Construction Economics and Building, 16(4), 68-85
Copyright: Construction Economics and Building 2016. © 2016 Craig Langston and Amir Naser Ghanbaripour. This is an Open
Access article distributed under the terms of the Creative Commons Attribution 4.0 Unported (CC BY 4.0) License
(https://creativecommons.org/licenses/by/4.0/), allowing third parties to copy and redistribute the material in any medium or
format and to remix, transform, and build upon the material for any purpose, even commercially, provided the original work is
properly cited and states its license.
Citation: Langston, C. and Ghanbaripour, A.N. 2016. A Management Maturity Model (MMM) for project-based organisational
performance assessment. Construction Economics and Building, 16(4), 68-85.
DOI: http://dx.doi.org/10.5130/AJCEB.v16i4.5028
Corresponding author: Craig Langston; Email - clangsto@bond.edu.au
Publisher: University of Technology Sydney (UTS) ePress
A Management Maturity Model (MMM) for project-based
organisational performance assessment
Craig Langston1 and Amir Naser Ghanbaripour 2
1Bond University, Australia
2Iran University of Science and Technology
Abstract
Common sense suggests that organisations are more likely to deliver successful projects if they
have systems in place that reflect a mature project environment based on a culture of continuous
improvement. This paper develops and discusses a Management Maturity Model (MMM) to
assess the maturity of project management organisations through a customisable, systematic,
strategic and practical methodology inspired from the seminal work of Darwin, Deming, Drucker
and Daniel. The model presented is relevant to organisations, such as construction and
engineering companies, that prefer to use the Project Management Body of Knowledge
(PMBOK™ Guide) published by the Project Management Institute (PMI), but without the
disadvantages of excessive time and cost commitments and a ‘one size fits all’ approach linked to
rigid increments of maturity. It offers a game-changing advance in the application of project-
based organisational performance assessment compared to existing market solutions that are
unnecessarily complex. The feasibility of MMM is field-tested using a medium-sized data centre
infrastructure firm in Tehran.
Keywords: Project management, delivery success, organisation maturity modelling, PMBOK
Paper type: Research article
Introduction
All kinds of organisations, whether they be government agencies, private companies, charitable
institutions or other collectives, spend time and effort to define their short, medium and long
term objectives and the strategies that help them to be achieved (Demir and Kocabaş, 2010). The
essence of project management is a direct outcome of what is the required scope of work and
how well it is implemented (Silva et al., 2014). The contemporary need for project management,
and the contribution that is possible from deploying a structured methodology, regardless of
industry sector or discipline, is well documented. Project management has become both a key
activity of organisational management and has enabled success, balance and harmony to be
realised by global organisations (Hutson, 1997).
The definition of organisational maturity refers to operations that are in perfect synergy to
achieve strategic objectives (Silva et al., 2014). Maturity models are considered to be tools that
simulate specific aspects of capability and define the qualitative attributes that characterise
competence at a particular level of performance (Demir and Kocabaş, 2010). These levels are
typically sequential (Kohlegger et al., 2009). The origins of maturity models lie in the discipline of
total quality management. They require a thorough understanding of an organisation’s current
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
69
strategic position and where it aims to be in the future (Brookes and Clark, 2009). A maturity
model provides a framework for systematic and continuous performance improvement.
Organisations are considered more likely to deliver successful projects if they have systems in
place that reflect a mature project management environment based on a culture of continuous
improvement (Crawford, 2011). Over the years research has been undertaken to develop
frameworks that objectively measure organisational maturity (Cooke-Davies, 2004; Nesensohn et
al., 2014). Popular frameworks in widespread use are generally complex and require a high degree
of expertise and time when deployed in practice.
Nesensohn et al. (2014) found that over the past two decades there has been a rapid growth in
publications about organisational maturity. Based on a search of four key databases (i.e. Business
Source Complete; Emerald; Scopus; Discover) from 1990 to 2013, they found that the number of
relevant articles per database has increased every year. There has been a simultaneous growth in
maturity models over this period.
The aim of this paper is to set out a management maturity model based on the plan-do-check-act
(PDCA) cycle to assess the maturity and performance of organisations in project management
environments. This includes a review of relevant literature, reflection of criticisms, model
development based on a unique conceptual approach, and field testing of this proposed solution
in a real organisation, followed by discussion of implementation feedback and final conclusions.
Literature review
The achievement of consistent project management excellence is assisted by mature
organisational systems and processes. The understanding of maturity, however, is often a
subjective concept (Pretorius et al., 2012). Maturity models typically have a conceptual
underpinning with constituent components that define the progressive development of
capabilities, and ideally outline the processes that organisations could implement to achieve a
more mature state (PMI, 2013). Maturity improvements require a concerted effort of continuous
review and reflection at an organisational management level.
It should be noted that maturity models, like the discipline of project management itself, apply
generically to any industry sector. For example, no compelling consensus was found in the
literature that organisations undertaking engineering and construction projects require a bespoke
solution. Some models have certainly emerged from a particular sector, such as software
development, but their subsequent application has been demonstrated over time to have a much
broader appeal.
There are now a number of maturity models operating within a range of business management
fields, and in particular within the discipline of project management. The three main players in
project management are discussed below.
Capability Maturity Model Integration (CMMI)
The Capability Maturity Model Integration (CMMI) project had its origins in a number of other
tools that were developed from 1986 and were combined together in 1993 to form a single
integrated tool (de Souza and Gomes, 2015). According to the CMMI Institute, over 10,500
individual CMMI appraisals have now been undertaken globally since 2007, making it the most
successful maturity tool available. The CMMI Institute operates through a network of CMMI
partners, which comprise trained and certified organisations and individuals providing official
training programs, appraisals and other consulting services. The CMMI Institute Partner
Network enables global reach to organisational clients and is the only avenue for authentic
CMMI services outside of the institute itself (http://cmmiinstitute.com/about-cmmi-institute).
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
70
Building on an organisation’s business performance objectives, CMMI provides a set of practices
for improving processes, resulting in a continuous improvement system that paves the way for
better operations and performance. CMMI applies to organisations that undertake software
development, systems engineering and product development through the use of a single tool to
assess maturity or capability, and provides direction while developing more sophisticated
processes (Staples et al., 2007; Pane and Sarno, 2015). There are five maturity levels used in the
‘staged’ representation of CMMI:
1. Initial: Processes are unpredictable, poorly controlled and reactive
2. Managed: Processes are characterised for projects and are often reactive
3. Defined: Processes are characterised for the organisation and are proactive
4. Quantitatively managed: Processes are measured and controlled
5. Optimising: There is a focus on process improvement
An immature organisation would display characteristics such as process improvisation, approved
processes being ignored, reactive as opposed to proactive decisions, unrealistic budget and
schedule constraints, quality sacrificed for schedule, and no objective measure of quality. In
contrast, the characteristics of a mature organisation include inter-group communication and
coordination, work accomplished according to plan, practices consistent with processes,
processes updated as necessary, well-defined roles/responsibilities, and formal commitment from
management.
CMMI can also be used as ‘continuous’ representation, where six capability levels apply instead.
In this case, ‘level 1: initial’ is subdivided into ‘level 0: incomplete’ and ‘level 1: performed’. The
remaining levels are the same. There is little significance between the meaning attached to
maturity and capability.
Some studies state that there is a problem with the adoption of CMMI by organisations, and
facilitation of the assessment is required to avoid wasting resources (Hardgrave and Armstrong,
2005; Staples and Niazi, 2010; Allué et al., 2013). According to Allué et al. (2013), one way of
achieving facilitation is to provide organisations with tools or software products that make the
adoption of CMMI easier. Few tools support all of the types of CMMI-related activities however
as the support level that is provided is often limited, and a tool’s ability to be customised
according to the users’ needs is quite small (Musat et al., 2010). CMMI is compatible with the
AGILE project management methodology (Jiang et al., 2004).
Portfolio, Program & Project Management Maturity Model (P3M3)
The Office of Government Commerce (OGC) fostered the development of a government
maturity standard called the Portfolio, Program and Project Management Maturity Model (P3M3),
aligned to the PRINCE2 methodology (González et al., 2007). According to Sowden et al.
(2008:8), “P3M3 is not simply about isolated, here-and-now assessments – it also acts as a roadmap for ongoing
improvement and progression towards realistic and achievable goals that are suitable for your business needs and
aspirations”. González et al. (2007) states that P3M3 focuses on the addition of portfolio and
program management domains to earlier versions of the model, helping to expand emerging
processes of project complexity that contribute to overall success. The levels of maturity in P3M3
are effectively identical to those for CMMI, and are described in Table 1.
P3M3, like PRINCE2, is a joint venture between OGC and Axelos and has a strong support base
in the United Kingdom. It is built on seven process-related perspectives that exist in project,
program and portfolio domains and is assessed at five levels of increasing maturity
(https://www.axelos.com/best-practice-solutions/p3m3/what-is-p3m3). These perspectives are:
1. Organisational governance
2. Management control
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
71
3. Benefits management
4. Risk management
5. Stakeholder management
6. Finance management
7. Resource management
Young et al. (2014:220) argue that one deficiency of the P3M3 model is that it “uses a single number
to represent maturity at the project, program and portfolio level, with this number being the lowest score in either
generic attributes or the process perspectives across each sub-model […] the single number reported is therefore
misleading and will generally report a lower level of maturity than what is present in an organisation, not only
painting a poorer picture than what might exist [… but] disregarding the relative closeness of the next higher
level”. Another shortcoming they mention is that the ‘generic attributes’ evaluated in all three
P3M3 domains are claimed as essential to achieving improvement in project management
maturity. It is doubtful however whether these generic attributes are appropriate for program and
portfolio management domains, which are typically more complex than standalone project
management (Artto et al., 2009; Young et al., 2014).
Table 1: P3M3 maturity levels (Sowden et al., 2008)
Organisational Project Management Maturity Model (OPM3)
Another important model used in the project management discipline is OPM3. Developed by a
team of volunteers from the PMI between 1998 and 2013, it is suitable for organisations of any
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
72
size, location or practice environment. It aims to enumerate the level of maturity of projects and
practices, based on best practices as a methodology for assessment. Similar to P3M3, it sets out
requirements to assist in the development of better capabilities that underpin projects, programs
and portfolios and assist organisations to realise strategic objectives through the delivery of
successful outcomes (PMI, 2013; Silva et al., 2014).
This model supports both continuous process improvement to diagnose existing organisational
systems, and uniquely highlights potential problems or deficiencies including the detailed design
of necessary improvements (Fahrenkrog et al., 2003). It is aligned specifically to the widely
recognised PMBOK methodology. OPM3 compares organisational activities with a large number
of standardised best practices, measuring them in project, program and portfolio management
contexts by examining capabilities and related outcomes. Organisations are then classified into
four levels of maturity development, not five as embedded in CMMI and P3M3, for each process
area in each domain (Pinto and Williams, 2013):
1. Standardise: Structured processes are adopted
2. Measure: Data is used to evaluate process performance
3. Control: Control plan developed for measures
4. Continuously improve: Processes are optimised
Cooke-Davies (2004) state that the basic ‘building blocks’ of OPM3 are:
1. Use of best practices related to organisational project management
2. Core capabilities that are needed to support the achievement of each best practice
outcome
3. Observable evidence that attests to the existence of specific capabilities that are routinely
applied within an organisation
4. Key performance indicators (KPIs) and other metrics that provide a basis for objective
outcome measurement
5. Pathways that identify the capabilities that aggregate to attainment of relevant best
practice outcomes
Importantly, OPM3 creates and advocates the critical connection between organisational strategy
and successful projects, as illustrated in Figure 1.
Figure 1: Core OPM3 philosophy (PMI, 2013)
OPM3 is by far the most sophisticated of the identified maturity models in the discipline of
project management, but also the most resource intensive (Hillson, 2003; Cooke-Davies, 2004;
Backlund et al., 2014). Current maturity models are unlikely to ever be the ‘silver bullet’ that one
might hope for because they typically:
1. Lack a well-researched and theoretical understanding of what is needed for successful
project management outcomes
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
73
2. Are founded on the assumption that there is an ideal path of development towards
maturity that most organisations should pursue regardless of discipline area, project scope,
competitive marketplace context or chosen strategy
3. Must walk a fine line “between the ‘Scylla’ of over-simplification and the ‘Charybdis’ of excessive
complexity” (Cooke-Davies, 2004:1252)
OPM3 is currently under review and is the subject of deep unrest between some of the certified
assessors and the PMI over the current direction and marketing of a product that comprises
shared intellectual property. Without full access to the best practice standards, which are the heart
of the model, assessors are unable to use this tool in practice. It is likely that in the years that lie
ahead OPM3 will be significantly changed and possibly rebranded.
Other models
A number of other maturity models discovered online were also reviewed:
1. The Berkeley Project Management Maturity Model (PM2):
http://www.ce.berkeley.edu/~ibbs/yhkwak/pmmaturity.html
2. Kerzner PM Maturity Assessment: http://www.iil.com/kpm3/default.asp
3. PM Solutions Project Management Maturity Model (PMMM):
http://www.pmsolutions.com/resources/view/what-is-the-project-management-
maturity-model/
4. The SUKAD Seven Elements of Project Management Maturity (7Es):
http://sukadway.sukad.com/project-management-maturity-model-overview)
5. Onemind: www.onemind.co.uk
6. Standardised Process Improvement for Construction Enterprises (SPICE):
http://usir.salford.ac.uk/9965/1/280_Jeong_KSStructured_Process_Improvement.pdf
7. IPMA Delta Module O (Organisation): http://www.ipma.world/certification/certify-
organisations/deltacompetence-classes/
General criticisms
One of the criticisms of applying the current models in organisations is the focus on explicit
project management knowledge areas rather than intangible assets, which are less obvious but
nevertheless contribute to a mature project management capability (Jugdev and Thomas, 2002).
Intangible assets include context-specific outcomes such as customer involvement and implicit
human factors including creativity, integrity and trust (Pasian et al., 2012; Backlund et al., 2014).
Another problem with many models is the complexity of their frameworks, which may prevent
potential users to implement them on the basis of time and cost commitment (Crawford, 2011).
Jugdev and Thomas (2002) also summarised some common criticisms of maturity models as
comprising:
1. The models are mostly inflexible to change and ongoing improvements and are not able
to address specific areas of specialisation
2. The models are often orientated towards identification of problems rather than solving
problems
3. The models do not take account of the rapid pace of change and emerging technologies
and innovative processes or practices adopted by organisations over time
4. The structured levels of maturity models do not propose sufficient detail to assess
progress achievement
5. The models methodologies are largely mono-disciplined, disconnected from practice, and
at times overwhelming
6. The models mostly ignore the human resource or operational aspects
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
74
Maturity models often have a limited theoretical basis and lack conceptual underpinning
(Backlund et al., 2014). A major research project by Thomas and Mullaly (2008) into the benefit
of project management identified the significance of ‘fit’ between implementation of projects and
organisational strategy, including the impact of internal and external contexts. Mullaly and
Thomas (2010) also highlight that this contradicts lessons from contingency theory, suggesting
that different organisational configurations can be successful provided the strategies are
consistent with their environment. In other words, maturity models need to provide a bridge
between project success and organisational strategy. Crawford (2011:1) makes the following
observation:
“Project management is now recognised as an organisational capability and there are numerous generic
‘maturity’ models providing one size fits all approaches to what is considered to be ‘best practice’. Both
maturity models and best practices are problematic. Maturity models typically suggest that all firms must
strive to progressively achieve prescribed levels of practice across the same range of ‘best’ practices. But what
constitutes best practice for whom and under what circumstances? If we look at an organisation’s project
management systems, although they may have similarities across firms, they are operating in different
contexts, driven by different strategies. What may be best for some may not be best for others.”
The literature highlights a situation where the dominant market solutions to organisational
maturity each have disadvantages that make them too rigid (one size fits all), deterministic (based
on hierarchical assessment), misaligned to objectives (not strategic) and impractical (disconnect to
project success). In addition, existing market solutions are complicated and resource intensive.
Given the above, it is suggested that an appropriate management maturity model should be
customisable by organisations (i.e. able to evolve according to their changing environment over
time), systematic in its assessment of organisational capabilities (i.e. continuous improvement
framework), aligned to organisational strategy at the level of project, program and portfolio (i.e.
management by objectives), and relevant to project delivery success in practice (i.e. use of
measurable critical success factors). There is opportunity to align the model to the PMBOK
methodology given that OPM3 is the main player in this domain, yet OPM3 is extremely
complicated, expensive (cost and time) and currently going through a tumultuous stage in its
development.
Proposed Management Maturity Model (MMM)
Each of the key criteria mentioned above is examined in this section. Inspiration is drawn from
the seminal work of Charles R. Darwin (1809-1882), W. Edwards Deming (1900-1993), Peter F.
Drucker (1909-2005) and D. Ronald Daniel (1931-) for the design of the proposed Management
Maturity Model (MMM). Intrinsic to the model’s approach is the need for it to also be practical in
the project management marketplace and hence capable of widespread adoption.
Customisable
The literature is clear that a ‘one size fits all’ approach to maturity assessment is flawed. Not only
are organisations different, but they also operate in a wide range of industries that themselves are
at different stages of maturity. It has always been a core objective of maturity models to enable
comparison of organisations in the context of benchmarking against ‘best practice’. What
constitutes best practice in one industry, however, may not be appropriate in another. It is also a
barrier to adoption if competitive advantage is lost through disclosure of levels of immaturity that
might affect reputation and market position. A more confidential way to benchmark performance
needs to be found.
Organisations evolve over time, and the strength of their capabilities dictates whether they are
successful or unsuccessful. Maturity assessment needs to provide guidance on positive
improvement and fix weaknesses that might lead to poor performance.
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
75
Charles Darwin is renown for his contribution to evolution theory. His research established that
all species of life have descended from common ancestors over time. His scientific theory was
that this branching pattern of evolution resulted from a process of natural selection, in which the
struggle to survive is similar to selective breeding programs. Darwin published his theory of
evolution together with compelling field evidence in his book On the Origin of Species (Darwin,
1859). By the 1870s, the scientific community and a significant proportion of the general public
believed evolution was indeed true, but it took many more years before a broad consensus
emerged that natural selection was the basis of evolutionary improvement and capable of
explaining the diversity of life on Earth. Darwin has been characterised as being one of the most
influential people in human history.
Using this concept, organisations can be viewed as ‘species’ that evolve and diversify. This is not
a function of maturation, but their agility to deal with external forces and trends within the
environment in which they operate. These influences change over time. Best practice is also fluid.
Generic capabilities and standard criteria for mature systems and performance is limiting and
inflexible. A better approach is for organisations to understand their journey of maturity over
time by assessing their own core strategic objectives. Benchmarking with others can take place
through the sharing of relevant organisational objectives used by market leaders or innovators
that describe capabilities that are considered critical to success. Rather than comparing maturity
levels to benchmark best practice, organisations adopt capabilities that are compatible with their
individual structure and vision. Customisable core strategic objectives and organisational
capabilities should be a key tenet in the process of maturity assessment.
Systematic
The literature is also clear that maturity assessment must be systematic and evidence-based.
Maturity by definition is a process of continuous improvement from a state of relative simplicity
(or naivety) to one of sophistication and rigour. This process needs to be capable of translation
into measurable evidence at each stage of development. The level of maturity of an organisation
is a function of the number of capabilities that can be observed to operate routinely at high levels
of optimisation. The underlying systems put in place form the evidence of a mature process.
Continuous improvement is both sequential and cyclical. It is sequential because there are
fundamental steps that must take place to reach higher levels of performance, and cyclical
because organisations need to be able to learn from their performances in order to further
improve the underlying processes and systematically pursue optimal outcomes (Wysocki, 2004).
Edwards Deming is credited with the well-respected plan-do-check-act (PDCA) continuous
improvement cycle (Wood and Wood, 2005). The PDCA (see Figure 2) built on the work from
Walter Shewhart’s book Statistical Method from the Viewpoint of Quality Control (Shewhart, 1939) to
produce the plan-do-study-act (PDSA) cycle. Nevertheless, Deming worked closely with
Shewhart to develop the idea of continuous improvement as part of a system where feedback
from the process and customer is evaluated against organisational goals (Moen and Norman,
2012). Deming is the father of the total quality management movement.
Continuous improvement can be applied to all management activities including project and
performance management (Du et al., 2008). For example, in PMBOK (2013), the process groups
are an example of PDCA, demonstrating that project management processes are similar to other
business processes when it comes to continuous improvement. The PMBOK™ Guide adopts six
process groups for projects – planning (plan), executing (do), monitoring (check) and controlling
(act) – fitting within the context of initiating at the start and closing at the end of the project life
cycle. The heart of the PMBOK methodology is closely aligned to PDCA.
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
76
Figure 2: The PDCA continuous improvement cycle
For any project type, it is necessary to plan, do, check, and act. PDCA provides a robust and
more tangible method for measuring maturity. The following analogy can be adopted for
evidence-based assessment:
1. Plan: Establish targets
2. Do: Measure outcomes
3. Check: Assess performance
4. Act: Enhance protocols
Full maturity is reached when there is evidence of routine adoption of the above sequence in the
underlying systems that support all of the appropriate organisational capabilities in the model.
Rather than use a hierarchy of maturity levels, this approach highlights the need for nurturing a
learning culture that aims to continuously improve (Stacey, 2003). A systematic cycle of
organisational growth is thus supported.
Strategic
The literature refers to organisational capabilities as a framework in which maturity can be
assessed. Capabilities are tied to core strategic objectives that are derived from a declared vision,
mission and set of organisational values. The notion is that if capabilities are mature, then the
achievement of organisational strategy is enhanced (Backlund et al., 2014). A large number of
detailed capabilities, however, can inadvertently diminish their connection to strategy. It hence
may be preferable to focus assessment on a smaller number of core capabilities (Nandyal, 2003).
The discipline of project management is commonly characterised as a combination of projects,
programs (i.e. multiple aligned project) and portfolios (i.e. collections of projects and programs).
It is likely that capabilities change and become more sophisticated on this continuum, and it
provides an opportunity to demonstrate a maturation pathway from small scale (local projects) to
large scale (global portfolios). In all cases, project management is achieved by the pursuit of
objectives.
Peter Drucker is credited with the concept of management by objectives (MBO). His work
contributed to the practical and philosophical foundations of the modern business corporation
and he is frequently described as the founder of modern business management. He was a writer,
academic, business consultant and self-acclaimed ‘social ecologist’ who explored the way that
people interact and organise themselves. MBO arose from his book The Practice of Management
(Drucker, 1954). It is a model of management that aims to improve organisational performance
by clearly articulating strategic objectives that are accepted by both management and staff.
According to the theory, participation in goal setting and the development of action plans leads
to higher levels of commitment towards organisational success, as well as alignment of objectives
across all parts of the business.
Plan
DoCheck
Act
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
77
There are countless ways to implement management by objectives in practice. One needs to set
core strategic objectives and then break these down into progressive targets. Organisations that
apply MBO frequently report higher rates for sales and improved worker productivity
(http://smallbusiness.chron.com/examples-managerial-objectives-23790.html). Objectives can
be defined at any level of an organisation – with collective or individual responsibility. Both
enable the task at hand to be more attainable and help people to visualise what needs to be
achieved and how this can happen. Objectives need quantifying and monitoring.
Organisational capabilities are similar to objectives and can be managed in the same way. These
capabilities can be used to track performance in the quest to move from lower capability to
higher capability over time (Dosi et al., 2000). Each capability requires a target goal to be
established, outcomes to be measured, assessment of performance and the enhancement of
systems and protocols where improvement is warranted.
Practical
The literature is clear that maturity models act as a bridge between organisational strategy and
project success. What is not so clear is how to measure success in an objective and organisation-
wide manner. Cooke-Davies (2002) highlights confusion between terms such as ‘project success’
(doing the right project) and ‘project management success’ (doing the project right), and between
‘success factors’ (that lead to success) and ‘success criteria’ (that evaluate success). In the latter
case, the list is long and criteria/factors are often specific to particular project types and client
objectives (Davis, 2014). Success criteria (such as KPIs) and success factors (such as core project
constraints) are commonly linked (Westerveld, 2003).
Ron Daniel developed the concept of success factors in the 1960s during his long-term role as
Managing Director of McKinsey & Co. The notion seems quite obvious: in any business
environment certain factors will be critical to the achievement of success, and so logically if
objectives associated with the factors are not realised, the business will fail – perhaps dramatically.
The objectives are examples of success criteria, and often presented in the form of KPIs. Critical
success factors were defined twenty year’s later by John Rockart as success factors that are
‘mission-critical’ (Rockart, 1979; Bullen and Rockart, 1981). Daniel’s work translates well to the
discipline of project management where successful project delivery is always the main goal.
Figure 3: 3D Project integration model (Langston, 2013)
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
78
Langston (2013) employs success factors and criteria to explain what successful projects might
look like. His AIPM and IPMA award-winning model (shown in Figure 3) for describing project
integration is presented as a tetrahedron containing all knowledge areas existing in the PMBOK™
Guide (Fifth Edition), plus a new area of project environmental management that can recognise
sustainability as an emerging aspect of modern project delivery (Ebbesen and Hope, 2013;
Fernández-Sánchez and Rodríguez-López, 2010; Hwang and Ng, 2013). Langston contends his
model can be deployed to measure the ability of project teams to deliver successful performances
at all stages of the project life cycle. This is achieved through the identification of success factors
(represented by the four vertices of the model) and success criteria (represented by the edges of
the model). KPIs are derived from the model to describe the relationships between success
factors. They are constructed so to be relevant to any project type as well as being capable of
numeric measurement. Project Integration Management, a key knowledge area in the PMBOK™
Guide, is intended to ensure that the right balance between all parts of a project is achieved over
the project life cycle, and is reflected in the 3D nature of the model itself.
This 3D project integration model includes six generic success criteria (KPIs) that are related to
project delivery success (PDS). They comprise:
1. Value: This KPI is described as project scope divided by cost (objective: maximise). Value
is assessed in the context of Project Stakeholder Management, including meeting
specified expectations and fostering ongoing engagement. Scope is interpreted as an
output and cost is interpreted as an input, therefore the more utility delivered per unit of
cost the more value for money is realised.
2. Efficiency: This KPI is described as project cost divided by time (objective: maximise).
Efficiency is assessed in the context of Project Human Resource Management, including
leadership and team high performance. Cost is interpreted as an output (i.e. the value of
work completed) and time is interpreted as an input, meaning that the more money
expended per unit of time the more efficient is the project delivery process.
3. Speed: This KPI is described as project scope divided by time (objective: maximise). Speed
is assessed in the context of Project Procurement Management, including outsourcing
strategies and parallel supply chains. Scope is interpreted as an output, and time is
interpreted as an input, such that the more utility provided per unit of time the faster the
project delivery process.
4. Innovation: This KPI is described as project risk divided by cost (objective: maximise).
Innovation is assessed in the context of Project Communications Management, including
knowledge management and research-informed learning. Risk is interpreted as an output
(innovation leads to development risks) and cost is interpreted as an input; therefore a
higher level of risk per unit of cost reflects the search for better ways of doing things (i.e.
extra risk is only warranted if competitive advantage is realised).
5. Complication: This KPI is described as project risk divided by time (objective: minimise).
Complication (originally known as ‘complexity’) is assessed in the context of Project
Quality Management, including being alert to excessive quality assurance paperwork and
engineering over design. Risk is interpreted as an output and time is interpreted as an
input, so a higher level of risk per unit of time is a sign of project difficulty that should
be avoided during rollout.
6. Impact: This KPI is described as project risk divided by scope (objective: minimise).
Impact is assessed in the context of Project Environmental Management, including
awareness of adverse sustainability outcomes and unnecessary resource consumption.
Risk is interpreted as an output and scope is interpreted as an input, meaning that a
higher risk level per unit of utility reflects unwanted environmental disruption.
The key relationships between the four success factors (cost, time, scope and risk) and the six
success criteria (value, efficiency, speed, innovation, complication and impact) are illustrated in
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
79
Figure 4. A 2D representation of the model is provided for ease of comprehension, but it
converts into a 3D tetrahedron by ‘folding’ along the dotted lines. Success factors are equally
weighted and are shown in upper case.
Figure 4: Success factors and success criteria (Langston, 2013)
Overall success (computed as the change in PDS between planned and actual performance) is
given by the following formula (Langston, 2013):
()= 3
where: s = scope baseline, c = cost baseline, t = time baseline and r = risk baseline
MMM design and testing
Drawing on the above issues, a new approach for the assessment of organisation maturity is
constructed. It is based on the six KPIs for project delivery success (value, efficiency, speed,
innovation, complication and impact) plus an overall KPI to take account of the combined effect
of the four success factors (scope, cost, time and risk). Continuous improvement based on
PDCA is the means for assessing maturity. Core objectives and capabilities for project, program
and portfolio domains can be identified. These are customisable and therefore can differ from
one organisation to the next. The full model, shown in Figure 5, is tested in the field based on a
medium-sized data centre infrastructure firm in Tehran. The data was collected anonymously and
as such the firm is referred to as ‘example organisation’.
The example organisation uses a management by project approach as the basis for its business
model. Within its niche market it is considered a medium-sized firm and employs approximately
270 people. It had a turnover last financial year of US$45 million and participated in numerous
Iranian data centre projects as designer, supplier and constructor. The firm builds the data centre
and then installs infrastructure using proprietary equipment sourced mainly from international
suppliers.
The standard used for data centre design in the example organisation is ANSI/TIA942-2005
issued by the American Telecommunication Industry Association. In this standard, data centres
are divided into different levels according to client requirements of reliability, infrastructure,
construction structure, electric facilities and mechanical facilities (Ye et al., 2014). The example
organisation is commissioned to design and build data centres according to client needs based on
a rating/tier (1, 2, 3 or 4). A team of auditors certified by Uptime Institute (USA) perform
monitoring compliance against the specified rating/tier.
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
80
Figure 5: Proposed Management Maturity Model (MMM)
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
81
The example organisation shared documents relating to organisational capabilities in action, and
facilitated interview responses from the Chief Executive Officer (CEO) and various program and
project managers who work at the firm. This access helped to identify the firm’s core strategic
objectives and relevant capabilities aligned to each KPI. Points were assigned only where
demonstrable evidence could be observed. This evidence was recorded electronically and
archived in a database underpinning the case study methodology.
To illustrate the process, the KPI of ‘value’ is discussed in more detail. Value is interpreted in the
context of stakeholder management. The core objective for this KPI is identified as ‘strategic
alignment to build market share’. In other words, value is strengthened when the performance of
a project, program or portfolio is aligned to the strategic vision, mission and values of the
organisation. This objective is then broken down into capabilities that enable repeat client work
(project level), market positioning (program level) and shareholder return (portfolio level). These
three capabilities are in increasing order of complexity and are scored according to evidence of
progressive PDCA improvement. Evidence of ‘Plan’ equals 1 point, ‘Plan+Do’ equals 2 points,
‘Plan+Do+Check’ equals 3 points, and ‘Plan+Do+Check+Act’ equals 4 points. Missing a step in
the PDCA sequence disables the scoring of further steps. The evidence collected from the
example organisation is shown in Figure 6.
Figure 6: Example of identified case study evidence for ‘value’
The maturity score for the example organisation is derived from a self-assessment process. Each
domain can have a maximum score of 28. The radar diagrams show the level of maturity for
project, program and portfolio domains, and the size of the mapped area gives a visual
impression of where strengths and weaknesses lie (Jin et al., 2014). An extra 4 bonus points are
awarded if a domain reaches this fully mature level. An extra 4 bonus points are awarded if all
three domains are fully mature, and this would then equal 100 points overall (i.e. 100% maturity).
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
82
The case study results show that the firm has a maturity score of 54% based on their own defined
strategy and capabilities. The radar diagrams highlight the weakest performance is in the domain
of portfolio management. The firm’s Project Management Office (PMO) has contributed to the
stronger performance at the level of individual projects. Results from discussions with key
personnel identify that the most important objective when operating in the data centre
infrastructure industry is to grow market share, and this is achieved by close alignment of all
activities with overall organisational strategy. In order to obtain feedback on the case study
findings, the CEO was later interviewed about the process and whether it was useful to the
organisation. His key comments are listed below (translated from Persian):
Our company is one the most active firms in the data centre infrastructure business in Iran. We have done several
ICT projects within this industry and our first priority is to meet customer expectations in order to get repeat work
from them. We have hired and trained a number of professional experts to help us in this regard.
The other aspects in which I feel we have developed maturity is our project management systems. Our PMO works
hard on supporting project managers with useful templates and documents, and evaluating their performance. The
project control team reviews data gathered from diverse projects located in different cities. However, there appear to
be some weaknesses here. For instance, as there are an overwhelming number of stakeholders on our projects, an
effective method of managing communications has not been achieved. Actually the problem runs deeper than that.
The lack of an effective method leads to overlooking important lessons that would help to improve future projects.
Recently, in order to increase the company’s technical capabilities, we established an R&D department that is
working to minimise the downtime on our DC projects and use leading standard industry practices to satisfy
auditors’ requirements. This has proven very valuable to ensuring customer satisfaction.
Overall, I reckon we have to put more effort on building and developing our reputation within the industry, and
controlling cost and time baselines to increase profit. I think that your approach to measuring our maturity is
something we would like to continue to use, with your input and advice. We need to continually improve if we want
to grow our current market share.
The CEO expressed high levels of satisfaction with both the method of maturity assessment and
the practicality of its application in the office. The case study demonstrated that organisational
strategy can be identified and capability can be demonstrated in terms of specific evidence
collected during an independent audit. The outcome score provides a more precise measure of
maturity than discrete hierarchical levels and involves up to 84 unique items of objective proof.
This case study highlights that maturity in the data centre infrastructure industry requires a set of
capabilities that are somewhat different to what might be expected in other fields. For example,
impact and environmental management are largely defined as relating to noise transfer to
adjoining spaces and neighbouring properties. The firm scored well in terms of their investment
in research and development (R&D) which is seen as critical to firm growth and market share. A
comprehensive human resource (HR) allocation system exists but has not been updated for many
years. A 360-degree appraisal is carried out annually to measure team performance. Overall, the
audit was able to make recommendations for improving system maturity, such as devoting more
effort towards better communication protocols to support competitive advantage. In particular,
some of the benefits of R&D activity were not being captured and disseminated throughout the
firm. Senior managers agreed that lessons learnt were not recorded in the PMO’s system in a
timely manner. Moreover, given the CEO manages the firm’s portfolio himself, the assessor
recommended that a team be established to handle this complex job in the near future.
MMM enables organisation maturity to be pursued via a customisable, systematic, strategic and
practical approach. While it produces an overall score that can be used for internal trend analysis
over time, the rigour of the process lies in the detailed assessment of individual capabilities.
However, as capabilities are variables and organisation-specific, the model does not enable
maturity to be compared across different organisations. Comparison is normally seen as a
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
83
potential barrier to implementation in practice given that the maturity of an organisation (and
hence the likelihood of achieving success in its endeavours) is not something to be broadcast to
either the market or to one’s competitors.
The approach used in MMM is facilitated by the involvement of experienced assessors. These
assessors are critical in helping to realise the following benefits:
1. Identifying appropriate objectives and capabilities: These can be freely shared between
organisations (via the assessors) since they reflect targets not performances
2. Certifying the self-assessment process: Evidence can be validated and audited by assessors to
ensure probity
3. Recommendations to enhance protocols: An experienced assessor can suggest ways to address
deficiencies and develop more mature systems to support business activities
Experienced assessors may be people who are already certifiers for other rival maturity models. It
would be advantageous to use a small panel of assessors on every assessment. They are also likely
to be drawn from senior project managers, directors of PMOs and qualified academics in the
project management field. Their role includes auditing maturity evidence and providing advice on
how to improve organisational systems and processes. International professional bodies such as
PMI and IPMA, and national bodies such as APM and AIPM should act as brokers for putting
organisations in touch with assessors, as well as ensuring assessors are appropriately trained.
Conclusion
The basis for achieving consistent excellence in project management is assisted by mature
organisational systems and processes. MMM is a simple yet robust model capable of guiding the
development of any project management environment that needs to support the business of
successful project, program and/or portfolio delivery. It forms a bridge between organisational
strategy and project success through compatibility with the PMBOK™ Guide and the 3D
Integration Model for assessing optimal delivery of individual projects. It can be adopted as a
self-assessment tool and enhanced by the employment of an experienced consultant or auditor to
provide improvement advice. It is a potential replacement for the complex OPM3 tool especially
for smaller organisations that cannot justify the resultant time and expense. MMM is the only
maturity model that uses the PDCA continuous improvement cycle embedded in the PMBOK
methodology, and the only maturity model that supports customisable organisational capabilities.
Field-testing on a medium-sized firm in Tehran suggests the implementation of MMM in practice
is feasible and considered valuable by organisational stakeholders. Despite established solutions
like CMMI, P3M3 and OPM3, there is still opportunity for MMM to improve current practices.
A Microsoft Excel™ template for calculation of maturity scores is freely available from the lead
author of this paper via an email request.
References
Allué, A., Domínguez, E., López, A. and Zapata, M.A. (2013) QRP: a CMMI appraisal tool for project quality
management, Procedia Technology, 9, 664-669. doi: https://doi.org/10.1016/j.protcy.2013.12.073
Artto, K., Martinsuo, M., Gemünden, H.G. and Murtoaro, J. (2009) Foundations of program management: a
bibliometric view, International Journal of Project Management, 27(1), 1-18. doi:
https://doi.org/10.1016/j.ijproman.2007.10.007
Backlund, F., Chronéer, D. and Sundqvist, E. (2014) Project management maturity models - a critical review: a case
study within Swedish engineering and construction organisations, Procedia Social and Behavioural Sciences, 119,
837-846. doi: https://doi.org/10.1016/j.sbspro.2014.03.094
Brookes, N. and Clark, R. (2009) Using maturity models to improve project management practice, POMS 20th
Annual Conference, Florida USA, May. Available from: http://pomsmeetings.org/ConfProceedings/011/
FullPapers/011-0288.pdf
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
84
Bullen, C.V. and Rockart, J.K. (1981) A primer on critical success factors, Boston: Center for Information Systems
Research, MIT.
Cooke-Davies, T. (2002) The ‘real’ success factors on projects, International Journal of Project Management, 20(3),
185-190. doi : https://doi.org/10.1016/j.protcy.2013.12.073
Cooke-Davies, T. (2004) Project management maturity models, in Morris, P.W.G and Pinto, J.K., The Wiley Guide
to Managing Projects, 1234-1255. doi: http://dx.doi.org/ 10.1016/S0263-7863(01)00067-9
Crawford, L. (2011) Fitting project management capability to strategy, 8th Annual Project Management Australia
conference (PMOz): Project management at the speed of light, Sydney, Australia, 2-5 August. Available from:
http://epublications.bond.edu.au/sustainable_development/122
Daniel, D.R. (1961) Management information crisis, Harvard Business Review, September-October.
Darwin, C. (1859) On the origin of species, London: John Murray.
Davis, K. (2014) Different stakeholder groups and their perceptions of project success, International Journal of
Project Management, 32(2), 189-201. doi: https://doi.org/10.1016/j.ijproman.2013.02.006
de Souza, T.F. and Gomes, C.F.S. (2015) Assessment of maturity in project management: a bibliometric study of
main models, Procedia Computer Science, 55, 92-101. doi:
https://doi.org/10.1016/j.procs.2015.07.012
Demir, C. and Kocabaş, İ. (2010) Project management maturity model (PMMM) in educational organisations,
Procedia Social and Behavioral Sciences, 9, 1641-1645. doi:
https://doi.org/10.1016/j.sbspro.2010.12.379
Dosi, G., Nelson, R.R. and Winter, S.G. (2000) The nature and dynamics of organisational capabilities, Oxford:
Oxford University Press.
Drucker, P.F. (1954) The practice of management, New York: Harper & Row.
Du, Q.L., Cao, S.M., Ba, L.L. and Cheng, J.M. (2008) Application of PDCA cycle in the performance management
system, 4th International Conference on Wireless Communications, Networking and Mobile Computing, 2008
(WiCOM'08), IEEE, October, 1-4. doi: https://doi.org/10.1109/WiCom.2008.1682
Ebbesen, J.B. and Hope, A. (2013) Re-imagining the iron triangle: embedding sustainability into project constraints,
PM World Journal, 2(III). Available from: http://nrl.northumbria.ac.uk/id/eprint/11311
Fahrenkrog, S., Abrams, F., Haeck, W. and Whelbourn, D. (2003) Project Management Institute’s Organisational
Project Management Maturity Model (OPM3), PMI North American Congress, Baltimore, MD, June.
Fernández-Sánchez, G. and Rodríguez-López, F. (2010) A methodology to identify sustainability indicators in
construction project management: application to infrastructure projects in Spain, Ecological Indicators, 10(6),
1193-1201. doi: https://doi.org/10.1016/j.ecolind.2010.04.009
González, N., Marle, F. and Bocquet, J.C. (2007) Measuring project maturity: example in a French automotive
organisation, International Conference on Engineering Design (ICED), August, 28-31. Available from:
http://www.designsociety.org/download-
publication/25671/measuring_project_maturity_example_in_a_french_automotive_organization
Hardgrave, B.C. and Armstrong, D.J. (2005) Software process improvement: it's a journey, not a destination,
Communications of the ACM, 48(11), 93-96. doi: https://doi.org/10.1145/1096000.1096028
Hillson, D. (2003) Assessing organisational project management capability, Journal of Facilities Management, 2(3),
298-311. doi: https://doi.org/10.1108/14725960410808276
Hutson, N. (1997) What is project management?, The 28th Annual Project Management Institute 1997 Seminars &
Symposium, Chicago: Project Management Institute, 1141-1142.
Hwang, B.G. and Ng, W.J. (2013) Project management knowledge and skills for green construction: overcoming
challenges, International Journal of Project Management, 31(2), 272-284. doi:
https://doi.org/10.1016/j.ijproman.2012.05.004
Jiang, J.J., Klein, G., Hwang, H.G., Huang, J. and Hung, S.Y. (2004) An exploration of the relationship between
software development process maturity and project performance, Information and Management, 41(3), 279-288.
doi: https://doi.org/10.1016/S0378-7206(03)00052-1
Jin, D., Chai, K.H. and Tan, K.C. (2014) New service development maturity model, Managing Service Quality: An
International Journal, 24(1), 86-116. doi: https://doi.org/10.1108/MSQ-10-2012-0134
Jugdev, K. and Thomas, J. (2002) Project management maturity models: the silver bullets of competitive advantage,
Project Management Institute. Available from: http://hdl.handle.net/1880/44250
Kohlegger, M., Maier, R. and Thalmann, S. (2009) Understanding maturity models: results of a structured content
analysis, IKNOW '09 and I-SEMANTICS '09, Graz, Austria, September, 51-61. Available from:
http://iwi.uibk.ac.at/download/downloads/Publikationen/KMM.pdf
Langston, C. (2013) Development of generic key performance indicators for PMBOK using a 3D project integration
model, Australasian Journal of Construction Economics and Building, 13(4), 78-91. doi:
https://doi.org/10.5130/ajceb.v13i4.3658 (winner: 2016 PMAA Australian National Research Award;
winner: 2016 IPMA Asia Pacific Regional Research Award; finalist: IPMA International Research Award)
Construction Economics and Building, 16(4), 68-85
Langston and Ghanbaripour
85
Lee, G. and Kwak, Y.H. (2012) An open government maturity model for social media-based public engagement,
Government Information Quarterly, 29(4), 492-503. doi: https://doi.org/10.1016/j.giq.2012.06.001
Moen R. and Norman C. (2012) Evolution of the PDCA Cycle. Available from: www.pkpinc.com
Mullaly, M.E. and Thomas, J.L. (2010) Re-thinking project management maturity: perspectives gained from
explorations of fit and value, PMI Research and Education Conference 2010: Defining the Future of Project
Management, Pennsylvania: Project Management Institute.
Musat, D., Castaño, V., Calvo-Manzano, J.A. and Garbajosa, J. (2010) Mature: a model driven based tool to
automatically generate a language that supports CMMI process areas specification, in Riel, A., O’Connor, R.,
Tichkiewitch, S. and Messnarz, R. (eds.), Systems, Software and Services Process Improvement, Springer, 48-59.
doi: https://doi.org/10.1007/978-3-642-15666-3_5
Nandyal, R.S. (2003) People CMM: interpreting people CMM for software organisations, New Delhi: Tata McGraw-
Hill Publishing Company Limited.
Nesensohn, C., Bryde, D., Ochieng, E. and Fearon, D. (2014) Maturity and maturity models in lean construction,
Australasian Journal of Construction Economics and Building, 14(1), 45-59. doi:
https://doi.org/10.5130/ajceb.v14i1.3641
Pane, E.S. and Sarno, R. (2015) Capability Maturity Model Integration (CMMI) for optimising object-oriented
analysis and design (OOAD), Procedia Computer Science, 72, 40-48. doi:
https://doi.org/10.1016/j.procs.2015.12.103
Pasian, B., Sankaran, S. and Boydell, S. (2012) Project management maturity: a critical analysis of existing and
emergent factors, International Journal of Managing Projects in Business, 5(1), 146-157. doi:
https://doi.org/10.1108/17538371211192946
Pinto J.A. and Williams N. (2013) Country project management maturity, 2013 PMI Global Congress Proceedings,
Istanbul.
PMI (2013) Organisational Project Management Maturity Model (OPM3), Third Edition, Pennsylvania: Project
Management Institute Inc.
Pretorius, S., Steyn, H. and Jordaan, J.C. (2012) Project management maturity and project management success in the
engineering and construction industries in South Africa, South African Journal of Industrial Engineering, 23(3),
1-12. doi: https://doi.org/10.7166/23-3-507
Rockart, J.F. (1979) Chief Executives Define their Own Data Needs, Sussex Business Review, March-April.
Shewhart, W.A. (1939) Statistical method from the viewpoint of quality control, Washington: U.S. Department of
Agriculture.
Silva, D., Tereso, A., Fernandes, G. and Pinto, J.Â. (2014) OPM3 Portugal project: analysis of preliminary results,
Procedia Technology, 16, 1027-1036. doi: https://doi.org/10.1016/j.protcy.2014.10.057
Sowden, R., Hinley, D. and Clarke, S. (2008) Portfolio, Programme & Project Management Maturity Model (P3M3),
Office of Government Commerce Journal, 1-4.
Stacey, R.D. (2003) The learning organisation. In: Stacey, R.D. Strategic Management and Organisational Dynamics,
Harlow: Pearson Education Ltd, 103-128.
Staples, M. and Niazi, M. (2010) Two case studies on small enterprise motivation and readiness for CMMI, 11th
International Conference on Product Focused Software, June, 63-66. doi:
https://doi.org/10.1145/1961258.1961274
Staples, M., Niazi, M., Jeffery, R., Abrahams, A., Byatt, P. and Murphy, R. (2007) An exploratory study of why
organisations do not adopt CMMI, Journal of Systems and Software, 80(6), 883-895. doi:
https://doi.org/10.1016/j.jss.2006.09.008
Thomas, J.L. and Mullaly, M.E. (2008) Researching the value of project management, Pennsylvania: Project
Management Institute.
Westerveld, E. (2003) The Project Excellence Model: linking success criteria and critical success factors, International
Journal of Project Management, 21(6), 411-418. doi: https://doi.org/10.1016/S0263-7863(02)00112-6
Wood, J.C. and Wood, M.C. (2005) W. Edwards Deming: critical evaluations in business and management (Volume
1), Routledge.
Wysocki, R.K. (2004) Project management process improvement, Artech House.
Ye, H., Song, Z. and Sun, Q. (2014) Design of green data centre deployment model based on cloud computing and
TIA942 heat dissipation standard, IEEE Workshop on Electronics, Computer and Applications, May, 433-437.
doi: https://doi.org/10.1109/IWECA.2014.6845649
Young, M., Young, R. and Romero Zapata, J. (2014) Project, programme and portfolio maturity: a case study of
Australian Federal Government, International Journal of Managing Projects in Business, 7(2), 215-230. doi:
https://doi.org/10.1108/IJMPB-08-2013-0034