the resulting environmentally friendly attitudes are increasingly used in construction projects. Designing in accordance with the principles of sustainable development has an impact on the costs of construction works. The authors of this paper proposed an approach to estimate the costs of sports field construction using the Case Based Reasoning method. In their analysis, they distinguished 16 factors that affect the cost of a construction project and are possible to already be described at an early stage of its preparation. The original elements of the work include: consideration of such environmental factors as the environmental impact of the building, materials used, the impact of the facility on the surroundings affecting the amount of implementation costs and development of own database containing 143 construction projects that are related to sports fields. In order to calculate the similarity of cases, different calculation formulas were applied depending on the type of data (quantitative, qualitative, uncertain, no data). The obtained results confirmed that the CBR method based on historical data and using criteria related to sustainable development may be useful in cost estimation in the initial phase of a construction project. Its application to the calculation of the costs that are related to the implementation of sports fields generates an error of 14%, which is a very good result for initial calculations. In the short run, such factors as the impact of the object and the type of materials that are used from the perspective of their influence on the environment may be decisive as far as the costs determined in the life cycle of the building are concerned, as well as the lowest costs of the building construction ensuring the appropriate quality and respect for the environment.
Article
Full-text available
Monitoring and controlling the progress of projects is always indispensable to project manager’s mission because it can help to produce updated pictures of how the project is progressing. Even with a target progress derived from a detailed project schedule, the actual progress, under the influence of many factors, may deviate significantly from the target, which requires to take corrective actions/control. A project monitoring and control system must provide the required information to answer the following questions: What is the difference between the planned and actual work performance? How is the project progressing in terms of completion of activities? How much ahead or behind schedule is the project? What is the efficiency of the time utilized on the project? In this paper, the concept of S-curve envelope is introduced. This S-curve envelope consists of two curves. The upper curve corresponds to the curve of the earliest times whereas the lower curve corresponds to the curve of the latest times. This S-curve envelope can be used as an early warning system to determine whether the S-curve from the actual progress data is reasonable or needs to be revised. If, when comparing the S-curve based on actual progress to the scheduled-based S-curve envelope, the project is running outside the envelope, appropriate action must be taken depending on whether the actual S-curve is below or above the envelope.
Conference Paper
Full-text available
Article
Full-text available
Risks pertaining to construction work relate to situations in which various events may randomly change the duration and cost of the project or worsen its quality. Because of possible significant changes of random events, favorable, moderate, and difficult conditions of construction work are considered. It is the first stage of the construction risk analysis. The probabilistic parameters of construction are identified and described by using the design characteristics model of the structure and the construction technology model. The first describes the probabilistic properties of the structure execution’s technology. The second describes the probabilistic properties of the works execution. Both models contain basic probabilistic data for scheduling, cost estimating, and risk assessment of the construction.
Article
The construction industry is a major sector in the economy of developing countries. During the last two decades in Algeria, many large-scale construction projects have been launched to develop the basic infrastructure facilities of the country. However, most of these projects experience extensive delays. The objective of this paper is to identify the causes of delay in the Algerian construction industry and assess their importance according to the main project stakeholders, which are the owner, the contractor and the consultant. Data were collected through a questionnaire and direct interviews of a sample of construction experts including 16 owners, 16 contractors and 20 consultants. Fifty-nine causes of delay were identified in this research. The results indicate that the five most important causes are slow change orders, unrealistic contract duration, slow variation orders in extra quantities, delays in payment of performed work and ineffective planning and scheduling by contractors. The study revealed that owner-related causes are the most important sources of delay. The findings of this research can be used to guide the improvements of the construction industry in Algeria.
Article
Earned Value Analysis (EVA) is an accepted theoretical technique advocated for the control of projects. This paper attempts to refine and improve the performance of traditional EVA by the introduction of a hybrid methodology based on work packages and logical time analysis entitled Work Package Methodology (WPM). The proposed WPM provides the means to periodically update project cost and time performance by restricting EVA calculations to individual work packages. These are then subjected to a logical time analysis to determine the predicted project cost and time to completion. A comparative analysis between WPM and EVA is then undertaken using adapted test data derived from knowledge of previous projects to identify the reasons for variation in the results obtained from both methods. The evaluation of the test results indicates that when the Cost Performance Index (CPI) and the Schedule Performance Index (SPI) are well above or below unity then, especially in the early stages of the project, traditionally applied EVA predictions can be un-realiable and require further investigation and evaluation. WPM provides a vehicle for judging the performance of EVA by applying an alternative logical time and cost utilizing work sequence and construction methods. The predictive performance of EVA is refined by these means.