ArticlePDF Available

Detecting failures in temporary supporting structures used in construction

Authors:

Abstract

The construction industry is significantly more hazardous than most others economic sectors'. Trying to reduce the incidence of construction failures is a continuous process and organizations such as Occupational Safety and Health Administration (OSHA) and others are dedicated to this goal². The European foundation (1991) found that 60% of the accidents it surveyed could have been eliminated, reduced, or avoided with more thought during the design stage³. A study on U.K. construction industry revealed that there is a certain relationship between safety of construction and decisions made in design process regarding the accident causation⁴. Temporary supporting structure fails persistently due to deficient design, substandard materials, worst workmanship, poor supervision, combination of any of these factors. These temporary structures are core support, in the formation of the main frame of the building3.5. Recent studies have shown that these type of failures results in minor to major losses and injuries to human from casualty to fatality5,6. Such failures are not instant and construction crews were unable to identify these failures since these supports are huge in volume⁷. The subject study attempted to design and install a detector to distinguish any deflection on these temporary supporting structures from the time of installation till dismantling on these temporary supporting structures. Further the detection system will notify such deflections to the construction crew for corrective action. © 2018 Structural Engineering Research Centre. All rights reserved.
JOURNAL OF STRUCTURAL ENGINEERING 467
Vol. 45, No. 5, DECEMBER 2018 - JANUARY 2019
Journal of Structural Engineering
Vol. 45, No. 5, December 2018 - January 2019 pp. 467-472 No. 45-SC
Detecting failures in temporary supporting structures used in construction
D. Kamalnataraj*, and V. Ramasamy**
Email: kamalnatarajsgi@gmail.com
*Department of Civil Engineering, Anna University, Chennai - 600 025, INDIA
**Department of Civil Engineering, Adhiparasakthi Engineering College, Melmaruvathur - 603 319, INDIA
Received: 13 May 2016; Accepted: 22 May 2018
The construction industry is signicantly more
hazardous
than most others economic sectors1. Trying
to reduce the incidence of construction failures is
a continuous process and organizations such as
Occupational Safety and Health Administration (OSHA)
and others are dedicated to this goal2. The European
foundation (1991) found that 60% of the accidents
it surveyed could have been eliminated, reduced, or
avoided with more thought during the design stage3. A
study on U.K. construction industry revealed that there
is a certain relationship between safety of construction
and decisions made in design process regarding the
accident causation4.
Temporary supporting structure fails persistently
due to decient design, substandard materials, worst
workmanship, poor supervision, combination of any
of these factors. These temporary structures are core
support in the formation of the main frame of the
building3,5. Recent studies have shown that these type
of failures results in minor to major losses and injuries
to human from casualty to fatality5,6. Such failures
are not instant and construction crews were unable to
identify these failures since these supports are huge
in volume7. The subject study attempted to design
and install a detector to distinguish any deection on
these temporary supporting structures from the time
of installation till dismantling on these temporary
supporting structures. Further the detection system will
notify such deections to the construction crew for
corrective action.
RESEARCH STUDY
General failures on temporary supporting structures
are due to loads which the structure could not bear.
These unexpected loads might cause minor damage to
complete collapse of the supporting frame. Supervising
the erection of each and every support of these structures
is mandatory. Thorough monitoring after installation
is also required. The key factors for these failures are
lack of testing each and every support for their rigidity.
The hesitance of the testing personnel in checking huge
number of supports lead to miserable accidents.
Hence an ideology of design and installation of a
device to detect all type of deection on these temporary
supporting structure and record the same to alert the
construction workers about the potential failures ahead
and urge them for corrective action.
Description of the device
This detector is mainly designed to predict the changes /
damages on the structural components of the temporary
supporting structure. This detector consists of many
components such as top plate, bottom plate, spring
and the circuit. The Fig. 2 shows the components of
the detector. The plates are made up of galvanized iron
to withstand heavy load. The springs are connected to
the top and bottom plate using the heavy duty bolts.
The circuit is placed in-between the top and the bottom
plates. The general working principle of this detector is,
“when the load is applied on the top plate, the detector
is subjected to a compressive force which activates the
468 JOURNAL OF STRUCTURAL ENGINEERING
Vol. 45, No. 5, DECEMBER 2018 - JANUARY 2019
switch followed by the alarm”. It predicts the structural
collapse and warns the humans about that collapse.
Fig. 1 Detector
MS angles Top load
bearing plate
Top enclosure
Alarm circuit
Heavy duty
springs enclosed
Heavy duty
galvanized rods
Central plastic piston
Bottom enclosure
Fig. 2 Components of the detector
The wires are extended outside the device to make
an external connection. This external connection is
made to place the alarm and the power source as per the
requirement. Using the external wires, the alarm can be
placed anywhere and the source of power can also be
changed. Backup power arrangement has to be done for
uninterrupted continuous operation. This detector has a
very simple circuit which consists of a power source, a
switch and an alarm only. The Fig. 3 shows the circuit
diagram of the detector.
Indicator installed in formwork
Fig. 3 Position of the detector in the formwork
The detector will work in two stages, the normal
stage and the activated stage. When the load is not
applied on the top plate, the detector is said to be in
normal stage. When the load is applied on the top plate,
the detector is said to be in the activated stage. In the
normal stage, the switch will be inactive which makes
the circuit open and hence there will be no current ow.
In the activated stage, the switch will be activated which
makes the circuit closed and thus the current ows from
the power source to the alarm through the switch.
PREDICTION OF TEMPORARY SUPPORTING
STRUCTURE COLLAPSE
The detector is designed to predict the collapse of
the temporary supporting structure mainly due to
unexpected / miscalculated load which may impact on
the supporting frames. The indicator is placed under
the sheathing of the formwork using jack, truss and
shores as shown in Figs. 3 and 4. A small space is left
between the sheathing of the formwork and the device
in order to nullify natural downward displacement of
the formwork during the application of the concrete.
The space to be provided depends upon the mass of the
concrete to be placed and the downward displacement
of the formwork. The inkling of the indicator will be
more accurate when the space between the sheathing
and the device decreases.
Indicator insert zoomed
Fig. 4 Zoom out of the indicator in the formwork
The indicator is placed at equal intervals (say 2
meters or 6 feet) to form a grid in the formwork as
shown in the Fig. 5. The interval in the grid may vary
depending upon many factors such as the dimension of
the roof slab, mass of the concrete to be placed and so
JOURNAL OF STRUCTURAL ENGINEERING 469
Vol. 45, No. 5, DECEMBER 2018 - JANUARY 2019
on. Deformation at any point of the formwork of the
roof slab can be monitored easily through the set of
indicators in the grid.
30
30
6666
Indicator
Roof slab
6
6
6
6
6
6
Fig. 5 Grid form of the detector in formwork
The indicator should be placed as a grid under the
sheathing of the formwork with small space in between
them. The alarm and the grid of indicators are connected
through electrical wiring. The alarms can be xed at
any place in any number at the site of the formwork and
the control room. When the indicator is in normal stage,
a minute space will exist between the indicator and the
sheathing which will endure until the deformation of
the formwork. The Fig. 6 shows the indicator in its
normal stage when placed in the formwork.
Concrete load
Concrete
Sheathing
Indicator
Alarm in the
control room
Jack
Shores
Fig. 6 Normal stage of the detector in the formwork
The formwork failure is caused due to many reasons
such as overloading of concrete, poor workmanship,
usage of low quality materials for formwork and so
on. When the formwork deforms at any place, the
excessive load is transferred to the nearby detector.
This load creates a compressive force in the detector
which contracts the springs in it and activates the
switch. The activated switch will further activate the
alarms which warn the humans in the formwork site
about the upcoming structural collapse. The prediction
stage of the detector in the formwork is shown in Fig. 7.
These detectors in the grid can be monitored and the
deformation of the formwork can be repaired instantly
which not only saves the human lives but also prevents
the great economic loss.
Compression
Alarm in the
control room
Fig. 7 Prediction stage of the detector in the formwork
ENHANCEMENT
This device can be developed further, by connecting
to a computer through a control panel which simplies
the monitoring of the detectors in the grid system.
The mobile alert system can also be enhanced with
this detector. The alert messages can be sent to the
required mobiles using zigbee chip. The Fig. 8 shows
the developed circuit of the detector.
In the building, the detectors in the grid should be
connected to a control panel through electrical wiring.
This control panel is used to monitor the inkling of
the detectors in the grid. The setup is computerized
by connecting the control panel to the computer. The
usage of the computer can serve various purposes such
as monitoring the detector, nding the cause of the
failure, measuring the total displacement and so on.
These computers can be further programmed to send
alert messages to the required mobile phones. The
Fig. 9 shows the developed grid in the building.
Building echanced
with damage
prediction device
Activation of device
due to failure of
substructure
Mobilization of
emergency
response team
Safe evacuation of
occupants
Initiation of
emergency alert
system
Central command
centre recievies
alert
Fig. 8 Enhanced device with its communication loop
470 JOURNAL OF STRUCTURAL ENGINEERING
Vol. 45, No. 5, DECEMBER 2018 - JANUARY 2019
EXPERIMENT
The detector is placed under the formwork in a
construction site as shown in Fig. 10. It is placed with a
small space in between the sheathing of the formwork
and the detector as shown in Fig. 11. The detector is
placed as a grid at every 2 meters in the construction
site.
Fig. 10 Detector in the formwork at the construction site
The concrete is lled upon the formwork and the
performance of the device in the grid is analyzed.
When concrete is placed upon the formwork, the
detector endures to be in normal stage when there is
no failure in the formwork. The formwork undergoes
some natural downward displacement due to the mass
of the concrete and the space between sheathing of the
formwork and the detector vanishes. When there is
further displacement of the sheathing due to failure of
the formwork, the load of the concrete is transferred to
the detector and it is subjected to a compressive force
which makes the detector to move on to the prediction
stage. In this stage, the springs in the device contracts
and the switch is activated. It further activates the alarm
which warns the humans in the construction site about
the failure of the formwork.
Fig. 11 Position of the detector in the formwork at the construction
site
OBSERVATION AND RESULTS
The detector is placed as a grid in the formwork at the
construction site and every placement is named with tag
as shown in the gure. Every position of the detector
is monitored and the observations are tabulated in
Table 1. Using tabulated information further action is
taken. The inkling of the detector at its each position is
checked. The detector showed inkling in the positions
A3, B2, C4, D1 and D3 which means that there is
30
30
6
6
6
6
6
6
6666
Indicator
System
Control
panel
Alarm
Project
manager
Project
engineer
Site
engineer
Site supervisor
Site foreman and
all site workers
Roof slab
Fig. 9 Schematic representation of detection and alert system
JOURNAL OF STRUCTURAL ENGINEERING 471
Vol. 45, No. 5, DECEMBER 2018 - JANUARY 2019
certain deformation / deection in the formwork at
those positions. Thus the damage of the formwork
at the detected positions were repaired. Also it was
found that the other positions in the formwork have no
failure since the detector showed no inklings on those
positions.
Fig. 12 Grid in the formwork at the construction site
CONCLUSION
Based on the results of the experiments, it is concluded
that this device is designed in such a way to detect
any minor / major deections on the temporary
supporting structures and alerting the site workers
for corrective action on immediate basis to avoid any
further deformation / collapses. This would facilitate
the site supervisory to monitor the performance of
material, installation crew and to save the possible
damages at site. The detector does not have any impact
on environment. The device should be maintained
periodically for its better performance. The device is
of simple design and can be fabricated personally. This
research attempted to predict the failures on temporary
structures prior to collapse and to repair the same for
acceptable conditions thus preventing major accidents
saving human life, property and time at a construction
site.
TABLE1
OBSERVATION OF THE DETECTOR IN THE FIELD
S.NO. Notation of the detector Indication of fall Cause for the fall Course of action
1 A1 NIL - NONE
2 A2 NIL - NONE
3 A3 YES Deformation of shuttering due to
poor supports
Repair the supports and reiterate
the shuttering back to its original
position
4 A4 NIL - NONE
5 B1 NIL - NONE
6 B2 YES
Deformation of shuttering base due
to over stocking of concrete at one
point
Distribute the stocked concretein
such away to forman uniform load
on top of the shuttering base
7 B3 NIL - NONE
8 B4 NIL - NONE
9 C1 NIL - NONE
10 C2 NIL - NONE
11 C3 NIL - NONE
12 C4 YES Failure of supports due to lack of
rm base slab
Ensure the supports are xed
properly on a rmbase slab.
13 D1 YES
Failure of connection between the
horizontal shuttering plate and its
vertical support
Ensure all the connection are made
as per the design and conrm the
bondage between them
14 D2 NIL - NONE
15 D3 YES
Deformation of shuttering base due
to over stocking of concrete at one
point
Distribute the stocked concretein
such away to forman uniform load
on top of the shuttering base
16 D4 NIL - NONE
472 JOURNAL OF STRUCTURAL ENGINEERING
Vol. 45, No. 5, DECEMBER 2018 - JANUARY 2019
REFERENCE
1. Nie, J.K, Ming. K, Hao. L.W. and Dong. M.H,,
“Improving bridge collapse detection and on-
site emergency alarms: A case study in Taiwan”,
Article in Safety Science, Vol. 70, 2014, pp 133
– 142.
2. Szymberki. R., “Construction Project Safety
Planning”, TAPPI Jl., Vol. 80, (11), 1997, pp 69-
74.
3. Eric Marks and Jochen Teizer, “Proximity sensing
and warning technology for heavy construction
equipment operation”, Construction Research
Congress DOI: Published online: July 2012.
4. Marks, E. and Teizer, J.,h “Proximity sensing
and warning technology for heavy construction
equipment operation”, Construct. Res. Cong.,
ASCE 2012.
5. Ung. K.L, Joo. H.K, Hunhee, C. and Kyung. I.K,
“Development of a mobile safety monitoring
system for construction sites”, Automat. in
Construct., Vol. 18, No. 3, 2009, pp 258–264.
6. Narito Kurata, Billie, F.S. and Manual Ruiz, S.,
“Building Risk Monitoring Using Wireless Sensor
network”, 13th World Conf. on Earthquake Engg.,
Vancouver, B.C., Canada, 2004, pp 1406.
7. Janet, K.Y. and Edward, E.L, “Documenting and
Analyzing Construction Failures”, Jl. of Construct.
Engg. and Manage. (ASCE), Vol. 128, 2002.
(Discussion on this article must reach the editor before
February 28, 2019)
Chapter
A significant part of the modern housing stock in Russia was built in the first period of industrial housing construction, which began in Moscow with a plan for the reconstruction of the capital in 1951–1960, and lasted until the end of the 60s. A significant part of residential buildings in the country’s housing stock, built during this period, are large-panel buildings of mass series. The volume of dilapidated housing in Russia is increasing every year. This means that this problem must be urgently solved, since with the passage of time, the volume of emergency housing will only increase. There will be an urgent need to relocate a huge number of people to new housing in a short time, which, given the limited amount of time for construction and affordable free housing on the market, will be extremely difficult to implement. Therefore, there is an urgent need for people’s relocation from this housing to a new one and for demolishing (dismantling) the old one. Thus, issues related to the demolition and dismantling of residential buildings built in the first period of industrial housing construction, whereas massive series of large-panel buildings occupy a significant place, is an extremely relevant and in-demand topic in our country at this time. The purpose of the study is to propose and substantiate the optimal (rational) set of organizational and technological parameters for dismantling large-panel residential buildings of the first mass series. In recent years, the construction industry has come to the conclusion that the one-time costs of capital investments for the demolition (dismantling) of a residential building and the construction of a new one in its place are less than the one-time costs for major repairs. Also, the liquidation of these objects allows getting additional free space for housing and civil construction, which is already insufficient in large cities of our country, given that significant areas are occupied by buildings of historical and architectural value. Therefore, it is timely now to relocate people from this housing to a new one and to demolish (dismantle) the old one. The assessment of the physical and technical parameters of the construction site territory is quite accurate and objective. Determining the parameters of the construction site and temporary infrastructure facilities will make it possible to design construction production more accurately and keep within the standard time frame. Thus, the planning of construction production largely depends on the organization of the construction site.KeywordsReconstructionDemolitionDismantlingOrganizational and technological parameters
Article
Full-text available
Buildings are subjected to natural hazards, such as earthquakes and winds, and man-made hazards, such as fires and crimes, during their long-term use. To mitigate these hazards, monitoring these risks by sensing certain types of physical values is necessary. Recently, a smart sensor based on the Berkeley Mote platform was introduced, and an application to the next generation of structural health monitoring and control was proposed [1, 2]. The Mote has on-board microprocessor and ready-made wireless communication capabilities. In this paper, the performance of the Mote is investigated through shaking table tests employing a two-story steel structure. The acceleration sensor is tested, and its performance for wireless measurement and specific risk monitoring applications, such as damage detection in the structure, is presented. The feasibility of risk monitoring for buildings is also discussed.
Conference Paper
The United States construction industry experienced 151 fatalities resulting from workers colliding with objects and equipment in 2009. These fatalities accounted for approximately 18% of the total construction fatalities and 3% of the total workplace fatalities experienced that year. Construction workers and equipment are often required to function at close proximity on construction jobsites. This paper evaluates the effectiveness of emerging radio frequency (RF) remote sensing technology that can promote safety in construction by providing real-time alerts for worker-on-foot and construction equipment operators when a potentially hazardous proximity situation exists. Numerous experiments designed to emulate typical interactions between workers-on-foot and construction equipment, including installing proximity sensing devices on actual construction equipment, were used to evaluate the proximity sensing technology. Results from the experiments indicate that real-time pro-active proximity sensing and warning technology can promote safety on construction jobsites.
Article
During the past decades in Taiwan, numerous scour problems have led to the collapse of bridges. Such accidents have caused severe economic losses and killed many people. Although Taiwanese government agencies have mitigated this relationship between natural hazards and bridge collapse, two problems still exist at bridge sites: the lack of convenient mechanisms for bridge collapse detection and the lack of active mechanisms for on-site emergency alarms. Therefore, based on an approach consisting of mixed collapse detectors (i.e., bi-axial tilt sensors, electronic circuits) and compounded wireless networks (i.e., low-rate wireless personal area network, wireless local area network, worldwide interoperability for microwave access), this study proposes a bridge safety monitoring information system. While the mixed collapse detectors identify the status of various bridge elements, the compounded wireless networks streamline the information transmission between on-site bridges and off-site headquarters. This research is composed of two-year tests on six bridges. After 382 earthquakes and 13 typhoons, this study confirmed that the stability of the bridge safety monitoring information system achieved the anticipated results. Thus, this study provides a sound reference for similar applications in bridge and disaster management.
Article
In spite of efforts to reduce fatal accidents on construction sites, such accidents continue to occur. In particular, fall accidents constitute the majority of these accidents, and therefore appropriate managing measures are needed. In this study, a safety monitoring system was established at a site where fall accidents often occurred, with the aim of reducing the rate of fatal accidents on the construction site. The system consisted of a mobile sensing device for detecting the worker's approach, transmitter sets and repeaters for sending the detected information to a receiver, and exclusive software for interpreting this information. The system was applied to a real construction site and tested in order to verify its utility and efficiency. It is expected that the system will decrease the potential for fall accidents and increase the efficiency of safety management.
Article
A research project was conducted to explore construction failure investigation techniques and processes to determine whether they were adequate and to develop failure investigation guidelines. Data was collected on failures and failure investigation techniques from surveying 115 members of the engineering and construction industry. Construction failure case studies were created using docu-mentation provided by the federal Occupational Safety and Health Administration, state offices of safety and health, and forensic engineers. The construction failure case studies were analyzed to determine how these organizations conduct their investigations and to develop guidelines that can be used for construction failure investigations. This article provides: 1 description of the methods used for the research; 2 results obtained from the industry survey; 3 summary of the results of an investigation into case studies on construction failures; 4 analysis of the results; 5 discussion on construction failure investigative techniques; 6 guidelines developed during the research project for investigating and documenting failures; and 7 recommended format for reporting the findings of failure investigations.
  • R Szymberki
Szymberki. r., "construction Project Safety Planning", TAPPI Jl., Vol. 80, (11), 1997, pp 69-74.