This article discusses in detail the Heidrun tension leg platform tethering operation which was successfully carried out in July, 1995. The tethers were pre-installed on the concrete foundation. Hold-back of the pre-installed tether groups, tether lock-off, and general subsea intervention had been identified as the critical areas. The offshore transport fleet and operations are outlined.