ArticlePDF Available

Towards Diminishing Judicial Intervention in Statutory Adjudication: A Pragmatic Proposal

Authors:

Abstract

Statutory adjudication was introduced into the Security of Payment (SOP) legislation as a fast-track payment dispute resolution process aiming to achieve the object of the legislation to facilitate cash flow within the construction contractual chain. However, there have been numerous judicial review applications with respect to adjudicators’ determinations, particularly in Australia, which have eroded the original object of the SOP legislation. The mission has been compromised particularly in ensuring that subcontractors are paid quickly for the work they do on an interim basis. This article reviews the evolving tension between the object of the legislation and judicial intervention and addresses the shortcoming of the main available approaches to diminish judicial intervention. The article then introduces a pragmatic proposal to address the problem going forward. The proposal calls for separating jurisdictional challenges from the merits in adjudication and establishing a legislative review tribunal to deal with jurisdictional challenges. This proposal may be applicable to many other jurisdictions having the SOP legislation.
Construction Act Review
Towards Diminishing Judicial
Intervention in Statutory
Adjudication: A Pragmatic
Proposal
Samer Skaik*
Jeremy Coggins**
Anthony Mills***
Australia; Challenges to jurisdiction; Construction industry; Statutory
adjudication
1. Introduction
Statutory adjudication was introduced into the Security of Payment (SOP)
legislation as a fast-track payment dispute resolution process aiming to achieve
the object of the legislation to facilitate cash flow within the construction contractual
chain. As such, adjudication determinations were usually released and enforced
on a “pay now, argue later”1basis in order to protect a vulnerable class of smaller
businesses within the building and construction industry. The SOP legislation was
extremely successful in attaining the stated object in the context of small adjudicated
payment claims where both parties used to comply with the adjudication
determination.
However, where larger payment claims are adjudicated, consequences of
adjudication outcome become more significant to stay in business. Accordingly,
parties were more inclined to challenge adjudication by way of judicial review as
demonstrated in Table 1 below. Some paying parties aggrieved by adjudication
determinations strive to challenge determinations in court in order to delay paying
or avoid payment of the adjudicated amounts. Therefore, they engage lawyers to
identify any fine legal flaws or loopholes to challenge determinations so that they
may eventually succeed in having the adjudication determinations quashed.2Other
paying parties seek to frustrate the adjudication process even before a determination
*Lecturer and PhD Researcher, School of Architecture and Built Environment, Deakin University, Locked Bag
20001, VIC 3220, Geelong, Australia; Founder and Director, Construction Management Guide, Email:
samer.skaik@deakin.edu.au or skaiknet@cmguide.org.
** School of Natural and Built Environments, University of South Australia, Adelaide, Australia.
*** School of Architecture and Built Environment, Deakin University, Australia.
1Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140 at [96], per Palmer J, adopting the language of
Ward LJ in RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd [2002] EWCA Civ 270; [2002]
1 W.L.R. 2344; [2002] C.L.C. 905.
2Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd [2009] VSC 156 at [46], per Vickery J.
659(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
is made. Challenging adjudication determinations is typically pursued on
jurisdictional grounds related to lack of adjudicator’s jurisdiction to hear the matter
and/or adjudicators exceeding their jurisdiction during the adjudication
decision-making process.
It is a frequent problem that a claimant, which obtains a favourable adjudicator’s
determination is denied the benefits and certainty of that determination if the paying
party opts to challenge the determination by invoking judicial review proceedings.
Judicially, Basten JA explained the uncertainty issue by noting that
“between the date of a purported determination and an order of the court
setting it aside, no-one could be sure whether the adjudicator had failed to
validly determine the application and it was only the order of the court which
would resolve that question”.3
Furthermore, Macfarlan JA has observed that
“a long period of time might elapse between a purported determination and
a court declaring it void. In the present case that period was seven months,
but in others the period might be much longer”.4
As a result, the claimant will be at a considerable risk of not only becoming
insolvent but also exercising its statutory right to suspend work in case of
non-payment.5In addition, the claimant will be more hesitant and reluctant to apply
for further adjudications on other payment claims until certainty manifests upon
the outcome of the judicial review of the first payment claim. The claimant may
also compromise its right and be compelled to settle the issue with the paying party
so as to avoid the huge expense and delay in going to court to defend the validity
of the adjudication determination. However, the worst consequence is to have lost
the right to use the statutory scheme because of the effluxion of time.6
This article sets out to firstly examine the evolving tension between the object
of the SOP legislation and judicial intervention and address the shortcoming of
the main available approaches to diminish judicial intervention. Then, the article
proposes two pragmatic measures to diminish judicial intervention in statutory
adjudication.
2. The evolving tension
Notwithstanding the fact that legislatures had attempted to insert privative clauses7
to exclude adjudication determinations from judicial review in order to safeguard
the SOP legislative object, those clauses became ineffective following the decision
of the High Court in Kirk8that
3Cardinal Project Services Pty Ltd v Hanave Pty Ltd [2011] NSWCA 399 at [50].
4Cardinal [2011] NSWCA 399 at [99].
5The risk of such suspension was well noted in Brodyn v Davenport [2005] NSWCA 394 at [51], per Hodgson
JA; Hickory [2009] VSC 156 [46]–[47], per Vickery J.
6This arises for example by the application of s.13(4) of the NSW Act and the decision of the court in Cardinal
[2011] NSWCA 399.
7See, e.g., ss.90 and 91 of the Justice and Other Legislation Amendment Act 2007 (Qld) which amended Sch.1 Pt
2 of the Judicial Review Act (Qld) to exclude the operation of that Act to decisions made under Pt 3 division 2 of the
Building and Construction Industry Payments Act 2004 (Qld); Amasya Enterprises Pty Ltd v Asta Developments
(Aust) Pty Ltd (2015) 297 FLR 203 at [68], per Vickery J.
8Kirk v Industrial Relations Commission of New South Wales (2010) 239 CLR 531 at [100].
660 Construction Law Journal
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
“[l]egislation which would take from a State Supreme Court power to grant
relief on account of jurisdictional error is beyond State legislative power”.
As a consequence, the mission of the SOP legislation has drifted away from its
original intent. Paying parties are left with no constraints (save for the high legal
cost and the potential cost of interest accumulating upon the adjudicator’s
determination if upheld by judicial review) by seeking judicial review in order to
frustrate the adjudication process. It is submitted that these cost factors are often
ignored by paying parties when balanced against the benefits of retaining the large
amounts in dispute as long as possible by seeking juridical review as a delaying
tactic. In practice, some aggrieved paying parties seek judicial review by exhausting
all appeal measures9to the very end, with the hope, the claimant may become
insolvent by the time the case is eventually decided, so that the paying party may
not be obliged to pay. There have also been a small number of claiming parties
seeking review, principally to prevent the loss of future claims by the statute
binding subsequent adjudicators.10
Table 1 below demonstrates the proportion of determined adjudication
applications which were the subject of judicial review applications before the
Supreme Court in New South Wales between2012 and 2014.11 The average figures
provide more representative figures for two reasons. First, judicial review
applications are usually decided by the court long after the release of the
adjudication decision. Secondly, it is extremely difficult and time-consuming to
marry judicial review applications with those reported in the financial year for the
sake of comparison to derive representative proportions.
As shown in Table 1, disputedpayment claims below AUD 25,000 do not reach
the Supreme Court for judicial review; even claims between AUD 25,000 and
AUD 40,000 are rarely dealt with by the Supreme Court. As such, McDougall J
noted that
“considerations of proportionality and, equally, considerations of common
sense must suggest that the conduct of litigation involving numerous volumes
of documents over less than $37,000.00 is unlikely to be a cost-effective
process”.12
That observation is well demonstrated in Table 1 which shows that the proportions
of juridical review applications from the relevant adjudicated claims are much
higher as the amount in dispute increases. For example, the average percentage of
judicial review applications of disputed amounts between AUD 40,000 and AUD
99,999 is only three per cent and it steadily increases until it reaches 11 per cent
for disputed amounts between AUD 500,000 and AUD 999,999. A brief analysis
of these judgments discloses that the majority of the adjudications deal with
9To this end several applications have been made to the High Court for review of the appellate courts findings in
SOP actions. At the date of writing the High Court has not accepted any applications for special leave in this area.
See for example Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd [2006] HCATrans 9.
10 See John Goss Projects v Leighton Contractors [2006] NSWSC 798.
11 At the time of writing, the 2015 annual report of NSW has not been issued. Figures of lodged applications are
extracted from the formal annual reports as being published by the Office of Finance and Services. Figures of Judicial
review applications are derived from Supreme Court judgments extracted from the databases of Australasian Legal
Information Institute (Austlii). Among those, there were a few applications which did not mention the amount in
dispute, hence ignored.
12 Seabreeze Manly v Toposu [2014] NSWSC 1097 at [51].
Construction Act Review 661
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
complex contractual entitlement issues and facts such as delay claims, liquidated
damages and variations of high value.
The table shows the challenges as a proportion of the determinations. Since
many determinations are in favour of the respondent in that they do not require
the respondent to make any progress payment or require a very small progress
payment, the challenges as a proportion of determinations requiring the respondent
to pay a significant amount would be much higher.
Table 1 Proportion of judicial review from adjudicated applications in New
South Wales
Judicial review applica-
tions
Judicial review chal-
lenges (calendar Year)
Determination released
(financial year)
Claimed mount/
amount in dis-
pute (AUD)
Avg201420132012Avg201420132012Avg201420132012
0%0%0%0%00003112343573410–24,999
3%
4%3%2%222275536910225,000–39,999
3%
3%3%2%3333108989713040,000–99,999
4%
3%6%4%4254867083106100,000–249,999
6%
9%8%2%242139462646250,000–499,999
11%
11%15%8%222219181325500,000–999,999
5%
8%0%7%230231372729 1,000,000
4%5%4%3%15161414358322315438Total
It could be argued that those average percentages tentatively represent those
claimants who struggle to get their payments following adjudication. The higher
percentages of judicial review with respect to larger adjudication determinations
are destructive to the statutory object “to ensure cash flow to businesses in the
building industry, without parties get tied up in lengthy and expensive litigation
or arbitration”.13 As such, they present a significant problem for the efficacy of the
Security of Payment (SOP) legislation. In his Second Reading Speech for the New
South Wales (NSW) Building and Construction Industry Security of Payment Bill
1999, the Minister (the Right Honourable Morris Iemma) made it clear that the
“further adjudication appeal process between the adjudicator’s interim decision
and the final decision would be unnecessarily burdensome and costly for
parties to construction contracts. It can also be a source of abuse by a desperate
respondent seeking to delay payment”.14
This led the Honourable Justice Robert McDougall to comment that “‘parliament
specifically wished for the courts not to be too readily involved”.15 Furthermore,
the Western Australian SOP legislation has an express object that the adjudication
13 Grocon Constructors Pty Ltd v Planit Cocciardi Joint Venture 26 VR 172; [2009] VSC 426 at [33], per, Vickery
J; see also, Brodyn v Davenport (2004) 61 NSWLR 421; [2004] NSWCA 394 at [87], per Hodgson JA.
14 M. Iemma, NSW Parliamentary Debates, Legislative Assembly, 29 June 1999 at 1598.
15 R. McDougall, “An examination of the role and content of natural justice in adjudications under construction
industry payment legislation”, 2009, p.9, retrieved on 4 Dec 2015, from http://www.supremecourt.justice.nsw.gov.au
/Documents/mcdougall110909.pdf [Accessed 5 August 2016] .
662 Construction Law Journal
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
process aims to resolve disputes fairly and as quickly, informally and inexpensively
as possible.16 The Minister (the Right Honourable Alannah MacTiernan) stated in
her second reading speech:
“The rapid adjudication process is a trade-off between speed and efficiency
on the one hand, and contractual and legal precision on the other. Its primary
aim is to keep the money flowing in the contracting chain by enforcing timely
payment and sidelining protracted or complex disputes.”17
3. Approaches to diminish judicial intervention
Various judicial and legislative approaches exist to diminish the scope for judicial
review, or to reduce its negative impact upon the efficiency of the adjudication
process. The main approaches, which are discussed in further detail below, include
the following.
1) The courts’ treatment of jurisdictional facts in a broad sense, as
opposed to a narrow sense.
2) Remittal of jurisdictionally—defective determinations by the court
to the adjudicator for reconsideration.
3) Severance of the infected part of an adjudicator’s determination,
rather than quashing the entire decision.
4) Improving the quality of adjudication determinations.
5) Legislative review of adjudicators’ “decisions to dismiss”, without
making determinations on the merits for lack of jurisdiction.
3.1 Broad approach to jurisdictional facts
The courts in the East Coast model jurisdictions have adopted a narrow approach
when considering jurisdictional facts for the purpose of judicial review, which has
led to the quashing of many determinations.18 Accordingly, the Victorian Supreme
Court has recognised that
“critically, an adjudicator is given no express power in s 23 of the Victorian
Act, or anywhere else in the Act, to decide facts which may go to his or her
jurisdiction”.19
Notwithstanding this, however, the Victorian Supreme Court has also highlighted
the drawbacks if a broad approach is not required by the legislation to be adopted
by the courts when considering essential jurisdictional facts, other than those
established in Brodyn, stating
“[i]f the Act does make the jurisdiction of an adjudicator contingent upon the
actual existence of a state of facts, as distinguished from the adjudicator’s
determination that the facts do exist to confer jurisdiction, in my opinion the
legislation would not work as it was intended to. Unnecessary challenges to
16 Construction contract Act 2004 (WA) s.30.
17 A.J. MacTiernan, WA Parliamentary Debates, Legislative Assembly, 3 March 2004 at 275.
18 See, e.g., Sugar Australia Pty Ltd v Southern Ocean Pty Ltd [2013] VSC 535 at [66]; Chase Oyster Bar v Hamo
Industries [2010] NSWCA 190.
19 See Sugar [2013] VSC 535 at [107].
Construction Act Review 663
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
the jurisdiction of an adjudicator appointed under the Act would expose the
procedures to delay, cost and expense. The very purpose of the Act would be
compromised”.20
His Honour went on to propose:
“For these reasons, in my opinion, in order to serve the purposes of the Act,
the intention of the legislation is to confer upon an adjudicator the capacity
to determine facts which go to his or her jurisdiction, subject to exceptions
of the type to which I have referred. It follows that, in making those
determinations, the Act confers on adjudicators jurisdiction to make an
incorrect decision in relation to such jurisdictional facts which will not be
overturned by certiorari.”21
In Western Australia, the Supreme Court has been consistent in adopting a broad
approach when dealing with jurisdictional facts under s.31(2)(a), considering the
adjudicator’s role to be analogous to an inferior court.22 However, in the recent
judgment of Laing O’Rourke,23 Mitchell J expressed his reservations about the
broad sense approach which an adjudicator is empowered to authoritatively to
determine.
In its recent report, The Society of Construction Law Australia (SoCLA)
recommended that:
“It would be desirable for any new legislation to discourage applications for
judicial review by making it plain that the jurisdictional facts relevant to an
application for adjudication are jurisdictional facts in the broad sense For
example, the legislation might explicitly provide that an adjudicator must
proceed to determine an application for adjudication if the adjudicator is
satisfied on reasonable grounds that the application was made within any
relevant time limits, rather than providing that the adjudicator must proceed
to determine an application for adjudication if the application was (in fact)
made within time. Decisions of adjudicators under the former type of provision
would still be subject to a level of judicial supervision but would limit the
availability of judicial review and discourage applications for judicial
review”.24
Whilst the SoCLA’s recommendation looks promising on its face, it is argued that
unless adjudicators are well—experienced and legally—trained in identifying
jurisdictional matters, the risk of judicial review arising due to jurisdictional errors
will still remain high.
3.2 Remitting jurisdictionally defective determinations
Australian case law has been inconsistent regarding the remittal of invalid
determinations to adjudicators. The legislation of the Australian Capital Territory
20 Grocon [2009] VSC 426 at [115].
21 Grocon [2009] VSC 426 at [116].
22 See, e.g., Wqube Port of Dampier v Philip Loots of Kahlia Nominees Ltd [2014] WASC 331 at [78]; Cape Range
Electrical Contractors Pty Ltd v Austral Construction Pty Ltd [2012] WASC 304 at [83].
23 Laing O’Rourke Australia Construction Pty Ltd v Samsung C & T Corporation [2015] WASC 237.
24 See Society of Construction Law Australia, Australian Legislative Reform Subcommittee, “Report on Security
of Payment and Adjudication in the Australian Construction Industry”, February 2014, p.68.
664 Construction Law Journal
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
(ACT) includes a unique section which gives the Supreme Court express authority
to remit adjudication decisions referred to it to the original adjudicator or a new
adjudicator appointed by the court, for reconsideration with its opinion on the
question of law the subject matter of appeal.25 If an adjudication decision is remitted,
the adjudicator must make the new adjudication decision within 10 business days
after the day the decision was remitted, or within a time period directed by the
Supreme Court.26 The ACT Supreme court exercised its remittal authority for the
first time in Fulton Hogan.27 In that case, Mossop AsJ found that the adjudicator
made a manifest error of law which could substantially affect the legal rights of
the parties and held:
“In my view it is appropriate to remit the adjudication decision to the
adjudicator who made the original decision. That is because there will be cost
and time efficiencies in having the original decision-maker reconsider the
claim. I do not accept that the fact that the adjudicator has been found to have
made an error of law is a reason for remitting the decision to a different
adjudicator.”
In Victoria, despite the fact the Victorian Act is silent regarding remittal, the
Victorian Supreme Court has nevertheless remitted several cases to the relevant
Authorised Nominating Authorities for further remittal to the original adjudicator.28
In Maxstra,29 Vickery J held that, where an order in the nature of certiorari is
granted, the usual form of relief is to quash the decision (or part thereof) under
review and remit it back to the tribunal for reconsideration according to law. In
Plenty Road,30 Vickery J examined whether the flawed determination should be
remitted to the original adjudicator, or a different one, eventuallydeciding to remit
the case to the original adjudicator to avoid delay in the process, since the original
adjudicator was fully familiar with the case. Vickery J further asserted that
“minimisation of delay in the decision-making process promotes a central aim of
the Act“.31
`In NSW, the Act is also silent as to whether the court has power to remit
erroneous determinations. However, an order under s.69 of the Supreme Court
Act 1970 (NSW) in the nature of mandamus could be made, so that the court may
order an adjudicator to reconsider an application and make a determination
according to law. This possibility was discussed, obiter by McDougall J in
Trysams.32 However, his Honour opined that
“there may arise cases where it would be inappropriate to make such an order,
and more appropriate to leave the dissatisfied claimant to its rights under
s26(2)”.33
25 Building and Construction Industry (Security of Payment) Act 2009 (ACT) s.436(b).
26 Building and Construction Industry (Security of Payment) Act 2009 (ACT) s.43(7).
27 Fulton Hogan Construction Pty Ltd v Brady Marine & Civil Pty Ltd [2015] ACTSC 384 at [67], per Mossop
AsJ.
28 See Maxstra Constructions Pty Ltd v Gilbert t/as AJ Gilbert Concrete [2013] VSC 243; Metacorp Pty Ltd v
Andeco Construction Group Pty Ltd (No.2) [2010] VSC 255.
29 Maxstra [2013] VSC 243 at [72].
30 Plenty Road v Construction Engineering (Aust) (No.2) [2015] VSC 680.
31 Plenty Road [2015] VSC 680 at [31].
32 Trysams Pty Limited v Club Constructions (NSW) Pty Ltd [2008] NSWSC 399 at [80]–[89].
33 Trysams [2008] NSWSC 399 [2008] NSWSC 399 at [90].
Construction Act Review 665
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
Eventually, the NSW Court of Appeal in Cardinal Project,34 resisted the possibility
of remittal. In that case, Macfarlan JA, with whom Tobias AJA agreed, pointed
out that, by the time the adjudicator decided the matter after remittal, circumstances
might have changed significantly from the time when the adjudicator was
considering his original determination (e.g. the payment schedule may be outdated,
other defects may have come to light and so on.). His Honour went on to say that
the exemption of adjudicators’ decisions under the Act from the scope of judicial
review is a further indication of a legislative desire that the Act’s mechanisms be
quick, cheap and simple. Also, any remittal order would necessarily require the
adjudicator to make a decision outside the time permitted by s.25(3), unless the
parties agreed to an extension of time. Macfarlan JA further opined that
“[i]f the legislature had adverted to the question of what should happen when
a purported but void determination is issued pursuant to an adjudication
application, it may have provided that that application should remain on foot
but be remitted to the original adjudicator”.35
In Queensland, the Court of Appeal, in Heavy Plant,36 followed a similar position
to that of Macfarlan JA, in which Muir JA, with whom Gotterson JA and Morrison
JA agreed, held that “the provision of such a remedy would be contrary to the
quick, cheap and simple processes envisaged by the Act”. In BM Alliance,37 Muir
JA, with whom Holmes JA and Lyons J agreed, stated that no arguments were
raised by the parties on whether remittal to the adjudicator was legally possible
and concluded that remittal is doubted to be a desirable option for that case. It was
also argued that any legislative amendment providing the court with an express
power to remit the matter to the adjudicator, or another adjudicator, is not a
preferable outcome.38
3.3 Severance of infected part of determination
Sometimes, a part of the adjudication decision may be infected by a jurisdictional
error, which would, generally speaking, invalidate the entire determination. This
rule has been criticised as it “produced inconvenient consequences”.39 However,
in Emergency Services,40 McDougall J, in an attempt to give indirect effect to an
invalid determination, required the respondent to pay the amount unaffected by
the error as a condition to set aside the adjudicator’s determination. In Cardinal,41
the NSW Court of Appeal held that:
“Such an approach has much to recommend it, particularly, it might be added,
if the claimant is otherwise unable to pursue its original payment claim to
achieve a second adjudication. However, such conditional relief can itself
only be valid if it is designed to achieve a legitimate purpose”.42
34 Cardinal [2011] NSWCA 399 at [100]–[103].
35 Cardinal [2011] NSWCA 399 at [97].
36 Heavy Plant Leasing Pty Ltd v McConnell Dowell Constructors (Aust) Pty Ltd [2013] QCA 386 at [67].
37 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd [2013] QCA 394 at [87].
38 A. Wallace, “Discussion Paper—‘Payment dispute resolution in the Queensland building and construction
industry-Final Report’”, 2013, p.224.
39 Sunshine Coast Regional Council v Earthpro Pty Ltd [2015] QSC 168 at [73], per Byrne SJA.
40 Emergency Services Superannuation Board v Sundercombe [2004] NSWSC 405.
41 Cardinal [2011] NSWCA 399 at [52].
42 Cardinal [2011] NSWCA 399 at [52].
666 Construction Law Journal
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
In Victoria, it was judicially decided that severance is technically possible as a
common law doctrine which helps attain the object of the legislation in some
cases.43 The logic of allowing severance was explained from a commercial
perspective as
“the parties may have already expended significant costs on the adjudication
and court processes. If the court is able to sever the affected part of the
adjudication decision then there will be significant cost advantages in doing
so”.44
As a result, Queensland amended its Act in 2014, introducing, inter alia, a new
section which provides that:
“If, in any proceedings before a court in relation to any matter arising from
a construction contract, the court finds that only a part of an adjudicator’s
decision under Part 3 is affected by jurisdictional error, the court may identify
the part affected by the error and allow the part of the decision not affected
by the error to remain binding on the parties to the proceeding”.45
In many other cases, the courts have emphasised that the legislation should be
amended so as to permit so much of an adjudicator’s decision as is not affected
by jurisdictional error to stand.46 Having said that, introducing such a provision
within legislation, without sufficient guidance on how a court is to allow part of
an adjudication decision, could bring many other difficult questions and valid
concerns regarding its practicality and application. For instance, it was argued: “Is
a breach of natural justice by an adjudicator a ‘jurisdictional error’ within the
meaning of s 100(4)?”47 However, it has been applied without issue.48
3.4 Improving the quality of adjudication determinations
In the wake of such inevitable drift in the legislative intent where more adjudication
determinations concerning large claims have been challenged successfully in court,
the Queensland legislation was substantially amended in December 2014.49 The
amendments include, inter alia, allowing longer timeframes for adjudicators, as
well as respondents, in complex cases and strict regulations to appoint, train and
maintain competent adjudicators. To cope with the introduced changes, the
legislation imposed mandatory transitional training upon all adjudicators, alongside
the “legally oriented” mandatory training course.50 That transitional training covers
43 Gantley Pty Ltd v Phoenix International Group Pty Ltd [2010] VSC 106 at [115]–[116]; Maxstra [2013] VSC
243 at [77].
44 Wallace, Discussion Paper—Payment dispute resolution in the Queensland building and construction
industry-Final Report, 2013, p.224.
45 Building and Construction Industry Payments Act 2004 (Queensland) s.100(4).
46 See, e.g., James Trowse Constructions Pty Ltd v ASAP Plasterers Pty Ltd [2011] QSC 345 at [57–[59]; Thiess
Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2012] QSC 373 at [61]–[62]; e.g., BM Alliance Coal Operations
Pty Ltd v BGC Contracting Pty Ltd (No.2) [2013] QSC 67 at [35]–[37]; Multiplex [2003] NSWSC 1140 at [90]–[92],
per Palmer J; Lanskey Constructions Pty Ltd v Noxequin Pty Ltd [2005] NSWSC 963 at [21]–[22].
47 P. Davenport, “An update on security of payment in the construction industry in Queensland”, paper presented
to RICS Cobra 2015, Sydney, p.8.
48 See Sunshine Coast [2015] QSC 168, and previous excision prior to the Queensland Building and Construction
Industry Payment Act being amended is evidenced in Hansen Yuncken Pty Ltd v Ian James Ericson trading as Flea’s
Concreting [2011] QSC 327.
49 See Building and Construction Industry Payments Amendment Act (2014), Act No.50 of 2014 (Qld).
50 See the Building and Construction Industry Payments Regulation 2004 Sch.1 Pt 2.
Construction Act Review 667
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
modules including the 2014 amendments, contract law, construction law, making
and writing decisions, judicial ethics and natural justice, deciding jurisdiction,
valuing work and legal principles. As such it was argued that with the longer
timeframes, it becomes more difficult and costly for contractors to obtain progress
payment. Appointing adjudicators where the government is party to adjudication,
selection criteria of adjudicators, and imposing further training on adjudicators
were also criticised for the Registrar’s lack of probity.51
Nevertheless, despite these amendments in Queensland, there have been seven
judicial review court applications between December 2014 and November 2015
(compared to 15 applications in the preceding year), in which the Queensland
Supreme Court found that adjudicators committed jurisdictional errors in three
cases.52 This may further emphasise that many desperate respondents may always
seek to knock at the door of judicial review as a gaming tactic, in an attempt to
delay payment, regardless of the quality of the adjudication outcome. Having said
this, it is probably too early to draw any firm conclusions as to the effectiveness
of the recent amendments to the Queensland legislation.
3.5 Internal review of adjudicators “decisions to dismiss”
applications for lack of jurisdiction
Under the Australian West Coast model, unlike all other jurisdictions, there is an
express right of review by application in respect of an adjudicator’s decision to
dismiss without a consideration of the merits of the application on certain grounds.
These grounds include that the contract concerned is not a construction contract,
the application has not been prepared and served in accordance with the
requirements of the Act, and the adjudicator is satisfied that it is not possible to
fairly make a determination because of the complexity of the matter or the
prescribed time or any extension of it is not sufficient for any other reason (See,
e.g., Construction Contracts Act 2004 (WA Act) s.31(2)(a)).
This review is carried out by the State Administrative Tribunal (WASAT) in
Western Australia (WA) and by the local court in the Northern Territory (NT).
The WASAT has jurisdiction to review the adjudicator’s “decision to dismiss”
upon application by either party and the reviewed decision can be affirmed, varied,
set aside, or sent back to the adjudicator for reconsideration, in accordance with
any directions, or recommendations, which the WASAT considers appropriate.53
If the decision is reversed and remitted, the adjudicator is to make a determination
within 14 days after the date upon which the decision was reversed, or any extension
of that time consented to by the parties.54
Judicially, it was decided that all grounds upon which a review is sought are
jurisdictional facts.55 In O’Donnell Griffin,56 Beech J held that the WASAT also
has jurisdiction to review the adjudicator’s “decision not to dismiss”. To reach
this proposition, Beech J examined the object of the WA Act and found that the
51 Davenport, An update on security of payment in the construction industry in Queensland”, paper presented to
RICS Cobra 2015, Sydney, p.9.
52 Queensland Building and Construction Commission, November 2015 monthly adjudication statistics, p.8.
53 State Administrative Tribunal Act 2004 (WA) s.29.(3).
54 See Construction Contracts Act 2004 (WA) s.46(2).
55 See Perrinepod Pty Ltd v Georgiou Group Building Pty Ltd [2011] WASCA 217 at [16].
56 O’Donnell Griffin Pty Ltd v John Holland Pty Ltd [2009] WASC 19 (Beech J).
668 Construction Law Journal
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
review by the WASAT of an adjudicator’s decision not to dismiss was “more
expeditious”57 and more consistent with the scheme of the WA Act than the “slower
and more cumbersome prerogative relief”.58 That proposition was eventually
overturned by the Court of Appeal in Perrinepod,59 in which the court held
“insofar as the Tribunal would provide a quicker avenue for relief, a right of
review to the Tribunal where an application is dismissed is conducive to the
statutory purpose of ‘keeping the money flowing’. On the other hand, no
evident statutory purpose is served by expediting a review of a ‘decision’
‘not to dismiss’, with a view to rendering inapplicable the adjudication process
facilitated by the Act.”
A review by the WASAT involves a hearing de novo on the merits in which
material which was not before the decision-maker may be considered.60 Apparently,
there is an inconsistency between the WA Act and a hearing de novo. In Marine
& Civil Bauer,61 strict limitations have been imposed upon allowing new
submissions before the WASAT and it was held:
“In my view, no new material should be permitted because, if the decision
under review is reversed, and the matter referred back to the adjudicator, I
consider that the adjudicator must remain bound to decide the matter on the
material which was originally before the adjudicator…”
Interestingly, s.46(3) of the WA Act provides that, except as provided as grounds
for the limited review, a decision or determination of an adjudicator on an
adjudication cannot be appealed or reviewed. The WA Supreme Court interpreted
this section in Red Ink Homes,62 stating that the provision only limits the appeal
before the Tribunal, whilst judicial review will still be open for the aggrieved party.
Furthermore, s.105 of the WASAT Act provides for an appeal to the Supreme
Court from a decision of the WASAT, provided that the Court grants leave to
appeal which is limited only on a question of law.
Since the commencement of the WA Act in 2005 until end of June 2015, the
WASAT has reviewed 37 decisions of adjudicators dismissing applications without
considering the merits. In 25 cases, the adjudicators’ decisions were confirmed,
whilst 12 cases (amounting to 37 per cent) were set aside or remitted to the original
adjudicator to revisit the original decision to dismiss. Notably, the review
applications before the WASAT have been constantly increasing over the years.
Table 2 below demonstrates an extract from the relevant annual reports on the
operation of the review mechanism from 2008 until 2015.
57 O’Donnell Griffin [2009] WASC 19 at [122].
58 O’Donnell Griffin [2009] WASC 19 at [131]. See also, Thiess Pty Ltd v MCC Mining (WA) Pty Ltd [2011]
WASC 80 at [44], per Corboy J.
59 Perrinepod [2011] WASCA 217 at [129].
60 State Administrative Tribunal Act (2004) s 27.
61 Marine & Civil Bauer Joint Venture and Leighton Kumagai Joint Venture [2005] WASAT 269 at [70]–[71].
62 Red Ink Homes Pty Ltd v Court [2014] WASC 52 at [72]–[76].
Construction Act Review 669
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
Table 2 Operation of the review mechanism of adjudicators’ decisions to
dismiss in WA63
Annual review applications by the WASATDescription
2014–152013–142012–132011–122010–112009-102008-9Financial year
235175208178197172105No. of lodged applications
52477440575725No. of dismissed application
by adjudicators for no juris-
diction.
8755344No. of review applications by
the WASAT
2312000No. of remittal/set aside cas-
es by the WASAT
4. A pragmatic proposal to diminish judicial review
Having examined the current tension between judicial review and the legislative
object as well as the shortcomings of the main existing approaches to diminish
judicial intervention, this article now turns its attention to the future by proposing
two pragmatics solutions as follows:
1) separating jurisdictional issues from the merits in adjudication; and
2) establishing an internal adjudication review mechanism with respect
to jurisdictional issues.
This proposal starts from the position that there is a need for a better legal
framework to reinstate the original mission of the SOP legislation as detailed
below:
4.1 Separating jurisdictional objections from the merits in
adjudication.
Since the majority of adjudicators possess no appropriate legal training,64 many of
them lack the competency to deal with jurisdictional objections, especially those
related to invalid appointment. In Singapore, which has modelled its SOP legislation
upon the NSW Act, Chan Sek Keong CJ in the Court of Appeal held that
adjudicators do not have the competency to deal with jurisdictional objections
apart from the basic function required by the legislation.65 Keong CJ also held that
any jurisdictional objection must be raised immediately before the court and not
the adjudicator by explaining that
“since the objection is against the adjudicator’s jurisdiction as an adjudicator,
he has no power to decide if he has jurisdiction or not. He cannot decide his
own competency to act as an adjudicator when such competency is being
challenged by the respondent”66.
63 Figures are extracted from the relevant annual reports on the WA Act as released by the Building Commissioner.
64 P. Yung, K. Rafferty,R. McCaffer and D. Thomson, “Statutory Adjudication in Western Australia: Adjudicators’
Views”, Engineering (2015) 22(1) Construction and Architectural Management 71.
65 Lee Wee Lick Terence v Chua Say Eng [2012] SGCA 63 at [64].
66 Lee Wee Lick Terence [2012] SGCA 63 at [36].
670 Construction Law Journal
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
This might be the reason for Keong CJ, in another forum, to suggest reform to the
Singaporean SOP legislation so as to separate jurisdictional issues from the merits
of the dispute, so that the adjudicator’s duty is only confined to deal with the
merits.67 This measure would enable both parties to adjudication to have certainty
about the likely outcome of the real issues in dispute and to plan their further
actions as well as financial resources accordingly. As such, it is proposed that the
Singaporean approach may “kill many birds with one stone”. First, adjudicators
can proceed comfortably with the determination on the merits only, whereas
jurisdictional objection are dealt with by a review tribunal as detailed under the
second proposed solution below. Secondly, there would be no crucial need to
legally train adjudicators about administrative law principles. Thirdly, with
adjudicators focusing upon the merits only, they would be better capable of abiding
by the set time limits, which promotes the legislative object quickly and
inexpensively resolving payment disputes on the merits.
It is worthwhile to note that, sometimes, it is incumbent upon adjudicators to
consider a question of mixed fact and law relating to a payment claim in which
jurisdictional issues cannot be divisible. As such, adjudicators must have an express
jurisdiction to decide upon such questions as long as that jurisdiction is necessary
so that they can perform their basic statutory functions. Therefore, any error in
considering that questions may be deemed an error within jurisdiction rather than
an error going to jurisdiction.68
4.2 Establish a legislative review mechanism for jurisdictional
challenges.
The review mechanism by the WASAT was capable of taking substantial caseload
of judicial review applications out of the Supreme Court. Since the commencement
of the legislation until June 2015, the WA Supreme Court had only reviewed 32
cases in connection with adjudication decisions. This means that the 37 cases
before the WASAT, as mentioned above, would have been an extra burden doubling
the caseload of the Supreme Court. Furthermore, there were only four Supreme
Court cases out of the 37 cases that were identified in which the WASAT’s
decisions were challenged unsuccessfully.69 It could then be argued that this fact
is a good indication of an ongoing satisfactory quality of the WASAT’s decisions
and/or reluctance on the part of the Supreme Court to interfere with the WASAT’s
decisions.
As such, there is no reason to believe that an intermediate platform between
adjudication and judicial review should not sound as a worthwhile option, save
for the main two barriers of extra time and cost. Those barriers can be managed
by deliberately devising an effective review scheme, as next proposed. The
alternative review remedy would have the potential to help diminish judicial
intervention of supreme courts in statutory adjudication by capturing and correcting
67 C. S. Keong, “Forword” in C. Fong, Security of Payments and Construction Adjudication, 2nd edn (LexisNexis,
2012).
68 See Brodyn Pty Ltd v Davenport [2004] NSWCA 394 at [66].
69 The identified cases are: Field Deployment Solutions Pty Ltd v SC Projects Australia Pty Ltd [2015] WASC 60;
Hire Access Pty Ltd v Michael Ebbott t/a South Coast Scaffolding and Rigging [2012] WASC 108; Perrinepod [2011]
WASCA 217; Thiess [2011] WASC 80.
Construction Act Review 671
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
erroneous adjudications through a legislative informal process. In BM Alliance,70
Applegarth J referred to various authorities and noted that
“one discretionary ground to decline to order certiorari is where there are
alternative and adequate remedies for the wrong of which complaint is made”.
In Field Deployment,71 Mitchell J considered a juridical review application
against two adjudicator’s decisions to dismiss (bypassing the available review
mechanism by the WASAT) and held that:
“The fact that an alternative remedy was available but not engaged is ordinarily
a powerful factor against the grant of a discretionary remedy by way of judicial
review”.
Furthermore, as to the use of the discretion to deny certiorari where there lies
another review option, the WA Supreme Court in Re Graham Anstee-Brook,72
referred to various authorities including the High Court’s decision in R. v Cook73
and held that
“availability of prerogative relief will be undermined by circumstances where
parties could avail themselves of alternative remedies by way of rehearing,
appeal or review”.
Forming the review mechanism
It is therefore proposed to introduce an alternative convenient review mechanism
of jurisdictional challenges. The review should be conducted by an institutional
“review tribunal” exclusively established for statutory adjudication and funded by
the government.74 However, parties are not required to be legally represented but
have the discretion to engage counsels provided that each party bear its own costs.
The members of the “review tribunal” should be selected from well experienced
legal practitioners such as retired judges, arbitrators or legally qualified senior
adjudicators. The “review tribunal” should enjoy similar powers and functions to
those of the WASAT, particularly, in its capacity to determine questions of law
and the limited appeal from the tribunal’s decision provided that a leave to appeal
is granted by a court.
The scope of the “review tribunal” should, in principle, extend to cover any
jurisdictional objection upon the valid appointment of the adjudicator whether or
not that adjudicator dismisses the case. Also, the scope should include errors of
law during the adjudication decision making process that is judicially reviewable.
Accordingly, the review mechanism should have two different processes to deal
with challenges related to “no jurisdiction” as well as challenges related to “excess
of jurisdiction” as detailed next. Regardless of the outcome of that review, the
claimant and respondent must be each liable to contribute to the payment of the
adjudicator’s fees in such proportions as the adjudicator may determine.
70 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd (No 2) [2013] QSC 67 at [8].
71 Field Deployment Solutions Pty v Jones [2015] WASC 136 at [18].
72 Re Graham Anstee-Brook; Ex Parte Mount Gibson Mining Ltd [2011] WASC 172 at [64].
73 R. v Cook Ex p. Twigg [1980] HCA 36 at [29], [30], [34]. See also, Re Baker Ex p. Johnston (1981) 55 ALJR
191 and Martin CJ in Re Carey Ex p. Exclude Holdings Pty Ltd [2006] WASCA 219 at [128]–[140].
74 The “no cost” approach was also adopted in the Building and Construction Industry Security of Payment
Amendment Bill (2015) 55 (Tas).
672 Construction Law Journal
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
Challenging the jurisdiction of adjudicator
The first proposed solution provides that an adjudicator should automatically
assume he or she has jurisdiction and immediately proceed with the determination
on the merits. However, an adjudicator may still dismiss an application if it
obviously appears on the face of the record that they do not have jurisdiction unless
both parties agree to extend the adjudicator’s jurisdiction. For example, it could
be easily found that the payment claim was made out of time. Another example
is where a claimant does not hold a requisite license to be eligible to use the
legislation as is the case in Queensland.75 In those circumstances, the claimant
should not be permitted to lodge a new adjudication application, or further invoke
the review mechanism in order to avoid an “abuse of process”. This will of course
save the time and efforts of both parties. The adjudicator, however, should still be
entitled to recover his or her adjudication fees from the claimant following the
dismissal.76
On the other hand, if a respondent opts to object the valid appointment of the
adjudicator due to lack of jurisdiction, that respondent may access the review
mechanism by lodging a “review application” with a copy to the claimant. The
“review application” must be lodged within the same time allowed for that
respondent to lodge an adjudication response on the merits of the payment dispute.
An express provision should be made that the silence or failure of a respondent to
make a “review application” within the prescribed time is deemed as an acceptance
of that respondent of the adjudicator’s jurisdiction to hear the matter provided that
the grounds of jurisdictional objection could have been reasonably known to the
respondent as at the time the adjudication application was made.77 A claimant must
be allowed to serve a “review reply” in response to the “review application” within
two business days to afford it procedural fairness. The “tribunal’s decision” must
then be released as soon as possible but not later than 10 business days from receipt
of the “review reply”. If the adjudicator determines that the respondent is required
to pay an adjudicated amount, the respondent must pay that amount to the claimant
within five days after the release of the “tribunal’s decision” provided that the
“review application” is dismissed.
Challenging the adjudicator’s excess of jurisdiction
If either party opts to challenge an adjudicator’s determination for excess of
jurisdiction, the applicant should invoke the review process by lodging a “review
application” no later than five business days from the release of the determination
with a copy to the other party “responding party”. The “responding party” should
be allowed to lodge a “review reply” within two business days from receipt of a
copy of the “review application”. The review should be conducted by way of de
novo rehearing but no new submissions should be permitted except, of course, for
those submissions on the law based on the material provided to the adjudicator.
The “review tribunal” must complete the review within seven business days after
75 See Cant Contracting Pty Ltd v Casella [2006] QCA 538.
76 The entitlement to remuneration is now express in the Queensland Building and Construction Industry Payment
Act at s.35.
77 Adopted from Rhodia Chirex Ltd v Laker Vent Engineering Ltd [2003] EWCA Civ 1859; [2004] B.L.R. 75;
(2004) 20 Const. L.J. 155 at [40].
Construction Act Review 673
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
the receipt of the “review reply” and can reasonably extend this period by making
a request to the relevant Governmental Official to extend the time up to additional
five business days depending on the complexity of the matter. During that time,
the adjudicator’s determination will be kept on hold and will not take any legal
effect until the “tribunal’s decision” is issued.
The “review tribunal” should have jurisdiction to substitute, severe and/or remit
the determination to the original adjudicator for correction within a specific
timeframe depending upon the case, but not exceeding five business days from
remittal. The remittal should only be construed if the identified error will require
lengthy or technical re-consideration of relevant matters. If remitted, the adjudicator
should only charge a discounted fee rate (i.e. say AUD 100 per hour) to release
the amended determination as a reasonable compensation to the parties affected
by the consequences of the first erroneous determination.
Benefits
The unsuccessful respondent, challenging the adjudicator’s jurisdiction, will be
faced with a further strong reason to release the due payment rather than seeking
judicial review. In this case, there will be no costs (other than the party’s own
costs) or time implications on the adjudication process which would be consistent
with the object of the SOP legislation. It is submitted that even in a case where
the determination is set aside by the “review tribunal” on the basis of adjudicator’s
lack of jurisdiction, and as such, the determination is deemed never to have existed,
both parties have, at least, gained the significant advantage by knowing the likely
outcome of the underlying dispute if they further seek negotiation or other
proceedings to finally settle their payment dispute.
Moreover, both parties will enjoy an increasing level of certainty with the
“tribunal’s decision” even if an aggrieved party seeks further challenges in court
where the opportunity of success may be very limited. This is because, not only
will the room for jurisdictional errors be drastically reduced down, but also the
Supreme Court (in excising its discretionary power) will be more reluctant to grant
relief with the availability of an appropriate remedy, as demonstrated above.
Barriers
In the case of review on the basis of “excess of jurisdiction”, an additional 14
business days may be added to the adjudication process in most of the cases until
a successful claimant actually gets paid. Having said that, the review mechanism
remains as a much faster and more inexpensive option than the judicial review,
especially in large cases, where either party, particularly the claimant, may not be
able to afford to go to court to defend a favourable adjudicator’s determination.
There is also a possibility for an “abuse of process” in using the review
mechanism. To counter this barrier, it could be worthwhile to equip the “review
tribunal” with the jurisdiction to make an order for a reasonable monetary penalty
as well as legal costs to compensate a party for any expenses, loss or inconvenience
as a result of the other party’s conduct. This would include situations when a party
conducts itself unreasonably or where a case is obviously frivolous, vexatious or
674 Construction Law Journal
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
unmeritorious.78 In addition, the ambit of review can be curtailed by fixing a
minimum monetary threshold. Also, respondents should be required to pay the
unpaid adjudicated amount into a trust account.
5. Conclusion
There have been numerous judicial review applications with respect to adjudicators’
determinations, which represent a drift in the original mission of the SOP
legislation. The article reviewed the evolving tension between the object of the
legislation and court’s involvement and addressed the shortcoming of the main
available approaches to diminish judicial review. Then, the article proposed two
pragmatic solutions moving forward, namely: separating jurisdictional challenges
from the merits in adjudication; and establishing a legislative review tribunal to
deal with jurisdictional challenges. It is suggested that both solutions may work
together for the maximum efficiency of the SOP legislation by diminishing judicial
intervention and therefore countering the effect of Kirk’s authority upon the
operation of the SOP legislation as originally intended. If adjudicators are to
continue dealing with jurisdictional issues, the proposed review mechanism
becomes more critical and crucial as a safety net to capture most of determinations
infected by jurisdictional errors away from judicial system. Both proposals
represents something of a “blunt instrument” and further consultation with the
building and construction industry will be required.
78 See WA Act s.34(2).
Construction Act Review 675
(2016) 32 Const. L.J., Issue 6 © 2016 Thomson Reuters (Professional) UK Limited and Contributors
... Affordability in terms of cost and time (Coggins et al., 2010, Wallace, 2013, Australian Legislation Reform Sub-Committee, 2014, Economics References Committee, 2015, Marquet, 2015, Skaik et al., 2016a, Skaik et al., 2016b, Murray, 2017, Skaik, 2017d, Skaik, 2017b, Fiocco, 2018 Lack of industry confidence (Ali, 2006, Chan, 2006, Kennedy, 2008, Supardi et al., 2011, Wong et al., 2014, Marquet, 2015, Skaik et al., 2015c, Yung and Rafferty, 2015, Jayasinghe and Ramachandra, 2016, Skaik, 2016, Skaik et al., 2016a, Skaik, 2017b, Lopez and Amara, 2018, Tay and Kong, 2018, Hassan et al., 2019, Munaaim, 2019 Lack of knowledge and awareness (Brand and Uher, 2010, Coggins et al., 2010, Wallace, 2013, Economics References Committee, 2015, Evans, 2015, Murray, 2017, Skaik, 2017d, Steensma and Evans, 2020 Impact on the business relationship (Brand and Uher, 2010, Coggins et al., 2010, Australian Legislation Reform Sub-Committee, 2014, Economics References Committee, 2015, Murray, 2017, Skaik, 2017d, Coggins and Donohoe, 2018 limited right to access the legislation (Bell, 2011, Gerber and Ong, 2013, Wallace, 2013, Australian Legislation Reform Sub-Committee, 2014, Evans, 2015, Skaik et al., 2015a, Skaik et al., 2015b, Murray, 2017, Skaik, 2017b, Fiocco, 2018 3.1 Affordability in terms of cost and time Cheung (1999) investigated twelve attributes that motivate a party to use any dispute resolution process. Cheung found that the cost and time to be the most significant ones affecting the utilisation of any process. ...
... Whilst the SOP process is perceived as cost and time effective, which should ease the accessibility to the process, the actual duration until getting paid and the total cost involved makes the process much less attractive. In practice, the prolonged and costly adjudication process is highly influenced by the complexity of the regime, the claimant's administrative burden as well as heavy involvement by lawyers and courts (Skaik et al., 2016b), as elaborated further below: ...
... Consequently, subcontractors might avoid accessing the process and seek other avenues for dispute resolution (Ali, 2006, Jayasinghe and Ramachandra, 2016, Tay and Kong, 2018, Munaaim, 2019. Alternatively, subcontractors will be left to negotiate their rights to settle the dispute to avoid going to court, which is typically considered unfeasible for small claims (Skaik et al., 2016b). ...
Conference Paper
Full-text available
Within the Australian construction industry, small subcontractors are highly vulnerable to insolvency risk due to poor payment practices. The Security of Payment legislation was introduced to ensure that those subcontractors are timely paid for the work they do. However, since the enactment of the legislation in Australia, the utilisation rates of the legislation have been relatively low. Through a desktop study, this paper aims to identify and discuss the main causes of the legislation under-utilisation including affordability, lack of industry confidence, lack of knowledge and awareness, impact on business relationships and limited right to access the regime. Moving further, this paper will acquaint the lead author's PhD study, which aims to address the barriers and solutions to achieve an appropriate utilisation of the security of payment legislation.
... The availability of review mechanism in Victoria did not stop respondents from seeking judicial review by bypassing the review mechanism 8 and it seems that the Victorian Supreme Court has overlooked the Australian High Court's decision in this regard. As to the use of the discretion to deny certiorari where there lies another review option, the WA Supreme Court in Re Graham Anstee-Brook; Ex Parte Mount Gibson Mining Ltd 9 referred to various authorities including the High Court's decision in The Queen v Cook; Ex parte Twigg 10 and held that "availability of prerogative relief will be undermined by circumstances where parties could avail themselves of alternative remedies by way of rehearing, appeal or review." ...
... The measures include the requirement to pay the disputed amount, appointment of experienced review adjudicators, apportionment of higher percentage of adjudication fees to respondents abusing the system and the award of legal costs. 8 : "Legislation which would take from a State Supreme Court power to grant relief on account of jurisdictional error is beyond State legislative power. Legislation which denies the availability of relief for non-jurisdictional error of law appearing on the face of the record is not beyond power." ...
Article
Full-text available
Notes Western Australia's Building and Construction Industry (Security of Payment) Bill 2020, intended to improve subcontractor and supplier protection in the construction industry, and evaluates its adjudication review mechanism (ARM). Discusses the background to the reform, the Bill's provisions governing ARM, and their potential shortcomings, including the uncertain effects of suspension. Suggests how the existing proposals might be improved.
Hire Access Pty Ltd v Michael Ebbott t/a South Coast Scaffolding and Rigging
The identified cases are: Field Deployment Solutions Pty Ltd v SC Projects Australia Pty Ltd [2015] WASC 60; Hire Access Pty Ltd v Michael Ebbott t/a South Coast Scaffolding and Rigging [2012] WASC 108; Perrinepod [2011] WASCA 217; Thiess [2011] WASC 80. 70 BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd (No 2) [2013] QSC 67 at [8]. 71 Field Deployment Solutions Pty v Jones [2015] WASC 136 at [18]. 72
The risk of such suspension was well noted in Brodyn v Davenport
  • Ja Per Hodgson
  • Hickory
The risk of such suspension was well noted in Brodyn v Davenport [2005] NSWCA 394 at [51], per Hodgson JA; Hickory [2009] VSC 156 [46]–[47], per Vickery J. 6
QSC 168, and previous excision prior to the Queensland Building and Construction Industry Payment Act being amended is evidenced in Hansen Yuncken Pty Ltd v Ian James Ericson trading as Flea's Concreting
  • See Sunshine Coast
See Sunshine Coast [2015] QSC 168, and previous excision prior to the Queensland Building and Construction Industry Payment Act being amended is evidenced in Hansen Yuncken Pty Ltd v Ian James Ericson trading as Flea's Concreting [2011] QSC 327.
  • See Brodyn
  • Pty Ltd
  • Davenport
See Brodyn Pty Ltd v Davenport [2004] NSWCA 394 at [66]. 69
NSWSC 1140 at [96], per Palmer J, adopting the language of Ward LJ in RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140 at [96], per Palmer J, adopting the language of Ward LJ in RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd [2002] EWCA Civ 270; [2002] 1 W.L.R. 2344; [2002] C.L.C. 905. 2
VSC 243; Metacorp Pty Ltd v Andeco Construction Group Pty Ltd
  • See Maxstra Constructions Pty Ltd V Gilbert
  • Gilbert Concrete
See Maxstra Constructions Pty Ltd v Gilbert t/as AJ Gilbert Concrete [2013] VSC 243; Metacorp Pty Ltd v Andeco Construction Group Pty Ltd (No.2) [2010] VSC 255. 29 Maxstra [2013] VSC 243 at [72]. 30 Plenty Road v Construction Engineering (Aust) (No.2) [2015] VSC 680. 31 Plenty Road [2015] VSC 680 at [31]. 32
Wqube Port of Dampier v Philip Loots of Kahlia Nominees Ltd [2014] WASC 331 at [78]; Cape Range Electrical Contractors Pty Ltd v Austral Construction Pty Ltd
  • E G See
See, e.g., Wqube Port of Dampier v Philip Loots of Kahlia Nominees Ltd [2014] WASC 331 at [78]; Cape Range Electrical Contractors Pty Ltd v Austral Construction Pty Ltd [2012] WASC 304 at [83]. 23
QSC 373 atAn update on security of payment in the construction industry in Queensland
  • Thiess Pty Ltd V Warren Brothers Earthmoving Pty
  • Ltd
Thiess Pty Ltd v Warren Brothers Earthmoving Pty Ltd [2012] QSC 373 at [61]–[62]; e.g., BM Alliance Coal Operations Pty Ltd v BGC Contracting Pty Ltd (No.2) [2013] QSC 67 at [35]–[37]; Multiplex [2003] NSWSC 1140 at [90]–[92], per Palmer J; Lanskey Constructions Pty Ltd v Noxequin Pty Ltd [2005] NSWSC 963 at [21]–[22]. 47 P. Davenport, "An update on security of payment in the construction industry in Queensland", paper presented to RICS Cobra 2015, Sydney, p.8. 48
  • Trysams
Trysams [2008] NSWSC 399 [2008] NSWSC 399 at [90]. 34 Cardinal [2011] NSWCA 399 at [100]–[103]. 35 Cardinal [2011] NSWCA 399 at [97]. 36
Discussion Paper—Payment dispute resolution in the Queensland building and construction industry-Final Report, 2013, p.224. 45 Building and Construction Industry Payments Act
  • Wallace
Wallace, Discussion Paper—Payment dispute resolution in the Queensland building and construction industry-Final Report, 2013, p.224. 45 Building and Construction Industry Payments Act 2004 (Queensland) s.100(4).