ArticlePDF Available

Planning Low-Carbon Electricity Systems under Uncertainty Considering Operational Flexibility and Smart Grid Technologies

Authors:

Abstract and Figures

Electricity grid operators and planners need to deal with both the rapidly increasing integration of renewables and an unprecedented level of uncertainty that originates from unknown generation outputs, changing commercial and regulatory frameworks aimed to foster low-carbon technologies, the evolving availability of market information on feasibility and costs of various technologies, etc. In this context, there is a significant risk of locking-in to inefficient investment planning solutions determined by current deterministic engineering practices that neither capture uncertainty nor represent the actual operation of the planned infrastructure under high penetration of renewables. We therefore present an alternative optimization framework to plan electricity grids that deals with uncertain scenarios and represents increased operational details. The presented framework is able to model the effects of an array of flexible, smart grid technologies that can efficiently displace the need for conventional solutions. We then argue, and demonstrate via the proposed framework and an illustrative example, that proper modelling of uncertainty and operational constraints in planning is key to valuing operationally flexible solutions leading to optimal investment in a smart grid context. Finally, we review the most used practices in power system planning under uncertainty, highlight the challenges of incorporating operational aspects and advocate the need for new and computationally effective optimization tools to properly value the benefits of flexible, smart grid solutions in planning. Such tools are essential to accelerate the development of a low-carbon energy system and investment in the most appropriate portfolio of renewable energy sources and complementary enabling smart technologies. This article is part of the themed issue ‘Energy management: flexibility, risk and optimization’.
Content may be subject to copyright.
rsta.royalsocietypublishing.org
Research
Cite this article: Moreno R, Street A, Arroyo
JM, Mancarella P. 2017 Planning low-carbon
electricity systems under uncertainty
considering operational exibility and smart
grid technologies. Phil.Trans.R.Soc.A375:
20160305.
http://dx.doi.org/10.1098/rsta.2016.0305
Accepted: 12 May 2017
One contribution of 13 to a theme issue
‘Energy management: exibility, risk and
optimization’.
Subject Areas:
power and energy systems, electrical
engineering, energy
Keywords:
low-carbon power system planning, smart
grid, exibility, stochastic optimization, robust
optimization, power system economics
Author for correspondence:
Rodrigo Moreno
e-mail: rmorenovieyra@ing.uchile.cl
Planning low-carbon
electricity systems under
uncertainty considering
operational exibility and
smart grid technologies
Rodrigo Moreno1,2, Alexandre Street3,
José M. Arroyo4and Pierluigi Mancarella5,6
1Department of Electrical Engineering (Energy Center), University of
Chile, Santiago, Chile
2Department of Electrical and Electronic Engineering, Imperial
College London, London SW7 2AZ, UK
3Department of Electrical Engineering, Pontical Catholic University
of Rio de Janeiro, Rio de Janeiro, Brazil
4Departamento de Ingeniería Eléctrica, Electrónica, Automática y
Comunicaciones, Universidad de Castilla-La Mancha, Ciudad Real,
Spain
5Department of Electrical and Electronic Engineering, University of
Melbourne, Parkville, VIC 3010, Australia
6School of Electrical and Electronic Engineering, The University of
Manchester, Sackville Street, Manchester M13 9PL, UK
RM , 0000-0001-5538-445X;PM,0000-0002-9247-1402
Electricity grid operators and planners need to
deal with both the rapidly increasing integration of
renewables and an unprecedented level of uncertainty
that originates from unknown generation outputs,
changing commercial and regulatory frameworks
aimed to foster low-carbon technologies, the evolving
availability of market information on feasibility and
costs of various technologies, etc. In this context,
there is a significant risk of locking-in to inefficient
investment planning solutions determined by
current deterministic engineering practices that
neither capture uncertainty nor represent the actual
operation of the planned infrastructure under high
penetration of renewables. We therefore present
an alternative optimization framework to plan
electricity grids that deals with uncertain scenarios
2017 The Author(s) Published by the Royal Society. Allrights reser ved.
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
This is for personal use only - For other use, please address yourself to the publisher
2
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
and represents increased operational details. The presented framework is able to model the
effects of an array of flexible, smart grid technologies that can efficiently displace the need
for conventional solutions. We then argue, and demonstrate via the proposed framework and
an illustrative example, that proper modelling of uncertainty and operational constraints in
planning is key to valuing operationally flexible solutions leading to optimal investment in a
smart grid context. Finally, we review the most used practices in power system planning under
uncertainty, highlight the challenges of incorporating operational aspects and advocate the
need for new and computationally effective optimization tools to properly value the benefits of
flexible, smart grid solutions in planning. Such tools are essential to accelerate the development
of a low-carbon energy system and investment in the most appropriate portfolio of renewable
energy sources and complementary enabling smart technologies.
This article is part of the themed issue ‘Energy management: flexibility, risk and
optimization’.
1. Introduction
(a) The evolving landscape: from conventional electricity systems to low-carbon smart
grids
Current electricity grids comprise large generating units that produce power generally far from
load centres, high-voltage transmission networks that ship power from production centres to load
centres (up to the so-called primary substations) and lower-voltage distribution networks that
transfer power from primary substations to commercial, industrial and residential consumers.
In this electricity system, referred to as conventional: (i) generation is typically carbon-intensive,
powered by fossil fuels, and in some cases supported by hydro plants that are usually large so as
to take advantage of economies of scale; (ii) transfer capability of networks (that are passive and
inflexible) is mainly delivered through more investment in asset-heavy infrastructure (e.g. lines
and transformers); and (iii) demand is mostly dominated by consumers’ end-use requirements
only and thus unresponsive to system/market conditions. In this context, operators aim to run
electricity grids in an economically efficient and reliable manner by mainly controlling generation
outputs. Such a control allows operators to maintain the instantaneous production–demand
balance and transfers within network capacity limits. In addition, sufficient security margins in
electricity infrastructure (generation and network) are retained to withstand credible outages (e.g.
sudden failure of a generating unit or network circuit). In planning time scales, network design
decisions attempt to eliminate congestions through investment in asset-heavy infrastructure up
to the point where the marginal benefit of more network capacity (i.e. savings in congestion
costs and reliability costs driven by the installation of further lines and transformers1)isequalto
the marginal cost of network investment [1]. While network infrastructure is centrally planned,
generation investment is generally market-driven and hence decentralized; historically, network
planners have thus responded through more network investment to new connection requirements
from generation, which engenders system expansion.
In the coming years, the above-mentioned conventional electricity network will evolve
towards the so-called smart grid. Firstly, generation will increasingly be low-carbon and
distributed across the electricity system, even being located at the point of power consumption
(e.g. rooftop photovoltaic (PV) panels). Low-carbon generation from renewables such as wind
and solar power will create the need to counteract their variable and partly unpredictable power
injections through operational measures so as to maintain the instantaneous production–demand
balance (i.e. system frequency), generation outputs and network transfers within capacity limits
1Congestion cost is driven by network transfer limits and is equal to the extra cost of operation due to network capacity
constraints, while reliability cost is driven by the demand curtailment associated with network capacity and is equal to the
expected unsupplied demand times the value of lost load, VoLL.
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
3
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
and the required security margins in generation and transfer capability (i.e. reserves and network
redundancy). Secondly, distribution networks will transition from mostly passive networks,where
the control problem is resolved at the planning stage by designing for the worst-case peak-
demand scenarios, to active systems, where new information and communications technologies
(ICT) and controllable distributed energy resources, including storage and flexible demand,
will provide real-time supply–demand balance to efficiently integrate local renewables while
also interacting with the transmission system [2,3]. Thirdly, the transmission system itself will
become much more active through: (i) new controllable and flexible technologies, such as
flexible AC transmission systems (FACTS) [4] and high-voltage DC (HVDC) systems [5], that can
control power flows through the network without changing power injections/withdrawals; (ii)
system integrity protection schemes (SIPS) that can enforce rapid increase/reduction of power in
importing/exporting areas after a network outage occurs by, for instance, curtailing generation
and/or demand [6]; and (iii) various wide-area monitoring and control equipment supported
by ICT technologies that will increase the capability of system operators to monitor and control
electricity assets in real time and throughout wider areas through increased communication
[7,8]. Last and more importantly, demand will be controllable and end-users will become active
participants in system and market operation, thereby opening up opportunities for aggregating
and coordinating consumers and system needs (e.g. for system balancing and congestion
management), taking advantage of flexibility from smart appliances (e.g. dishwashers and tumble
dryers), electric heaters, batteries, etc. [9,10]. Also, electrification of other energy demands from
the heating/cooling (e.g. electric heat pumps and heating ventilation and air conditioning
equipment) and transport (e.g. electric vehicles) sectors can further expand the opportunities to
control electricity loads and coordinate them with system needs, owing to their intrinsic virtual
storage capabilities [11,12].
In the low-carbon smart grid context outlined above, and focusing on the system as a whole
and the transmission level, a change in system frequency due to system level supply–demand
imbalance can be resolved through the combined action of various fast generating units and loads
(e.g. disconnection of non-critical load from dishwashers and/or refrigerators [10], contribution
from distributed battery systems, including those from parked electric vehicles, connection of
distributed back-up generation, etc.), while network congestions can be resolved through changes
in topology and/or impedances (e.g. changing FACTS set points) rather than through costly
changes in the output of generation. This increase in operational flexibility can be used to address
both real-time operation and time-ahead scheduling, where strategic decisions are made in
advance (e.g. a few hours ahead relative to real time) to deal with the uncertain evolution of wind
and solar power generation, and so adapt to different realizations that may happen in real time.
In this context, generation reserves can be coordinated with demand response, charge/discharge
actions from storage and even network topology reconfiguration so as to deliver the needed
balancing services requested in real time due to wind/solar forecast errors and their potentially
high variability [9,13]. In particular, such coordination of multiple, flexible operational measures
can increase network utilization and decrease holding levels of generation reserves that may
be significantly costly due to the high levels of wind and solar power expected in the near
future [14,15].
In smart grid planning, it remains unclear whether new asset-heavy investment (e.g. a new
line and/or transformer) will be needed even in the presence of increased ICT infrastructure and
fast control of network devices, storage and demand, which can rapidly instigate reduction of
transfers and even eliminate network congestion [14]. The availability of distributed storage,
for instance, could locally provide power to consumers while battery charging and transfer
actions take place during hours where the network is not congested. Likewise, fast control of
network devices could eliminate post-contingency, real-time congestion by changing network
topology (e.g. through line switching), impedances (e.g. through the adjustment of FACTS set
points and soft normally open points [16], i.e. relying on power electronics-based technology)
and power flows (e.g. through dispatchable HVDC links), thereby reducing the need for
network redundancy. Furthermore, the reliability role of redundant transmission and generation
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
4
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
infrastructure could be substituted by the deployment of flexible devices that can carry out
advanced operational measures, creating a strong relation between planning and operation
that should be carefully studied when expanding the system [17]. In addition, economics
and reliability will not be the only drivers of network planning, and thus new investment
solutions should also facilitate the achievement of environmentally driven energy policy targets.
Furthermore, owing to the increased levels of requests for new renewable generation connections
featuring extremely shorter construction times (shorter than those needed to build network
infrastructure and definitely shorter than those needed to build large conventional power plants),
network planners will need to undertake proactive investment, in anticipation of connection
requirements from generation, taking real advantage of the economies of scale of transmission
investment.2In the smart grid paradigm, network planners should thus proactively drive system
expansion rather than react to generation proposals, and support network decisions through the
deployment of flexible, smart network technologies in order to more effectively adapt to the
unfolding future scenarios.
(b) Opportunities for advanced optimization models to plan electricity grids
The increase in automation and flexibility due to new generation, storage, network, demand and
ICT technologies is paramount to face intermittent and uncertain power outputs from renewable
generation and defer the need for conventional network infrastructure. In fact, any attempt to
face the increase in renewables through current practices and without the adequate upgrade
in emerging network technologies could be extremely costly and even infeasible [14]. To truly
unleash flexibility, however, operators will need to control a much wider array of set points
to ensure that economics and reliability are maintained at acceptable levels. For example, it is
expected that in the UK generating units providing fast frequency control (i.e. fast balancing)
could increase from about 10 (large generating units providing frequency control) to some 600 000
(if 10% of small PV and wind units support frequency control); network automatic controls
such as voltage regulation devices could increase from 10 000 to 900 000; and automatic controls
in homes (energy management systems) could increase from virtually zero to 15 million (if
half of the installed smart meters were to link with energy management devices) [18]. Along
with the increase in control set points (and thus optimization variables), the amounts of data
available in operational time scales will escalate at all levels due to technologies such as smart
meters—at the consumer level—and phasor measurement units [19]—at both transmission and
distribution network levels—which will allow operators to significantly improve their visibility
and thus state estimation of the system. With a clearer picture of system conditions in real
time through increased volumes of data and with a higher level of controllability of network
equipment, operators will thus be able to run the system in a more secure fashion, using network
infrastructure at higher levels (i.e. with less redundancy and less congestion) and therefore
improving the overall economic performance of the system operation activity as well as deferring
the need for conventional electricity infrastructure investment.
In addition, there is an increasing need to capture coordination actions across various energy
vectors, including all electricity sectors (from local energy management systems, distribution and
transmission networks to generation), gas, heat/cooling and transport [12]. In fact, flexibility from
electricity demand can be coupled with heat and/or mobility needs from consumers, and this may
have important impacts on electricity network operation and investment beyond distribution
networks, affecting also the transmission and generation infrastructure. For example, flexible
demand from electric vehicles (i.e. battery charging/discharging actions) or heat pumps [11]can
be controlled so as to reduce electricity demand during peak hours, provide frequency control
services, provide congestion management services (in distribution and transmission networks),
2Building a 1000 MW line in anticipation of connection requirements is likely to be more efficient than building 10 lines of
100 MW as a result of 10 different connection requirements at different points in time, albeit there is a risk associated with the
potential stranded network infrastructure if generation projects do not materialize as anticipated.
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
5
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
etc., ultimately driving both less costly operation and less investment in network and generation
assets [9,20]. Coupling with other pieces of infrastructure, for example the gas network, can
then further increase the power system’s flexibility and support integration of larger volumes
of renewables [21], as well as even provide new forms of storage [22].
Recognition of power system dynamics and stability phenomena (that are usually in the
time scale of a few seconds) is also becoming increasingly important in both the operational
and planning decision-making processes [23,24], and this is also crucially linked with the
penetration of advanced ICT infrastructure in power networks. Indeed, it is envisaged that
current redundancy levels (that are used to provide security under the current operational
doctrine) will be replaced with increased automation, monitoring, communication, control, etc.
(i.e. via corrective control actions) [24]. However, these might fail to properly operate in real time,
and such malfunctions, for example in the form of delays in communication, could originate
network stability problems and even a cascading load disconnection [25,26]. Hence, adequate
balance between network redundancy and advanced corrective control actions will need to be
recognized so as to properly determine (i) transfer limits and congestion levels in operational
time scales and (ii) the need for new network reinforcements in the long term, considering both
power and ICT network reliability [27,28].
Finally, an adequate treatment of uncertainty in both operational and planning time scales
will be essential in the presence of renewables in order to minimize the risk of locking in to
inefficient solutions which ignore the multiple possible evolutions that networks may experience.
In operational time scales, prediction of renewable generation production from wind and solar
power plants will give rise to certain levels of forecast error against which operators hedge
through balancing services [29,30]. Thus, if wind power outputs, for example, are less than
expected, there will be a mix of generation and demand-based services that can counteract
the lack of wind energy production. It will also be important that network congestion be
efficiently managed in real time, even under those conditions where large forecast errors
are realized. In this context, the location of reserve services and the possibility to undertake
corrective actions over flexible network components will be paramount. In planning time
scales, network design will need to anticipate renewables connection and thus face uncertainty
levels associated with the location and volume of new generation. Hence, planners will
require a strategic approach and determine a balanced portfolio of present and future network
investments in such a way that present, ‘here-and-now’ decisions (using stochastic programming
terminology) are sufficiently flexible to be adapted by further investment in the future when
information regarding new generation capacity becomes more certain. Under this paradigm,
flexible investment options and ‘wait-and-see’ investment strategies may be valuable to avoid
the implementation of network solutions that cannot be efficiently adapted to the unfolding
future [3133].
Overall, the comparison among alternative solutions when planning electricity grids will
become increasingly complex since an extremely large set of options need to be objectively
assessed before implementation, including calculation of their performance in operational time
scales. In fact, as we will also demonstrate in this work, neglecting operational aspects, as
customarily done in traditional planning tools, will provide inefficient solutions in a low-carbon
smart grid context. Moreover, there will be a large volume of information that will become
available due to new monitoring technology and a large number of control variables across
voltage levels, electricity sectors/markets and energy vectors that need to be coordinated even
across borders (in the so-called whole-system approach). In this regard, time resolution will also
be critical to capture the effect of variable generation, the need for ancillary services (e.g. reserves)
and even the occurrence of complex stability phenomena that can jeopardize system security. In
addition, uncertainty will need to be recognized at various time scales in order to minimize the
risk of locking in to inefficient solutions [34]. Furthermore, there are also multiple objectives,
beyond economics, that need to be balanced, including security of supply, carbon emissions and
energy policy targets that should be met in the long term. Clearly, this creates a challenging
environment for modellers who attempt to identify optimal decisions in planning.
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
6
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
(c) Paper scope and contributions
On the above premises, the goals of this paper are threefold:
—- to explain the new level of complexity associated with the low-carbon, smart grid context
(especially when compared with that of conventional electricity systems), highlighting
how this affects infrastructure planning concepts and practices;
—- to propose an alternative optimization framework to plan infrastructure in smart grids,
exposing the modelling and computational challenges related to its implementation in
actual power systems; and
—- to demonstrate the importance of considering uncertainty along with operational
flexibility when planning investment in innovative, smart grid technologies.
Note that there are a range of studies in the context of power system expansion planning under
uncertainty [17,31,3364] and power system expansion planning with representation of increased
operational details, including unit commitment constraints [58,60,6568]. Expanding on this, we
propose a unified framework that couples infrastructure investment with market clearing/unit
commitment and real-time decisions, while considering the uncertainties in both planning and
operational time scales. We argue that the proposed framework is of utmost importance in the
smart grid context, where the value of new, innovative technologies is fundamentally based on the
provision of flexibility services that allow planners and operators to efficiently deal with various
sources of uncertainty and constraints affecting both investment decisions and system operation.
The remainder of this paper is organized as follows. Section 2 presents the proposed modelling
framework to value smart grid technologies. Section 3 describes the formulation of an instance
of the proposed framework and its application to a small, textbook-like case study. The main
notation used throughout the paper is described here. Section 4 reviews the state of the art in
power system planning under uncertainty and discusses the challenges, at the computational
and algorithmic levels, of embedding operational aspects and scaling the optimization models to
real-size power networks. Finally, section 5 concludes.
2. The modelling framework to value smart grid technologies
As argued in the previous section, the true value of smart grid technologies lies in their
flexibility and thus ability to cope with uncertainty and variability,3and this will need to be
properly recognized when planning electricity system infrastructure. In this context, we propose
a modelling framework based on mathematical programming concepts, which can capture the
effects of relevant operational constraints (so as to recognize the necessary flexibility levels to
deal with a number of variable conditions in operational time scales), as well as the importance
of uncertainty when planning new investment. To do so, the proposed framework considers
decision variables in two different time scales (investment and operation), and the presence of
long-term uncertainty to reflect the changing landscape faced by system planners, especially in
terms of available technologies, costs and market conditions, energy policy and incentives, etc.
(which may affect, for example, the future development of generation capacity that will in turn
affect network expansion). In this framework, optimal investment decisions are made before the
realization of uncertain scenarios (e.g. investment cost of a new technology), whereas operational
decisions aim to run the resulting infrastructure after each possible uncertain scenario is realized
and for a number of operating conditions (e.g. demand levels, wind power outputs, etc.). The
optimal investment decisions minimize a given metric or objective function (e.g. expected total
cost, maximum cost, maximum regret among all scenarios) and comply with a set of constraints
that ensure feasibility under an array of physical laws and market rules, as well as certain
reliability levels (e.g. system reserves requirements). The mathematical framework is shown
3Uncertainty refers to the set of alternative scenarios that may potentially occur (in the long or short term) following a known
or unknown probability distribution, while variability is certain and refers to the time-varying operating conditions that the
electricity system will face in operational time scales (i.e. combination of demand levels and renewable generation outputs).
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
7
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
in equations (2.1)–(2.3), where functional fε{·} represents the chosen utility function to select
the optimal investment vector x(·), CI(·,·)andCO(·,·) represent the investment and operational
cost functions, respectively, y(·) is the matrix of operational decisions (per component and per
operating condition or time period), εrepresents a given scenario of the uncertainty set Eand X(·)
and Y(·,·) are the feasibility sets of investment and operational decisions, respectively, where the
latter depends on the optimal investment vector x(·):
min
x(·),y(·)fε{CI(x(ε), ε)+CO(y(ε), ε)}(2.1)
subject to x(ε)X(ε), εE(2.2)
and y(ε)Y(x(ε), ε), εE. (2.3)
The proposed framework is general enough to accommodate both two- and multi-stage
optimization programs, x(·) not being dependent on εin the former case. Functional fε{·} defines
whether the model corresponds to a stochastic [69,70] or robust optimization program [71]. Set
Y(·,·), which aims to capture how the resulting infrastructure is operated and its corresponding
costs, contains the physical (and market) laws associated with power system operation and may
include first and second Kirchhoff’s laws and power flow equations, generation and network
capacity constraints (including minimum and maximum limits), inter-temporal constraints
including minimum up and down times and ramping limitations, system reserves requirements,
etc. [72]. Note that operational constraints characterize the system flexibility levels from existing
and prospective generation and network infrastructure. Therefore, these constraints are critical
to determine the need for flexible, smart grid technologies when increasing levels of renewable
generation are integrated into the electricity system.
Furthermore, we can add another level of complexity to our framework if we consider that
system operation has to be planned ahead of real time (as well as investment has to be planned
ahead of system operation). Under this new consideration, network infrastructure has to be
also flexible to deal with the forecast errors (or short-term uncertainty) related to actual system
conditions that will realize in the short-term future (e.g. next hours, next day) with respect to the
expected conditions forecasted in advance by system operators. Clearly, poor forecast methods
used, for example, to predict future wind and solar power outputs will need higher flexibility
levels from the electricity system infrastructure so as to deal with unforeseen events. In this
context, new investments should be able to cope not only with various long-term uncertainties
(e.g. trends in the investment cost of a new technology that may affect the development of
generation capacity in the future), but also uncertain changes that may occur more rapidly
in real time (e.g. due to wind forecast errors). To that end, the above-mentioned framework
can be extended as shown in equations (2.4)–(2.7), where fε,ξ{·} models the objective function
being minimized, whereas y(·)andz(·,·) represent the operational decisions undertaken in the
scheduling or operations planning time scale (e.g. day ahead) and in real time, respectively, ξ
represents a given scenario of the uncertainty set Ξthat contains a number of realizations of
operational parameters such as outputs of wind and solar power generation, generation and
network outages, etc., and set Z(·,·,·,·) represents the operational decisions that can be made in
real time (e.g. actual deployment of generation reserves), which clearly are constrained by prior
decisions made during the investment time scale (vector x(·)) and operations planning time scale
(matrix y(·)):
min
x(·),y(·),z(·,·)fε,ξ{CI(x(ε), ε)+CO(y(ε), z(ε,ξ), ε,ξ)}(2.4)
subject to x(ε)X(ε), εE, (2.5)
y(ε)Y(x(ε), ε,ξ), εE,ξΞ(2.6)
and z(ε,ξ)Z(x(ε), y(ε), ε,ξ), εE,ξΞ. (2.7)
As discussed in subsequent sections, both frameworks pose important challenges at the
computational and algorithmic levels that will need to be carefully addressed in the future to
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
8
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
work with scalable optimization models suitable for large-scale power networks. For illustration
purposes, the next section is devoted to the description of an instance of equations (2.1)–(2.3) and
its application to a small, textbook-like case study.
3. Eects of long-term uncertainty and short-term operational constraints on
system investment portfolios
(a) Overview
In order to illustrate the effects of relevant system operational constraints, as well as
the importance of uncertainty when planning new investment, we formulate an integrated
generation and network planning model jointly capturing both operational aspects and long-term
uncertainty. The resulting optimization program is a particular instance of equations (2.1)–
(2.3) that is subsequently applied to a three-node test system. The proposed model allows the
system operator/planner to manage (i) short-term constraints associated with the (in)flexibility
of conventional plants to cope with uncertainty and fast variability of renewables’ outputs and
(ii) long-term uncertainty associated with the evolution of investment costs of new technologies.
In this context, the proposed framework provides the system operator/planner with efficient
investment solutions (which we consider here as portfolios of generation, transmission, storage
and flexible transmission equipment) in order to facilitate the operational management of the
system (especially under high penetration of renewables) and permit a cost-effective adaptation
of the infrastructure even under the realization of unfavourable scenarios in the long term.
Importantly, the model also recognizes the prolonged construction times of investments such as
conventional plants and long transmission lines (that create a lag between the investment decision
and commissioning time4), as well as the faster installation process of infrastructure such as wind
and solar power units, batteries and FACTS devices (that are assumed to be installed right after
investment decisions have been made).
(b) Problem formulation
Using the notation presented in table 1, we formulate our integrated generation and network
planning problem as a stochastic, mixed-integer linear program. Note that, for unit consistency,
some variables and parameters are expressed in per unit (pu), and hourly time periods are
considered in the operation.
(i) Long-term uncertainty
Long-term uncertainty is modelled through a multi-stage scenario tree (figure 1), which describes
potential evolutions of future investment costs (especially in renewable technologies such as
solar power generation), albeit further uncertainties can be included in a straightforward manner.
Hence, as formulated in equation (3.1), the model minimizes the expected value of the total cost,
which includes the costs of investments and system operation as shown in equations (3.2) and
(3.3), respectively:
min
mM
ρmrm(τIIm+τOOm), (3.1)
Im=
gˆ
G
πIG
g¯
PG
g,m+
lˆ
L
πIL
lμL
l,m+
bˆ
B
πIB
b¯
PB
b,m+
lˆ
LQ
πIQ
lμQ
l,m,mM(3.2)
and Om=
tT
gG
πOG
gPG
g,m,t,mM. (3.3)
4Commissioning time refers to when an asset starts its operation (e.g. when a line starts transferring power). The commissioning
time minus the decision time is equal to the construction time of an asset.
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
9
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Table 1. Nomenclature (pu =per unit).
symbol meaning unit
variables
..........................................................................................................................................................................................................
¯
Cexpected total cost across all scenarios $
..........................................................................................................................................................................................................
Cmaximum total cost across all scenarios $
..........................................................................................................................................................................................................
fl,m,tpower ow of line lin scenario tree node min time period (hour) tMW
..........................................................................................................................................................................................................
fL
l,m,tpower ow of line lin scenario tree node min time period (hour) t(without the
contribution from the FACTS device)
MW
..........................................................................................................................................................................................................
fQ
l,m,tpower ow contribution of the FACTS device in line lin scenario tree node min time period
(hour) t
MW
..........................................................................................................................................................................................................
Iminvestment cost of scenario tree node m$
..........................................................................................................................................................................................................
Omoperational cost of scenario tree node m$
..........................................................................................................................................................................................................
¯
PB
b,mcapacity of battery storage plant bin scenario tree node mMW
..........................................................................................................................................................................................................
PB
b,m,tpower output of battery storage plant bin scenario tree node min time period (hour) tMW
..........................................................................................................................................................................................................
PB+
b,m,tdischarge power of battery storage plant bin scenario tree node min time period (hour) tMW
..........................................................................................................................................................................................................
PB
b,m,tcharge power of battery storage plant bin scenario tree node min time period (hour) tMW
..........................................................................................................................................................................................................
PBE
b,m,tenergy stored in battery storage plant bin scenario tree node min time period (hour) tMWh
..........................................................................................................................................................................................................
¯
PG
g,mcapacity of generator gin scenario tree node mMW
..........................................................................................................................................................................................................
PG
g,m,tpower output of generator gin scenario tree node min time period (hour) tMW
..........................................................................................................................................................................................................
θFrom/To
l,m,tvoltage angle in From/To node of line lin scenario tree node min time period (hour) trad
..........................................................................................................................................................................................................
μL
l,minstallation of line lin scenario tree node m{0,1}
..........................................................................................................................................................................................................
μQ
l,minstallation of the FACTS device in line lin scenario tree node m{0,1}
..........................................................................................................................................................................................................
parameters
..........................................................................................................................................................................................................
AG
g,tavailability factor of generator gin time period (hour) tpu
..........................................................................................................................................................................................................
Dn,m,tdemand in node nin scenario tree node min time period (hour) tMW
..........................................................................................................................................................................................................
¯
flcapacity of line lMW
..........................................................................................................................................................................................................
¯
fQ
lmaximum capability to shift power of the FACTS device in line lMW
..........................................................................................................................................................................................................
rmdiscount factor of scenario tree node mpu
..........................................................................................................................................................................................................
RDW
gdownward ramp rate limit of generator gasapercentageofitscapacityperhour %h
1
..........................................................................................................................................................................................................
RUP
gupward ramp rate limit of generator gasapercentageofitscapacityperhour %h
1
..........................................................................................................................................................................................................
Xlreactance of line lΩ
..........................................................................................................................................................................................................
ηbround-trip eciency of battery storage plant bpu
..........................................................................................................................................................................................................
λrisk-aversion factor pu
..........................................................................................................................................................................................................
πIB
bunitary investment cost of battery storage plant b(annuitized) $ MW1yr1
..........................................................................................................................................................................................................
πIG
gunitary investment cost of generator g(annuitized) $ MW1yr1
..........................................................................................................................................................................................................
πIL
linvestment cost of line l(annuitized) $ yr1
..........................................................................................................................................................................................................
πIQ
linvestment cost of the FACTS device in line l(annuitized) $ yr1
..........................................................................................................................................................................................................
πOG
gvariable cost of generator g$MWh
1
..........................................................................................................................................................................................................
(Continued.)
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
10
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Table 1. (Continued.)
symbol meaning unit
ρmprobability of scenario tree node mpu
..........................................................................................................................................................................................................
τB
benergy capacity of battery storage plant bmeasured in hours at full power capacity h
..........................................................................................................................................................................................................
τIscaling factor to transform annuitized investment cost into investment cost in an epoch pu
..........................................................................................................................................................................................................
τOscaling factor to transform operational cost in representative days into operational cost in
an epoch
pu
..........................................................................................................................................................................................................
Ψsuciently large positive constant MW
..........................................................................................................................................................................................................
set-related symbols
..........................................................................................................................................................................................................
Bset of battery storage plants
..........................................................................................................................................................................................................
ˆ
Bset of candidate battery storage plants
..........................................................................................................................................................................................................
Bnset of battery storage plants in node n
..........................................................................................................................................................................................................
Fromnset of lines that start from node n
..........................................................................................................................................................................................................
Gset of generators
..........................................................................................................................................................................................................
ˆ
Gset of candidate generators
..........................................................................................................................................................................................................
GCset of conventional generators
..........................................................................................................................................................................................................
ˆ
GCset of candidate conventional generators
..........................................................................................................................................................................................................
Gnset of generators in node n
..........................................................................................................................................................................................................
Lset of lines
..........................................................................................................................................................................................................
ˆ
Lset of candidate lines
..........................................................................................................................................................................................................
ˆ
LQset of candidate FACTS devices
..........................................................................................................................................................................................................
Mset of scenario tree nodes
..........................................................................................................................................................................................................
MSset of the scenario tree nodes that contains one child node of each parent node in the
scenario tree
..........................................................................................................................................................................................................
Nset of nodes
..........................................................................................................................................................................................................
p(m) parent node of scenario tree node m
..........................................................................................................................................................................................................
Smset of sibling nodes of scenario tree node m
..........................................................................................................................................................................................................
SC set of uncertain scenarios
..........................................................................................................................................................................................................
Scjset of scenario tree nodes in scenario j
..........................................................................................................................................................................................................
Tset of time periods (hours)
..........................................................................................................................................................................................................
Tonset of lines that go to node n
..........................................................................................................................................................................................................
As formulated in equation (3.2), investment costs include terms related to new conventional
and renewable generation, new lines, new storage plants and new FACTS devices (shown in this
order in equation (3.2)). Equation (3.3) models the fuel costs of thermal power units across all time
periods.
As per equations (3.4) and (3.5), we assume that investments are irreversible and that some of
them feature a lag of one epoch (i.e. several years) between decision and commissioning times,
respectively. Note that equation (3.5) constrains some investment decisions to be equal among
sibling nodes, which is caused by the above-mentioned one-epoch lag. Owing to their prolonged
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
11
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
2 is
parent
of 4
1 is
parent
of 2
2 and 3
are
siblings
epoch
1
epoch
2
epoch
3
time
m=2
m=4
m=5
m=1
m=6
m=7
m=3
r4
r2
r1
r5
r6
r3
r7
r
24
r
25
r
12
r
36
r13
r
37
Figure 1. Multi-stage scenario tree indicating epochs (i.e. discretization of the time horizon; equivalent to a group of years),
parent nodes, sibling nodes, transition probabilities (ρij) and node probabilities (ρm).
construction times, investment in conventional assets cannot be commissioned in epoch 1 as
imposed in equation (3.6):
¯
PG
g,m,μL
l,m,¯
PB
b,m,μQ
l,m¯
PG
g,p(m),μL
l,p(m),¯
PB
b,p(m),μQ
l,p(m),gˆ
G,lˆ
L,bˆ
B,m∈{M\m=1},
(3.4)
¯
PG
g,m=¯
PG
g,k,gˆ
GC,mMS,kSm,
μL
l,m=μL
l,k,lˆ
L,mMS,kSm,
(3.5)
¯
PG
g,1 =0, gˆ
GC,
and μL
l,1 =0, lˆ
L.
(3.6)
(ii) System operation
The effect of the transmission network is characterized by a linearized power flow model.
Equation (3.7) models the first Kirchhoff’s law for nodal injections and withdrawals, whereby the
sum of power inputs is equal to the sum of power outputs in a node. Power flows through a line
can be decomposed into a transfer contribution from the line itself and another from its FACTS
device (if installed) as shown in equation (3.8) (this is known as the power injection model of a
FACTS device [73]), and the total transfer is limited by the capacity of the line (see equation (3.9)).
Equation (3.10) shows that FACTS devices (in this case a quad-booster phase-shifting transformer
[73]) also have limited capability to shift power. In addition, equation (3.11) represents the second
Kirchhoff’s law, where a disjunctive, big-M-based model [74] is used for new lines, Ψbeing
a sufficiently large positive constant. For existing network infrastructure, we can assume that
μL
l,m=μQ
l,m=1 in all equations. Similarly, for those lines where there are no candidate FACTS
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
12
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
devices (i.e. l/ˆ
LQ), we assume μQ
l,m=0 and, therefore, fQ
l,m,t=0:
gGn
PG
g,m,t+
bBn
PB
b,m,tDn,m,t=
lFromn
fl,m,t
lTon
fl,m,t,nN,mM,tT, (3.7)
fl,m,t=fL
l,m,t+fQ
l,m,t,lL,mM,tT, (3.8)
¯
flμL
l,mfl,m,t¯
flμL
l,m,lL,mM,tT, (3.9)
¯
fQ
lμQ
l,mfQ
l,m,t¯
fQ
lμQ
l,m,lL,mM,tT, (3.10)
and Ψ(1 μL
l,m)+θFrom
l,m,tθTo
l,m,t
Xl
fL
l,m,tθFrom
l,m,tθTo
l,m,t
Xl
+Ψ(1 μL
l,m),
lL,mM,tT. (3.11)
Generating units are also constrained by both their available power capacity (driven by the
availability of renewable resources, the maximum generation capacity for all units and outages
for conventional units) and their ramp rate limits (equations (3.12) and (3.13), respectively, where
we assume that only conventional generation features ramping-related limitations). Furthermore,
energy storage plants, which are modelled through equations (3.14)–(3.17), can provide services
associated with energy arbitrage (i.e. charge/discharge actions to improve the system load
factor, charging during off-peak periods and discharging during peak periods following the
minimization of the total cost in equation (3.1)) and flexibility (since storage plants are not affected
by ramp rate constraints such as those specified in equation (3.13) for generating units):
PG
g,m,t¯
PG
g,mAG
g,t,gG,mM,tT, (3.12)
RDW
g¯
PG
g,mPG
g,m,tPG
g,m,t1RUP
g¯
PG
g,m,gGC,mM,tT, (3.13)
¯
PB
b,mPB
b,m,t¯
PB
b,m,bB,mM,tT, (3.14)
PB
b,m,t=PB+
b,m,tPB
b,m,t,bB,mM,tT, (3.15)
PBE
b,m,t=PBE
b,m,t1PB+
b,m,t+PB
b,m,tηb,bB,mM,tT(3.16)
and PBE
b,m,t¯
PB
b,mτB
b,bB,mM,tT. (3.17)
Finally, all decision variables are continuous and non-negative, except for (i) power transfers,
voltage angles and net outputs of storage plants, which may be negative, and (ii) investment
variables associated with new network infrastructure, which are binary, indicating whether a
candidate asset has been chosen for investment (binary variable equal to 1) or not (binary variable
equalto0).
Note that further details can be included in a straightforward manner in the operational
model by adding more variables, constraints and cost functions related to units’ minimum stable
generations, start-up and shut-down costs, minimum up and down times, etc. (see, for instance,
[65,67,68,75]), albeit the current level of detail (equations (3.1)–(3.17)) suffices to illustrate the
importance of operational constraints (through ramp rate and time-coupling constraints, besides
power flow and capacity constraints) when planning future infrastructure. Likewise, further
details associated with the necessary security margins (e.g. generation and network reserves)
to face random faults of system components can also be critical in investment planning models
[28]. In the context of stochastic programming, these considerations will significantly increase the
number of variables and constraints and thus the computational burden, as discussed in §4.
(iii) Risk aversion
While the previous objective function in equation (3.1) corresponds to a risk-neutral planner, the
decision-making process of a risk-averse, conservative planner can also be accommodated in the
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
13
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
G1
G3 N3 S
D
N1 N2
L23
L13
L¢23
G2
W
B
QB
L12
Figure 2. Three-node system topology, where candidate assets for investment are shown in dashed lines.
proposed optimization framework. To that end, equation (3.1) is replaced with equations (3.18)–
(3.20) where a weighted average of the expected total cost and the maximum total cost across
scenarios is minimized:
min{λ¯
C+(1 λ)C}, (3.18)
¯
C=
mM
ρmrm(τIIm+τOOm) (3.19)
and C
mScj
rm(τIIm+τOOm), jSC. (3.20)
(iv) Planning under perfect (deterministic) information
Note that we can also minimize each scenario’s total cost as shown in equation (3.21). Here, the
planner assumes perfect information of the future and thus the associated (deterministic) solution
may represent an investment option that cannot be efficiently adapted if a different scenario
(which was, in fact, ignored) is realized. This case can also be considered as a base, reference
case:
min
mScj
rm(τIIm+τOOm)
,jSC. (3.21)
(c) Illustrative example
(i) Input data
We study the electricity network depicted in figure 2 with three nodes (N1, N2 and N3),
three existing conventional generators (G1, G2 and G3), three existing lines (L12, L13 and L23)
and one load (D). In order to face the forecasted demand growth along a planning horizon
comprising three epochs spanning five years each, the system can be expanded through wind
power generation (W), solar power generation (S), a line (L’23), a FACTS device, namely a quad-
booster phase-shifting transformer (QB) [73], and a battery storage system (B). The input data
used to run our stochastic program are shown in table 2, where base values for power and voltage
are 100 MVA and 66kV, respectively.
For illustration purposes, uncertainty is solely associated with the future evolution of
investment costs of solar power generation. The problem’s scenario tree is illustrated in figure 3,
which describes both the transition probabilities between nodes and PV investment costs in each
node (relative to that listed in table 2). Note that investment costs of solar power generation might
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
14
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Table 2. Relevant input data.
..........................................................................................................................................................................................................
investment cost
..........................................................................................................................................................................................................
wind power generation ($ MW1yr1) 150 000
..........................................................................................................................................................................................................
solar power generation ($ MW1yr1) 250 000
..........................................................................................................................................................................................................
battery ($ MW1yr1) 130 000a
..........................................................................................................................................................................................................
QB ($ yr1) 8000
..........................................................................................................................................................................................................
L’23 ($ yr1) 10 000
..........................................................................................................................................................................................................
operational cost
..........................................................................................................................................................................................................
G1 ($ MWh1)50
..........................................................................................................................................................................................................
G2 ($ MWh1)30
..........................................................................................................................................................................................................
G3 ($ MWh1)100
..........................................................................................................................................................................................................
demand
..........................................................................................................................................................................................................
yearly growth rate (%) 1
..........................................................................................................................................................................................................
peak (MW) 100
..........................................................................................................................................................................................................
capacity
..........................................................................................................................................................................................................
G1 (MW) 60
..........................................................................................................................................................................................................
G2 (MW) 60
..........................................................................................................................................................................................................
G3 (MW) 100
..........................................................................................................................................................................................................
L12 (MW)
..........................................................................................................................................................................................................
L13 (MW)
..........................................................................................................................................................................................................
L23 (MW) 57
..........................................................................................................................................................................................................
L’23 (MW ) 57
..........................................................................................................................................................................................................
QB (MW) 9
..........................................................................................................................................................................................................
storage
..........................................................................................................................................................................................................
eciency (%) 90
..........................................................................................................................................................................................................
energy capacity (in hours at maximum power output) (h) 2
..........................................................................................................................................................................................................
further data
..........................................................................................................................................................................................................
yearly discount rate (%) 5
..........................................................................................................................................................................................................
lines’ reactance (pu) 0.01
..........................................................................................................................................................................................................
G1 ramp rate (% h1)10
..........................................................................................................................................................................................................
G2 ramp rate (% h1)30
..........................................................................................................................................................................................................
aInvestment cost in the rst epoch. Weassume that the investment cost of the battery storage system decreases down to 50% and 20% of its
original value in epochs 2 and 3, respectively.
fall significantly in the future in scenario 1. Under such a scenario, solar power plants might be
installed at the consumers’ location, leaving conventional generation and network assets stranded
(at least partially). On the other hand, if future investment costs remain at today’s levels, as
modelled in scenario 4, wind power generation (which is assumed to be significantly less costly
at present) is likely to be installed. Given that the location of candidate wind power generation
is far from the load centre, investment in this technology would also require further transmission
investment that needs to be planned significantly ahead of actual commissioning. In fact, we
assume that while the transmission line features a lag of 1 epoch (e.g. 5 years), the remaining
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
15
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
m=4
m=2
m=5
m=6
m=3
m=7
epoch
1
epoch
2
epoch
3time
m=1
100%
scenario 4: high investment
cost of solar power generation
scenario 3: mid-high investmen
t
cost of solar power generation
scenario 2: mid-low investment
cost of solar power generation
scenario 1: low investment
cost of solar power generation
90%
90%
80%
50%
50%
40%
0.5
0.5
0.5
0.5
0.5
0.5
Figure 3. Three-stage scenario tree indicating investment cost evolutionof solar power generation (as a percentage of the cost
listed in table 2) and transition probabilities. We dene set MS={2,4,6}, which contains one child node per parent node.
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1 2 3 4 5 6 7 8 9 101112131415161718192021222324
power (pu)
time (h)
demand
wind power
solar power
Figure 4. Demand, wind and solar power proles (per unit, pu) in the representative day.
assets can be commissioned faster (i.e. with negligible lag). Further to the need for dealing with
investment uncertainty, the planner may also face important challenges at the operational time
scale when managing increased amounts of renewable generation. In this outlook, demand, wind
and solar power profiles, as shown in figure 4, are used to clearly illustrate the need for ramping,
which will be used here as an example of an operational constraint to be considered in planning.
Owing to the illustrative purpose of this example, days are assumed equal across a year and thus
weekly and seasonal variations are ignored. While this simplification does not affect our general
conclusions, further details like those neglected in this example may need to be captured for real
applications.
The proposed model has been implemented using FICO®Xpress [76]. For the sake of
reproducibility, the code and associated data files can be downloaded from [77].
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
16
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Table 3. Results from the deterministic model: expansion plan per epoch and scenario, and costs per scenario (W, S, L’23, B
and QB mean investments in wind power generation, solar power generation, line, battery and quad-booster transformer,
respectively, and the additional capacity in MW is indicated within ).
scenario 1 low scenario 2 mid-low scenario 3 mid-high scenario 4 high
expansion plan per epoch and scenario
..........................................................................................................................................................................................................
epoch 1 W16W16W19W19
..........................................................................................................................................................................................................
epoch 2 S39S39W7, L’23 W7, L’23
..........................................................................................................................................................................................................
epoch 3 S18S5,W2W1W1
..........................................................................................................................................................................................................
costs per scenario (k$)
..........................................................................................................................................................................................................
investment 59 896 60 047 38 665 38 665
..........................................................................................................................................................................................................
operation 240 974 244 321 270 624 270 624
..........................................................................................................................................................................................................
total 300 870 304 368 309 289 309 289
..........................................................................................................................................................................................................
(ii) Results
Eects of long-term uncertainty on system planning
Table 3 shows the results per epoch and scenario attained by the deterministic model (equation
(3.21)). While in scenarios 1 and 2 the significant drop in investment cost of solar power generation
encourages the adoption of this technology in the future (producing power right at the point of
consumption), the still relatively high investment cost of solar power generation in later epochs
of scenarios 3 and 4 encourages investment in wind power, far from the load centre. Expectedly,
conventional network reinforcement in the form of a new transmission line is needed in scenarios
3 and 4 (unlike in scenarios 1 and 2) in order to transfer power from remote areas to the load
centre. In the first epoch when the investment cost of solar power generation remains relatively
high, wind power plants are built in all scenarios.
Table 4 presents the results per epoch and scenario determined by the risk-neutral stochastic
model. In contrast to the above deterministic case, this table demonstrates that in no scenario is
there any conventional network investment needed to cope with the uncertainty levels faced by
the planner in the first epoch. Indeed, the model determines that epoch 1 is too early to decide
whether to invest in a long power line (commissioned at the beginning of epoch 2) that may
end up stranded under the realization of scenarios 1 and 2 where solar power emerges right at
the location of consumption. Rather, the stochastic approach chooses to ‘wait and see’ and thus
potential network congestions (under scenarios 3 and 4) are managed in the operational time scale
through smart technologies such as FACTS/QB devices that can be chosen and quickly installed
right in epoch 2. This solution is complemented later on with a battery storage plant to face larger
amounts of wind power that materialize towards the end of the analysed planning horizon, also
considering the drop in cost of batteries in the meantime.
It is important to point out that table 3 shows the costs associated with the best expansion plan
for each scenario considered by the planner to characterize the uncertain future. In contrast, the
solution summarized in table 4 corresponds to the investment plan performing best on average
for the scenario set under consideration. In other words, the costs reported in table 3 will only
be incurred if the corresponding scenario actually materializes. Otherwise, the costs associated
with such expansion plans may significantly differ should other scenarios occur. Moreover, the
expected total costs for the deterministic solutions summarized in table 3 are greater than or equal
to that of the optimal stochastic solution. Table 5 presents the total costs per scenario and the
expected total costs for the deterministic solutions reported in table 3 and the stochastic solution
given in table 4. As can be observed, the stochastic solution is identical to the best expansion plans
for scenarios 1 and 2, whereas, for scenarios 3 and 4, a slight 0.03% cost increase is incurred over
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
17
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Tabl e 4. Results from the risk-neutral stochastic model: expansion plan per epoch and scenario,costs per scenario and expected
costs (W, S, L’23, B and QB mean investments in wind power generation, solar powergeneration, line, battery and quad-booster
transformer, respectively, and the additional capacity in MW is indicated within ). Note that the results follow the scenario
tree structure depicted in gure 3.
scenario 1 low scenario 2 mid-low scenario 3 mid-high scenario 4 high
expansion plan per epoch and scenario
..........................................................................................................................................................................................................
epoch 1 W16
..........................................................................................................................................................................................................
epoch 2 S39W10,QB
..........................................................................................................................................................................................................
epoch 3 S18S5,W2B1B1
..........................................................................................................................................................................................................
costs per scenario (k$)
..........................................................................................................................................................................................................
investment 59 896 60 047 35 853 35 853
..........................................................................................................................................................................................................
operation 240 974 244 321 273 517 273 517
..........................................................................................................................................................................................................
total 300 870 304 368 309 370 309 370
..........................................................................................................................................................................................................
expected costs (k$)
..........................................................................................................................................................................................................
investment 47 912
..........................................................................................................................................................................................................
operation 258 082
..........................................................................................................................................................................................................
total 305 994
..........................................................................................................................................................................................................
Table 5. Total costs per scenario and expec ted total costs for the deterministic solutions and the stochastic solution.
deterministic
solution for
scenario 1
deterministic
solution for
scenario 2
deterministic
solution for
scenario 3
deterministic
solution for
scenario 4
stochastic
solution
total cost per scenar io (k$)
..........................................................................................................................................................................................................
scenario 1 low 300 870 301 287 309 289 309 289 300 870
..........................................................................................................................................................................................................
scenario 2 mid-low 304 853 304 368 309 289 309 289 304 368
..........................................................................................................................................................................................................
scenario 3 mid-high 330 777 327 587 309 289 309 289 309 370
..........................................................................................................................................................................................................
scenario 4 high 334 760 330 668 309 289 309 289 309 370
..........................................................................................................................................................................................................
expected total cost (k$) 317 815 315 977 309 289 309 289 305 994
..........................................................................................................................................................................................................
the best expansion plans for such scenarios. On the other hand, cost increases as high as 8.2%
can be experienced if the planner adopts a deterministic solution and a different from forecasted
scenario is realized. Moreover, table 5 also shows that the stochastic solution outperforms all
deterministic solutions in terms of the expected total cost, with considerable improvement factors
ranging between 3.7% and 1.1%.
Interestingly, although the stochastic model constrains the final volume of wind capacity
connected in scenarios 3 and 4, it is possible to demonstrate that, overall, this is better than
building a line that ends up stranded in scenarios 1 and 2. In fact, a sensitivity analysis where we
force the stochastic model to commission a new transmission line in epoch 2 (shown in table 6)
reveals that costs under scenarios 1 and 2 escalate with respect to those observed under the truly
stochastic solution and this cannot be compensated for by the cost reduction under scenarios 3
and 4. Furthermore, the early investment in a transmission line is not only economically inefficient
but also prevents the utilization of smart grid technologies (FACTS/QB and battery plant) that
have been displaced by the line.
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
18
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Table 6. Results from the risk-neutral stochastic model with forced commissioning of conventional network infrastructure:
expansion plan per epoch and scenario, costs per scenario and expected costs (W, S, L’23, B and QB mean investments in wind
power generation, solar powergeneration, line, battery and quad-booster transformer, respectively,and the additional capacity
in MW is indicated within ). Note that the results follow the scenario tree struc ture depicted in gure 3.
scenario 1 low scenario 2 mid-low scenario 3 mid-high scenario 4 high
expansion plan per epoch and scenario
..........................................................................................................................................................................................................
epoch 1 W16
..........................................................................................................................................................................................................
epoch 2 S39, L’23 W10, L’23
..........................................................................................................................................................................................................
epoch 3 S18S5,W2W1W1
..........................................................................................................................................................................................................
costs per scenario (k$)
..........................................................................................................................................................................................................
investment 59 959 60 110 36 487 36 487
..........................................................................................................................................................................................................
operation 240 975 244 321 272 859 272 859
..........................................................................................................................................................................................................
total 300 934 304 431 309 346 309 346
..........................................................................................................................................................................................................
expected costs (k$)
..........................................................................................................................................................................................................
investment 48 261
..........................................................................................................................................................................................................
operation 257 753
..........................................................................................................................................................................................................
total 306 014
..........................................................................................................................................................................................................
Note that the stochastic model builds minimum amounts of wind power infrastructure in
epoch 1 so as to ‘wait and see’ whether the investment cost of solar power decreases; if it
does, then solar power investment is preferred (scenarios 1 and 2), more wind power being
commissioned otherwise. Table 7, where the maximum amount of wind power has been forcedly
commissioned in epoch 1, shows that installing higher levels of wind power generation in
epoch 1 (as the deterministic model suggests) will limit the ability to integrate solar power
in the future when investment costs fall, thereby decreasing the overall cost efficiency of the
stochastic solution.
It is important to point out that the forced commissioning of network and generation assets
yields solutions with expected total costs that are slightly higher than that incurred by the optimal
stochastic solution and well below those featured by the deterministic solutions. Thus, tables 4,
6and 7show the inefficiencies (advantages) of implementing deterministic (stochastic) solutions
when planning under uncertainty. Note that, in this illustrative example (which demonstrates
the need to make investment plans more flexible through smart grid technologies and thus face
uncertain scenarios more efficiently), uncertainty is associated with investment costs of solar
power generation only. Hence, the consequences of following deterministic planning can be much
more significant in real systems subject to additional sources of uncertainty such as energy policy
incentives, development of new technologies, demand growth, various decentralized decisions
from market participants, etc.
Finally, risk aversion is analysed through the minimization of a weighted average of the
expected and the maximum total costs across scenarios (table 8), with parameter λin equation
(3.18) taken as equal to 0.5 for the low-aversion case, and equal to zero in the high-aversion
case (corresponding to the min–max cost optimization). As compared with the risk-neutral
solution shown in table 4, the optimal risk-averse investment plans feature larger volumes of
wind power generation in epoch 1. Although both expansion plans are less efficient solutions in
terms of the expected total cost, increasing the levels of wind power generation commissioned in
epoch 1 is an effective measure to reduce the costs in the more costly scenarios, i.e. scenarios 3
and 4. Interestingly, for low levels of risk aversion, the planner prefers to install larger amounts
of wind power generation capacity in epoch 1 rather than investing in conventional network
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
19
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Table 7. Results from the risk-neutral stochastic model with forced commissioning of higher levels of wind power generation
in the rst epoch: expansion plan per epoch and scenario, costs per scenario and expected costs (W, S, L’23, B and QB mean
investments in wind power generation, solar power generation, line, battery and quad-booster transformer, respectively, and
the additional capacity in MW is indicated within ). Note that the results followthe scenario tree structure depicted in gure 3.
scenario 1 low scenario 2 mid-low scenario 3 mid-high scenario 4 high
expansion plan per epoch and scenario
..........................................................................................................................................................................................................
epoch 1 W19
..........................................................................................................................................................................................................
epoch 2 S38W7,QB
..........................................................................................................................................................................................................
epoch 3 S19S5B1B1
..........................................................................................................................................................................................................
costs per scenario (k$)
..........................................................................................................................................................................................................
investment 64 533 63 856 38 030 38 030
..........................................................................................................................................................................................................
operation 236 500 240 593 271 283 271 283
..........................................................................................................................................................................................................
total 301 033 304 449 309 313 309 313
..........................................................................................................................................................................................................
expected costs (k$)
..........................................................................................................................................................................................................
investment 51 113
..........................................................................................................................................................................................................
operation 254 914
..........................................................................................................................................................................................................
total 306 027
..........................................................................................................................................................................................................
infrastructure that can allow the planner to install further wind power generation capacity
towards the last epoch. This is so because conventional network investment would unnecessarily
increase the total costs in scenarios 1 and 2 (and thus the expected total cost). For higher levels of
risk aversion and, in the extreme case, for the fully averse min–max cost solution, conventional
network investment is necessary to minimize the total costs under the worst conditions, which
also eliminates the need for smart grid solutions. It is important to mention that this extreme
solution focuses on total cost minimization under the worst conditions (in this case, scenarios 3
and 4) irrespective of the inefficiencies caused in terms of the expected total cost and, in particular,
under those scenarios where solar power generation is realized in the future (when the new
transmission line becomes unnecessary and stranded).
Eects of short-term operational constraints on system planning
In the previous examples, the results discussed in tables 38account for ramp rate constraints in
all scenarios, as indicated in table 2.Table 9 shows the resulting infrastructure investment and the
total costs for the solutions to the following three different deterministic cases for scenario 1, which
corresponds to a low investment cost of solar power generation.
(i) When the infrastructure is optimized by ignoring ramp rate constraints: although the
total cost is the lowest, it underestimates the actual cost of operating large volumes of
renewables.
(ii) When the infrastructure is optimized by ignoring ramp rate constraints and the actual
cost of operation is adequately quantified in a second stage when considering actual
ramp rate limitations: the total cost is the highest since the planner ignores important
operational constraints (when the system infrastructure was determined).
(iii) When the infrastructure is adequately planned and optimized by accounting for ramp
rate constraints (G1 and G2’s ramp rates equal to 10% h1): this corresponds to the true
cost of the optimal solution.
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
20
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Tabl e 8. Results from therisk-aversemodel: expansion planper epoch andscenario,costs per scenarioand expected costs (W,S,
L’23, Band QB meaninvestmentsin wind powergeneration,solar power generation,line, batteryand quad-booster transformer,
respectively, and the additional capacity in MW is indicated within ). Note that the results follow the scenario tree structure
depicted in gure 3.
scenario 1 low scenario 2 mid-low scenario 3 mid-high scenario 4 high
risk-averse solution 1 (low aversion)
..........................................................................................................................................................................................................
expansion plan per epoch and scenario
..........................................................................................................................................................................................................
epoch 1 W19
..........................................................................................................................................................................................................
epoch 2 S38W7,QB
..........................................................................................................................................................................................................
epoch 3 S19S6B1B1
..........................................................................................................................................................................................................
costs per scenario (k$)
..........................................................................................................................................................................................................
investment 63 485 62 888 37 603 37 603
..........................................................................................................................................................................................................
operation 237 501 241 525 271 721 271 721
..........................................................................................................................................................................................................
total 300 986 304 413 309 324 309 324
..........................................................................................................................................................................................................
expected costs (k$)
..........................................................................................................................................................................................................
investment 50 395
..........................................................................................................................................................................................................
operation 255 617
..........................................................................................................................................................................................................
total 306 012
..........................................................................................................................................................................................................
risk-averse solution 2 (high aversion, min–max cost)
..........................................................................................................................................................................................................
expansion plan per epoch and scenario
..........................................................................................................................................................................................................
epoch 1 W19
..........................................................................................................................................................................................................
epoch 2 S38, L’23 W7, L’23
..........................................................................................................................................................................................................
epoch 3 S19S5W1W1
..........................................................................................................................................................................................................
costs per scenario (k$)
..........................................................................................................................................................................................................
investment 64 597 63 919 38 665 38 665
..........................................................................................................................................................................................................
operation 236 499 240 593 270 624 270 624
..........................................................................................................................................................................................................
total 301 096 304 512 309 289 309 289
..........................................................................................................................................................................................................
expected costs (k$)
..........................................................................................................................................................................................................
investment 51 461
..........................................................................................................................................................................................................
operation 254 586
..........................................................................................................................................................................................................
total 306 047
..........................................................................................................................................................................................................
The results shown in table 9 demonstrate that modelling detailed operational constraints can
be critical when planning electrical infrastructure. For example, if this electricity system were
planned with fully flexible ramp rates from conventional plants (in other words, ignoring ramp
rate constraints as in solution (i), which is a widespread implicit assumption in most planning
exercises and available planning tools), larger volumes of renewables would be installed with
no need for storage plants. This would clearly increase the cost of operation in reality, when
considering the actual system’s flexibility limitations (see solution (ii)), and would probably result
in investment into suboptimal technologies. In contrast, if ramp rates are adequately considered
in the planning model as in solution (iii), then less renewable energy capacity is built because of
the diminished ability of the system to cope with intermittency. Further, storage capacity becomes
necessary to provide operational flexibility.
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
21
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Table 9. Results from the deterministic model under three dierent assumptions on system’s exibility for scenario 1
corresponding to a low investmentcost of solar power generation: expansion plan per epoch and solution, and costs per solution
(W, S, L’23, B and QB mean investments in wind power generation, solar power generation, line, battery and quad-booster
transformer,respectively,and the additional capacityin MW isindicatedwithin ). Roman numeralsof the solutions correspond
to the cases described in the main text.
solution (i) solution (ii) solution (iii)
expansion plan per epoch and solution
..........................................................................................................................................................................................................
epoch 1 W16W16W14
..........................................................................................................................................................................................................
epoch 2 S39S39S40
..........................................................................................................................................................................................................
epoch 3 S18S18S11,B5
..........................................................................................................................................................................................................
costs per solution (k$)
..........................................................................................................................................................................................................
investment 59 896 59 896 55 507
..........................................................................................................................................................................................................
operation 240 974 242 437 246 467
..........................................................................................................................................................................................................
total 300 870 302 333 301 974
..........................................................................................................................................................................................................
Tabl e 10. Results from the risk-neutral stochastic model without ramp rate constraints on G1 and G2: expansion plan per epoch
and scenario, costs per scenario and expected costs (W, S, L’23, B and QB mean investments in wind power generation, solar
power generation, line, battery and quad-booster transformer, respectively, the additional capacity in MW is indicated within
and N/I refers to ‘no investment’). Note that the results follow the scenario tree structure depicted in gure 3.
scenario 1 low scenario 2 mid-low scenario 3 mid-high scenario 4 high
expansion plan per epoch and scenario
..........................................................................................................................................................................................................
epoch 1 W16
..........................................................................................................................................................................................................
epoch 2 S39W10,QB
..........................................................................................................................................................................................................
epoch 3 S18S5,W2N/I N/I
..........................................................................................................................................................................................................
costs per scenario (k$)
..........................................................................................................................................................................................................
investment 59 896 60 047 35 827 35 827
..........................................................................................................................................................................................................
operation 240 974 244 321 273 525 273 525
..........................................................................................................................................................................................................
total 300 870 304 368 309 352 309 352
..........................................................................................................................................................................................................
expected costs (k$)
..........................................................................................................................................................................................................
investment 47 899
..........................................................................................................................................................................................................
operation 258 087
..........................................................................................................................................................................................................
total 305 986
..........................................................................................................................................................................................................
Furthermore, table 10 shows that if the system is planned through the risk-neutral stochastic
model while ignoring ramp rate constraints, storage infrastructure (originally installed in scenarios
3 and 4 as shown in table 4) is not needed. This illustrates the importance of considering both the
system’s flexibility limitations (table 9) and uncertainty (table 10) in order to properly capture the
value of smart grid technologies and invest in the most appropriate portfolio in the first place.
Discussion
As mentioned earlier, it is important to emphasize that there are a range of studies in the context of
power system expansion planning under uncertainty (see, for instance, [17,31,3364]) and power
system expansion planning with representation of increased operational details, including unit
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
22
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
commitment constraints (see, for instance, [58,60,6568]). Expanding on this, we argue that the
proposed unified framework evaluated above is of utmost importance in the smart grid context,
where the value of new, innovative technologies is fundamentally based on the provision of
flexibility services that allow planners and operators to efficiently deal with various sources of
uncertainty and constraints affecting both investment decisions and system operation.
Furthermore, notice that the above results correspond to an instance of equations (2.1)–(2.3),
where operational uncertainty has been neglected and, instead, replaced with the modelling of
variability in operational parameters such as wind and solar power outputs. Another level of
complexity will be to run an instance of equations (2.4)–(2.7) where uncertainty is considered
in both planning and operational time scales. Under this consideration, generation and network
infrastructure have to be also flexible to deal with equipment outages and forecast errors that
may happen in real time, and thus new investments should be able to cope with both long-term
uncertainties and also uncertain changes that may occur rapidly in real time. There are various
studies that demonstrate the importance of short-term uncertainty and security for power system
planning (see, for instance, [28]), and we believe that, with the advent of new technology, such
importance will be exacerbated since innovative technologies can successfully provide (at least
partially) the flexibility and security needed in real time and hence displace (or at least defer)
part of the new conventional infrastructure. Therefore, modelling both long- and short-term
uncertainty will be key to properly quantify the benefits of smart grid technologies.
4. Modelling and computational challenges
Following up on our multi-stage stochastic programming modelling framework presented above
and demonstrated on a small test system, and with reference to the state of the art in power
system planning under uncertainty, in this section we aim: (i) to present in more general
terms the main families of problems dealing with power system planning under uncertainty
(of which our framework is a subset); (ii) to discuss the main challenges, at the computational
and algorithmic levels, of embedding detailed operational aspects in planning under uncertainty
problems, especially when dealing with real-size networks; and (iii) to advocate the need for new
optimization tools that could address these computational challenges in order to properly value
the benefits of flexible, smart grid solutions in planning.
Current models for power system planning under uncertainty lie within one of the four
classes of problems resulting from the combination of: (i) the temporal framework adopted for
decisions with uncertainty about future evolution, namely, dynamic (or multi-stage), whereby in
each period decisions are made under uncertainty of successive ones, versus static (or single-stage),
whereby decisions are made in a single period under the same information level for all future
periods [48]; and (ii) the modelling of uncertainty characterization,namely,stochastic programming,
which uses probabilistic models to characterize uncertainty [70], versus robust optimization,which
ensures feasibility for a user-defined set of uncertainty realizations or scenarios and is particularly
useful when the definition of a probability distribution is not an easy task, e.g. occurrence of
contingencies, strategic actions of market participants and evolution of fuel prices [71].
(a) Multi-stage stochastic planning
The class of multi-stage stochastic optimization models [70] is of great importance in power
system planning and encompasses many applications in many subareas (e.g. hydrothermal
planning [35], transmission expansion planning [42,49] and generation expansion planning
[41,50,51]) and aims to emulate the way decisions are made in the real world while uncertainty
is revealed over time. For computational tractability, this logic is applied only to investment
decisions and long-term uncertainties, while short-term operational uncertainties and decisions
are generally simplified or even disregarded, on the basis of the (traditionally) weak time
dependence between short-term and investment-related decisions. However, as we argued
through our multi-stage optimization textbook-like examples, it is key that operational aspects
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
23
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
that come with smart grid technologies and flexible devices are suitably taken into account in
planning too.
The requirement for more detailed modelling of operational flexibility introduces manifold
computational and methodological challenges in multi-stage stochastic planning problems, which
may be intractable for real-life benchmarks. Decomposition techniques can, therefore, be most
useful. In this outlook, a natural decomposition scheme arises from the temporal and conditional
nature of the uncertainty revelation structure, whereby the problem can be cast as a discrete-time
control problem that follows Bellman’s principle, thus being suitable for dynamic programming.
Benders-type decomposition procedures and dynamic programming [70], as well as sampling
techniques such as Monte Carlo simulation, are well-known approaches used to find high-quality
solutions [35,78,79] due to their scalability and computational efficiency to solve realistic problems
from industry. For instance, the stochastic dual dynamic programming (SDDP) approach [35]is
used in most hydrothermal-based power systems worldwide. However, the discrete nature of
state variables in planning problems introduces loss of convexity that prevents the direct use of
the SDDP approach. This is also the case when considering nonlinear relations or discrete actions
at the market or operational levels, such as those arising when modelling network flexibility. In
this sense, recent advances in decomposition methods provide algorithms capable of dealing with
some of these non-convexities in different ways [8082]. In general, developing computationally
efficient methods to address non-convexities is an important research avenue to be able to fully
capture the benefits of smart grid technologies in realistic planning problems.
(b) Static stochastic and robust planning
The class of static stochastic and robust planning models arises when, roughly speaking, all
the investment decisions x(·) in the model comprising equations (2.4)–(2.7) are in the first
stage, and the uncertainty realizations are in the second stage (two-stage stochastic or two-
stage robust problems). Static planning is largely used in industry applications, particularly for
grid reinforcements, whereby the decision and uncertainty hierarchy is typically the following:
‘investment decisions for the whole time horizon (x)’ ‘long-term uncertainty revelation (ε)’
‘unit commitment or market scheduling decisions (y(ε))’ ‘short-term uncertainty revelation
(ξ)’ ‘short-term operational decisions (z(ε,ξ))’. Depending on the application, one of the three
decision levels is simplified and, in general, two-stage decision models are used to address static
problems. Such two-stage models use a simplified (or ‘myopic’) and in general more conservative
approach for investment dynamics. Thus, much more detailed operational aspects and short-
term uncertainties can be considered relative to the multi-stage approach (which uses simplified
operational models to avoid tractability issues). As a result, the two-stage framework is largely
adopted by industry. However, two-stage models require the consideration of many epochs
and snapshots of the system operation. Therefore, again, Benders decomposition [80], Dantzig–
Wolfe [41], progressive hedging [54] and column-and-constraint generation methods [17,83]are
common approaches used to decompose the original problems into two stages: the planning
stage, where the set of decision variables comprises variables x(·), and the operational stage,
where decision variables y(·) are scenario-dependent.
While in the stochastic framework, with a probabilistic model being used to characterize
uncertainty, the decision-maker risk attitude is expressed through utility functions and risk
measures [64], in robust optimization the decision-maker imposes feasibility for all scenarios
within a given set, denoted by uncertainty set, thereby giving rise to a worst-case setting. In
this case, the risk level (or ‘conservativeness’ level, as commonly referred to in the literature on
robust optimization [71,84,85]) is accounted for by means of the comprehensiveness (or ‘broadness’,
in the sense of cardinality) of the set of scenarios. Available approaches to uncertainty modelling
(e.g. ellipsoidal uncertainty sets [85,86] and polyhedral uncertainty sets [84]) define convex sets
relying on nominal values for the uncertain coefficients of linear inequality constraints and on
distance norms limiting the size of the uncertainty sets. Therefore, differently from the stochastic
optimization framework, where the explicit evaluation of the short-term operational cost for all
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
24
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
the scenarios is needed, in the robust optimization framework the worst-case scenario is found
through parametrized optimization problems. Hence, robust optimization implicitly accounts
for all the scenarios within the uncertainty set through efficient search algorithms, thereby
addressing some of the tractability issues associated with the consideration of many scenarios
in the stochastic optimization approach. This is a salient virtue of the robust approach that
has recently triggered an increasing number of publications in robust models for power system
operation and planning (e.g. [17,39,46,48,53,62,63,87,88]). This virtue notwithstanding, there are
still several challenges that should be addressed in the field of robust optimization models for
power system planning. In particular, two relevant avenues of research are devoted to (i) the
characterization of uncertainty sets that preserve relevant statistical properties of the uncertainties
and (ii) addressing the tractability issues associated with the presence of non-convexities in
the second-stage problem. Recently, promising results propose new perspectives for merging
stochastic and robust optimization, thereby giving rise to the notion of distributionally robust
optimization [71,89].
5. Conclusion
In the context of the transition from conventional power systems to low-carbon energy systems,
whereby a control-based paradigm relying on flexible smart grid technologies replaces the
classic asset-based paradigm, this paper has discussed some of the main challenges associated
with planning future energy systems to securely and cost-effectively integrate renewable energy
sources. In particular, we have presented an optimization framework to plan electricity grids that
deals with uncertainty and properly accounts for relevant operational constraints, so that truly
optimal solutions, based on flexible technologies, can be determined (although this is limited, in
practice, by computational burden and the ability to deal with very large optimization problems
through suitable algorithms). In fact, the resulting investment options contain an array of smart
grid technologies that can effectively provide the needed flexibility in operation to cope with
renewables’ fluctuations and the necessary adaptation capacity in the long term to adjust system
expansion more cost-effectively even under the occurrence of unfavourable scenarios. We thus
demonstrated that and how smart grid technologies can displace the need for conventional
network assets that are instead preferable when uncertainty is ignored and operational constraints
are neglected.
Two key conceptual results of our work, with important policy implications, are (i) investment
in specific low-carbon generation technologies over time may strongly depend on the
(deterministic, stochastic or robust) approach and risk aversion of the planner, and (ii) optimal
generation investment decisions need to be complemented by decisions on investment in smart
grid technologies and/or network assets. In these regards, the proposed model allows one to
fully capture synergies and competition among different generation, smart and transmission
technologies so that the truly optimal solution is attained. In contrast, the deterministic planning
approaches (often in the form of ‘roadmaps’) and relevant planning tools that are currently used
are bound to deliver solutions that are not only more expensive, but also misleading in terms
of optimal technology mix (generation, storage, etc.). This is particularly important in the light
of, for example, setting policy incentives for certain technologies, for which enabling smart grid
technologies such as FACTS and batteries should also be considered to be optimal complements
to renewable generation.
Following up on the findings highlighted above, we then also presented the state of the art in
power system planning under uncertainty and discussed the need for new optimization tools
that can properly value the benefits of flexible, smart grid solutions by embedding detailed
operational aspects in the planning problem. In particular, important progress is necessary in
terms of sampling techniques, decomposition methods, parallel and cloud computing, among
others, to fully unlock the application of mathematical programming to plan investments in
electricity grids when considering a large number of potential future scenarios in the long term,
and a detailed representation of system operation in the short term.
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
25
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
Data accessibility. The code and associated data files can be downloaded from [77].
Authors’ contributions. R.M. designed and conducted the numerical studies. The manuscript was drafted by R.M.
and A.S. All authors edited and approved the manuscript.
Competing interests. We declare we have no competing interests.
Funding. R.M. gratefully acknowledges the financial support of Conicyt-Chile (through grants Fondecyt/
Iniciacion/11130612, Newton-Picarte/MR/N026721/1, Fondef/ID15I10592, SERC Fondap/15110019 and the
Complex Engineering Systems Institute (CONICYT–PIA–FB0816; ICM P-05-004-F)). A.S. acknowledges the
National Council for Research and Development (CNPq), Brazil. J.M.A. acknowledges the financial support of
the Ministry of Economy and Competitiveness of Spain under Project ENE2015-63879-R (MINECO/FEDER,
UE) and the Junta de Comunidades de Castilla-La Mancha under Project POII-2014-012-P. P.M. acknowledges
the partial support of the UK EPSRC through the ‘MY-STORE’ research project (EP/N001974/1).
References
1. Kirschen DS, Strbac G. 2004 Fundamentals of power system economics. Hoboken, NJ: John
Wiley & Sons.
2. Momoh J. 2012 Smart grid: fundamentals of design and analysis. Hoboken, NJ: John Wiley & Sons.
3. Saint-Pierre A, Mancarella P. In press. Active distribution system management: a dual-
horizon scheduling framework for DSO/TSO interface under uncertainty. IEEE Trans. Smart
Grid.(doi:10.1109/TSG.2016.2518084)
4. Zhang X-P, Rehtanz C, Pal B. 2012 Flexible AC transmission systems: modelling and control.
Heidelberg, Germany: Springer.
5. Kim C-K, Sood VK, Jang G-S, Lim S-J, Lee S-J. 2009 HVDC transmission: power conversion
applications in power systems. Hoboken, NJ: John Wiley & Sons.
6. Madani V, Novosel D, Horowitz S, Adamiak M, Amantegui J, Karlsson D, Imai S,
Apostolov A. 2010 IEEE PSRC report on global industry experiences with system integrity
protection schemes (SIPS). IEEE Trans. Power Deliv. 25, 2143–2155. (doi:10.1109/TPWRD.2010.
2046917)
7. Zima M, Larsson M, Korba P, Rehtanz C, Andersson G. 2005 Design aspects for wide-area
monitoring and control systems. Proc. IEEE 93, 980–996. (doi:10.1109/JPROC.2005.846336)
8. Zhu K, Chenine M, Nordström L. 2011 ICT architecture impact on wide area monitoring
and control systems’ reliability. IEEE Trans. Power Deliv. 26, 2801–2808. (doi:10.1109/
TPWRD.2011.2160879)
9. Strbac G. 2008 Demand side management: benefits and challenges. Energy Policy 36, 4419–
4426. (doi:10.1016/j.enpol.2008.09.030)
10. Siano P. 2014 Demand response and smart grids—a survey. Renew. Sustain. Energ. Rev. 30,
461–478. (doi:10.1016/j.rser.2013.10.022)
11. Papadaskalopoulos D, Strbac G, Mancarella P, Aunedi M, Stanojevic V. 2013 Decentralized
participation of flexible demand in electricity markets—Part II: application with electric
vehicles and heat pump systems. IEEE Trans. Power Syst. 28, 3667–3674. (doi:10.1109/TPWRS.
2013.2245687)
12. Mancarella P. 2014 MES (multi-energy systems): an overview of concepts and evaluation
models. Energy 65, 1–17. (doi:10.1016/j.energy.2013.10.041)
13. Han J, Papavasiliou A. 2016 The impacts of transmission topology control on the European
electricity network. IEEE Trans. Power Syst. 31, 496–507. (doi:10.1109/TPWRS.2015.2408439)
14. Moreno R, Strbac G, Porrua F, Mocarquer S, Bezerra B. 2010 Making room for the boom. IEEE
Power Energy Mag. 8, 36–46. (doi:10.1109/MPE.2010.937597)
15. Rahimi F, Ipakchi A. 2010 Demand response as a market resource under the smart grid
paradigm. IEEE Trans. Smart Grid 1, 82–88. (doi:10.1109/TSG.2010.2045906)
16. Bloemink JM, Green TC. 2010 Increasing distributed generation penetration using soft
normally-open points. In 2010 IEEE Power and Energy Society General Meeting, Providence, RI,
25–29 July, 8pp. Piscataway, NJ: IEEE. (doi:10.1109/PES.2010.5589629)
17. Moreira A, Pozo D, Street A, Sauma E. In press. Reliable renewable generation and
transmission expansion planning: co-optimizing system’s resources for meeting renewable
targets. IEEE Trans. Power Syst.(doi:10.1109/TPWRS.2016.2631450)
18. The Institution of Engineering and Technology (IET). 2015 Modelling requirements for GB power
system resilience during the transition to low carbon energy. IET Report for the Council of Science
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
26
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
and Technology. London, UK: IET. See http://www.theiet.org/sectors/energy/documents/
cst-part1-main.cfm?type=pdf.
19. Phadke AG, Thorp JS. 2008 Synchronized phasor measurements and their applications.NewYork,
NY: Springer.
20. Good N, Ceseña EAM, Zhang L, Mancarella P. 2016 Techno-economic and business case
assessment of low carbon technologies in distributed multi-energy systems. Appl. Energy 167,
158–172. (doi:10.1016/j.apenergy.2015.09.089)
21. Clegg S, Mancarella P. 2015 Integrated modeling and assessment of the operational impact of
power-to-gas (P2G) on electrical and gas transmission networks. IEEE Trans. Sustain. Energy
6, 1234–1244. (doi:10.1109/TSTE.2015.2424885)
22. Clegg S, Mancarella P. 2016 Storing renewables in the gas network: modelling of power-to-
gas seasonal storage flexibility in low-carbon power systems. IET Gener. Transm. Distrib. 10,
566–575. (doi:10.1049/iet-gtd.2015.0439)
23. Ulbig A, Borsche TS, Andersson G. 2014 Impact of low rotational inertia on
power system stability and operation. IFAC Proceedings Volumes 47 (3), 7290–7297.
(doi:10.3182/20140824-6-ZA-1003.02615)
24. Pipelzadeh Y, Moreno R, Chaudhuri B, Strbac G, Green TC. 2017 Corrective control with
transient assistive measures: value assessment for Great Britain transmission system. IEEE
Trans. Power Syst. 32, 1638–1650. (doi:10.1109/TPWRS.2016.2598815)
25. Panteli M, Crossley PA, Fitch J. 2014 Quantifying the reliability level of system integrity
protection schemes. IET Gener. Transm. Distrib. 8, 753–764. (doi:10.1049/iet-gtd.2013.0450)
26. Calvo JL, Tindemans SH, Strbac G. 2016 Incorporating failures of system protection
schemes into power system operation. Sustain. Energy Grids Netw. 8, 98–110. (doi:10.1016/
j.segan.2016.10.002)
27. Moreno R, Pudjianto D, Strbac G. 2012 Integrated reliability and cost–benefit-based standards
for transmission network operation. Proc. Inst. Mech. Eng. Part O, J. Risk Reliab. 226, 75–87.
(doi:10.1177/1748006X11424103)
28. Moreno R, Pudjianto D, Strbac G. 2013 Transmission network investment with probabilistic
security and corrective control. IEEE Trans. Power Syst. 28, 3935–3944. (doi:10.1109/
TPWRS.2013.2257885)
29. Tuohy A, Meibom P, Denny E, O’Malley M. 2009 Unit commitment for systems with
significant wind penetration. IEEE Trans. Power Syst. 24, 592–601. (doi:10.1109/TPWRS.
2009.2016470)
30. Schachter JA, Mancarella P. 2016 Demand response contracts as real options: a probabilistic
evaluation framework under short-term and long-term uncertainties. IEEE Trans. Smart Grid
7, 868–878. (doi:10.1109/TSG.2015.2405673)
31. Konstantelos I, Strbac G. 2015 Valuation of flexible transmission investment options under
uncertainty. IEEE Trans. Power Syst. 30, 1047–1055. (doi:10.1109/TPWRS.2014.2363364)
32. Schachter JA, Mancarella P. 2016 A critical review of real options thinking for valuing
investment flexibility in smart grids and low carbon energy systems. Renew. Sustain. Energy
Rev. 56, 261–271. (doi:10.1016/j.rser.2015.11.071)
33. Schachter JA, Mancarella P, Moriarty J, Shaw R. 2016 Flexible investment under uncertainty in
smart distribution networks with demand side response: assessment framework and practical
implementation. Energy Policy 97, 439–449. (doi:10.1016/j.enpol.2016.07.038)
34. Carpaneto E, Chicco G, Mancarella P, Russo A. 2011 Cogeneration planning under
uncertainty. Part I: multiple time frame approach. Appl. Energy 88, 1059–1067. (doi:10.1016/j.
apenergy.2010.10.014)
35. Pereira MVF, Pinto LMVG. 1991 Multi-stage stochastic optimization applied to energy
planning. Math. Program. 52, 359–375. (doi:10.1007/BF01582895)
36. de la Torre T, Feltes JW, San Roman TG, Merrill HM. 1999 Deregulation, privatization, and
competition: transmission planning under uncertainty. IEEE Trans. Power Syst. 14, 460–465.
(doi:10.1109/59.761866)
37. Roques FA, Newbery DM, Nuttall WJ. 2008 Fuel mix diversification incentives in liberalized
electricity markets: a mean–variance portfolio theory approach. Energy Econ. 30, 1831–1849.
(doi:10.1016/j.eneco.2007.11.008)
38. Huang Y-H, Wu J-H. 2008 A portfolio risk analysis on electricity supply planning. Energy
Policy 36, 627–641. (doi:10.1016/j.enpol.2007.10.004)
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
27
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
39. Wu P, Cheng H, Xing J. 2008 The interval minimum load cutting problem in the process of
transmission network expansion planning considering uncertainty in demand. IEEE Trans.
Power Syst. 23, 1497–1506. (doi:10.1109/TPWRS.2008.922573)
40. Roh JH, Shahidehpour M, Wu L. 2009 Market-based generation and transmission planning
with uncertainties. IEEE Trans. Power Syst. 24, 1587–1598. (doi:10.1109/TPWRS.2009.
2022982)
41. Singh KJ, Philpott AB, Wood RK. 2009 Dantzig–Wolfe decomposition for solving multistage
stochastic capacity-planning problems. Oper. Res. 57, 1271–1286. (doi:10.1287/opre.1080.
0678)
42. Akbari T, Rahimikian A, Kazemi A. 2011 A multi-stage stochastic transmission expansion
planning method. Energy Conv. Manag. 52, 2844–2853. (doi:10.1016/j.enconman.2011.02.023)
43. van der Weijde AH, Hobbs BF. 2012 The economics of planning electricity transmission to
accommodate renewables: using two-stage optimisation to evaluate flexibility and the cost of
disregarding uncertainty. Energy Econ. 34, 2089–2101. (doi:10.1016/j.eneco.2012.02.015)
44. Pozo D, Contreras J, Sauma E. 2013 If you build it, he will come: anticipative power
transmission planning. Energy Econ. 36, 135–146. (doi:10.1016/j.eneco.2012.12.007)
45. Pozo D, Sauma EE, Contreras J. 2013 A three-level static MILP model for generation
and transmission expansion planning. IEEE Trans. Power Syst. 28, 202–210. (doi:10.1109/
TPWRS.2012.2204073)
46. Jabr RA. 2013 Robust transmission network expansion planning with uncertain renewable
generation and loads. IEEE Trans. Power Syst. 28, 4558–4567. (doi:10.1109/TPWRS.2013.
2267058)
47. Meunier G. 2013 Risk aversion and technology mix in an electricity market. Energy Econ. 40,
866–874. (doi:10.1016/j.eneco.2013.10.010)
48. Munoz FD, Sauma EE, Hobbs BF. 2013 Approximations in power transmission planning:
implications for the cost and performance of renewable portfolio standards. J. Regul. Econ.
43, 305–338. (doi:10.1007/s11149-013-9209-8)
49. Rahmani M, Vinasco G, Rider MJ, Romero R, Pardalos PM. 2013 Multistage transmission
expansion planning considering fixed series compensation allocation. IEEE Trans. Power Syst.
28, 3795–3805. (doi:10.1109/TPWRS.2013.2266346)
50. Baringo L, Conejo AJ. 2013 Risk-constrained multi-stage wind power investment. IEEE Trans.
Power Syst. 28, 401–411. (doi:10.1109/TPWRS.2012.2205411)
51. Feng Y, Ryan SM. 2013 Scenario construction and reduction applied to stochastic power
generation expansion planning. Comput. Oper. Res. 40, 9–23. (doi:10.1016/j.cor.2012.05.005)
52. Munoz FD, Hobbs BF, Ho JL, Kasina S. 2014 An engineering-economic approach to
transmission planning under market and regulatory uncertainties: WECC case study. IEEE
Trans. Power Syst. 29,307–317. (doi:10.1109/TPWRS.2013.2279654)
53. Chen B, Wang J, Wang L, He Y, Wang Z. 2014 Robust optimization for transmission
expansion planning: minimax cost vs. minimax regret. IEEE Trans. Power Syst. 29, 3069–3077.
(doi:10.1109/TPWRS.2014.2313841)
54. Munoz FD, Watson J-P. 2015 A scalable solution framework for stochastic transmission
and generation planning problems. Comput. Manag. Sci. 12, 491–518. (doi:10.1007/s10287-
015-0229-y)
55. Ruiz C, Conejo AJ. 2015 Robust transmission expansion planning. Eur. J. Oper. Res. 242, 390–
401. (doi:10.1016/j.ejor.2014.10.030)
56. Ceseña EAM, Capuder T, Mancarella P. 2016 Flexible distributed multienergy generation
system expansion planning under uncertainty. IEEE Trans. Smart Grid 7, 348–357.
(doi:10.1109/TSG.2015.2411392)
57. Velásquez C, Watts D, Rudnick H, Bustos C. 2016 A framework for transmission expansion
planning: a complex problem clouded by uncertainty. IEEE Power Energy Mag. 14, 20–29.
(doi:10.1109/MPE.2016.2547278)
58. Hobbs BF, Xu Q, Ho J, Donohoo P, Kasina S, Ouyang J, Park SW, Eto J, Satyal V. 2016 Adaptive
transmission planning: implementing a new paradigm for managing economic risks in grid
expansion. IEEE Power Energy Mag. 14, 30–40. (doi:10.1109/MPE.2016.2547280)
59. Bruno S, Ahmed S, Shapiro A, Street A. 2016 Risk neutral and risk averse approaches to
multistage renewable investment planning under uncertainty. Eur. J. Oper. Res. 250, 979–989.
(doi:10.1016/j.ejor.2015.10.013)
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
28
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
60. Inzunza A, Moreno R, Bernales A, Rudnick H. 2016 CVaR constrained planning of renewable
generation with consideration of system inertial response, reserve services and demand
participation. Energy Econ. 59, 104–117. (doi:10.1016/j.eneco.2016.07.020)
61. Muñoz-Delgado G, Contreras J, Arroyo JM. 2016 Multistage generation and network
expansion planning in distribution systems considering uncertainty and reliability. IEEE
Trans. Power Syst. 31, 3715–3728. (doi:10.1109/TPWRS.2015.2503604)
62. Mínguez R, García-Bertrand R. 2016 Robust transmission network expansion planning
in energy systems: improving computational performance. Eur. J. Oper. Res. 248, 21–32.
(doi:10.1016/j.ejor.2015.06.068)
63. Dehghan S, Amjady N. 2016 Robust transmission and energy storage expansion planning in
wind farm-integrated power systems considering transmission switching. IEEE Trans. Sustain.
Energy 7, 765–774. (doi:10.1109/TSTE.2015.2497336)
64. Molina JD, Contreras J, Rudnick H. In press. A risk-constrained project portfolio in centralized
transmission expansion planning. IEEE Syst. J.(doi:10.1109/JSYST.2014.2345736)
65. Ma J, Silva V, Belhomme R, Kirschen DS, Ochoa LF. 2013 Evaluating and planning
flexibility in sustainable power systems. IEEE Trans. Sustain. Energy 4, 200–209. (doi:10.1109/
TSTE.2012.2212471)
66. Vithayasrichareon P, MacGill IF. 2014 Incorporating short-term operational plant constraints
into assessments of future electricity generation portfolios. Appl. Energy 128, 144–155.
(doi:10.1016/j.apenergy.2014.04.052)
67. Palmintier BS, Webster MD. 2016 Impact of operational flexibility on electricity generation
planning with renewable and carbon targets. IEEE Trans. Sustain. Energy 7, 672–684.
(doi:10.1109/TSTE.2015.2498640)
68. Flores-Quiroz A, Palma-Behnke R, Zakeri G, Moreno R. 2016 A column generation approach
for solving generation expansion planning problems with high renewable energy penetration.
Electr. Power Syst. Res. 136, 232–241. (doi:10.1016/j.epsr.2016.02.011)
69. Conejo AJ, Carrión M, Morales JM. 2010 Decision making under uncertainty in electricity markets.
New York, NY: Springer.
70. Birge JR, Louveaux F. 2011 Introduction to stochastic programming, 2nd edn. New York, NY:
Springer.
71. Bertsimas D, Brown DB, Caramanis C. 2011 Theory and applications of robust optimization.
SIAM Rev. 53, 464–501. (doi:10.1137/080734510)
72. Carrión M, Arroyo JM. 2006 A computationally efficient mixed-integer linear formulation
for the thermal unit commitment problem. IEEE Trans. Power Syst. 21, 1371–1378.
(doi:10.1109/TPWRS.2006.876672)
73. Noroozian M, Andersson G. 1993 Power flow control by use of controllable series
components. IEEE Trans. Power Deliv. 8, 1420–1429. (doi:10.1109/61.252669)
74. Binato S, Pereira MVF, Granville S. 2001 A new Benders decomposition approach to
solve power transmission network design problems. IEEE Trans. Power Syst. 16, 235–240.
(doi:10.1109/59.918292)
75. Zhang L, Capuder T, Mancarella P. 2016 Unified unit commitment formulation and fast multi-
service LP model for flexibility evaluation in sustainable power systems. IEEE Trans. Sustain.
Energy 7, 658–671. (doi:10.1109/TSTE.2015.2497411)
76. FICO Xpress. http://www.fico.com (accessed 7 March 2017).
77. Moreno R, Street A, Arroyo JM, Mancarella P. 2017 Code and data repository. https://goo.
gl/GK60K8 (accessed 11 May 2017).
78. Shapiro A. 2011 Analysis of stochastic dual dynamic programming method. Eur. J. Oper. Res.
209, 63–72. (doi:10.1016/j.ejor.2010.08.007)
79. Girardeau P, Leclere V, Philpott AB. 2014 On the convergence of decomposition methods
for multistage stochastic convex programs. Math. Oper. Res. 40, 130–145. (doi:10.1287/moor.
2014.0664)
80. Römisch W, Vigerske S. 2010 Recent progress in two-stage mixed-integer stochastic
programming with applications to power production planning. In Handbook of power systems I
(eds S Rebennack, PM Pardalos, MVF Pereira, NA Iliadis), pp. 177–208. Heidelberg, Germany:
Springer.
81. Cerisola S, Latorre JM, Ramos A. 2012 Stochastic dual dynamic programming applied
to nonconvex hydrothermal models. Eur. J. Oper. Res. 218, 687–697. (doi:10.1016/j.ejor.
2011.11.040)
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
29
rsta.royalsocietypublishing.org Phil.Trans.R.Soc.A375: 20160305
........................................................
82. Zou J, Ahmed S, Sun XA. 2016 Nested decomposition of multistage stochastic integer
programs with binary state variables. Optimization Online.Seehttp://www.optimization-
online.org/DB_FILE/2016/05/5436.pdf (accessed 2 March 2017).
83. Zeng B, Zhao L. 2013 Solving two-stage robust optimization problems using a column-and-
constraint generation method. Oper. Res. Lett. 41, 457–461. (doi:10.1016/j.orl.2013.05.003)
84. Bertsimas D, Sim M. 2004 The price of robustness. Oper. Res. 52, 35–53. (doi:10.1287/opre.
1030.0065)
85. Ben-Tal A, Goryashko A, Guslitzer E, Nemirovski A. 2004 Adjustable robust solutions of
uncertain linear programs. Math. Program. 99, 351–376. (doi:10.1007/s10107-003-0454-y)
86. Boyd S, Vandenberghe L. 2004 Convex optimization. Cambridge, UK: Cambridge University
Press.
87. Moreira A, Street A, Arroyo JM. 2015 An adjustable robust optimization approach for
contingency-constrained transmission expansion planning. IEEE Trans. Power Syst. 30, 2013–
2022. (doi:10.1109/TPWRS.2014.2349031)
88. Street A, Oliveira F, Arroyo JM. 2011 Contingency-constrained unit commitment with nK
security criterion: a robust optimization approach. IEEE Trans. Power Syst. 26, 1581–1590.
(doi:10.1109/TPWRS.2010.2087367)
89. Klabjan D, Simchi-Levi D, Song M. 2013 Robust stochastic lot-sizing by means of histograms.
Prod. Oper. Manag. 22, 691–710. (doi:10.1111/j.1937-5956.2012.01420.x)
on October 20, 2017http://rsta.royalsocietypublishing.org/Downloaded from
... I. INTRODUCTION Going forward, electricity systems will need to integrate increasing amounts of variable renewable energy sources (VRES), requiring substantial investments in transmission networks and energy storage infrastructure. Planning these investments optimally, though, require advanced mathematical models [1]. This is so since, first, the planning problem needs to recognize the significant levels of uncertainty faced in the long-term from various uncertainty sources (demand growth, distributed energy resources (DER) deployment, penetration of VRES, etc.), which is hard to incorporate without increasing computational burden [2]. ...
... Most industry-based studies still uses deterministic models to determine, in practice, power system plans [4]- [6]. Despite this, there has been an increasing focus in the academia on models that can explicitly cope with uncertainty [1], [7], [8]. From these models (divided into stochastic and robust optimization models [1]), stochastic ones promise a more efficient cost/risk balance since risks can be better quantified through probabilities. ...
... Despite this, there has been an increasing focus in the academia on models that can explicitly cope with uncertainty [1], [7], [8]. From these models (divided into stochastic and robust optimization models [1]), stochastic ones promise a more efficient cost/risk balance since risks can be better quantified through probabilities. Importantly, the vast majority of stochastic models for planning are two-stage [7], [9], [10], but multi-stage models are being proposed lately in order to better capture the decision dynamics [1], [7], [8], [11]- [13]. ...
Article
Full-text available
Power system operators and planners are dealing both with the integration of unparalleled levels of variable renewable energy sources and deep uncertainties that originate from new technological developments, changing regulatory frameworks, unknown investment, operational costs of technologies, etc. An inadequate representation of the uncertainties may result in a substantial risk of deploying inflexible investment solutions incapable of adapting efficiently to evolving scenarios. In this context, this work studies the effects of increasing the granularity used to represent the long-term uncertainty by analysing its impact on the resulting optimal portfolios of new transmission lines, battery energy storage systems and pumped-hydro storage systems. The studies are conducted on an instance of the Australian power system described by the system operator for planning purposes, including four types of uncertainty granularity, namely deterministic representation, and 2-stage, 3-stage and 4-stage stochastic representations. To address the computational challenges associated with the large mixed-integer linear stochastic problems, the different instances are reformulated using Dantzig-Wolfe decomposition, enabling the use of a column generation approach to solve the investment problem. The case study applications show substantial adjustments in the investment portfolios as uncertainty granularity changes, with a clear tendency to increase battery storage investment as uncertainty is better represented.
... A new tool for economic assessment of technology impacts and unlocking of decentralized flexibility should provide several benefits compared with pre-existing studies [11][12][13][14]. ...
... In turn, the authors in [14] claim that the conventional electricity network will evolve into the so-called smart grid, which comprehends: ...
... This new operational flexibility can be utilized to deal with both real-time operation and time-ahead scheduling (where decisions are made regarding the uncertainty of variable generation). Such management of multiple operational flexibilities would increase network utilization and reduce levels of costly generation reserves [14,20,24]. ...
Article
Full-text available
In order to succeed in the energy transition, the power system must become more flexible in order to enable the economical hosting of more intermittent distributed energy resources (DER) and smart grid technologies. New technical solutions, generally based on the connection of various components coupled to the power system via smart power electronic converters or through ICT, can help to take up these challenges. Such innovations (e.g., decarbonization technologies and smart grids) may reduce the costs of future power systems and the environmental footprint. In this regard, the techno-economic assessment of smart grid technologies is a matter of interest, especially in the urge to develop more credible options for deep decarbonization pathways over the long term. This work presents a literature survey of existing simulation tools to assess the techno-economic benefits of smart grid technologies in integrated T&D systems. We include the state-of-the-art tools and categorize them in their multiple aspects, cover smart grid technology, approach methods, and research topics, and include (or complete) the analysis with other dimensions (smart-grid related) of key interest for future power systems analysis such as environmental considerations, techno-economic aspects (social welfare), spatial scope, time resolution (granularity), and temporal scope, among others. We surveyed more than 40 publications, and 36 approaches were identified for the analysis of integrated T&D systems. As a relatively new research area, there are various promising candidates to properly simulate integrated T&D systems. Nevertheless, there is not yet a consensus on a specific framework that should be adopted by researchers in academia and industry. Moreover, as the power system is evolving rapidly towards a smart grid system, novel technologies and flexibility solutions are still under study to be integrated on a large scale. This review aims to offer new criteria for researchers in terms of smart-grid related dimensions and the state-of-the-art trending of simulation tools that holistically evaluate techno-economic aspects of the future power systems in an integrated T&D systems environment. As an imperative research matter for future energy systems, this article seeks to contribute to the discussion of which pathway the scientific community should focus on for a successful shift towards decarbonized energy systems.
... VOLUME 11, 2023 When the system is overwhelmed and displaced from its normal operational state, the absorptive capacity is relied upon to preserve the essential basic structure and functions of the system whilst avoiding permanent components or system damages. This phase is often referred to as the ''disruption transition'' [9] or ''disturbance progress'' [30], [34]. System degradation can be viewed as progressively moving from an alert stage, R 1 , which is an initial violation of operational constraints [6] to the emergency stage, and ultimately, the system might descend to an extreme state, R 2 at t 2 , below which a total blackout is imminent [9]. ...
... Ultimately, resilience was evaluated using classical reliability indices. Although reliability studies are generally considered inadequate for assessing resilience, reliability metrics (Loss of Load Expectation (LOLE), Loss of Load Frequency (LOLF), and Energy Not Supplied (ENS)) are commonly used [16], [34], [44] in quantifying resilience given that, with slight alterations (such as considering tail-end values of probability distributions), they do capture the essential operational output of the system under extreme disruptions. ...
Article
Full-text available
The requirement for a sustained supply of electricity intensifies during and in the aftermath of extreme events. In the past, events were considered extreme based on their extensive and devasting impacts and