A Review of Agile Software Effort Estimation Methods
Samson Wanjala Munialo.
Department of Information Technology
Meru University of Science and Technology
Meru - Kenya
Geoffrey Muchiri Muketha
Department of Information Technology
Murang’a University College
Murang’a - Kenya
Abstract: Software cost estimation is an essential aspect of software project management and therefore the success or failure of a software
project depends on accuracy in estimating effort, time and cost. Software cost estimation is a scientific activity that requires knowledge of a
number of relevant attributes that will determine which estimation method to use in a given situation. Over the years various studies were done
to evaluate software effort estimation methods however due to introduction of new software development methods, the reviews have not
captured new software development methods. Agile software development method is one of the recent popular methods that were not taken
into account in previous cost estimation reviews. The main aim of this paper is to review existing software effort estimation methods
exhaustively by exploring estimation methods suitable for new software development methods.
Keywords: Lines of codes, Cost constructive model, Function point, Agile, software effort estimation.
1. INTRODUCTION
Demand for more functionality, higher reliability and higher
performance has resulted to higher competitiveness among
software developers. To stay competitive, software developers
need to deliver software products on time, within the budget and to
the agreed level of quality. Most projects fail due to planning issues
such as cost, time and requirements specifications. A study on
software projects in 2012 by Standish shows that 43% of projects
were challenged and 18% failed due to over budget, late delivery
and less than required features or functions [1]. This illustrates the
necessity for reliable software development method and software
cost estimation method.
For faster and quality delivery, software vendors are moving from
structured development methods where requirements are well
known in advance to agile development which welcomes customer
changing requirements at later stages of software development [2].
The shift from traditional development methods to agile is due to
the high cost of affecting changes request by users at later stages of
software development. Agile encourage changes, therefore
decreasing the cost of change and reduce the overall development
cost. Agile make this possible as a result of simple design,
collective ownership, continuous testing and short releases cycles.
Many estimating methods have been proposed since 1950’s and
many studies have evaluated their effectiveness. The most popular
traditional cost estimation methods are Expert judgment, Analogy,
Wideband Delphi, Source lines of codes, Function points [3],
Object points and Cost constructive model (COCOMO) [4] [5].
However, they are not effective when dealing with agile software
estimation. Estimating agile software is a problem due to varying
requirements and incremental development. This prompted the
introduction of cost estimation methods such as planning poker [6]
in 2003 which is one of the most popular agile estimation methods.
However, planning poker depends on expert experience on
previous projects and its estimates are specific to the team; another
team may estimate different story point for the same project
Recently other methods such as Bayesian Belief Network,
AgileMOW[7] and Constructive Agile Estimation algorithm [8]
were introduced to deal with uncertainty and iterative nature of
agile software development. Estimation of effort and cost depends
on accurate estimation of the software size which helps to predict
the project scope. Apart from size, other indicators such as project
complexity factors are considered when estimating effort.
Therefore, a reliable software cost estimation method must include
critical cost indicators for more accurate estimation. The main
objective of this paper is to discuss existing software cost
estimation methods including their features and situations where
they are applicable. This paper is organized in 6 sections which
include introduction, background, Traditional effort estimation
methods, agile effort estimation methods, discussion and
conclusion.
2. BACKGROUND
Software estimation is a critical component of software project
management. Cost overruns increased from an average of 56% in
2004 to 59% in 2012 in sampled software projects while time
overruns increased from 71% in 2010 to 74% in 2012 [1]. More
accurate estimation helps software developers to gain profit and
customers to be more satisfied. On the other hand, high costing can
lead to lost profit by losing bidding while low costing can lead to
cost overruns and poor quality of end product. Software estimation
comprise of estimating software cost, size, effort and time required
to develop the software [9]. Software developers require an
effective software cost estimation model to facilitate project
planning and eventually successful implementation of a software
project.
Agile software development method is one method that provides a
challenge to existing software cost estimation techniques. Agile
software development is based on iterative development where
requirements evolve through collaborations. Scope is continuously
adjusted throughout the project and new tasks are discovered [10].
It emphasizes on working software, customer collaboration,
response to change on demand and does not support well defined
requirements like the traditional waterfall method. All these
challenges make most of the existing software cost estimation
techniques to appear limited when dealing with agile software.
Software developers have had the interest of estimating accurately
the cost of developing software products. The first methods were
only based on software size using lines of codes or function points
to estimate the cost. Currently other cost drivers such as process
International Journal of Computer Applications Technology and Research
Volume 5Issue 9, 612-618, 2016, ISSN:-23198656
www.ijcat.com 613
factors and human factors have been included in estimation
methods to improve on software estimation accuracy [7]. However,
demand for new functionalities, quick delivery of software such as
mobile applications established a need for new software
development methods. Currently other features such software re-
use, component based development, distributed systems and
iterative development are common features in software engineering
industry. Evolution in software engineering industry provided a
challenge to software estimations researcher to come up with
methods that will estimate more accurately.
3. TRADITIONAL COST ESTIMATION
METHODS
Cost estimating models are classified as non-algorithmic and
algorithmic. Non-algorithmic methods estimation relies on experts
who have experience on similar previous projects while
algorithmic methods use parametric in their estimation.
3.1 Non-Algorithmic estimation methods
Most non-algorithmic cost estimation techniques are based on
analytical comparison with previous similar projects and expert
experience [10]. Most popular methods in terms of recent
publications in this group are expert judgment, Analogy, top-down,
bottom-up, price-to-win and Wideband Delphi.
3.1.1 Expert judgment
Expert Judgment technique is the most frequently applied cost
estimation method where experts are responsible for estimating the
size and cost of a software. This method is based on the project
manager experience in similar software projects. Expert cost
estimation method is helpful when there is limitation in finding data
and gathering requirements [10] [11] [12]. Expert judgment is
prone to human errors and biasness. Its success is based on expert
judgment that is expert experience may differ from one expert
resulting to varying estimates on the same type of project.
However, it is helpful in small and medium sized software project
and when the development teams and software attributes have not
experienced significant changes as compared to previous projects.
3.1.2 Analogy technique
Analogy technique estimation is done according to the actual cost
of one or more completed projects that are similar to the new
project to be estimated [8][10] [11]. Estimation can be done at the
total project level or at sub system level. The strength of estimation
by analogy is that the estimate is based on actual project experience
and estimation can be done in the absence of an expert. However,
it does not take into consideration the extent of other relevant cost
factors in the previous project such as the environment and
functions which may differ with new project cost factors [13]. In
addition, a lot of past information about past projects is required
whereas in some situations there may be no similar projects
developed in the past to compare with.
3.1.3 Price-to-win, Bottom-up and Top-up
Price-to-win estimation method is based on customer budget
instead of software parameters or features. Example is when a
customer is willing to pay for 6 persons-month and the project
estimate is 8 persons-month then estimation is done as per the
customer ability to pay. This may cause delays and force
developers to work overtime [13]. Price-to-win method helps in
getting the contract but it generally causes cost and time overruns.
Bottom-up estimation method estimates by separating each
software component then summed to give the overall estimate for
the product. It is possible only when the requirements and design
of the system are known at an early stage of software development
[11] [14]. While top-down method established an overall estimate
for the project then the system is sub-divided into its functional
components which are then estimated based on the overall estimate
[13] [14]. The design and requirements must be well defined to
partition software to its component.
3.1.4 Wideband Delphi
Wideband Delphi method is a cost estimation technique where
effort and cost are estimated centered on team consensus. It is done
by getting advices from experts who have extensive experiences in
similar projects. Wideband Delphi technique was introduced by
Barry Boehm and John Farquher in 1970s. It uses work breakdown
structure as the basis for estimating project size, effort and cost [12]
[15]. This method emphasizes on consultations, communication
and interaction among participants.
Participants include customer representatives and technical team
members that will be involved in development of the software
product. Each member estimates for each task and identify changes
and missing assumptions in work breakdown structure. Members
with high or low estimates are asked to justify, and then members
revise the estimates. The cycle repeats until when estimators agree
on the estimates. The coordinator collects estimates from team
members and assembles the tasks and estimates into a single final
task list.
Wideband Delphi depends on team members experience and
agreement among members and thus it is not appropriate method
when applied to a software project that is unfamiliar to members
[14] [15]. Furthermore, it is a preferred method when requirements
are well defined and therefore, cannot work for software
development methodologies where requirements are not clear.
However, it encourages collaboration among estimators. Lastly, the
technique is simple to apply and supports consensus-based
estimates. Even though Wideband Delphi estimates are consensus-
based, experts may be biased, optimistic or pessimistic in their
estimation given that this method cannot be quantified.
3.2 Algorithmic software cost estimation methods
These models use a formula to calculate the software cost estimate
[13]. They rely on a combination of related cost factors which are
input to mathematical equation to do the estimation. Most common
algorithmic software cost estimation methods includes Source line
of codes (SLOC), Object points, Function-Point(FP)[3],
Constructive Cost Model-I (COCOMO-I) [4] and Constructive
Cost Model-II (COCOMO-II) [5].
3.2.1 Source line of codes (SLOC)
Source line of codes is a size metric that illustrates the number of
program statements and data definition but does not include
comments. SLOC is the earliest cost estimation method used to
estimate the size of FORTRAN and assembly language which are
line based programming languages. SLOC uses historical data of a
previously completed project of the same size whose SLOC was
computed before then compared with the actual one to estimate
project size. The size estimate is eventually used to estimate the
project scope, effort and cost [10]. SLOC is dependent on the
programming language and therefore cannot compare different
International Journal of Computer Applications Technology and Research
Volume 5Issue 9, 612-618, 2016, ISSN:-23198656
www.ijcat.com 614
programming language lines of codes. Source line of codes cannot
estimate the size of non-procedural languages and software
complexity is not taken into consideration when estimating size.
3.2.2 Function Point Analysis
Albrecht’s introduced Function point analysis method in 1983 [3]
which had better estimation than source lines of codes. Function
point is a size metric that quantifies the size and complexity of a
software system with regard to functions that the system will
deliver. Function count is arrived at by counting the basic software
components which include external inputs, external outputs,
external inquiries, logical internal files and external interfaces.
Each of the function is weighed by complexity factor ranging from
low, average to high [3] [11] [14]. Each function component is
multiplied with a respective complexity level then summed up to
give Function Count (FC).
Function point can be applied at requirement specification or
design phase of system development [14]. Furthermore, function
point is independent of language or methodologies used in software
development [3]. Lastly, Non-technical user can easily understand
the method. However, Function point cannot be used in situation
where requirements are not clear such as in agile software
development.
3.2.3 Object Point
It estimates the size of software based on number and complexity
of objects [11] [17]. The objects are screens, reports and 3GL
components. The steps for estimation effort using object point
include: counting the number of objects, classification of objects
(simple, medium, average), weight objects with regard to difficulty
as shown in table 1.
Table 1: Classification of objects weight
Object type
Simple
Medium
Difficult
Screen
1
2
3
Report
2
5
8
3 GL
components
10
Object point is determined by adding all the weights of object
instances to get object point count.
Estimate percentage re-use then compute the overall object points
(NOP) where, NOP = (Object Point) * (100-% reuse)/100
Furthermore, developers’ productivity is weighted from low to
highest then effort is estimated by dividing net object point by
productivity [11]. It is easy to apply object point method at any
stage of software development but on the other hand requirements
must be well defined. Object point only considered 3GL and 4GL
factors and thus cannot apply to current programming languages.
3.2.4 Constructive Cost Model (COCOMO)
COCOMO models were proposed by Barry Boehm [4]. These
methods use parameters which were derived from previous
experiences about software projects for estimation. Due to
COCOMO methods popularity various studies have extended
COCOMO framework to develop cost estimation methods with an
aim of improving software estimation accuracy. The 4 COCOMO
methods are simple COCOMO, Intermediate COCOMO, Detailed
COCOMO and COCOMO II.
Basic COCOMO computes software effort and cost as a function
of program size expressed in thousands lines of codes (KLOC)
using the formula:
Effort = a(KLOC)b
Where a and b are complexity factors which are assigned weights
according to software project complexity as shown in table 2.
Table 2: Complexity factor weights
Model
A
Organic (Simple)
2.4
Semi-detached(Average)
3.0
Embedded (Complex)
3.6
With the advancement in software development methods and
environment, basic COCOMO was not able to capture all relevant
cost factors in its estimation. Therefore, intermediate COCOMO
was released to include emerging software attributes in their
computation of software estimates.
Intermediate COCOMO uses Kilo lines of codes as in basic
COCOMO but it includes EAF (Effort adjustment factors) which
includes subjective assessment of products, hardware, personnel
and project attributes [5] [13]. Effort adjustment factors consider a
set of four factors, with each factor having a number of attributes.
The complexity factors are hardware, personnel, project and
product with the following attributes.
Hardware attributes: Run-time performance constraints,
Execution time constraint, Memory constraints,
Volatility of the virtual machine environment and
Required turnabout time.
Personnel attributes : Analyst capability, Software
engineering capability, Applications experience, Virtual
machine experience, Programming language experience
Project attributes: Use of software tools, Application of
software engineering methods and required development
schedule.
Product attributes: Required software reliability, Size of
application database and Complexity of the product,
required reusability.
Each of the 17 attributes is rated on a 6 point scale that ranges from
very low to very high. Based on the rating, an effort multiplier is
determined and the product of all effort multipliers results is an
effort adjustment factor (EAF). Typical values for EAF range from
0.9 to 1.4 The intermediate COCOMO model takes the form
EFFORT = a* (KLOC)b * EAF.
Another COCOMO version is detailed COCOMO which
incorporates all characteristics of intermediate COCOMO on each
step of software development process (Analysis, Design, coding
and testing). The 17 attributes are used in each step to estimate
software development effort [5] [10] [11] [13].
COCOMO-II was introduced in 1997 is an extension of
intermediate COCOMO. It predicts the amount of effort based on
Person-Month (PM) in the software projects [5][13]. It uses
Thousands lines of code or function point as the size metrics and
the number Effort adjustment factors attributes were increased by
5 to 22 attributes. The Usage of COCOMO II is very wide and its
results usually are more accurate. The 5 additional effort
adjustment factors are:
International Journal of Computer Applications Technology and Research
Volume 5Issue 9, 612-618, 2016, ISSN:-23198656
www.ijcat.com 615
- Precedents’(PREC)- Previous experience of the
organization
- Development Flexibility (FLEX) Degree of flexibility
in development process.
- Risk resolution (RESL)- Extent of risk analysis carried
out.
- Team cohesion (TEM)- How well development team
knows each other
- Process maturity (PMAT)- Process maturity of the
organization
COCOMO II formula takes the same format as intermediate
COCOMO formula of estimating effort [5] [10] [11].
All COCOMO methods capture a wide range of parameter when
estimating the cost of a project. So far COCOMO methods are the
most popular methods with clear results. The use of COCOMO
requires clear and well defined requirements [16]. However, a lot
of data is required to estimate effort and the model is presented as
black box to the user. However, COCOMO methods are challenged
when requirements are not clear and when the project is subject to
user request changes at later stages of software development.
3.2.5 Other software cost estimation methods
In recent years researchers have attempted to introduce more cost
and effort estimation techniques to improve on estimation
accuracy. One of the methods is Bayesian Belief Network which
estimate software effort by forecasting software cost when
information about the past and present is incomplete, vague and
uncertain [18]. It includes a network of probabilities that captures
the probabilistic relationship between variables in historical data
[11]. The advantage of this method is not being dependent on
knowing exact historical data. On the other hand, it requires
knowledge of related parameters of previous project to be used in
estimation.
The other method is Neural Networks which is based on the
principle of learning from examples. Neural network use back
propagation trained feed forward network to estimate software
development effort [17] [11]. The network is trained with a series
of inputs from previous projects to predict the effort of the current
project. Neural network provided a more accurate estimate
compared to other methods but it depends on data from previous
projects.
4. AGILE COST ESTIMATION METHODS
The emergence of agile methods has presented many opportunities
and challenges. One of the challenges is estimating the effort of
developing agile software. Although traditional methods are used
to estimate effort for agile software, they provide inaccurate results.
Agile is a popular development method as it emphasize on
collaboration with customer, communication among developers,
rapid delivery of software and change of requirements on demand
[20] [21]. Popular agile methods are Extreme programming, scrum,
crystal, Feature driven development and learn development.
Some of the challenges of estimating agile methods include work
assigned to a team and not an individual, emphasis is on collective
effort and work is quantified in terms of effort rather than time and
changing requirements on demand. Various studies were done in
recent years and have come up with cost estimation methods suited
for agile with the most popular one being planning poker [6].
Planning poker is a non-algorithmic method and is simple to
implement. Other agile estimation methods introduced so far are
constructive agile estimation algorithm [8] and AgileMOW [7]
although their accuracy has not yet been calibrated by other
researchers.
4.1 Planning Poker
Planning poker is an estimation method that is based on
collaboration and consensus among team members like Wideband
Delphi technique. It was initially proposed by Greening in 2003
and popularized by Cohn in 2005 [6] for agile software
development such as scrum. Planning poker session is done at the
beginning of an iteration of agile development involving a team of
developers from different disciplines.
Each member in the team is given a deck of planning poker cards
with values preferably Fibonacci sequence (1, 2, 3, 5, 8, 20, 40,
100) representing story points or ideal days. The nonlinear
sequences reflect less uncertainty with smaller units and greater
uncertainty when dealing with greater units [6]. A story in agile
development is a brief description of functionality as viewed by the
user or product owner. Story points are a relative unit of measure
used to estimate the story size by taking into account effort,
complexity and risk [19]. On the other hand, ideal days estimate a
story with regard to the number of days or time it will take to
translate a story to a system function or feature.
When a story has been fully discussed, each member privately
estimates a story by selecting a card to represent the estimate. All
cards are revealed at the same time and if the estimates are the
similar then it becomes the agreed estimate. If not, high and low
estimates are justified and discussed further. Then each member
selects a card after the discussion and cards are revealed again. The
process is repeated until consensus is achieved [19]. Two main
reasons why planning poker is an effective way of estimating agile
software is that it involves a team of experts from different
disciplines who collaborate and justify their estimations to come
with better results as compared to one expert providing estimate
especially when there is high uncertainty and missing information.
4.2 Constructive Agile Estimation Algorithm
Constructive agile estimation algorithm was introduced in 2009 [8].
The algorithm uses vital factors namely project domain,
performance, configuration, data transaction, complex processing,
ease of operation and security which are weighed then incorporated
in the estimation.
Constructive Agile Estimation algorithm divides estimation
process into two phases called early estimation and Iterative
estimation. The purpose of early estimation is to identify the initial
scope just enough to draw the initial budget. Iterative estimation is
done at the start of an iteration to include new requirements. In both
cases story point is used to estimate the size of a feature as
described by the user. Vital factors are identified on the grade of
low, medium and high using Fibonacci series then multiplied to
story point to get the final estimate.
Constructive Agile estimation algorithm identified factors that are
critical in determining software effort but in addition people factors
are also important especially in agile where collaboration and
teamwork is an important ingredient for successful completion of a
software project but they are not included in this algorithm.
International Journal of Computer Applications Technology and Research
Volume 5Issue 9, 612-618, 2016, ISSN:-23198656
www.ijcat.com 616
4.3 AgileMOW
AgileMOW was introduced to estimate the cost of developing web
applications using agile methods [7]. This method uses both expert
judgment and algorithm to estimate effort. AgileMOW uses people
and environment attributes described in COCOMO II which are
aligned to agile manifesto. Factors used in this method include
communication skills, proximity of team, feedback, courage,
management skills, technical ability, reliability, ease of use and
early delivery. The method use web objects to estimate size of a
web application and people factors are weighed. Effort expressed
in person-month is computed by multiplying web application size
and weighted people and environment factors.
On main advantage of AgileMOW is that it identifies factors that
align to the principles of agile software which focuses on
communication and interaction. However, it cannot estimate the
cost of other software rather than web application. Lastly, the
method only focused on people factors whereas other factors such
as product and process factors are also important when estimating
agile software effort.
5. DISCUSSION
None of software cost estimation method is better or worse than the
other, each has its own strength and weakness which are
complementary to each other. Furthermore, software estimation
methods are specific to a specific type of project or development
method or software to be developed [5] [15]. Estimation methods
such as Function point analysis, Object point and COCOMO are
suitable when developing software in which requirements are fully
known upfront such waterfall method. In contrast, these methods
are challenged when requirements keep on changing such as in
agile which require an estimation method that adapt to changes in
such as planning poker estimation method.
Different situations and development environment determine the
appropriate software cost method to be used. There are situations
where accuracy in estimation is critical then a more accurate
method should be employed, in other instance, winning a contract
is important therefore, price-to-win becomes the most appropriate
method [11]. Furthermore, small projects can easily be estimated
using expert judgment but when the project becomes larger it
requires more technical estimation method such as analogy and
COCOMO. In addition, availability of data from previous project
provides an opportunity to use analogy estimation method.
Several cost drivers should be considered to estimate software
effort and cost. The most common cost driver among all estimation
methods is the software size. Effort and cost can be estimated
directly upon estimating the software size using one of the software
size metrics such as source lines of codes, function point and object
point. Agile size estimation is done using story point. Size is also
used together with other factors to estimate software development
effort when using most of algorithmic estimation methods.
Therefore, software project managers must understand the key
attributes in a project to identify an estimation method that will
estimate accurately.
Each effort and cost estimation method has strengths and
weaknesses based on the capabilities of the method. Table 4 shows
a summary comparison of popular cost estimation methods.
Table 4: Comparison of software effort estimation method
Method
Strength
Weakness
COCOMO
- Clear results
- Independent on
programming
language
- Much data required
- Requirements must
be clear.
- Not adopted to
changes in
requirements
Function
point
- Clear results
- Independent on
programming
language
- Requirements must
be clear.
- Not adopted to
changes in
requirements
Expert
- Less data required
- Adopt to special
projects
- Its success depend on
the expert
Analogy
- Based on similar
project experience
- More accurate
- Information about
past projects is
required
- Historical data may
not be accurate
Price-to-
win
- Gets contract
- High overruns
Top-down
- Faster to implement
System level focus
- Minimal project
details required
- Less stable
- Less detailed
Bottom-up
- Based on detailed
analysis
- Support project
tracking
- Difficult to estimate
early in the life cycle
- Time consuming
Wideband
Delphi
- Reduced biasness
by involving a team
of experts
-Its success depend on
the expert
-Not adopted to
changes in
requirements
Planning
Poker
- Adopt to changes in
requirements
- Reduced biasness
by involving a team
of experts
- Its success depend on
team of experts
- Estimation is relative
to a team.
6. CONCLUSION
This paper provided a comprehensive overview of existing
software cost estimation models describing their strengths and
limitations. It is important for the software project manager to
understand key factors relevant in estimating the cost of software
and situations where an estimation method will be appropriate. No
existing model can estimate the cost of software development with
a high degree of accuracy, therefore the study of software cost
estimation is necessary to improve on estimation accuracy.
With the emergence of new software development methods and
techniques, future work will be to identify key estimation indicators
in new software development methods and devise new cost
estimation method.
International Journal of Computer Applications Technology and Research
Volume 5Issue 9, 612-618, 2016, ISSN:-23198656
www.ijcat.com 617
7. REFERENCES
[1] The Standish group, 2013, Chaos Manifesto: Think big,
Act small, The Standish Group Intenational.
[2] Coelho, E.,Basu, A.,2012, Effort Estimation in Agile
Software Development using Story Points, International
Journal of Applied Information Systems.
[3] Albrecht, A.J., Gaffney, G.E., 1983, Software Function,
Source lines of Codes, and Development Effort
Prediction: A Software Science Validation, IEEE Trans
Software Engineering.
[4] Boehm, 1981, Software Engineering Economics,
Prentice Hall.
[5] Boehm, B.W. et al, 2000, Software Cost Estimation with
COCOMO, Prentice-Hall.
[6] Cohn, M.,2006, Agile Estimating and Planning, Pearson
Education
[7] Litoriya, R., Kothari, A.,2013, An Efficient Approach for
Agile Web Based Project Estimation: AgileMOW,
International Journal of Computer Science and Computer
applications.
[8] Bhalerao, S., Ingle,M.,2009, Incorporating Vital factors
in agile estimation through algorithmic method,
International Journal of Computer Science and Computer
applications.
[9] Ziauddin, Tipu, S.K., Zia, S., 2012, An Effort Estimation
Model For Agile Software Development, Advanced
Computer Science and Its Applications.
[10] Khatibi, V., Jawawi, D.N., 2010, Software Estimation
Methods: A review, Journal of Emerging Trends in
Computing and Information Sciences.
[11] Borade, G, J.,Khalker, R,V.,2013, Software project effort
and cost estimation techniques, International Journal of
Advanced Research in Computer Science and Software
Engineering.
[12] Gandomani, T.,Wei, T., Binhamid, K., 2014, Software
Cost Estimation Using Expert Estimates, Wideband
Delphi and Planning Poker Technique, International
Journal of Software Engineering and its applications.
[13] Kumari, S., Pushkar, S., 2013, Performance Analysis of
software cost Estimation methods: A Review,
International Journal of Advanced Research in Computer
Science and Software Engineering.
[14] Sharma, N., Bajpai, A., Litoriya, R., 2012, Software
Effort Estimation, International Journal of Computer
Science and Applications.
[15] Stellman, A., Greene, J.,2005, Applied Software Project
management, O’Relly Media.
[16] Basha, S.,Dhavachelvan, P.,2010, Analysis of Empirical
Software Effort Estimation Model, International Journal
of Computer Science and Information Security.
[17] Bogdan, S., 2003, Software Development Cost
Estimation Methods and Research trands”, Computer
Science.
[18] Angyan Y., Charlottesville, 2003, A Bayasian Belief
Network approach to certifying Reliability of COTS
software systems”, Annual Reliability and
maintainability Symposium, IEEE.
[19] Calefato, F., Lanubile, F., A Planning Poker Tool for
Supporting Estimation in Distributed Agile
Development, The Sixth International Conference on
Software Engineering Advances
International Journal of Computer Applications Technology and Research
Volume 5Issue 9, 612-618, 2016, ISSN:-23198656
www.ijcat.com 618
[20] Cao, L., 2008, Estimating Agile Software Project Effort:
An empirical study, Association of Information Systems
AIS Electronic Library(AISeL), Americas Conference
on Information Systems.
[21] Schmietetendorf, A., Kunz, M., Dumke, R, 2008, Effort
Estimation for Agile Software Development Projects,
Proceedings 5th Software Measurement European
Forum, Milan
... Another widely used method, PERT [3,4], is relatively easy but does not take into account the agile nature of modern software development projects. Agile-oriented methods like planning poker, Tshirt sizing, affinity grouping, and their variations are rather applicable by agile teams at the implementation stage [5][6][7][8]. A common downside of the existing methods (except COCOMO II) is that they do not cover the whole software development life cycle starting from project ideation and ending with production, including maintenance and support. ...
... The most commonly used category is based on the idea of function points [16]. Such units as object points [2], use-case points [17], story points [5][6][7][8], etc., are derived from the concept of function points. Another wellknown development effort measurement unit comprises logical lines of code (the so-called SLOC metric) used by COCOMO [18] and COCOMO II [2]. ...
... However, some of their elements can also be applied in the early project life cycle phases before the development start, even before forming an agile team. One such method is affinity grouping [5][6][7][8]: tasks are grouped into clusters by their similarity (e.g., estimated efforts or complexity), and then the clustered tasks are assigned with estimates. Another well-known method is T-shirt sizing [5][6][7][8], where tasks are attributed to one of the predefined categories that usually correspond to the sizes of T-shirts: XS, S, M, L, XL, etc. ...
Article
Full-text available
In the early software development stages, the aim of estimation is to obtain a rough understanding of the timeline and resources required to implement a potential project. The current study is devoted to a method of preliminary estimation applicable at the beginning of the software development life cycle when the level of uncertainty is high. The authors’ concepts of the estimation life cycle, the estimable items breakdown structure, and a system of working-time balance equations in conjunction with an agile-fashioned sizing approach are used. To minimize the experts’ working time spent on preliminary estimation, the authors applied a decision support procedure based on integer programming and the analytic hierarchy process. The method’s outcomes are not definitive enough to make commitments; instead, they are supposed to be used for communication with project stakeholders or as inputs for the subsequent estimation stages. For practical usage of the preliminary estimation method, a semistructured business process is proposed.
... Although, there are several benefits of using group-based effort estimation techniques reported. However, there are numerous shortcomings of their use also reported such as lack of experts and biasness in expert opinion [8], [9]. Moreover, analogy-based methods are the other most common effort estimation tool used by industry experts [7]. ...
... Moreover, analogy-based methods are the other most common effort estimation tool used by industry experts [7]. However, it also has some limitations which include a lack of historical data, especially in small organizations [8]. Even though the research community is very active and has proposed many estimation methods, the results are not substantial as observed in the analysis of the Standish group [6]. ...
... But these methods do not give significant results due to their above-discussed limitations. The shortcomings of group-based effort estimation include lack of experts and biasness in expert opinion [8], [9], Furthermore, in analogy-based estimation, the accuracy of estimates significantly depends on the availability of historical data [8]. This study proposed a blockchain-based solution that will overcome the above-mentioned limitations and improve the estimation results. ...
Article
Full-text available
Context: The success or failure of any software development project significantly depends on the accuracy of its effort estimates. Software development effort estimation is the foundation for project bidding, budgeting, planning, and cost control. Problem: The literature shows that a lot of work has been done on software effort estimation. But still, there is a need for improvement in effort estimation by introducing new methodologies. The structured group-based and analogy-based effort estimations are the widely used estimation methods. Nevertheless, there are several shortcomings of using these methods such as lack of experts, lack of historical data, and biasness in expert opinion, which negatively affect the estimation results. Motivation: With the advancement of technologies, such limitations could be overcome. Such as leveraging the applicability of blockchain in several domains such as improvement in software development process and network security. Method: In this article, we have proposed a Blockchain-Based Software Effort Estimation (BBSEE) methodology to improve the software effort estimation. We employ the proposed method using Web and blockchain technologies. Moreover, we also proposed an evaluation criteria to assess the efficacy of the proposed method in terms of Mean Magnitude of Relative Error (MMRE), Mean Absolute Error (MAE), and percentage of successful predictions falling (PRED (25)). Result: We performed several case studies and analyses expert opinion of 52 organizations to present the efficacy of the proposed method. Conclusion: We observe that BBSEE method outperforms than expert judgment and analogy-based effort estimation methodologies in terms of software effort estimation.
... The Agile estimation identified factors that are critical in determining software effort. In addition, people factors are also important because the estimation process involves a team of developers from different disciplines (Munialo & Muketha, 2016). Therefore, this study is conducted to find the significant factors that influence effort estimation in Agile. ...
... In the Agile effort estimation, the project factors are essential to determine. In addition, people factors are also important because the estimation process involves a team of developers from different disciplines (Munialo & Muketha, 2016;Popli & Chauhan, 2014). People-related factors represented each team's expertise, experience, domain knowledge, and technical ability (Popli & Chauhan, 2014). ...
... This study found that the project-related factors, represented by requirement and design implementation, and people-related factors, which consist of experience, knowledge, and technical ability, proved influential simultaneously to effort by 31.1%. This outcome supports and aligns with Popli and Chauhan's (2014) research result and Munialo and Muketha's (2016). Although all factors simultaneously influence effort, not all factors have a positive relationship and significant influence. ...
Article
The Agile effort estimation involves project-related and people-related factors. This research objective is to find the factors that influence Agile effort estimation significantly through path analysis using a structural equation model. This research built an agile effort estimation path coefficient model from six constructs from theories and previous studies. Project-related factors represent by requirement and design implementation constructs. People-related factors are measured by the construct of experience, knowledge, and technical ability. The last construct is the effort itself. SmartPLS is employed for the confirmatory composite analysis and the structural model assessment. The confirmatory composite analysis indicated that all constructs are reliable and valid. Furthermore, the structural model assessment found that all factors of project-related constructs have a positive relationship and significant influence, showing a coefficient path value of 59.1% between requirement and design implementation constructs. All constructs represent people-related factors indicated by the coefficient path value of 67% between experience and knowledge, 42.6% between experience and technical ability, and 54.4% between knowledge and technical ability. In addition, all constructs proved influential simultaneously to effort by 31.1%. Positively contribute provided by requirement, experience, and technology’s ability. Significantly influenced provided by constructs of the developer’s knowledge and technical ability. The largest effect is given by technical ability, knowledge, and experience on medium and small scales. Contrarily, both constructs from project-related effects can be negligible because there was no influence. Based on the result, this study concludes that the significant factors in Agile effort estimation are technical ability, knowledge, and experience.
... As he stated, "Estimating the time required for software development tasks accurately is notoriously difficult", which is the result of several interconnected aspects: the high level of complexity and uncertainty in software projects, the overly optimistic nature of software developers and their managers and frequent unexpected technical issues, combined with changing requirements and integration challenges. However, effort estimation in software projects is a well-developed area, full of proven techniques and tools that can be used for accurate estimates [4][5][6][7][8][9][10]. The authors include and explain expert judgement, analogy-based methods, use case points, linear regression, robust regression, neural nets, constructive agile estimation algorithms, COSMIC FP, silent grouping, Delphi methods, COCOMO methods, planning poker and others. ...
... The authors include and explain expert judgement, analogy-based methods, use case points, linear regression, robust regression, neural nets, constructive agile estimation algorithms, COSMIC FP, silent grouping, Delphi methods, COCOMO methods, planning poker and others. The mentioned methods [4][5][6][7][8][9][10] are either time-consuming or fine-tuned for a particular project and/or development team. A novel approach to effort estimation that is based on generative AI is also emerging. ...
Article
Full-text available
Effort estimation is critical in software engineering to assess the resources needed for development tasks and to enable realistic commitments in agile iterations. This study investigates whether generative AI tools, which are transforming various aspects of software development, can improve effort estimation efficiency. A controlled experiment was conducted in which development teams upgraded an existing information system, with the experimental group using the generative-AI-based tool GitLab Duo for estimation and the control group using conventional methods (e.g., planning poker or analogy-based planning). Results show that while generative-AI-based estimation tools achieved only 16% accuracy—currently insufficient for industry standards—they offered valuable support for task breakdown and iteration planning. Participants noted that a combination of conventional methods and AI-based tools could offer enhanced accuracy and efficiency in future planning.
... On the other hand, usage of these methods is not possible before starting project implementation (e.g., in the analysis and design phase) when a team is not built yet. Such drawbacks of the Planning Poker-like methods are addressed in the Constructive Agile Estimation Algorithm (CAEA) [19,20] which combines story point-based sizing with the algorithmic part dividing the estimation process into two phases-early estimation and iterative estimation (an example of using CAEA is represented in the estimation framework from [21]). As shown in [22,23], the current research efforts aiming at estimation in Agile software development are mainly directed to such categories of techniques as machine learning-based, expert judgment, and algorithmic. ...
... where U is a set of all possible values of NDWT, U. In essence, NDC expresses the maximum possible amount of scope that can be implemented by a particular developer or the whole team within a certain time range (e.g., project sprint). Drawing the parallels with the Agile estimation techniques [8,[17][18][19], NDC is nothing else as a forecast of the velocity of a Scrum team expressed in time-based units. For a development team with differentiated specializations, NDC is defined as a vector each item of which corresponds to a particular specialization: ...
Article
Full-text available
Estimation is an essential step of software development project planning that has a significant impact on project success—underestimation often leads to problems with the delivery or even causes project failure. An important aspect that the classical estimation methods are usually missing is the Agile nature of development processes in the implementation phase. The estimation method proposed in this article aims at software development projects implemented by Scrum teams with differentiated specializations. The method is based on the authors’ system of working-time balance equations and the approach to measuring project scope with time-based units—normalized development estimates. In order to reduce efforts spent on the estimation itself, an analysis of dependencies among project tasks is not mandatory. The outputs of the methods are not recommended to be treated as commitments; instead, they are supposed to be used to inform project stakeholders about the forecasted duration of a potential project. The method is simple enough to allow even an inexpensive spreadsheet-based implementation.
... O fator de custo mais comum entre todos os métodos de estimativaé o tamanho de software [Munialo and Muketha 2016]. Portanto, esforço e custo podem ser estimados diretamente do tamanho do software usando alguma das MTS [Javdani et al. 2013]. ...
Article
A administrac~ao publica tem utilizado cada vez mais metodosageis, adequando-se a realidade do mercado. Muito embora continue obrigadaa mensurar suas entregas atraves de alguma metrica de tamanhode software, a escolha adequada dessa metrica pode denir o nvel desucesso dos projetos publicos. Neste artigo, identica-se as congurac~oesde metricas de tamanho de software em conjunto com metodos ageisno setor publico. Como instrumento metodologico para a identicac~aode evid^encias foi utilizada a revis~ao sistematica da literatura. A metricaPonto de Func~ao IFPUG e o metodo Manifesto Agil e Scrum foramidenticados como os mais utilizados no setor publico. A denic~ao decongurac~oes de uso de metricas e metodos ageis no setor publico tornapossvel direcionar a tomada de decis~oes para a conclus~ao com sucessodos projetos, no menor tempo possvel, com o menor custo aceitavel eentregando valor agregado perceptvel a sociedade.
... One of the essential aspects of developing software projects is software effort estimation (SEE) [1][2][3][4][5]. In the early stages of project development, resources or budgets must be measured. ...
Article
Full-text available
The prediction level at x (PRED(x)) and mean magnitude of relative error (MMRE) are measured based on the magnitude of relative error between real and predicted values. They are the standard metrics that evaluate accurate effort estimates. However, these values might not reveal the magnitude of over-/under-estimation. This study aims to define additional information associated with the PRED(x) and MMRE to help practitioners better interpret those values. We propose the formulas associated with the PRED(x) and MMRE to express the level of scatters of predictive values versus actual values on the left (sigLeft), on the right (sigRight), and on the mean of the scatters (sig). We depict the benefit of the formulas with three use case points datasets. The proposed formulas might contribute to enriching the value of the PRED(x) and MMRE in validating the effort estimation.
... predictive approaches are called non-algorithmic techniques [3], [4], [5]. In contrast, algorithmic-based techniques can be utilized to measure the effort of software projects in terms of software functional size. ...
Article
Full-text available
This study compares the performance of Pytorch-based Deep Learning, Multiple Perceptron Neural Networks with Multiple Linear Regression in terms of software effort estimations based on function point analysis. This study investigates Adjusted Function Points, Function Point Categories, Industry Sector, and Relative Size. The ISBSG dataset (version 2020/R1) is used as the historical dataset. The effort estimation performance is compared among multiple models by evaluating a prediction level of 0.30 and standardized accuracy. According to the findings, the Multiple Perceptron Neural Network based on Adjusted Function Points combined with Industry Sector predictors yielded 53% and 61% in terms of standardized accuracy and a prediction level of 0.30, respectively. The findings of Pytorch-based Deep Learning are similar to Multiple Perceptron Neural Networks, with even better results than that, with standardized accuracy and a prediction level of 0.30, 72% and 72%, respectively. The results reveal that both the Pytorch-based Deep Learning and Multiple Perceptron model outperformed Multiple Linear Regression and baseline models using the experimental dataset. Furthermore, in the studied dataset, Adjusted Function Points may not contribute to higher accuracy than Function Point Categories.
Article
Full-text available
Agile software development has been gaining popularity and replacing the traditional methods of developing software. However, estimating the size and effort in Agile Software development still remains a challenge. This paper gives an overview of the different size estimation methods traditionally used and discusses in details the method based on Story Points, which is at present the most widely used estimation technique in Agile Software Development. The paper describes the steps followed in Story Point based method and highlights the area which needs to be looked into further.
Article
Full-text available
There exist numerous sophisticated models and methods for estimating the size, cost and schedule of software projects. However, the ability to accurately predict the software cost of web based software for agile software projects is still dubious. The most appropriate web based software cost estimation in an agile software development environment is a big problem due to varying levels of customer requirement and different individual personnel capabilities. Also, the need to develop a separate model to estimate web based project is rising. In this research paper, we present AgileMOW, an approach to model a software cost estimation process which will evaluate effort and cost of software development for web based projects developed using Agile methodology with a number of constraints imposed by stakeholders and environmental characteristics, thereby satisfying multitudinous criteria by making use of COCOMO II model, a famous traditional algorithmic technique. Most importantly, the paper identifies the difference between conventional and web projects. The proposed estimation model enhances the level of visibility in the planning stages.
Article
Full-text available
This Article shows a Case Study research that is performed to compare effectiveness of the Planning Poker and Wideband Delphi in two case studies. Although, Wide Band Delphi has been proposed many years ago and has enough supports in both industry and academic area but, Planning Poker is somewhat new. The study showed that applying these techniques in two companies which were using expert’s view for software cost estimation, increased the accuracy of cost estimation. Also, the results showed that Planning Poker led to better accuracy comparing to Wideband Delphi. However, this accuracy is not too much than Wideband Delphi, it was important that Planning Poker led to reducing financial risks of the projects comparing to Wideband Delphi. The study also showed that both Wideband Delphi and Planning Poker reduced the underestimates significantly.
Article
Full-text available
Software effort estimation process in any software project is not only essential, but also a very critical component. The success or failure of projects depends heavily on the accuracy of effort and schedule estimations, among other things. The emergence of agile methods in the software development field has presented many opportunities and challenges for researchers and practitioners alike. One of the major challenges is effort estimation for agile software development. Though traditional effort estimation approaches are used to estimate effort for agile software projects but they mostly result in inaccurate estimates. This research focuses on development of effort estimation model for agile software projects. Construction and use of the model is explained in detail. The model was calibrated using the empirical data collected from 21 software projects. The experimental results show that model has good estimation accuracy in terms of MMRE and PRED (n).
Conference Paper
Full-text available
Estimating and planning are critical to the success of any software project, also in the case of distributed agile development. Previous research has acknowledged that conventional agile methods need to be adjusted when applied in distributed contexts. However, we argue that also new tools are needed for enabling effective distributed agile practices. Here, we present eConference3P, a tool for supporting distributed agile teams who applies the planning poker technique to perform collaborative user story estimation. The planning poker technique builds on the combination of multiple expert opinions, represented using the visual metaphor of poker cards, which results in quick but reliable estimates.
Conference Paper
This paper describes an empirical study of effort estimation in agile software development. Estimated effort and actual effort of a 46-iteration project are collected and analyzed. The results show that estimation in agile development is more accurate than that in traditional development even though agile developers still underestimate the effort. However, estimation accuracy is not improved over time as expected by agile communities.