People in the project and business environment are familiar with the terms ‘logistics management’ and ‘supply chain management’, until they’re asked to explain the difference. In this article, we discuss these terms and then focus on the unique aspects of ‘project logistics’. Another frequently used term in the building industry is ‘construction logistics’, but we’ll explain why we steer away from using it for projects in the process industries.
Content may be subject to copyright.
An Introduction to Project Logistics
Management
_____________________________
Jurie Steyn & Dirk Lourens
May 2017
Introduction
Consider the situation: your project, in some faraway location, is partly completed, but
you urgently need 20 12high-pressure valves to proceed. This is not an item stocked
by local suppliers, if indeed there are any suppliers in the area. Sourcing the items
from your preferred supplier will take at least two weeks.
Now, if the installation of these valves is not on the critical path for the project, it should
not result in schedule slippage. The required items can be sourced and delivered in
time, albeit at a cost premium. If it is on the critical path, you stand to delay completion
by two weeks. This is something any respected project manager would want to avoid.
Is there anything worse, not considering accidents and manpower problems, than not
having the specific items required for your project at the right place, at the right time
and in the right quantities? We can think of several:
The items are available in the project store, but nobody knows it’s there;
Items not meeting the required specification;
The items were mistakenly used for another application; and
The items were deliberately used for another application.
These are all matters relating to logistics, in general, and project logistics, in particular.
Project logistics in perspective
Most people in the project and business environment are familiar with the terms
‘logistics management’ and ‘supply chain management’, until they’re asked to explain
the difference. In this article, we discuss these terms and then focus on the unique
aspects of ‘project logistics’. Another frequently used term in the building industry is
‘construction logistics’, but we’ll explain why we steer away from using it for projects in
the process industries.
The Council of Supply Chain Management Professionals (CSCMP, 2016) defines
logistics management is that part of supply chain management that plans, implements,
2
and controls the efficient forward and reverses flow and storage of goods, services and
related information between the point of origin and the point of consumption to meet
customers' requirements.
Supply chain management encompasses the planning and management of all
activities involved in sourcing and procurement, conversion, and all logistics
management activities (CSCMP, 2016). It also includes coordination and collaboration
with supply chain partners, namely suppliers, intermediaries, third-party service
providers, and customers. Supply chain management effectively integrates supply and
demand management within and across companies.
From the two definitions, we see that logistics management is a subset of supply chain
management. Considering the discipline of project management for a moment, we see
that this overlaps onto supply chain management, insofar as construction of a new
facility is concerned: materials and services need to be available when needed by the
construction crew. This is illustrated in Figure 1, where the overlap gives rise to the
terms ‘project supply chain management’ and ‘project logistics management’. Project
logistics is a subset of logistics and project supply chain management a subset of
supply chain management.
Figure 1: Project logistics in perspective
This begs the question: is project logistics then just simplified logistics? The answer is
‘yes’, in the sense that there is only inbound logistics, with perhaps some reverse
logistics to return faulty equipment. However, every project is unique and every project
site is different. This effectively means that for every project, every supply chain is new
and has not had the benefit of supply chain optimisation and fine-tuning. In this sense,
the answer to the question is a resounding ‘no’.
3
New process facilities can consist of hundreds of thousands of individual components.
Each should be available at the right location, the right time, the right quality and at the
right price.
Characteristics of project logistics
Projects logistics already commences in the feasibility study stage of a project.
Accessibility to the site, in terms of transport routes, rail carrying capacities and bridge
widths, can dictate the design approach to be followed. In the situation where very
long lead-times for equipment apply, it may have to be ordered before completion of
the final design. It is this early involvement of supply chain professionals in a project
which guides us away from the term ‘construction logistics’ and is why we rather use
‘project logistics’.
The different component delivery channels for a typical large process facility is shown
in Figure 2. Some of the transport options are also shown in the graphics. Considering
the large number of components for a given project, the complexity of project logistics
can be appreciated.
Figure 2: Component delivery channels
The project supply chain is characterised by the following elements, which differentiate
it from supply chains for manufacturing and retailing:
Converging: All materials converges on the construction site where the facility is
assembled from incoming materials. The construction effort is directed to a single
product, namely the processing facility;
4
Temporary: Apart from rare exceptions, a project supply chain is temporary,
producing one-off construction projects through repeated reconfiguration of project
contractors and suppliers; and
Made-to-order: Projects require made-to-order supply chains, with every project
creating a new facility. There is little repetition, again with minor exceptions.
What is required for a process plant?
We’ve already mentioned the large number of materials, components, equipment and
services that are required for the construction of a process plant. In this section, we
briefly describe the different categories of materials and equipment.
An overview of the materials, components and equipment for a process plant is given
in Figure 3.
Figure 3: Materials, components and equipment for a process plant
We categorise the materials, components and equipment as follows:
Bulks: Bulk and generic materials, requiring basic specifications, no pre-delivery
checking and limited quality control. Examples include basic building materials like
sand, stone, wood, cement and bricks. We group common safety equipment like
hard hats, safety boots and safety gloves in this category;
5
Commodities: Generic equipment, bought to specification following a visit to the
suppliers site and requiring active quality control. Examples include structural steel,
pipes and pipe fittings, valves, small pumps, cabling, field instruments, etc.;
Process equipment: This category covers process equipment requiring detailed
specifications, astute vendor selection, site visits and quality control. Examples
include process vessels, tanks, heat exchangers, columns, and process control
equipment;
Modular plant units: Modular plant units are prefabricated process units
designed, built, tested and then delivered to site. Plant modules could be anything
from basic pre-assembled pipe-racks (PARs) to third generation plug-and-play
modules;
One-off high-value items: One-off high-value items are typically large high-value
and long-lead items built to very strict specifications with continuous quality
assurance. Examples include large distillation units, unique process reactors and
custom compressors and turbines; and
Construction equipment: Heavy equipment to be used for the construction phase
of the project, including cranes, graders, loaders, excavators, forklifts, bull dozers
and trucks. Also includes the hand tools used by the construction artisan.
Logistics outsourcing
To become more cost effective and efficient, project managers and managing
contractors have started to outsource project logistics. Outsourcing is the transfer of a
function previously performed in-house to an outside service provider. Outsourced
providers are often referred to as contractors or ‘third parties’. When work is
outsourced, the outsourcing business or agency still provides oversight.
The concept of third-party logistics, or 3PL, appeared on the scene in the 1970s as the
way to reduce costs and improve services. In the project environment, 3PL service
providers would handle tasks ranging from trucking, marine cargo transport and
specialist transport of very heavy loads, to broader activities serving the total project
supply chain, such as inventory management and order processing.
In the past, many 3PL providers didn't have adequate expertise to operate in complex
and one-off supply chain structure such as is required for the construction of a large
process facility. The result was the inception of another concept, namely fourth-party
logistics or 4PL. Fourth-party logistics refers to a party who works on behalf of the
client, typically the managing contractor responsible for engineering, procurement and
construction (EPC), to do contract negotiations and management of performance of
3PL providers.
This concept is illustrated in Figure 4, where four different 3PL service providers are
shown, each with his area of specialisation. These four 3PL service providers report
6
to a coordinating 4PL service provider. As said above, the 4PL service provider reports
to the project managing contractor, who is accountable to the business owner.
Figure 4: Third- and fourth-party logistics (Adapted from Benjabutr, undated)
Is this the full story?
To give a very short answer: “no”. The longer answer follows below.
The concept of logistics can be traced back to the wars of the Greek and Roman
empires, when specific military officers were assigned the duties of providing services
related to supply and distribution of troops and other resources.
During World War II, logistics evolved greatly. The United States military ensured that
the required personnel, services and supplies were provided at the right time and at
the right place. In their efforts to provide these services in the most optimal and
economical manner, best practices to do the tasks were developed.
In the light of this little history lesson, the making available of qualified and experienced
artisans and engineers at the project site is a crucial logistical issue. This is especially
true if the chosen project site is far away from developed areas. Depending on the
assignment of responsibilities in the project team, the project logistics manager may
also be tasked with the provision of the workforce and other site infrastructure. These
matters, critical to project success, which also require the benefit of project logistics
management, include:
Personnel supply: The right mix of engineers, welders, electricians, safety
officers, clerks and labourers as may be required for the project;
Personnel transport: Transport is required to get the personnel to their places of
work and for personnel movement as the work dictates;
7
Housing: Adequate housing for the personnel on or near the project site. In some
cases, the erection of the required housing is the first part of a project;
Canteen facilities: The personnel must be provided with nutritious and tasty meals
three times a day to keep up their strength;
Computing infrastructure: No project can proceed without an integrated
business management system in place for the project execution phase
Communication infrastructure: Intra-site communication, as well as facilities to
allow site workers to communicate with their loved ones;
Medical support: This is especially needed for undeveloped areas. Emergency
medical treatment is required as a minimum, with arrangements in place for
evacuation to a medical centre;
Psychological support: Project work is a high-pressure environment and
arrangements must be in place for psychological support for work or personal
problems
Waste management: Much waste is generated during the construction of any
facility. Waste, especially hazardous waste needs to be disposed of responsibly,
even if this means the construction of a dedicated hazardous waste disposal site.
Concluding remarks
Project logistics is a very complex field and covers a great many aspects. Apart from
making sure that the hundreds of thousands of different items are available when
required, the responsibilities of the project logistics manager can also include the
supply and well-being of the construction team. We believe that this introduction to
project logistics management will give the reader some appreciation of the complexity.
Outsourcing project logistics to third- and fourth-party logistics service providers (3PL
and 4PL) can help the owner organisation and the EPC contractor achieve cost
reductions and improves the probability of a successful project. Both the owner and
the EPC contractor can learn from the project logistics service providers, because of
the exposure to the best available project logistics practices and techniques.
There are several very useful books on construction and project logistics (Pryke, 2009;
Sullivan, Barthorpe & Robbins, 2010; Lundesjö, 2015). Those who wish to learn more
about supply chain management and logistics in projects are advised to read one, or
more, of these.
References
Benjabutr, B., Undated, What is logistics and supply chain management? Available
from http://www.supplychainopz.com/2012/04/what-is-logistics-and-supply-chain-
management.html Accessed on 8 February 2017.
8
CSCMP (Council for Supply Chain Management Professionals), 2016, CSCMP Supply
chain management terms and glossary. Available from
http://cscmp.org/imis0/CSCMP/Educate/SCM_Definitions_and_Glossary_of_Terms/C
SCMP/Educate/SCM_Definitions_and_Glossary_of_Terms.aspx?hkey=60879588-
f65f-4ab5-8c4b-6878815ef921 Accessed on 4 April 2017.
Lundesjö, G. (ed), 2015, Supply chain management and logistics in construction:
delivering tomorrow’s built environment. Kogan Page Limited, London.
Pryke, S. (ed), 2009, Construction supply chain management. Wiley-Blackwell,
London.
Sullivan, G., Barthorpe, S. & Robbins, S., 2010, Managing construction logistics.
Wiley-Blackwell, London.
... Logistics management. The Council of Supply Chain Management Professionals atau CSCMP (2016) mendefinisikan bahwa, "logistics management is that part of supply chain management that plans, implements, and controls the efficient forward and reverses flow and storage of goods, services and related information between the point of origin and the point of consumption to meet customers' requirements"(Steyn, 2017).c. Distribution management.Menurut Corporate Finance Institute atau CFI (2022), "distribution management is part of the supply chain process that ultimately delivers goods to end-users or consumers. ...
Chapter
Bab ini menjelaskan konsep dasar valuta asing & pasar portofolio internasional
Article
Full-text available
Purpose of the article – Abnormal cargo will create abnormal problems and those require exceptional logistics solutions. This study delves into the complexities and challenges of transporting project cargo, explicitly focusing on items with extraordinary dimensions, weights, and shapes. Despite its small volume in global cargo flow, project cargo presents significant operational risks and contributions, particularly in the logistics sector. The research concentrates on the Balkan Peninsula, aiming to unravel the critical factors influencing project cargo transport and highlighting the challenges faced by industry experts. Research methodology – Employing the Delphi method, initially developed for military applications and now prevalent in project management, the research seeks expert consensus on critical elements affecting project cargo logistics in the Balkans. This method facilitates the gathering and analysis of expert opinions to identify and address the core factors impacting project cargo transport. Findings – The study uncovers various critical factors and challenges in project cargo logistics within the Balkan region. It provides insights into risk minimization, deviation control, and effective achievement of logistical objectives. Practical implications – The research offers valuable perspectives for reducing risks and optimizing operations in project cargo transport. It also opens avenues for further research and development in the project logistics sector in the Balkans, contributing to enhanced efficiency and effectiveness. Originality/Value – This research contributes uniquely by focusing on the lesser-explored area of project cargo transport in the Balkans. Employing the Delphi method brings forward expert insights, thus enriching the academic and practical understanding of this specialized logistics sector.
Chapter
Supply chain management (SCM) is the management of a sequence of dynamic activities concerned with the planning, control, and execution of the flow of goods in various stages of manufacture—from raw materials to production through distribution to the end customer, in the most streamlined and cost‐effective manner possible. This chapter examines SCM, including its benefits, critical areas, and issues relating specifically to project management. It discusses value drivers in SCM, and presents a project supply chain process framework. The chapter explores supply chain integration, performance metrics, and future issues in project SCM. Effective SCM requires companies to focus on the following critical areas: customers, suppliers, design and operations, logistics, and inventory. Value drivers in a project supply chain are those strategic factors that significantly add or enhance value and provide a distinct competitive advantage to the chain.
Article
Most projects require routine and consumable materials from third parties, and planning, ordering, transporting, storing, tracking, and controlling these material resources can take a lot of time and effort, so proper logistics support is a critical necessity in project management. Therefore, the article analyzes the key changes in the 7-th edition of Project Management Body of Knowledge. It was determined that flexible approaches to project management ceased to be an addition to the standard, they became part of it, including in matters of supply chain management and project logistics. Key areas of project execution are analyzed that clearly emphasize the importance of materials, equipment, supply and logistics management in a project-oriented context and the importance of working with contractors and suppliers to plan and manage procurement and contracts. A brief overview of those industries for which project logistics management is one of the main directions for obtaining a competitive advantage and completing the project on time. The approach to planning the delivery of materials and equipment in projects, which are necessary for the construction of roads, bridges and other infrastructure, with a view to ensuring the continuity of work in the process of project management. The model estimates the amount of materials that must be available at a given time on the construction site to ensure the desired level of protection against changes in delivery dates and project progress.