Technical ReportPDF Available

Case Study on Mersing Telekom Building

Authors:
MERSING TELECOMMUNICATION COMPLEX
THE PROJECT MANAGEMENT CASE STUDY ON
MERSING TELEKOM BUILDING
SOLARIS SDN BHD
PROPOSED PROJECT:
THE PROPOSED THREE STOREY
TELECOMMUNICATION EXCHANGE CENTER AND
OFFICE FOR MERSING, JOHOR DARUL TAKZIM .
PROJECT OWNER:
TELEKOM (M) BERHARD
REFERENCE:
PREPARED BY: REVIEW BY: APPROVED BY:
CHUA BOON PIN ELMEY YUSOF RAJA SULAIMAN
DATE: DATE: DATE:
0
MERSING TELECOMMUNICATION COMPLEX
EXECUTIVE SUMMARY
This report is written to portray the application of Project Management knowledges for a
selected project, going through the process of planning, allocating of resources, scheduling
of resources, costing to accomplish the given objective in an efficient and prompt manner.
A Project Management Plan (PMP) is a method statement depicts the whole project
working process, during the planning stage of the project. PMP goes indepth of project
with the help of PM Bok Guide, leave no stone unturn for the Proposed Project. From
initial stage, step by step planning and analysis the costing, work schedule, monitoring
cash flow, control the quality of works, until the closure of Project. The Project Success
can be asserted by project planning. In preparing for the proposed Mersing
Telecommunication complex, the project management consultant drafts out this report
covering the following key management areas:
i. Scope Management
Scope involves getting information required to start a project. The work that needs
to be accomplished to deliver the project. Project scope is the listing of tasks to
carry out in accordence to the required quality, quantity and within cost. Work
Breakdown Structure (WBS) is the tool to assist the planning process of scope
management.
ii. Cost Management
The process of estimate the project cost, financial planning and control statement.
iii. Schedule Management
This section cover the Project Works Schedule by using Gantt Chart and Critical
Path method.
iv. Stakeholder Management
The identifing key project stakeholders. Analysis the stakeholders’ influence and
power of decision making towards the sucess of Project.
v. Risk Management
1
MERSING TELECOMMUNICATION COMPLEX
To determine any potential risk, plot out the risk register, arrest the risk if any and
propose risk mitigation process.
vi. Communication Management
To touch on the flow of communication and it’s process.
Vii Procurement Management
This section deal with procurement contract.
Viii Transition Management / Close out
The final stage of the Project. The inspection, the acceptance from client and official
handing over. The completion stage of project management and financial close out. The
Project team have done their job for this project and moving out to next phase.
Hence PMP is a detail workable Project Plan, it is the hand book for the proposed project.
Traditional wisdom is that planning and analysis are important and the more planning there
is in a project, the more successful the project will be Time spent on these activities will
reduce risk and increase project success. On the other hand, inadequate analysis and
planning will lead to a failed project.
2
MERSING TELECOMMUNICATION COMPLEX
TABLE OF CONTENT
EXECUTIVE SUMMARY……………………………………………………………..2
PROJECT MANAGEMENT PLAN……………………………………………………8
1.0 INTRODUCTION………………………………………………………………8
1.1 The Company……………………………………………………………8
1.2 The Project Objective and overview………….…………………………9
1.3 The Project brief……………………………………………………...…10
1.4 The Focus Area In Relation To PMBOK……………………………….12
1.5 Key Stakeholder………………………………………………………...13
1.6 Key management area……………………………….………………….14
2.0 PROJECT ORGANISATION…………………………………………………..15
2.1 Key project management team………………………………………….16
2.2 Management roles, responsibilities, accountability and Authorities……17
3.0 PROJECT MANAGEMENT PLAIN MAIN AREAS..…………………………..20
3.1 Scope Management……………………………………...………………20
3.2 Cost Management……………………………………………………….33
3.3 Schedule Management…………………………………………………..44
3.4 Stakeholder Management……………………………………………….48
3.5 Risk Management……………………………………………………….53
3.6 Communication Management…………………………………………..57
3.7 Procurement Management ……………………………………………...61
3.8 Transition Management/Close out………………………………………65
4.0 CONCLUSION…………………………………………………………………70
5.0 RECOMMANDATIONS……………………………………………………….74
REFERENCES………………………………………………………………………….75
APPENDICS……………………………………………………………………………77
3
MERSING TELECOMMUNICATION COMPLEX
LIST OF FIGURES
Figure 1.1 Mersing location…………………………………………………………11
Figure 1.2 The proposed site locations………………………………………………12
Figure 2.1 The proposed organisation structure for Mersing project………………..16
Figure 3.1 Project life cycle………………………………………………………….20
Figure 3.2 Proposed Telecommunication Complex Site Layout Plan…………….…23
Figure 3.3 Create WBS input, tools & technique, and output……………………….24
Figure 3.4 Proposed WBS for Mersing Telecommunication Complex……………...26
Figure 3.5 Typical template of WBS Dictionary…………………………………….27
Figure 3.6 Project Triple Constraint……………………………………………….…30
Figure 3.7 Project Cost Management Overview……………………………..............33
Figure 3.8 Histogram showing Tender Price compare to Budget Baseline…… ……36
Figure 3.9 Pie Chart shows the weightage of the Budget cost……………………….37
Figure 3.10 Histogram showing Budget versus Timeline……………………………..37
Figure 3.11 Mersing Project S-curve…………………………………………………..38
Figure 3.12 Plan Schedule Management input, tools & techniques and output……….43
Figure 3.13 The Gantt Chart Schedule…………………………………………………46
Figure 3.14 The Human Resource distribution for Mersing Project…………………..47
Figure 3.15 General Identifying Stakeholders…………………………………………48
Figure 3.16 Potential Key Stakeholders………………………………………………..49
Figure 3.17 Stakeholder Analysis for Mersing Project………………………………...50
Figure 3.18 Stakeholder Analysis……………………………………………………...52
Figure 3.19 Risk Assessment Matrix for Mersing Project…………………………….54
Figure 3.20 Distribution of Risk Intensity……………………………………………..55
Figure 3.21 Flow Chart of Communication Management Process……………………58
Figure 3.22 Project Close Out Check List Template………………………………….67
Figure 3.23 Lesson Learn Life Cycle………………………………………………….69
LIST OF TABLES
Table 1.1 Focus Area In related to PMBOK……………………………………………13
Table 3.1 WBS Dictionary for Mersing Project………………………………………...27
Table 3.2 Estimated Project Cost Baseline……………………………………………..35
Table 3.3 Project Budget versus Contract Sum………………………………………...35
Table 3.4 Comparison of Tender Price and Budget Baseline…………………………..38
Table 3.5 High Level Budget for Mersing Project……………………………………..39
Table 3.6 Mersing Project Cost Contingency Plan……………………………………..40
Table 3.7 Critical Path Table……………………………………………………………45
Table 3.8 Risk Register for Mersing Project……………………………………………54
Table 3.9 Risk Response Strategy on Negative Risks and Threats……………………..55
Table 3.10 Risk Response Strategy on Positive Risks and Opportunities……………….56
Table 3.11 Risk Response Strategy on Negative Risk for Mersing Project……………..56
Table 3.12 Communication Matrix for Mersing Project…………………………………59
4
MERSING TELECOMMUNICATION COMPLEX
LIST OF ABBREVIATIONS
No. Abbreviation Explanation
BLMT Build, Lease, Maintain and Transfer
BOT Build, Operate and Transfer
BQ Bill of Quantity
CIDB Construction Industries Development Board
LAD Liquidated Ascertained Damages
LOI Letter of Intend
LOA Letter of Award
M & E Mechanical and Electrical
PD Project Director
PM Project Manager
PMP Project Management Plan
PMBOK Project Management Body of Knowledge
PQP Project Quality Plan
QESH Quality, Environmental and Safety & Health
QS Quantity Surveyor
SI Site Instruction
SO Superintendence Officer
SOP Standard Operation Procedure
TM Telekom Malaysia Berhad.
TNB Tenaga National Berhad
VO Variation Order
WBS Work Breakdown Structure
WBGL Works Below Ground Level
RWDP Rain Water Down Pipe
GRD Ground
DP Dry Powder
NSC Nominated Sub-Contractor
BWK Brick Work
5
MERSING TELECOMMUNICATION COMPLEX
THE PROPOSED THREE STOREY
TELECOMMUNICATION EXCHANGE CENTER AND
OFFICE FOR MERSING, JOHOR DARUL TAKZIM .
6
MERSING TELECOMMUNICATION COMPLEX
7
MERSING TELECOMMUNICATION COMPLEX
The Front View of Mersing Telecommunication Complex
PROJECT MANAGEMENT PLAN
1.0 INTRODUCTION
1.1 The Company;
Company Name: Solaris Sdn. Bhd.
Corresponding Address: 702 Block B, Kelana Business Centre,
97, Jalan SS7/2, Kelana Jaya, Selangor Darul Ehsan.
Email: Solarisselatan@gmail.com
OUR VISION
To excel as “The Project Management Consultant (PMC)” in this Region.
OUR MISSION
To excel as professional Project Manager;
To strictly work in accordance to the QESH Management System;
To comply with the legal requirements.
AREA OF EXPERTISE
i. Building and Civil works Planning & Design;
ii. Turnkey Contract Management; and
8
MERSING TELECOMMUNICATION COMPLEX
iii. Tendering Management.
Being pioneer to set up Solaries Sdn. Bhd., Ir Raja Sulaiman has a vision to operate
professionally in the field of PMC. The full support and commitment of the team member
has gain sound reputation in the field of PMC as “The Project Management Consultant”.
The management also concerned of site operation safety and health. Organising regular
site inspection and fuming of site to stop mosquito breeding and fight the treat of dengue.
This is part of the community awareness.
Solaris Sdn. Bhd. practicing management system which is conformed to ISO 9001:2015
and ISO 1400:2015. We are in the process of obtaining the OHSAS 1800:2007 standard
certifications.
With leadership of Ir Raja Sulaiman, we are confident that the company will excel and we
are determined and dedicated to:
i. Provide comprehensive Project Management Plan for the client and reduce and
foreseeable risk and financial cost;
ii. Provide our clients with upmost professional management service;
iii. Managing our task to the highest safety and health standard;
iv. Conduct the Development of the project in accordant to the legal requirements and
regulations;
v. Practice the ISO and QESH standard operating system, and quality work standard
in term of craftsman standard and quality materials use; and
vi. Satisfied clients are our greatest pride and fulfilment of success.
1.2 THE PROJECT OBJECTIVE AND OVERVIEW
Mersing is a fishing village and a ferry terminal for ferry to and from Tioman and
surrounding islands. The development of the village is increasing, when the state
government and district office have put in effort to bring in investment to set up factories
and industries estate for SME, for example, factory producing seafood cracker, and other
commercial activities in the surrounding of Mersing. The improved road system leading
from Kuantan to Mersing is widened and it is pleasant to travel in this newly upgraded
9
MERSING TELECOMMUNICATION COMPLEX
road. It is convenient to approach Mersing via Kluang and Bukit Tinggi Johor. The tourist
promotion campaign on the islands resort and scuba diving helps to draw lot of visitors to
Mersing too. The demand for telecommunication service is increased, upgrade of the
facility is urgently requested, as to provide good service not only during the casual time,
but it is most important during the emergency time.
The current set of telecommunicating equipment is housed in a 40 foot container. The
capacity of the equipment is far from coping up with the demand of the end users. There is
urgently in need to expend the number of telephone line, internet system and increase the
size of communication capacity. The operation, sale and service office is in a small
wooden hut. Hence it is badly in need of a proper building designed to house all the
required telecommunication equipment.
Telekom Malaysia Berhad (TM) consider the situation and agree the go ahead of
increasing the capacity of the telecommunication service.
The proposal design criteria of the project as follow:
i. To design a well-planned building to house the communication equipment;
ii. To facilitate the rapid demand of internet facilities;
iii. To increase the capacity of the telecommunication ability by 10 folds (in stages);
iv. To provide administration facility and
v. To provide sales and services front office.
1.3 THE PROJECT BRIEF
The selected location for the proposed Project at Lot 497,Jalan Ismail , Bandar Mersing,
Daerah Mersing, Johor Darul Takzim.
The Proposed three storey building consists of sales and service office at ground floor,
occupy about one third of the ground floor area. The other two third consist of computer
10
MERSING TELECOMMUNICATION COMPLEX
flooring; will house the telecommunication computer system. A backup batteries room and
a workshop.
Main telecommunication system will be installed on first and second floor. Portable water
tank is located on the roof floor and all air-conditioning units will be located in the rood
floor.
There are other ancillary buildings like Pump house for fire fighting, TNB (Tenaga
National Board) substation, guard house and Telecommunication Steel Tower.
The Project focus on the three storey building, whereby most construction activities will be
on this building. Other ancillary buildings’ and installation works can fit into the schedule,
as the working schedule of the main building is the critical path. Therefore it is a clear
case study of the critical path, where the works take the longest time to complete, while
other works can tagged in between and can be completed before the main building
completion.
THE SITE LOCATION
11
MERSING TELECOMMUNICATION COMPLEX
Figure 1.1 : Map showing the location of Mersing , Johor Darul Takzim
Source : Adopted from Google Map
Figure 1.2 : The Proposed Site location
Source : Adapted from Google Map
1.4 THE FOCUS AREA IN RELATION TO PMBOK
The preparation of this Project Management Plan is drawn out inaccordance to the Project
Management Body of Knowledge (PMBOK, 6th Edition). The Planning Structure of this
report uses PMBOK’s guideline of Project Life Cycle of Initiation, Planning, Organising,
Execution, Tracking, Controlling and Close out. The Project’s Objective have to be
sucessfully fullfiled, leave not chance for any mistake to take place and reduce the risk to
the minimium.
12
MERSING TELECOMMUNICATION COMPLEX
Table 1.1 : Forcus Area In Relation to PMBOK
No Focus Area PMBOK Focus Area PMBOK
Section Ref
1 Scope
Management
What is Project Management
Project Intergration &Scope
Management
5
2 Cost
Management
Project Cost Management 7
3 Schedule (Time)
Management
Project Time Management 6
4 Stakeholder
Management
Project Stakeholder Management
Stakeholder Influences &
Project Life Cycle
13
5 Risk Management Project Risk Management 11
6 Communications
Management
Project Communications
Management
10
7 Procurement
Management
Project Procurement
Management
12
8 Transition Management
Close out
Source: Derived from the research paper and PMBOK 6th Edition (2017)
1.5 KEY STAKEHOLDER
Internal stakeholder
i. The Owner or owner’s representatives of the Project;
ii. The Project management team;
iii. Contractors and sub contractors;
iv. The supervisor, craftman and labour force.
External stakeholder
i. The Local Authorities;
ii. The Suppliers and Vendors of Building Material, Plant & Equipements;
iii. The Telecommunication users/ End users;
13
MERSING TELECOMMUNICATION COMPLEX
iv. The Creditors / Financiers;
v. Local community;
vi. Consultant
vii. Auditor; and
viii. The NGO (Non Government Organisation).
1.6 KEY MANAGEMENT AREAS.
This Project Management Plan (PMP) will be written in accordance to PMBOK, 6th
Edition (Project Management Body of Knowledge, 2017 ) key management areas and
guild line for Project Planning, Scheduling, Control, tracking towards the final stage of
closing the project. The Key PMBOK management areas will be discuss in detail as
follow:
i. Scope Management;
ii. Cost Management;
iii. Time (Schedule) Management;
iv. Stakeholder Management;
v. Risk Management;
vi. Procurement Management;
vii. Communication Management; and
viii. Transition Management / Close
14
MERSING TELECOMMUNICATION COMPLEX
2PROJECT ORGANISATION
INTRODUCTION TO PROJECT ORGANISATION
Project organisation is grouping each every individual with the right capability performing
the correct task. The ultimate aim of the organisation is to fulfil the set goal. Let’s discuss
some of the known organisation structure as follow:
FUNCTIONAL STRUCTURE
A functional organization structure, people who have the same skill or knowledge be group
together to perform similar task. So all civil engineers are placed in the construction
department and the marketing staffs are in the marketing department, operations, senior
management and human resources departments. Team members are group by their
speciality and work independently.
The advantages of this kind of structure include quick decision making, because the group
members can easily communicate. They can also learn from each other, since they already
possess similar skill sets and interests.
The Mersing Project Organisation using FUNCTIONAL STRUCTURE.
15
MERSING TELECOMMUNICATION COMPLEX
2.1 KEY PROJECT MANAGEMENT TEAM
The Proposed Project Management team is structured to the need of this project. The
proposed project is not a large operation, therefore we proposed to use functional
Organisation Structure for efficient operation. The Key Project Management Team as
shown below:
Figure 2.1: The Proposed Organisation Structure for Mersing Project
Source: Derived for this report
Project Director is the main key team leader; he liaises between the owner representative,
the local authorities, the consultants, Project Manager and the working team.
16
Surveyor
Solaris Sdn Bhd (PMC) Project
Director
Quantity Surveyor
(QS)
Project Manager/
Contract Manager
Site Manager/Site
Engineer
Building Supervisor
Structural
Contractor
M & E
Contractor
Engineering
consultant
M & E
consultant
Architect
Consultant team
Staff
Staff
Staff
Staff
Staff
Contract & Safety
Team
M&E Supervisor
Staff
Staff
Contract &
Procurement
Safety & Health
MERSING TELECOMMUNICATION COMPLEX
2.2 MANAGEMENT ROLES, RESPONSIBILITIES, ACCOUNTABILITY AND
AUTHORITIES
PROJECT DIRECTOR
i. The leader of the whole Project Management Team;
ii. To coordinate and oversee the success of the Proposed Project;
iii. To acts as Superintendence Officer ( SO );
iv. Establish objectives, policies and strategies to meet the Project’s requirement;
v. Defines responsibility and authority of the key team member; and
vi. Liaison officer with the owner representative.
PROJECT MANAGER
i. To lead the project team and manage the whole project externally and internally;
ii. To communicate well to all levels internally and externally;
iii. To liaise with the consultants on design related works;
iv. To implementing the Project as per the approved drawing;
v. To conduct periodic meeting to track the progress and the quality of the Project.
vi. To ensure the progressive claim is in order;
vii. To establish risk assessment meeting and to strategy the action remedial or
prevention plan;
viii. To liaise with the local authorities, compliance to all regulation requirement;
ix. To monitor the quality standard applied and compliance;
x. To take appropriate action when work progress is behind time schedule and make
catch up plan to meet the close up;
xi. To control the cost of the Project and not to over run the cost;
xii. Be effective lead with sound technical skills; and
xiii. Be Empathetic and enthusiastic.
17
MERSING TELECOMMUNICATION COMPLEX
SITE MANAGER / SITE ENGINEER
i. To overall in charge of the site operation, quality assurance, work force monitoring,
site safety & health treat;
ii. To liaise with all level of personal at site on technical matter, if necessary feedback
to consultant team for assistance;
iii. To follow up liaising with local authorities;
iv. To communicate at all level;
v. To negotiate for procurement’s best deal;
vi. To plan the whole construction works and mitigate any problem arises; and
vii. To track the progress of works and monitor the progress.
CONSULTANT TEAM
i. To design the building to suite the owner required perimeter and needs;
ii. To liaise with the local authorities on statutory requirement;
iii. To inspect the construction work is done and maintain in accordance to
specification;
iv. To prepare the tendering documents; and
v. To survey and demark the working boundary and building position.
CONTRACT AND SAFETY TEAM
i. To prepare contract for purchase of building materials;
ii. To organise the storage area and logistic materials, plants and equipment;
iii. To prepare contract for successful contractor and sub-contractors;
iv. To establish safety rules and regulation in accordance to QESH requirement;
18
MERSING TELECOMMUNICATION COMPLEX
v. To prepare the risk registration and draw out strategies to overcome or preventing
the risk to occur;
vi. To inspect the site for Safety and Health related problem. Immediate action is
prompted;
vii. To monitor cost and expenditure, ensure the cost stay within the budget;
viii. To monitor VO (Variation Order ) and SI (Site Instruction ) for progressive claim;
and
ix. To maintain and upkeep the site storage and keep track on material flow to reduce
wastages;
SUPERVISOR
i. Assist the Project Manager to all aspect of works at site;
ii. Record the site diary and control the progress of works;
iii. Supervise work in progress for safety, in accordance to specification and correct
quality and quantity;
iv. Plan ahead of the contractor on physical works, hold meeting with contractor for
material requirement and work force head count;
v. Supervise and conduct the necessary test at site or outside and monitor the outcome
of test results to confer to the standards of practice or specification before proceed
to next stage of construction works; and
vi. Check the setting out and confirmed the positioning and floor high is correctly
measured and transferred.
19
MERSING TELECOMMUNICATION COMPLEX
3PROJECT MANAGEMENT PLAIN MAIN AREA
3.1.0: SCOPE MANAGEMENT
Project scope management is the process to define and include all work required to
complete the project successfully ( PMBOK 2017 ). The process includes
i. Initiation:- Authorizing the project or phase;
ii. Scope planning:- developing a written scope statement or work statement (Project
Charter);
iii. Scope definition:- subdividing the project into smaller, more manageable
components, that is Work Breakdown Structure (WBS );
iv. Scope verification:-formalizing acceptance of the project scope;
v. Scope change control:- controlling change.
vi. Collect Requirements; and
vii. Validate Scope
20
MERSING TELECOMMUNICATION COMPLEX
Figure 3.1: Project Life Cycle
Source: Adopted from Google search
3.1.1 THE PROJECT SCOPE STATEMENT ( SOW )
The Proposed project is not a large one; the site is divided into 5 zones.
i. The 3 storey main building;
ii. The Communication Tower;
iii. The Main Entrance & Guard house, and rear gate;
iv. The Sub-station; and
v. The Fire fighting pump house and water tank.
ZONE 1: THE 3 STOREY MAIN BUILDING
Ground floor consist of Front office, which house the reception area, 2 executive rooms,
one discussion room, Some display area and 3 number customer service counters. There is
staircase for access to other floor. Female & Male toilet includes some service ducts for
Piping and cable respectively. Standby Battery Room is next to Dust proof and pressurised
room for sophisticated communicating equipment’s (The installation of the sophisticated
21
MERSING TELECOMMUNICATION COMPLEX
communicating equipment’s and computer system will be done by TM own Technical
Division.). There is a fire escape stair at the rear portion of the Ground Floor.
Second and Third floors are the computer raise floor system for the telecommunication
exchange and computer system. Special pressuriser Dry power fire fighting system is
installed for Second and Third Floors where all equipment’s are related to electricity.
Sprinkle system being installed for Ground floor and front office.
The whole building is fully installed with Air Conditioning. The second and third floor
have the privilege for a stronger and enhanced Air Conditioning System for both below
raise floor and above raise floor.
Septic tank for 15 persons is installed to service Ground, second and third floor Toilets.
Surau for male and female separately constructed on third floor near to staircase lobby for
the convenience of the TM staff.
Loading bay at the rear of the building, there is horst crane for second and third floor. The
wall is to be roller shuttle instead of brick wall for the hosting area.
The roof is flat roof, to be waterproof. Service Water Tank for toilets is to be installing
here and all the air conditioning external units are arranged in zone and label according to
the corresponding units and floor level for easy identify during maintenance and repair.
External Works Around Main Building
Access road linking Main entrance and rear entrance. In front of the front office is the car
park for TM customers. At the rear of the building is the loading bay. Landscaping on
verge between road kerbs to the fencing. Plants and grass will be planted for shed and
greenery. Street light will be install along the access road, car park and loading bay.
There will install fencing light at every fencing pole.
ZONE 2: THE COMMUNICATION TOWER
22
MERSING TELECOMMUNICATION COMPLEX
It is a 150 meter steel structure tower. There is two nos. 10x10 ft. control room servicing
the tower before connection to the main building. Communication satellite disks and
connection to be install and control by TM Technical personal.
ZONE 3: THE MAIN ENTRANCE AND GUARD HOUSE AND REAR GATE
The Main Entrance is the main access for the public and staff. There is a Guard house
complete with WC facilities for security personals. A rear gate is installed for the
maintaining staff and access for equipment’s.
ZONE 4: THE SUBSTATION
The substation is a double chambers station. TNB main supply is connected at this
substation and step down the current for a stable supply to the main building ( exchange
building) and Tower. The equipment’s, transformers and switch gear will be installed by
TNB personal.
ZONE 5: THE FIRE FIGHTING PUMP HOUSE AND WATER TANK
The will be a Fire fighting pump house with 500 gallons of water tank, ready for any
incident of fire outbreak. In the computer raise floor system where water is hazardous, dry
power fire fighting system is specially installed for electrical installation. Together there is
2 numbers of Fire Hydrant which is connected to the main water supply for emergency.
The Site Plan as follow:
23
MERSING TELECOMMUNICATION COMPLEX
Figure 3.2: Proposed Telecommunication Complex Site Layout Plan
Source: Derive from the research
3.1.2: WORK BREAKDOWN STRUCTURE ( WBS )
Work Breakdown Structure (WBS) is a powerful tool which breaks each task into smaller
and manageable components. These small and manageable components are achievable
and deliverable.
24
MERSING TELECOMMUNICATION COMPLEX
Figure 3.3: Create WBS: inputs, Tools & Technique, and Output
Source : Adopted from PMBOK, 6th Edition)
An Effective Work Breakdown Structure:
i. Is a deliverable-oriented grouping of project elements;
ii. Is created by detail planning and analysis;
iii. Contains 100% of the work defined by the scope or contract and captures all
deliverables (Internal, External, Interim) in terms of work to be completed;
iv. Defines the context of the project, clarifies the work and communicates project
scope to all stakeholders;
v. Is expressed as a chart or outline, providing a graphical or textual breakdown;
vi. Arrangement of all major and minor deliverables in a hierarchical structure - and is
constructed so that each level of decomposition contains 100% of the work in the
parent level;
vii. Should contain at least 2 levels;
viii. Evolves along with the progressive elaboration of project scope, up to the point of
scope baseline, and thereafter in accordance with project change control - allowing
for continual improvement; and
ix. Employs a coding scheme for each WBS element that clearly identifies the
hierarchical nature of the WBS when viewed in any format.
To develop WBS, one has to follow the guideline and reference to key documents such as
(may not limited to):
i. The Project Charter;
ii. The Project problem statement or scope definitions;
iii. The appointment Contract or agreement; and
iv. Project Management Practice.
Understanding the WBS process, Let us start working on the WBS for this project. Since
the project is divided into different Zone, the work break down decomposition of work
trade will be by each individual Zone. With this effect, any alteration and change on any
Zone will not affect or cross over to other Zone. The Zoning will help to monitor, track
and control the progress of each Zone.
25
MERSING TELECOMMUNICATION COMPLEX
Figure 3.4: Proposed WBS for Mersing Telecommunication Complex
Source : Derived from this research paper
Table of Works Breakdown Structure (WBS ) is enclosed in Appendix 1: WBS schedule ,
Appendix 2: WBS schedule (continue), Appendix 3 Inspection Check list and Appendix
4:Close Out check list, for cross reference with Figure 3.4. This table will be utilized in
the Project Transition and Close Out as Inspection, Testing and commissioning check list.
26
Proposed 3 storey Telecommunication Complex
Site Survey
and setting out
Off Site Tower
Steel structure
Fabrication
Footing &
Ground Beam
Temporary
Access
Site Office &
temp. Utilities
Local Authorities’
approval & to start work
Design &
Technical
Site Preparation
Piling
Pile Cap &
Ground beam
Below Ground
Level Cable
Trench
Below Ground
Level Water
Reticulation &
sanitary piping,
manhole, pump
sump
External Road kerf
& road work
Water main at rear
entrance
Road side
monsoon drain &
manhole
Electrical wiring
system
Installation of
Steel Tower
Pile Cap &
Ground beam
GH Structure
Roofing
Main & rear
Entrance Gate
sliding door
railing
Water proofing to
Roof
Below Ground level,
street lighting cabling
Instal sliding
door
Air conditional
system
Septic tank
installation & Hydrant
piping
Footing &
ground beam
Substation
structure
Footing &
ground beam for
pump house
Footing for Water
tank
Pump house
Water tanl
Water proof
to flat roof
Below
Ground level
cable trench
Power supply for
pump & lighting
CCTV wiring
system
Pump installation
Sanitary
system for
WC
Wiring for
lighting &
power for
Fire Fighting
control panel
& CCTV
control panel
Zone 1
Main Building
Zone 2
Communication Tower
Zone 3
Guard House
Zone 5
Fire Fighting
Zone 4
Sub Station
MERSING TELECOMMUNICATION COMPLEX
3.1.3 WBS DICTIONARY
WBS dictionary is a document prepared with detailed information about deliverables,
activity, with milestones, dates, resources, costs, quality and time schedule for each
component as descript in the proposed WBS. WBS can be plotted using spread sheet
record WBS element name, provides description of works in that element at a minimum.
A designated field of Statement of Work (SOW) is covered by that WBS element. This
mapping relates the two structures to each other and opens up a lot of capabilities for
understanding how the project is planned, how it is performing and what is the cost.
WBS Dictionary records information’s of the project, not limit to the following:
i. Name of Project and Project Number (if any);
ii. Project Manager Name;
iii. Date & Document Number;
iv. WBS Code;
v. Resources Requirement and Allocation;
vi. Cost Estimation;
vii. Name of the components and work Description;
viii. Quality Need and Acceptance Criteria; and
ix. Due Date.
Figure 3.5 : Typical template of WBS Dictionary
27
MERSING TELECOMMUNICATION COMPLEX
Source : Adopted from Google Search
Table 3.1 shows Proposed WBS Dictionary for Mersing Telecommunication Complex
derived from the Bill of Quantity (BQ).
Table 3.1 : WBS Dictionary for Mersing Project
Source: Derived from this research paper
3.1.4: SCOPE BASELINE
Scope baseline consist of :
i. Work Breakdown Structure (WBS );
ii. Work Breakdown Structure Dictionary; and
iii. Scope statement.
We have cover WBS and WBS Dictionary on 3.1.2 and 3.1.3 respectively. For Scope
statement we have make a check list derived from 3.1.1: Scope Structure (SOW ). This
check list is useful for final inspection of the deliverable during the close out stage and it is
enclosed in Appendix 4.
28
MERSING TELECOMMUNICATION COMPLEX
Project Scope deals with the specific requirements or deliverable task to complete the
project. Scope is important to manage on any project, if Project Manager cannot control
the scope of the project; it is not likely to deliver the project on time and within budget!.
Stakeholder’s expectation to the project play a key factor in managing and establishing
scope Stakeholders can often have new demands, e.g. that the requires to alter design
during the course of project, and Project Manager needs to be able to assuage their
expectations. This can especially be the case in long term projects where there might be
new stakeholders introduced in the middle of the project.
In order to accommodate the requests of stakeholders, and new demands that arrive
naturally as projects unfold, Project Manager needs to be able to manage change. This can
include managing change requests. When managing change requests, be sure to
accommodate those that are necessary to achieve project goals and deliverables.
These scope management steps are all essential because the amount of time take for each
task requires is critical and effecting the Quality and Cost of the Project. In turn it will
impact the cost and whole schedule of the Project.
3.1.5 PROJECT GENERAL ASSUMPTION
The general assumption of the Project is to complete the project in time, within budget and
will not change for the whole duration of Project. PMBOK advocates that Project
assumption is a factor in Planning Process that is considered to be true, real or certain after
without any proof or demonstration. Assumption 2 extreme answers – true or not true. The
one assumption turns out to be not true, and this change can impact the Project decisions,
estimation and the designs. Assumptions play an important role in developing the risk
management plan. Therefore, as a project manager you must collect and identify as many
as assumptions you can. It will assist you in developing a sound risk management plan
29
MERSING TELECOMMUNICATION COMPLEX
This PMP makes a few assumptions for Mersing Telecommunication Complex:
i. Weather during North East Monsoon will start at end of November and stop around
January next year. The assumption references to the meteorological report. Extra
time allowance for works and tasks during that period will be lengthened;
ii. Due to site constrain, there is a school nearby, Project schedules and stop the
external operating activities during the school break time period to avoiding jam up
the traffic and post hazard to the passer-by;
iii. The budget of the project has been allocated and the fund was tabled during the last
TM general meeting and approval was given to commence work at the earliest date
possible. Hence the design plans have to be ready before commencement;
iv. Assume that relevant stakeholders will support the Project throughout the whole
duration of the Project;
v. Consultants have submitted Plans to Authorities for approval and follow up action
to speed up the approval; and
vi. There is provisional sum and NSC sum reserved for any changes or unforeseen
occurrence for the Project.
3.1.6 PROJECT CONSTRAIN
The Constrains as defined by PMI, are non-other than Project Scope, Time and Cost.
Quality of works must not be sacrificed when any constrain is being altered. Thus the
Cost
The
financial
30
MERSING TELECOMMUNICATION COMPLEX
commitment of the project is dependent on several
variables. There are the resources involved, from
materials to people, which include labour, plant and
machineries costs. There are other outside forces that
can impact a project, which must be considered in the
cost of the work.
Figure 3.6: Project Triple Constraint (source; PMI)
Source: Adopted from PMI
There are also the fixed and variable costs inherent in any project.. This can seriously
come into play with the use of contract workers or outsourcing, for example sub contract
some portion of works to sub contractor.
Cost processes include cost estimating to figure out the needed financial commitment for
all resources necessary to complete the job. Cost budgeting creates a cost baseline. Cost
control works to manage the fluctuation of costs throughout the project.
There are several methods for estimating project cost:
i. Historic Data: Using the costs of passed projects for comparison;
ii. Resource Costs: Determining the rate of cost for goods and labour by unit;
iii. Bottom Up: Estimating from the lowest- to the highest- level work package;
iv. Parametric: Measure statistical relationship between historic data and other
variables;
v. Vendor Bid: Average of some vendor bids on supply;
vi. Reserve: Aggregate cost of activities; and
vii. Quality Analysis: Estimate cost of highest quality for activities.
Cost is one of the more complicated points on the Triple Constraint triangle. To ensure that
the estimated rates are as accurate as possible, it’s recommended to use project
management tools to calculate the cost variances.
31
MERSING TELECOMMUNICATION COMPLEX
3.1.7 TIME
The schedule is the estimation of time allotted to each task in order to complete the project,
or producing the deliverable. The first step is to derive all the necessary tasks from the start
to the finish of the project. A Work Breakdown Structure (WBS) is used to take the large
project goal and break it down into a series of more manageable tasks. These tasks are then
prioritized, dependencies are linked, and then placed on a timeline. The Project Schedule is
drawn using Gantt Chart, and determine duration for each task. Passed Project data can be
referring for accurate estimation.
According to the Project Management Body of Knowledge (PMBOK), the schedule can be
managed through a process of time management. Those steps are as follows:
i. Plan Schedule Management: Creating policies, procedures and documentation for
planning, executing and monitoring the project schedule;
ii. Define Activities: Identifying and documenting what actions must be done to
produce the project deliverables;
iii. Sequence Activities: Identifying and documenting the logical order of work to be
most efficient;
iv. Estimate Activity Resources: What type and how many materials, people,
equipment, supplies, etc. are needed to perform each activity;
v. Estimate Activity Durations: How long will it take to complete each activity with
the resources allocated;
vi. Develop Schedule: Analyse activity, duration, resources and timeline to develop a
schedule. Useful tool to assist in scheduling is Microsoft Project Software; and
vii. Control Schedule: Comparing planned schedule to actual progress to determine that
the project is on track.
3.1.8 `PROJECT SUCCESS FACTORS
32
MERSING TELECOMMUNICATION COMPLEX
The community of Mersing have long waiting for the upgrade of the telecommunication
system. There is no return but to go all out to make the Project success. The brainstorming
section has identified the Factors which will affect the Success of the Project.
i. The full commitment from the team member, owner, and all stakeholders is
important factors governing the success of the Project;
ii. Quality assurance;
iii. Proper project planning;
iv. Practice good communication; and
v. Work within budget.
3.2 COST MANAGEMENT
The Cost Management is the process to ensure the project is completed within the
approved budget ( PMBOK 2017 ). The Cost management sets a baseline for Project Cost,
where Project Manager is governed by this baseline for their decision and direction when
managing Project cost. Project Cost Management includes activities and tools assisting
Project Manager to complete the Project within the approved budget.
33
MERSING TELECOMMUNICATION COMPLEX
Figure 3.7: Project Cost Management Overview
Source: Adopted from PMBOK 6th Edition.
3.2.1 RESOURCES PLANNING
In the initial phase of a project the required resources to complete the project activities
need to be defined. Work Breakdown Structures (WBS) and historical information of
comparable projects can be used to define which physical resources are needed. The
required for time, material, labour, equipment, etc. Once the resource types and
quantities are known the associated costs can be determined.
Our team of Quantity Surveyor works on the taking off works quantity, using Work
Breakdown Structures to define the physical resources required, e.g. time, material, labour
34
MERSING TELECOMMUNICATION COMPLEX
and equipment to complete the proposed project, and has determined the baseline of cost
estimation.
3.2.2 ESTABLISH PROJECT COST BASELINE
Several cost estimating methods
can be applied to predict how much it will cost to
perform the project activities. The choice for the estimation method depends on the level
of information available. Analogous estimating using the actual cost of previous or
similar projects can serve as a basis for estimating the current project. Another option is
to use parametric models
in which the project characteristics are mathematically
represented. Estimates can be refined when more information becomes available during
the course of a project. Eventually this results in a detailed unit cost estimate with a high
accuracy. Remaining uncertainties in estimates that will likely result in additional cost
can be covered by reserving cost (e.g. using escalation and contingencies).
The cost estimate together with project schedule form the input for cost budgeting. The
budget gives an overview of the periodic and total costs of the project. The cost estimates
define the cost of each work package or activity, whereas the budget allocates the costs
over the time period when the cost will be incurred. A cost baseline is an approved time-
phased budget that is used as a starting point to measure actual performance of project’s
progress.
Table 3.2. : Estimated Project Cost Baseline
35
MERSING TELECOMMUNICATION COMPLEX
Source: Derived from this research paper
As for the Proposed Project the estimation of the project Tendered cost as appended
below:
Table 3.3: Project Budget versus contract sum
Source: Derived from this research paper
Cost budget (baseline) is the estimated cost budget of the project which is approved by the
company before the Project tendering exercise.
36
MERSING TELECOMMUNICATION COMPLEX
The comparison Budget versus Timeline as shows below:
Figure 3.8: Histogram showing Tender Price Compare to Budget Baseline
Source: Derived from this research paper
The main budgeted cost is the Main Building at Zone 1, its recorded 74.91% of the
total budget price. It is due to this Main Building is designed to house the sophisticated
telecommunication equipment. Therefore lots of facilities focus on the main building,
especially the installation of air condition system, raised floor system and back up battery
room for emergency use.
Figure 3.9 shows the cost weightage by using pie chart.
37
MERSING TELECOMMUNICATION COMPLEX
Figure 3.9 : Pie Chart shows the weightage of the budget cost.
Source : Derived from this research paper
38
MERSING TELECOMMUNICATION COMPLEX
Figure 3.10: Histogram showing Budget versus Timeline
Source: Derived from this research paper
Figure 3.11: Mersing Project S-Curve
Source: Derived from this research paper
Table 3.4: Comparison of Tender Price and Baseline Budget
Source: Derive from this research paper
39
MERSING TELECOMMUNICATION COMPLEX
3.2.3 PROJECT BUDGET ( HIGH LEVEL)
Table 3.5: High Level Budget for Mersing Project
Source: Derived from this research paper
The high level Project Budget consist of :
i. Labour costs;
ii. Material costs; and
iii. Non-labour costs.
The high-level; budget provides the Project Sponsor and estimate of the total
expenditures expected for the project and allocate fund to support the project. A high-
level budget is a summary of estimated costs to complete the high-level project
milestones.
The proposed project expected to profit of 19.16% at the value of RM16,087,300.00.
The profit level is slightly lower than 20%, for any changes and risk arises will has
impact on the profitability. Project Management Consultant has to monitor and tracking
the project closely not to go off the schedule, budget and eliminate any possible ricks.
40
MERSING TELECOMMUNICATION COMPLEX
There are some reserved fund to take care of unexpected risks and changes. This sum is
useful when in need, and the expenses for change and risk will eat into the budgeted
profit.
3.2.4 COST BUDGET AND CONTINGENCY FOR RISKS
The PMC estimate some fund for any unforeseen Risks. It is due to unknown possible
problem or any need to alter plan or perhaps some change of environmental requirement,
any little change may affect the cost, the time of completion of project. Therefore
allocation for the contingency sum of RM8 million is located as provisional sum. Any
alteration of work or additional work can be taking care of. It is about 10 per cent of the
total budget sum. On top the provisional sum an allocation of RM3.5 million as sum for
Nominated Sub Contractor (NSC) is allocated if there is in need to employ other
contractor or special contract to take care of specialised to and unexpected task. So the
total allocation as contingency of the project is about close to 13.70 per cent of the total
budget price as show in Table 3.6. The allowance of anything below 10% for
contingency is a bad budget.
Table 3.6: Mersing Project Cost Contingency Plan
41
MERSING TELECOMMUNICATION COMPLEX
Source: Derived from this research paper
3.2.5 COST CONTROL
Cost control is concerned with measuring variances from the cost baseline and taking
effective corrective action to achieve minimum costs. Procedures are applied to monitor
expenditures and performance against the progress of a project. All changes to the cost
baseline need to be recorded and the expected final total costs are continuously
forecasted. When actual cost information becomes available an important part of cost
control
is to explain what is causing the variance from the cost baseline. Based on this
analysis, corrective action might be required to avoid cost overruns.
Dedicated cost control software
tools can be valuable to define cost control procedures,
track and approve changes and apply analysis. Furthermore, reporting can be enhanced
and simplified which makes it easier to inform all stakeholders involved in the project.
Projects are updating the project cost estimates, monitoring the costs of the project,
controlling the project costs, calculating and releasing specific contingencies, calculating
42
MERSING TELECOMMUNICATION COMPLEX
the margins and analysing profitability. The most important challenges based on our
empirical study are the following:
Due to uniqueness of each project there is no accurate information for pricing and setting
up appropriate contingencies in the sales phase. For example, cost of purchasing unique
services is difficult to estimate. Prices of resources can vary during a long project, which
causes problems for estimating costs. In complex projects, there are more project
management and integration engineering costs, which are more difficult to calculate that
product costs. Numerous legal entities require their own margin calculation.
Profitability of the project is difficult to calculate and requires well-designed transfer
pricing when project is implemented in several independent business units. If the project
size is large as compared to parent organization, cost overruns may results financial
challenges to parent organization.
3.2.6 CHANGE BUDGET ALLOCATED
High uncertainty leads to large contingencies. Multiple contingencies are related to the
different WBSs, so perceiving the total value of the contingencies is challenging. Long-
term and high-value projects require the use of the percentage of completion (POC)-
method. This requires the use of the recognition of accrued revenue, which leads to
contingencies having to be released during the project. There are two stakeholders, the
owner of the project and authority will cause change of project planning or statutory
change of bylaw. A contingency sum is reserved to take care of this kind of change.
Usually change made by the owner, it is fair to claim from the owner, since the final design
plan was tabled for the client approval, and the design of the facilities is in accordant to the
requirement of the client needs. Where change made by the authority is something not
likely to happen. Since the by law and those requirements are all set and proven to be
acceptable. Therefore the contingency sum usually will not be use, unless un-avoided
circumstances a raised.
43
MERSING TELECOMMUNICATION COMPLEX
3.3 SCHEDULE ( TIME ) MANAGEMENT
Schedule or Time Management is the document record the allocation of 3 main items:
i. What to do?
ii. When to do and take how long to do it? And
iii. Who to do it?
The Project is break down into deliverables tasks, and it can be sub divided into many
smaller tasks. Each smaller task cannot start work until other related track has completed
the work or near to complete the task. The dependency of tacks will be reflected in the
schedule. This Dependency linkage of tasks formed the longest time period to complete
the Project as termed Critical Path.
Each has the man hour or machining time to complete the task, the working hour time the
quantity of task is the time taken to complete the task. E.g. plastering of wall, skill craft
man can plaster 80 sq. meter of wall. If the total wall area is 800 sq. meters, then his team
of 3men (craft man plus two helpers) can complete plastering wall in 10 days.
44
MERSING TELECOMMUNICATION COMPLEX
There are other researchers have made up the full working time for every task and trade.
With the BQ, it is easy to work out the time sheet of each task and trade. As plotting the
schedule, it is much easier by using Microsoft Project.
Figure 3.12 : Plan Schedule Management: inputs, Tools & Techniques, and Outputs
Source : Adopted from PMBOK 6th Edition (2017)
3.3.1 THE PROJECT SCHEDULE
The main activities of Mersing Telecommunication Complex are focus on Zone 1, where it
is going to house the sophisticated equipment and the networking. Every stages of
construction of the building works are the milestone of the project. The total time taken to
construct the building will be the critical path of this project. The construction time for
auxiliary buildings and steel tower can easily fit during the construction period of 30
months.
Table 3.7, Appended the written critical path planning for Mersing Telecommunication
Complex. It important to work within the time frame, because the telecommunication
equipment delivery time is fixed to this time table mile stone (Refer to Appendix 7:
Schedule Mile Stone – Critical). The sophisticated equipment are not allow to store under
weather condition, especially in Mersing, where the sea is close by and the salty
atmosphere will damage the equipment.
45
MERSING TELECOMMUNICATION COMPLEX
Table 3.7: Critical Path Table
46
MERSING TELECOMMUNICATION COMPLEX
47
MERSING TELECOMMUNICATION COMPLEX
Source: Derived from this research paper
3.3.2 THE GANTT CHART SCHEDULE
The schedule of the project as per the critical path table is drafted into Gantt chart as
follow:
48
MERSING TELECOMMUNICATION COMPLEX
Figure 3.13 The Gantt Chart schedule
Source: Derived from this research paper
49
MERSING TELECOMMUNICATION COMPLEX
From the Gantt Chart schedule, the fabrication of steel tower member will start as early as
after confirmation of fabrication purchase order was made. The installation or erection of
the steel tower will commence after the concrete foundation gain the full strength. The
time taken will be longer since test and commission is carryout stage by stage. A checklist
of test and commission is enclosed in Appendix 3 & 4. The process is essential at the stage
of handing over the plant and equipment.
The work force of the site head count from 5 persons during the piling stage, it gradually
increase to the highest number of 60 workers. Figure 3.14 shows the distribution of work
force.
Figure 3.14: The Human Resources distribution for Mersing Project
Source: Derived from this research paper
50
MERSING TELECOMMUNICATION COMPLEX
3.4 STAKEHOLDER MANAGEM,ENT
The stakeholder of the project include internal and external stakeholder. The identifying
stake holder for any given project as per the figure shows:
Figure 3.15: General Identifying Stakeholder
Source: Adopted from Google search
51
MERSING TELECOMMUNICATION COMPLEX
3.4.1 IDENTIFY KEY PROJECT STAKEHOLDER
Although the project of Mersing Telecommunication Complex is a small project, but the
key project stakeholders are similar to any other Project. Solaris Sdn Bhd has identified
the following key project Stakeholder as shown in Figure 3.16:
Figure 3.16: Potential Key Stakeholder for Mersing Project.
Source: Derived from this research paper
The Internal stakeholders
i. Board of Directors: Solaris Sdn. Bhd. Board of Directors are the owner of the
company, their interest mainly focus on the profitability of the company. The
project undertake by the company would bring in revenue to the company, so it is
a concern for Board of Directors to be of interest towards the Project’s Progress;
ii. Managers and Project Manager: Manager and Project Manager are the key
Management personnel who manage the Project. Their main concern is the success
of the Project.
iii. Project Team: The key and direct participant of the Project. The success of project
means the yardstick of their capability of managing the Project; and
iv. Project Coordinator: Staff coordinates to all party internally as well as externally,
especially with the local authorities. Project Coordinator’s responsibility is to
Getting approval on drawings and designs prior to commencement of Work.
During the Close Out, he will arrange for authorities’ inspection and getting the
final certification of fitness etc.
The External stakeholders
52
MERSING TELECOMMUNICATION COMPLEX
i. Suppliers for materials and equipment: Building material supplier, ready mix
vendor, excavator & crane vendors;
ii. Sub-Contractor for all trades: Sub-con on building work, Brick layer, plasterer and
concreter. Sub-con for electricity wiring and plumbing;
iii. Local authorities, Bomba, Town council, Health etc.;
iv. Creditor or Banker;
v. Consultant, Engineer, Architect, QS & Surveyor;
vi. TM the owner;
vii. Community, People of Mersing;
viii. The customer of TM (End users);
ix. The neighbouring school; and
x. The NGO.
3.4.2 STAKEHOLDER ANALYSIS
The process of brainstorming, collecting and understanding quantitative and qualitative
information of potential stakeholder and determine whose interest should by mitigate,
communicate with them and monitor them throughout the whole duration of the project.
i. To identify, recognize and acknowledge the potential stakeholder;
ii. To access the likely action & reaction of stakeholder project situation;
iii. To determine the stakeholders’ influence and interest; and
iv. To establish strategy and plan to communicate and mange with project stakeholder.
Figure 3.17: Stakeholder Analysis for Mersing Project
53
MERSING TELECOMMUNICATION COMPLEX
Source: Derived from this research paper
(additional info on appendix 8)
High Power, less interested people (Keep Satisfied): The Sub-cons, Suppliers and Local
Authorities are the people need to keep them satisfied;
High Power, highly interested people (Manage Closely): fully engage these people and
make the greatest efforts to satisfy them, they are the owner and company board of
Directors;
Low Power, highly interested people (Keep informed): Provide sufficient information
for these people. Dialog with them so as no major issues arises;
Low Power, less interested people (Monitor): Monitor these people, sufficient
communication will keep them happy.
3.4.3: STRATEGY TO DEAL WITH PROJECT STAKEHOLDER
i. TM Bhd. is the Project Owner, and Board of Directors they are the key player of
the project, the highly interested and high power bodies and both has the say in the
project and with great interest of the project success. Engage and consult
regularly.
ii. The Suppliers, the sub-con and local authorities. They are of High power and less
interest group:- To meet their needs. Engage & consult on interest area. Try to
increase level of interest and aim to move into the next level of higher
interested group.
iii. The Project Team:- General communication, memo. Try to increase their level
of interest and aim to move into the next level of higher interested group.
54
MERSING TELECOMMUNICATION COMPLEX
iv. The Creditor, User or customer, NGO:- Show consideration. Keep them
informed & consult on their interest area. They are the potential supporters
and goodwill ambassador.
Figure 3.18: Stakeholder Analysis
Source: Adopted from Google search
3.4.4 STAKEHOLDER ENGAGEMENT PLAN
Stakeholder Engagement Management is the process of communicating and working with
stakeholders to meet their needs and expectations, and to address issues as they occur.
Stakeholder Engagement Management, the process of systematically foster appropriate
stakeholder engagement in project activities throughout the life of the project. The key
benefit of this process is to allow the Project Manager to increase support and minimize
resistance from stakeholders, significantly increasing the chances to achieve project
success (PMBOK 5th Edition).
To effectively manage stakeholder engagement, the Mersing Project will utilize the
Communication Plan and strategies identified the stakeholder and communicate with them
on project related information in a proactive and timely manner. Leveraging the
information provided in the Communication Plan (i.e., stakeholder groups, communication
items, purpose, method of communication, and frequency), the project will have the ability
to increase support and minimize stakeholder resistance throughout the life of the project.
Managing stakeholder engagement helps to increase the probability of project success by
ensuring that stakeholders clearly understand the project goals, objectives, benefits, and
risks.
55
MERSING TELECOMMUNICATION COMPLEX
In line with the analysis above, the project team will be actively listening and soliciting
input and feedback to make sure that communications are being received and understood
by targeted stakeholder. The feedback captures important information to help making
necessary adjustments and to respond to any problem areas.
3.5 Risk Management
Risk Management is the systematic process of identifying, analysing, and responding to
project risk. It also includes maximizing the probability and consequences of positive
events and minimizing the probability and consequences of adverse events to project
objectives ( PMBOK 6 ). The effect of uncertainty on objective as defined by ISO 31000
(2009).
3.5.1 Project Risk register
As defined by ISO 73:2009 a risk register to be a “Record of information about
identified risks”. A Risk Register can contain many different items. There are
recommendations for Risk Register content made by the Project Management
Institute Body of Knowledge (PMBOK) and PRINCE2.
A typical risk register contains:
i. A risk category to group similar risks;
ii. The risk breakdown structure identification number;
iii. A brief description or name of the risk to make the risk easy to discuss;
iv. The impact (or consequence) if event actually occurs rated on an integer scale;
v. The probability or likelihood of its occurrence rated on an integer scale;
vi. The Risk Score (or Risk Rating) is the multiplication of Probability and Impact and
is often used to rank the risks; and
vii. Common mitigation steps are Identify, Analyze, Plan Response, Monitor and
Control.
56
MERSING TELECOMMUNICATION COMPLEX
3.5.2 RISK MATRIX
Figure 3.19: Risk Assessment Matrix for Mersing Project
Source: Adopted from Google search
To determine the Risk, Project Team have to sit down, brainstorming and list down the
potential risks. The risk register is compute red as table below:
Table 3.8: Risk Register for Mersing Project
57
MERSING TELECOMMUNICATION COMPLEX
Source: Derived from this research paper
From the table 3.8 above, we plotted the Risk Register Number into the Risk Matrix, the
result as follow:
Figure 3.20: Distribution of Risk intensity
Source: Adopted from Google search
58
MERSING TELECOMMUNICATION COMPLEX
Risk 1 and 10 are the two most critical risks. Risk 2, 3and 9 are less critical but still is on
the high side. Risk 4, 5, 6, 7 and 8 are of medium risk.
Table 3.9: Risk Response Strategy on Negative Risks and Threats
Risk Response
(negative /
threat)
Detail Description
Avoid A risk response strategy whereby the project team acts to eliminate the
threat or protect the project from the impact. It involves the removal of
tasks that contain the risk from the project or utilized alternative
means.
change the project scope, resources, time impact. This is the easiest
way of removing risk from a project.
Source: Derived from this research paper
Table 3.10: Risk Response Strategy for Positive Risks or Opportunities
Risk Response
(positive /
opportunities)
Detail Description
Exploit This strategy seeks to eliminate the uncertainty associated with a
particular upside risk by ensuring the opportunity definitely happens.
Source: Derived from this research paper
3.5.3 RISK RESPONSE STRATEGY
Table 3.11: Risk Response Strategy on Negative Risks for Mersing Project
59
MERSING TELECOMMUNICATION COMPLEX
Source: Derived from this research paper
3.6 Communications Management
The Communication Management that details the specific communication products,
events, recipients, timelines, frequency and other pertinent communications information.
Project Management deliverables can be considered principal communications tools.
The objective of the Communications Management process are:
i. To define the stakeholders communications needs of the project;
ii. To conduct stakeholder analysis and identify stakeholders, their roles in the project,
and develop stakeholder management plan;
60
MERSING TELECOMMUNICATION COMPLEX
iii. To define required messages, appropriate media and channels, task assignments
and timings for communications delivery that will allow project to meet those
needs; and
iv. To ensure that “ The right people receive the right information at the right time to
meet their needs and to achieve project objectives”.
The Communications Management Process is a set of steps taken every time formal
communications are undertaken in and organisation. It helps to ensure the project
stakeholders are kept regularly informed. By using the Communications Management
Process will ensure that no miscommunication occurs, can communicate effectively and
able to receive feedback and improve future communications.
Effective Communications to all level and all stakeholders of the project is essential and is
part and parcel of the Project Management tool and the road to success. Any miss
communications will lead to miss understanding; the message will not be passed on, that is
to say no action to carry out the tasks.
3.6.1 COMMUNICATION MANAGEMENT PROCESS
61
MERSING TELECOMMUNICATION COMPLEX
Figure 3.21: Flow chart of Communications Management Process
Source: Adopted from Project Communication Handbook (2007)
The Mersing Project Communication Plan as shows in Table 3.5.1 in which is tight back to
the Stakeholder engagement plan.
62
MERSING TELECOMMUNICATION COMPLEX
3.6.2 COMMUNICATION MATRIX
Table 3.12: Communication Matrix for Mersing Project


 

 

 







!
"
 #
#$
"
 $
$
 $
$
%
&$$

'($
$$ $

)$'


)

($$
 $
$
#
*
"

+
!$!)
,$-
$


$,

$
$
"

)


#
.
/
*
"

0&

$


$,

"


1

#

#
*
"

&$

Source: Derived from this research paper
According to PMBOK, sources of information typically used to identify the define
project communication requirements include, but are not limited to:
i. Project Management Organization charts;
ii. Define Disciplines, departments and specialties involved in the project;
iii. Internal information needs;
iv. External information needs;
v. Project organization and stakeholder responsibility relationships;
vi. Logistics of how many persons will be involved with the project and at which
Locations; and
vii. Stakeholder information and communication requirements from within the
stakeholder register.
63
MERSING TELECOMMUNICATION COMPLEX
Communication Methods available:-
i. Interactive communication : Meetings, phone calls, instant messaging,
video conferencing
ii. Push Communication : Letters, memos, reports, emails, faxes, voice
mails, blogs, press releases
iii. Pull Communication : Intranet sites, e-learning, lessons learned
Databases, knowledge repositories
3.6.3 Project Communication Governance
Project governance is a critical element of any project since the accountabilities and
responsibilities associated with an organization’s business as usual activities are laid
down in their organizational governance arrangements. The role of Project Governance
is to provide a decision making framework that is logical, robust and repeatable to govern
an organization activities, and Project change.
The decision making framework is supported by three pillars.
1st pillar : Structure, the governance committee structure or Project Board or Project
Steering Committee. It may include key stakeholder. This will form a
portfolio decision making group. The Policy and procedural documentation
laid down the decision rights of all these committees member and how they
are related.
2nd pillar : People. Project Management is to manage people and the effective way of
managing people is through dialog , that is communication.
64
MERSING TELECOMMUNICATION COMPLEX
3.7 PROCUREMENT MANAGEMENT
3.7.1 COMPANY PROCUREMENT POLICY
The company has set up policy (refer Appendix 9) on procurement with the following
objectives;
i. To establish standard policies, procedures and guidelines for reference in
conducting procurement activities within the Company;
ii. To comply with the spirit of Corporate Governance in respect of procurement
processes;
iii. To ensure that procurement of works, services, supply and acquiring professional
services is obtained at a reasonable price, in economic quantity, high quality and
timely delivery;
iv. To provide relevant supporting document at all stages of procurement process
framework; and
v. To ensure that Solaris Sdn. Bhd.’s procurements are obtained at best value and
awarded only to the contractors, suppliers or service providers who offer the best
contract package in terms of cost, service level and quality.
The Company Procurement Policy is attached in the Appendix 1. For Contractor and sub-
con there are various standard form of contract, namely:
% PAM Standard Form of Contract , 2006(With or without Quantity);
% CIDB Conditions of Contract (refer to Appendix 10); and
iii. JKR Standard form of contract for building works 2000.
Above mentioned Standard form of contract are attached in the Appendix.
For the Mersing Telecommunication Complex, the client (TM Bhd.) agreed with the
proposal made by Solaris Sdn. Bhd. to use CIDB Standard Form of Contract ( With
Quantity ). It is due this project mainly concerned with Building Works.
65
MERSING TELECOMMUNICATION COMPLEX
3.7.2 General Statement for Procurement Management
Procurement Management is a process and planning to establish and maintain relationships
with the supplier, sub-con and vendors of goods and services throughout the project life
cycle. It is also an essential part of supply chain management.
Procurement Management consist of 4 major processes:
i. Planning Process
The creation of official procurement management plan. The Management has to
decide the mode of procuring, which item by internal sourcing and others
externally outsourced. The mode of procuring will impact the project’s budget and
financial scope. Next step will be preparing procurement documents and draw out
frameworks for vendor and sub-con selection;
ii. Selection Process
Suppliers and sub-con will be informed to participate in the bidding process. The
process of comparing and contrasting suppliers’ and sub-con’s advantages,
disadvantages, and their contractual offerings. Vendors’ proposals are carefully
evaluated and decision of awarding the successful bidders through collaborations
of various committee members;
iii. Administration Process
The administration phase results in the continual creation of procurement
documents and spreadsheets that may drive project changes. A centralized system
of contract change monitoring and control will be used to evaluate and determine
whether potential changes to contracts are needed. There are formal physical
inspections, internal audits and reviews of procurement operations in order to
generate synthesized performance reports that provide real-time feedback; and
iv. Closing Process and hand over of project.
The closing process isn’t just about ending procurement contracts; it’s about noting
weaknesses, documenting successful processes and summarizing the project for future
needs. Some companies prefer to conduct simple audits using performance matrices in
order to grade the overall project. Documentation is important for future projects, which
may involve entirely different teams in new locations. During the closing process,
66
MERSING TELECOMMUNICATION COMPLEX
negotiations may be necessary to resolve contract disputes. Ideally, potential issues will be
noted during the administration process in order to begin the mediation process.
For Mersing Project, CIDB Standard Forms of contract (With Quantity) is used (refer to
Appendix 10). The same Standard Forms of contract also used for the suppliers of
materials and Sub-con (refer to Appendix 11).
3.7.3 Procurement Risk Policy
The process of risk management involves a cycle of identifying risks, evaluating their
potential consequences and determining the most effective methods of responding to them.
This means reducing the chances of their occurrence and reducing their impact if they do
occur.
Appropriate procedures are in place to identify and assess all relevant risks throughout the
procurement cycle. As a general principle, risks should be borne by the party best placed to
manage them. While a detailed exposition of risk assessment and management is beyond
the scope of these guidelines, typically, risk will impact the project at different stages and
it should be addressed appropriately as follows:
i. Project risk. This encompasses risk to the project from the inadequate definition or
assessment of the need, scope, scale and financing of the project. These should be
addressed in the business case;
ii. Process risk. This is risk resulting from an inadequate knowledge of national
procurement policy and law and from incorrectly or inadequately carrying out a
procurement procedure. Process risk is addressed by adhering to these guidelines
and to the other documents referenced herein;
iii. Relationship risk. This is risk resulting from inadequate relationships with the contract
holder and the implementation of the project. It is addressed by the contract, the
project management plan, project management procedures and by review
procedures (e.g. mid-term review, independent peer review, etc.);
67
MERSING TELECOMMUNICATION COMPLEX
iv. Termination risk. This is risk resulting from inadequate definition of project
boundaries, of ‘project creep. It is addressed by having a business case that
specifies the scope of the project; a contract that states how and when project
change can occur; by change management procedures.
Procurement has the potential to Create Many Risks. It may due to
i. misinterpretation of user needs;
ii. inadequate statement of requirements;
iii. fail to identify potential sources;
iv. impractical timeframe;
v. no response from known quality suppliers;
vi. selecting an inappropriate supplier; and
vii. Ineffective contract management.
3.8 Transition Management / Close Out
3.8.1 Handover of project.
68
MERSING TELECOMMUNICATION COMPLEX
This is the stage when all project team are looking forwards to. The stage of handing over
the project means the stakeholders or owner of the project is accepting the quality
specifications of the project. In order to make the handover goes smoothly, there are
documentation of criteria of performance well-kept and documented from the beginning of
the project. This information should be documented in the project management plan,
which include all changes requested throughout the life cycle of the project.
The project may not be complete or handover to the owner if the following process or
documents were not included, but not limited to:
i. Obtain acceptance from customer to formalize close process for the project or
phase;
ii. Full set of as-built drawing;
iii. Final project report;
iv. Provision of training to operate facility;
v. Update risk and work register;
vi. Settle all invoices;
vii. Full documentation on facility warranties and guarantees;
viii. Complete set of M & E operating manual;
ix. Contract final account; and
x. Documentation on lessons learned.
Project Close-Out Process
i. Declaration of Works Completion
PMC or main contractor after going through the process of inspection on all work
done by Sub-cons’ and suppliers’ deliverable works. Site preparation works for
hand over include make good all defects, site cleaning, demobilization of all plants,
and machineries.
ii. Testing & Commissioning
The testing and commissioning was scheduled in the work time sheet. All testing
and commissioning is carrying out in accordance to the specification and the
requirement. Procedure of test is to carry out to the upmost satisfaction of the
tester, if special professional assistance is required.
iii. Issuance of Interim Certificate of Completion
Upon satisfaction of the full testing & commissioning of the Plant & Equipment
installation, list of building works defect being compiled and agreed to complete
69
MERSING TELECOMMUNICATION COMPLEX
the defect during the defect liability period. Then the certificate of Interim
Completion is Issued.
iv. Application of Certificate of Fitness (CF)
Inspection by relevance Government Departments were arrange, and obtain their
acceptance of the installation in accordance to bylaw. Application for Certificate of
Fitness will be submit with acceptance letter from relevance Departments.
v. From the Project Management record, highlighted alteration of the original drawing
need to be arrest and the complete set of As-Build-Drawing + Hand book +
operating manual + warranty certificates will be compiled. Endorsed As-Built-
Drawing will be submitted 3 months after the issuance of interim certificate of
completion.
vi. Defect Liability Period
The remedial work for defect will be carrying out during the Defect Liability
Period. Final inspection will be carrying out at the end of Defect Liability Period.
vii. Final Contract Account
The owner of the project will issue letter of acceptance to indicate the satisfaction
of the project and accept the project without Liquidated Ascertained Damages
(LAD). When there is no delay on works without valid approval, there will not
impose LAD on PMC and sub-con/supplier. So half moiety is withhold by the
client until the full completion of Defect Liability Period. The owner will return
the Performance Bond to PMC and all contractors/supplier.
viii. Handover Project Ceremony
At the moment of obtaining the certificate of fitness from the authority, a formal
“Handover Project Ceremony” will be organized of commendable moment.
Handing over of project can carry out before the final defect liability period end.
3.8.2 Acceptance issue.
Those criteria including performance requirements and essential conditions which must be
met before project deliverables are accepted. Satisfying all acceptance criteria implies that
the needs of the owner have been met. Acceptance criteria were created before beginning
of project activities. Acceptance criteria not only determine whether the project is
successful it also indicates that the project is complete. It is a check list that contains clear
and measurable items that, when complete, mean that the project has delivered the required
result to owner.
70
MERSING TELECOMMUNICATION COMPLEX
Figure 3.22 : Project Close Out check list Template
Source: Adopted from Google search
3.8.3 CLOSE OUT OF SUB-CONTRACTORS/ SUPPLIERS
The close out process is the same as total project close out. Individual Contractor has their
tasks to complete and everyone has their own deliverable checklist. The deliverable check
list document a proof of tasks completion with satisfactory standard. The check list and
suppliers’ work order must be accepted and endorsed by the owner’s representation.
3.8.4 ADMINISTRATION CLOSE-OUT
Solaris Sdn Bhd will send out official notice to inform the suppliers for close out of the
project and the termination of the Purchase Order. If there is balance quantity left from
Purchase Order, and other site may require, then redirecting the supply to the site
mentioned.
The Administration Department has to compile all the work order, Purchase order, Labour
time card, machineries time sheet and provide summary for the account department.
71
MERSING TELECOMMUNICATION COMPLEX
3.8.5 FINAL ACCOUNTS CLOSING
Final statement of account session with all sub-contractors and suppliers to ensure that the
all the tasks in the contract fulfilled and the final account shall include:
i. Adjustment on additional work;
ii. Adjustment on any Liquidated Ascertained Damages;
iii. Adjustment of variation order; and
iv. The agreed retention sum for defect liability period.
Solaris Sdn. Bhd. Has to proceed to Final account with the owner and claim the balance
sum. The same procedure apply to sub-cons and suppliers. There will be retention of half
moiety for the defects liability period (18 months). Upon completion of the defects
liability period and all defects as per defects list were completed satisfactory,
recommendation to release of 2nd moiety.
3.8.6 PROJECT LESSON LEARNED
The learning gained from the process of performing the Project, and the formal conducted
Lessons Learned session will be held during project close-out. This the experiences
distilled from a project that should be actively taken into account in future projects.
Kotnour (1999) said that the project management discipline should embody a framework
of learning. The learning framework will help the project manager accomplish three goals:
i. Deliver a successful project;
ii. Deliver a series of successful projects; and
iii. Build capabilities.
The gained knowledge can be used to train the new staff and sharing of the lesson learned
within the organization can prevent making the same mistake in future.
72
MERSING TELECOMMUNICATION COMPLEX
Figure 3.23: Lesson Learned Life Cycle
Source: Adopted from Google search
Capture the “what went wrong, what was right, what to improved” to be lesson learned for
future improvement. Communicate and collaborate with team member for information’s
and mistakes. Preventing the recurrent of the same mistake and improve own capabilities.
4. CONCLUSION
4.1 Scope Management
Any given project, there are process to carry out and deliverable. The process of doing the
deliverable with scope of works. Project success depends on the pre implementation
Project planning, and one of the crucial part of the planning is Scope Management. On
73
MERSING TELECOMMUNICATION COMPLEX
the Scope Management Planning using WBS to break down the works scope. These action
is helpful for drafting the work schedule, when all tasks are appended. Scope Management
is important as WBS planning will assist in costing too. The list of Task and works break
down will the check list for project close out. Each every task will be inspected and proof
of deliverable. The setting of specification on task is depending on Scope Management
break down list. The Project Scope Management process work on 3 basis elements:
i. Planning: The break down work task and define the work task for the project.
ii. Controlling: The Planning to control , monitor, documenting on scope creep. The
check on change, updating the change, and controlling change.
iii. Closing: The planning of final audit procedures of deliverables and confirm the
work done are in accordance to the specification and quality required.
The Scope Management Planning Statement should include the following:-
i. The overview of the total Project and its final deliverable;
ii. Listing of special requirement for resources or technical support. Advance
arranging specialist schedule to fit in the Project work schedule; and
iii. Arrest the assumptions area which can be a hurdle, and affect the final deliverable.
4.2 Cost Management
It is the costing process of the Project. Cost Management is about estimating cost,
allocation of financial cost, controlling cost, and tracking cost of the Project. Overview of
total budget, provide contingency fund for changes and control the risk of overrun budget.
Calculate the Project cost baseline, monitor the progress spending and control the spending
within the budget.
Cost Planning and estimation process have to be alert and provision of the follow
assumptions to be considered:
i. Be sensitive on Price movement. Any change of unit rate will affect the cost of the
task. A validity period for price offer is one way to protect us from price
fluctuation;
ii. Design change, usually by Owner, then there is possible chance of claim. But if
the design change is due to the change of authorities’ requirement then the
chances of claim is slim. Hence the contingency has to chip in to take care of
the difference;
74
MERSING TELECOMMUNICATION COMPLEX
iii. Cost estimate is more concerned on those items or materials which need to import
from overseas. The exchange rate affecting the unit rate and the delivery time
is not consistence. Special items which need licences, control items and
difficult handling items are some area of concern on price negotiation. Usually
special conditions to be set to protect us from unforeseen circumstances.
Cost Management is a sensitive process, reference to previous or similar project’s lesson
learn is important. Control, tracking and monitoring has to apply throughout the whole
Construction period. Tight control on cost expenditure and work within budget will
ensure profitability, otherwise it will be cost overrun.
4.3 Time ( Schedule ) Management
The Time Management, is how to use the time given by the project. Fit in the work
activity for the project deliverable. By using the Work Breakdown Structure, all task will
be allocated with time frame and resources to complete the task.
Microsoft Project software is available to assist in plotting out the whole schedule of the
project. Pre-set the criteria for the project. E.g. working hour per week, Public holiday,
workers daily wage, and overtime etc. can be set before plotting the schedule.
Schedule is planned to set realistic target of activities, and should be an achievable
schedule. Tracking and control make easy when everyone follow the schedule and work
within cost.
4.4 Stakeholder Management
Project of Big or small, situated in town or outside town, there sure involve with different
level stakeholder. They are internal and external stakeholder. They are important, because
they are influencing, miscommunication with stakeholder will lead to work not move
smoothly, it even affect the progress of work. Therefore it is important to mitigate,
communicate closely, and provide necessary information to respective stakeholder. Keep
them informed and get their support towards the project.
Project Manager has to identify and recognized the key respective stakeholders. He has to
plan strategized dealing with these stakeholders. Properly managed stakeholders will help
and speed up the progress of works and obtained all necessary approvals.
4.5 Risk Management
75
MERSING TELECOMMUNICATION COMPLEX
For every project, there are risks, therefore Project team have to sit down and list out the
possible risks. Register the identified risk, recognised the risk, analyse and quantified risk
and plan the mitigation strategized to overcome the risks and respond to risk.
Risks can be
i. Avoiding or eliminate the risk by other means;
ii. Strategized plan to reduce the effect of risk to the lowest if this risk can not be
avoided or eliminated; and
iii. Plan ahead and arrest the risk before the risk occur, then the damage will be
reduced.
4.6 Communication Management
Communication Management is an important process to bridge people especially
communicating with the stakeholders. Messages clearly relayed to project team members
and stakeholders to inform of what is expected from them, their roles and responsibilities.
Sending messages to well inform of the Project progress and receive feedbacks.
Communication planning is to identify the flow of communication, who should receive
what information and the frequency of passing messages. Information in the form of
project progress report, which will includes but not limit to the following:
i. Brief detail of project;
ii. Project Budget cost and tender cost;
iii. Forecast S curve versus progressive S curve;
iv. Project Schedule and actual progress;
v. Risk registration and the outcome of arresting risk;
vi. Change process and record. Changes may form part of the variation order;
vii. Site photos to show the actual progress; and
viii. Financial outcome. Payment status to contractors, sub-con and suppliers.
4.7 Procurement Management
Procurement management is actually money management. How to conclude the contract;
what type of contract to use; which contract is most suitable for particular contract. In
general Malaysia contract practice using Standard Forms of Contract, which were
established by respective Institutions. Use correct Standard Forms of Contract for the right
contract. For Mersing Project, it is building works, therefore the forms used is from CIDB
76
MERSING TELECOMMUNICATION COMPLEX
Standard Forms of Contract with Quantity. There are other CIDB Standard Forms of
contract specially formulated for sub-cons and suppliers.
4.8 Transition / Close Out
Transition and Close Out is the final process to determine the Project is constructed in
accordance to general good practice and specification set by the standard. The Close Out
take into considerate the follow:
i. Assurance of and agreed upon that all works specified by the drawings have been
completed according to specification and standards;
ii. All materials used are of quality product and test results being compiled for record;
iii. Close out the administration, and record the lesson learn for future reference;
iv. Final account with Owner, all sub-cons and all suppliers. First moiety release and
retention of 2nd moiety until full settlement of maintenance period or Defects
Liability Period (18 months). The list of defects was established during the
commissioning and final inspection period. Final inspection to confirm the
defects are done and completed satisfactory, then only recommending the
release of 2nd moiety.
v. Compile of As Built Drawings, Equipment’s operating manuals, and guarantees as
handing over handbook for the owner safe keeping.
vi. Obtain Certificate of Fitness from the local authorities and to be handed over to the
owner.
vii. Acknowledge letter of appreciation from Owner is important as future job
reference.
5. RECOMMDATION
Mersing Telecommunication Complex is not a big project but the basic requirement are the
same. Prior to site procession, suggest to Solaris Sdn. Bhd. and the sub-com to establish a
check list of what to do and when to do:
i. Site condition and temporary facilities arrangement;
ii. Drawing approval by owner and local authorities;
iii. Application for temporary supply of water and electricity;
77
MERSING TELECOMMUNICATION COMPLEX
iv. Submit start work request to local Municipal. Inform the local Municipal of the
inconvenient and the necessary closure of part of road next to the site during
construction;
v. The cooperation and adhering of all site personal be aware of Site Safety and
Health regulations and upkeep the site with cleanliness and tidiness; and
vi. Overview of the whole project discussion and brainstorming, on areas of important,
the scope of work and schedule, planning of resources, site security matter,
establish line of communication, works Quality expected, and stress the
important of on time completion of task.
78
ATTACHMENT
REFERENCES
Akintoye, A.S., & Macledo,M.J (1997). Risk analysis and management in construction.
Internaltional journal of project management, 15(1), 31-38BC housing. (2012). Guide to
Building Handover - Checklist Companion Documents for : Development Teams,
Owner/Operators, (June2%
Dvir, D., Tsvi Raz & Shenhar, A. (2003). An empirical analysis of the relationship
between project planning and project success. International Journal of Project
Management, 89--95.
Kotnour, T. (1999, June). A learning framework for project management. Project
Management Journal, 30(2), 32-38.$
HILLSON, D. (2002), Extending the risk process to manage opportunities. International
Journal of Project Management, Vol. 20 No 3, pp. 235-240.
Howell, D., Windahl, C., & Seidel, R. (2010). A Project Contingency Framework Based
on Uncertainty and its Consequences. International Journal of Project
Management, 28 (3), 256-264.
Isaac Tetth (Ed.). (2014). Use of Project Management Methods.
ISO/DIS 31000 (2009). Risk management Principles and guidelines on
implementation. International Organization for Standardization.
ISO/IEC Guide 73:2009 (2009). Risk management — Vocabulary. International
Organization for Standardization.
Jugdvev, K., & Muller, R. (2005). A Retrospective Look at our Understanding of Project
Success. Project Management Journal, 36 (4), 19-31.
Office of Project Management Process Improvement. Project Communication
Handbook. 2nd Edition, 2007.
Pinto, J. K., & Slevin, D. P. (1988). Critical Success Factors across the Project Life
Cycle. Project Management Journal, 19(3), 67-75.
Project Management Institute, PMBOK, 6th Edition (2017)
Morris, P. W. G. (1998). Key issues in project management. In J. K. Pinto (ed.),Project
Management Institute Project management handbook.
75
SAUSER, B.J., REILLY, R.R., SHENHAR, A.J. (2009), Why projects fail? How
contingency theory can provide new insights A comparative analysis of NASA’s
Mars Climate Orbiter loss. International Journal of Project Management, Vol. 27
No 7, pp. 665-679.
Thomas, M., Jacques, P. H., Adams, J. R. & Kihneman-Woote, J. (2008). Developing an
effective project: planning and team building combined. Project Management
Journal, 39 (4), 105--113.
Wang, Y.-R. & Gibson, G. E. (2008). A study of preproject planning and project success
using ann and regression models. In The 25th International Symposium on
Automation and Robotics in Construction. ISARC2008 (pp. 688--696).
Appendix List
1. WBS Schedule……………………………….77
2. WBS schedule (conti.)……………………….78
3. Inspection list………………………………..79
4. Close out check list………………………….80
5. Schedule 1……………………………………81
6. Schedule ……………………………………..81
7. Schedule Mile Stone – Critical………………82
8. CIDB Standard Forms of Contract…………..83
9. Procurement Policy…………………………..84 to 90
10. Stakeholder Analysis…………………………91
76
Appendix 1
Appendix 2
77
Appendix 3
78
Appendix 4
79
Appendix 5
80
Appendix 6
Appendix 7
81
Appendix 8
82
Appendix 9
83
SOLARIS SDN. BHD.
PROCUREMENT POLICY
PROCUREMENT OF GOODS
PURPOSE OF PROCUREMENT
The overall purpose of procurement regulations is to ensure that Solaris Sdn. Bhd. gets
the highest quality of desired goods and services at the best price possible. Further, the
regulations are aimed at streamlining the process of procurement while maintaining
adequate controls. These procurement procedures apply to all staff involved in the
procurement process and to all types of procurement.
THE PROCUREMENT COMMITTEE
The Solaris Sdn. Bhd. procurement committee shall be composed of Board of Director,
Managing Director, Finance Officer, and administration representatives. The committee
shall meet when there is need to deliberate on issues pertaining to procurement. The key
terms of reference for the committee shall be to:
i) Award tenders ;
ii) Approve orders;
iii) Award contracts; and
iv) Approve variation of contracts conditions
SEPERATION OF DUTIES
There shall be proper separation of duties between::
i) The person who orders a particular purchase from a vendor;
ii) The person who satisfies that the goods supplied are satisfactory;
iii) The person who accepts goods into store; and
iv) The person who authorizes payment.
PROCUREMENT PLANNING
Procurement planning is part of the annual budgeting process. Each departmental
head is responsible for planning his/her project’s estimated procurement needs on an
84
annual basis through the use of the annual procurement plan (APP), which indicates
the items to be bought in the various quarters of the year. The procurement officer
will use the APP to plan for requisitions. It is crucial that the procurement committee
discuss the APP at the beginning of each year and as need may arise within the year.
The APP will also require the final approval of the project coordinator, who will share
it with the executive director for comments before approval.
PROCUREMENT REQUISITION (PR)
Each specific procurement procedure process shall be initiated by procurement
requisitions to the procurement officer from the requesting department and should
show detailed specifications and 2 requirements for the item(s) being requested. They
should also indicate that the item is budgeted for. The PRs allows the departments
flexibility within the overall annual plans regarding specifications, exact quantities,
delivery dates, etc. They are also used to cater for un-planned or emergency
procurement. The PR form will show the following:
i) Items required.;
ii) Quantities;
iii) Delivery dates and locations;
iv) Accounting information;
v) Whether procurement is within APP/budget or emergency or unplanned;
vi) Signature of the preparing person; and
vii) The departmental head.
Some donors do prescribe some conditions or restrictions required to be observed in
the course of procurement pertaining to the project they fund. It is the responsibility
of the procurement committee to ensure that such donor requirements and restrictions
are observed in the procurement of goods and services but within the framework of
Solaris Sdn. Bhd. procurement guidelines.
All requisitions must be signed by the departmental heads or designate, who should
ensure that the item(s) are in APP or should seek authority to procure as per policy.
Any persons designated to authorize requisitions in acting capacity must have the
authority given in writing clearly stating the period authorized.
85
CONTROLS ON PROCUREMENT
Goods and services will only be procured within approved budgets except in case of
emergencies, which has to be approved by the executive director. Thus, in addition to
being responsible for preparing the APP/budget, the departmental heads should
ensure that actual procurement throughout the year remains within the budget. Each
requisition should reference the APP line bearing the item or requisition and if need,
be attached to the page of the APP where such line is contained.
The financial officer shall assist the procurement officer in conducting periodic
checks on procurement activities to ensure that they conform to APPs, donor
procurement requirements, and Solaris Sdn. Bhd. policies and procedures.
It is the responsibility of the person who signs the local purchase order (LPO) to
verify that the following have been, done whether or not he/she actually collects the
goods concerned.
(i) That the correct quantity has been received and signed;
(ii) That the quality and price of goods is as agreed;
(iii) That all goods delivered have been securely and inventory records
appropriately updated; and
(iv) That the delivery note is checked, signed, and forwarded to the financial
officer to await the invoice.
Purchases under petty cash must not exceed the maximum amount established and
documented by the financial officer.
Procurement staff and all members of the procurement committee will be required to
sign a ‘conflict of interest’ document stating that they will not purchase goods or
services from a company they have a vested interest.
THE PROCUREMENT PROCESS REPORT
Upon receipt of requisitions, the procurement officer will first verify that the
requisition is properly approved according to the signing authority. He/she will then
enter the requisition details into the procurement report worksheet. After this, he/she
will begin the process of sourcing for the goods.
86
The procurement report worksheet is updated to reflect requisition as they are
received. It also includes information on status of each procurement requisition,
complete with expected delivery date. This is to be submitted to projects department
on a monthly analysis.
The procurement officer is required to present a monthly financial and narrative
report on procurement to the executive director, through the administrative assistant
and a copy forwarded to the financial officer.
VENDOR SELECTION
Careful selection of vendors should be done to ensure that best possible price,
quality and delivery time available within the markets is obtained. A list of suitable
vendors (the list of pre-qualified vendors), for each type of goods and services based
on letters of introduction and past performance shall be maintained. This will make
the process of vendor identification much faster. The vendor list shall be reviewed
and updated periodically to ensure that current known factors are taken into
consideration. Once the previous year’s list of vendors has been updated and
approved by the procurement committee, procurement of goods, and services can be
effected. Vendor selection for inclusion on the list of pre-qualified vendors will take
place once per year and will be done by the procurement committee.
VENDOR SELECTION CRITERIA
The following set of criteria is essential for deciding on choice of vendors:
i) Price;
ii) Quality of goods/services. Such a justification must be verifiable;
iii) Availability of goods/services within the required delivery time;
iv) After sale services, including availability of parts/supplies;
v) Bidder’s previous records of performance and service;
vi) Ability of bidder to render satisfactory service in this instance;
vii) Financial stability of the vendor;
viii) Availability of bidder’s representatives to call upon and consult with;
ix) Payment terms;
x) Warranty offered; and
xi) Ability to provide samples.
87
PROCEDURE FOR TENDER
The procurement office and the heads of the various departments may recommend
potential vendors but the selection of those invited will be left to the discretion of
the procurement committee. The procurement officer will send an invitation to
tender to each supplier listed to be invited. The vendors will pick up tender
documents at Solaris Sdn. Bhd. offices specifying the goods and details or any
relevant information needed to get accurate bids. All suppliers must receive the same
information.
USE OF DEALERS AND SOLE SUPPLIERS
In the interest of ensuring quality, reliability and timeliness, the procurement officer
may establish purchase agreements or contracts with main dealers of regularly
purchased goods. Where possible due to other factors, the procurement office will
negotiate rates and discounts with the supplier or a method to determine price for
invoice justification. These agreements and prices (net of discounts) should be
reviewed annually to ensure that they are competitive. LOCAL PURCHASE
ORDERS (LPO) WITH VENDORS
The LPO is a contract with vendors should include all information regarding the
goods and services being procured as well as standard terms of delivery, payment
and arbitration in case of dispute. If contracts are precise and clear, possibilities of
disputes will be reduced and Solaris Sdn. Bhd. will stand far greater chance of
receiving the goods and services as expected. Upon selection of a vendor, a legally
binding contract or work order should be drawn-up for the goods and services in
question and signed by both parties prior to procurement. Detailed specifications;
quantities, unit prices, delivery deadlines, locations, and payment schedules must be
specified in such contracts.
ORDER FOR RECURRING REQUISITION
Procurement of a recurrent nature, i.e. where the same goods and services may be
issued several times a year, one vendor may be selected for a period of up to one
88
year. In some cases, particularly for services, contracts for the goods or services can
be drawn up once, which may then be reference every time those goods or services
are required without requiring separate quotations and contracts on each occasion. In
other cases, particularly for regularly purchased goods, vendors can be selected
once, but separate contracts drawn-up on each occasion the vendors are used.
CERTIFYING DELIVERY OF GOODS AND SERVICES
The procurement process cannot be completed without certification that the goods
and services procured have been received entirely to Solaris Sdn. Bhd. satisfaction,
in particular, to the 5 satisfaction of the requisition. The procedure for receiving
goods and services is therefore important in ensuring that vendors have entirely met
their obligations. Once Solaris Sdn. Bhd. has certified that goods and services have
been received to their satisfaction, it has little further resources to complain about a
vendor’s performance; and payment can then be made.
In all cases, the certification of receipts of goods and services is pre-requisite to
Solaris Sdn. Bhd. and the following guidelines are essential for that purpose.
i. The procurement office should ensure that goods and services are checked
against contracts, waybills, invoices, or delivery notes;
ii. Requisition department at the time of delivery will facilitate the receiving
and checking of goods and services whereby the receiving person will have
to sign the delivery notes or any other documents during delivery;
iii. Physical checking should be done by the requisitioning department and not
by the procurement office;
iv. In some cases, receiving of goods and physical checking of goods or services
may be delegated to other Solaris Sdn. Bhd. officers who are so authorized
by the procurement officer. Such might include cases where goods of
services are delivered directly to a project field location; or where specialists
technical certification is required; and
v. Any differences between documents done physical checks should be noted
and reported to the procurement officer for action.
PAYMENT-PROCESSING PROCEDURE
89
The recipient department is responsible for preparing payment requisition which
then it forwards to the procurement office for checking and certifying. The
document is then sent to the finance department for further checking and necessary
approval and authority to pay. All payments must be made in accordance to the
contractual terms between the vendor and Solaris Sdn. Bhd. and in reference to the
financial policies.
Appendix 10
90
Stakeholders Analysis
91
ResearchGate has not been able to resolve any citations for this publication.
ResearchGate has not been able to resolve any references for this publication.