ArticlePDF Available

Building information modeling (BIM): Now and beyond

Authors:

Abstract and Figures

Building Information Modeling (BIM), also called n-D Modeling or Virtual Prototyping Technology, is a revolutionary development that is quickly reshaping the Architecture-Engineering-Construction (AEC) industry. BIM is both a technology and a process. The technology component of BIM helps project stakeholders to visualize what is to be built in a simulated environment to identify any potential design, construction or operational issues. The process component enables close collaboration and encourages integration of the roles of all stakeholders on a project. The paper presents an overview of BIM with focus on its core concepts, applications in the project life cycle and benefits for project stakeholders with the help of case studies. The paper also elaborates risks and barriers to BIM implementation and future trends.
Content may be subject to copyright.
Building Information Modeling (BIM): Now and
Beyond
Salman Azhar, (Auburn University, USA)
Malik Khalfan and Tayyab Maqsood, (RMIT University, Australia)
Abstract
Building Information Modeling (BIM), also called n-D Modeling or Virtual Prototyping
Technology, is a revolutionary development that is quickly reshaping the Architecture-
Engineering-Construction (AEC) industry. BIM is both a technology and a process. The
technology component of BIM helps project stakeholders to visualize what is to be built in a
simulated environment to identify any potential design, construction or operational issues.
The process component enables close collaboration and encourages integration of the roles
of all stakeholders on a project. The paper presents an overview of BIM with focus on its
core concepts, applications in the project life cycle and benefits for project stakeholders with
the help of case studies. The paper also elaborates risks and barriers to BIM implementation
and future trends.
Keywords: Building Information Modeling (BIM), n-D Modeling, Collaboration, Integrated Project
Delivery (IPD), Information Technology, Project Management
Introduction
Building Information Modeling (BIM) is a revolutionary technology and process that has
quickly transformed the way buildings are conceived, designed, constructed and operated
(Hardin, 2009). Although the roots of BIM can be traced back to the parametric modeling
research conducted in USA and Europe in late 1970s and early 1980s, the Architecture-
Engineering-Construction (AEC) industry practically started to implement it in projects from
the mid-2000s. During the last seven years, the term BIM has gone from being a buzzword
to the centerpiece of AEC technology (Khemlani, in Eastman et al., 2011).
The National Building Information Modeling Standards (NBIMS) committee of USA defines
BIM as follows: “BIM is a digital representation of physical and functional characteristics of a
facility. A BIM is a shared knowledge resource for information about a facility forming a
reliable basis for decisions during its life cycle; defined as existing from earliest conception to
demolition. A basic premise of BIM is collaboration by different stakeholders at different
phases of the life cycle of a facility to insert, extract, update or modify information in the BIM
to support and reflect the roles of that stakeholder (NBIMS, 2010).
The Associated General Contractors of America (AGC) perceived BIM as: Building
Information Modeling is the development and use of a computer software model to simulate
the construction and operation of a facility. The resulting model, a Building Information
Model, is a data-rich, object-oriented, intelligent and parametric digital representation of the
facility, from which views and data appropriate to various users’ needs can be extracted and
analyzed to generate information that can be used to make decisions and improve the
process of delivering the facility (AGC, 2005).”
As is clear from the above two definitions that BIM is not just software; it is a process and
software. BIM means not only using three-dimensional intelligent models but also making
significant changes in the workflow and project delivery processes (Hardin, 2009). BIM
represents a new paradigm within AEC, one that encourages integration of the roles of all
stakeholders on a project. It has the potential to promote greater efficiency and harmony
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 16
among players who, in the past, saw themselves as adversaries (Azhar et al., 2008a). BIM
also supports the concept of Integrated Project Delivery (IPD) which is a novel project
delivery approach to integrate people, systems, business structures and practices into a
collaborative process to reduce waste and optimize efficiency through all phases of the
project life cycle (Glick and Guggemos, 2009).
The purpose of this paper is to provide an overview of BIM concept, applications, benefits,
risks and associated challenges to the AEC industry. In the following section, the BIM
concept is discussed from technology and process standpoints. After that, the BIM
applications in the project life cycle programming, design, preconstruction, construction
and post-construction are discussed. This is followed by discussion on BIM benefits for
project stakeholders namely owners, designers, constructors and facility managers. After
that, BIM risks and barriers to implementation in the AEC industry are elaborated. At the
end, the future of BIM is examined and conclusions are drawn.
Understanding BIM
BIM as a Technology
From technology perspective, a building information model is a project simulation consisting
of the 3D models of the project components with links to all the required information
connected with the project planning, design, construction or operation as depicted in Figure
1 (Kymmell, 2008). The BIM technology hailed from the object-oriented parametric modeling
technique (Azhar et al., 2008b). The term “parametric” describes a process by which an
element is modified and an adjacent element or assembly (e.g. a door attached to a wall) is
automatically adjusted to maintain a previously established relationship (Stine, 2011).
Figure 1 A Visual Representation of BIM Concept
The principal difference between BIM technology and conventional 3D CAD is that the latter
describes a building by independent 3D views such as plans, sections and elevations.
Editing one of these views requires that all other views must be checked and updated, an
error-prone process that is one of the major causes of poor documentation. In addition, data
in these 3D drawings are graphical entities only, such as lines, arcs and circles, in contrast
to the intelligent contextual semantic of BIM models, where objects are defined in terms of
building elements and systems such as spaces, walls, beams and columns. A building
Building
B
Residential
Commercial
Healthcare
Institutional
Sports
Entertainment
Information
I
Spatial
Elements
Systems
Quantities
Schedule
Operations
Modeling
M
Site
Architectural
Structural
MEP Systems
Sustainability
Management
Program-
ming Design Pre
construction Construction Operations Demolition
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 17
information model carries all information related to the building, including its physical and
functional characteristics and project life cycle information, in a series of “smart objects”. For
example, an air conditioning unit within a BIM would also contain data about its supplier,
operation and maintenance procedures, flow rates and clearance requirements (Azhar and
Richter, 2009; CRC Construction Innovation, 2007).
Eastman et al. (2011) indicated that the following types of digital models do not fall under the
category of BIM: (1) models that contain 3D data only and no object attributes (i.e. missing
“i” of BIM) ; (2) models with no support of behavior; (3) models that are composed of multiple
2D CAD reference files that must be combined to define the building; and (4) models that
allow changes to dimensions in one view that are not automatically reflected in other views.
BIM as a Process
BIM can be viewed as a virtual process that encompasses all aspects, disciplines, and
systems of a facility within a single, virtual model, allowing all team members (owners,
architects, engineers, contractors, subcontractors and suppliers) to collaborate more
accurately and efficiently than traditional processes. As the model is being created, team
members are constantly refining and adjusting their portions according to project
specifications and design changes to ensure the model is as accurate as possible before the
project physically breaks ground (Carmona and Irwin, 2007). The foundations of BIM are laid
on two pillars, communication and collaboration. The successful implementation of BIM
requires early involvement of all project stakeholders. It means that the traditional project
delivery systems (e.g. design-bid-build) have very limited role in BIM-based projects.
Recently the Integrated Project Delivery (IPD) concept emerges as a natural companion to
BIM. IPD brings key construction management, trades, fabrication, supplier and product
manufacturer expertise together with design professionals and the owner earlier in the
process to produce a design that is optimized for quality, aesthetics, constructability,
affordability, timeliness and seamless flow into lifecycle management. In the United States,
the IPD has become a preferred project delivery system for all major projects involving BIM
(McGraw-Hill Construction, 2008). Figure 2 illustrates the difference between “traditional”
and “BIM” process.
Figure 2 A Comparison between “Traditional” and “BIM” Process
(Courtesy of: Holder Construction, Atlanta, Georgia, USA)
BIM Applications in the Project Life Cycle
BIM applications spans over the entire life cycle of a facility. This section presents a brief
overview of important BIM applications in the project programming, design, preconstruction,
construction, and post-construction (operations and maintenance) phases.
BIM and Project Programming
The use of BIM in the project programming phase allows project team to analyze space and
understand the complexity of space standards and land regulations, which saves time and
provide the team with opportunity of doing more value-added activities (CICRP, 2009).
‘Traditional’ Process
AC
S
M
E
Concept & Design Documents & Drawings Construction & Operation
x
x
x
‘BIM’ Process
AC
S
M
E
P
Cost FP
Prog
FM
Data
Relational Database
(Design, Documents, Data)
Construction
& Operation
Active Access,
Sharing & Data Use
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 18
Recently, some researchers have investigated the integration of BIM with GIS (Geographical
Information Systems) which can aid project planners in selecting appropriate site and
conducting project feasibility and marketing studies (Berlo and Laat, 2011; Isikdag et al.,
2008). Following are some of the benefits of ‘GIS-BIM’ based site analysis (CICRP, 2009):
Aid in determining if potential sites meet the required criteria according to project
requirements, technical and financial factors, etc.
Decrease costs of utility demand and demolition.
Minimize risk of hazardous materials.
The advances and economy of 3D laser scanning equipment has allowed practitioners to
accurately scan existing utilities and integrate them in the BIM model as show in Figure 3. In
addition, 3D laser scanning can be used to scan and accurately (within industry tolerances)
develop BIM models of existing facilities which can be later used for renovation and adaptive
re-use of existing buildings.
Figure 3 Utilization of BIM Model for Underground Utilities Coordination
(Courtesy of: Holder Construction, Atlanta, Georgia, USA)
BIM and Project Design
The architects and engineers can take advantage of BIM applications at different stages of
project design namely schematic design (SD), detailed design (DD) and construction
detailing (CD). Table 1 illustrates specific BIM applications in each stage of project design.
Schematic design
Detailed design
Construction Detailing
Options Analysis (to
compare multiple design
options)
Photo Montage (to
integrate photo realistic
images of project with its
existing conditions)
3D exterior and interior models
Walk-through and fly-through
animations
Building performance analyses
(e.g. energy modeling)
Structural analysis and design
4D phasing and scheduling
Building systems analysis
(e.g. clash detections)
Shop or fabrication drawings
Table 1 BIM applications in project design phase
Case study 1 (Azhar, 2011)
This case study illustrates the use of BIM in the schematic design phase. The Options
Analysis was performed for selecting the most economical and workable building layout. The
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 19
project is a higher education facility at Savannah State University, Savannah, Georgia, USA.
For this project, the general contractor coordinated with the architect and the owner at the
schematic design phase to prepare building information models of three different design
options. For each option, the BIM-based cost estimates were also prepared using three
different cost scenarios (budgeted, midrange, and high range), as shown in Figure 3. The
owner was able to walk through all the virtual models to decide the best option that fit his
requirements. The entire process took 2 weeks, and the owner achieved roughly $1,995,000
cost savings at the schematic design stage by selecting the most economical design option.
Although it could be argued that the owner may have reached the same conclusion using
traditional drawings, the use of BIM technology helped him make a quick, definitive, and
well-informed decision.
Owner’s
Requirements
Option A
Option B
Option C
Not specified
2
2
3
$11,000,000
$12,897,111
$12,270,919
$10,910,894
$13,030,325
$15,276,800
$14,535,140
$12,924,100
$14,891,800
$17,459,200
$16,611,600
$14,770,400
Figure 3 Options Analysis for the Savannah State Academic Building
(Courtesy of: Holder Construction Company, Atlanta, GA)
BIM in the Preconstruction Phase
The applications of BIM in the preconstruction phase can be summarized as follows:
Estimating: From building information models, the contractors can perform fairly accurate
quantity survey and prepare detailed estimates. Based on the data of 32 major projects,
the Stanford University’s Center for Integrated Facilities Engineering (CIFE) reported that
the accuracy of BIM-based estimates was within 3% with up to 80% time reduction in
generating these estimates (cited by CRC Construction Innovation, 2007).
Site coordination: Using 3D or 4D site coordination models, the contractors can plan for
site logistics, develop traffic layouts, and identify potential hazards at the jobsite which
can aid in preparing a more realistic site safety plan.
Constructability analysis: Using BIM models, the project team can perform detailed
constructability analysis to plan sequence of operations at the jobsite.
Case study 2
This case study illustrates the use of BIM for safety planning and management. The project
is Wellness Center Building at the campus of Auburn University, Auburn, Alabama which is
currently under construction and planned to complete by April 2013. The project team
developed the BIM model of the facility in the project design phase and uses it for site
coordination and constructability analysis. Through coordinated meetings involving project
managers, site superintendents, and subcontractors, all possible major and minor site
Option A
Option B
Option C
Option A
Option B
Option C
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 20
hazards are identified and appropriate mitigation plans are developed (see Figure 4). The
relevant 4D animations are also used in the tool box meetings to illustrate daily construction
activities to the workers. So far, no major or minor accident is reported at the site. The site
superintendents rated BIM as “… a great tool for educating workers in quick time about the
site hazards” (Azhar et al., 2012).
(a) Fall protection railings
(b) Fall protection plan for roof workers
Figure 4 A BIM-based site specific safety plan (Azhar et al., 2012)
BIM in the Construction Phase
In the construction phase, the project team can use BIM for the following activities: (1)
Project progress monitoring using 4D phasing plans; (2) For trade coordination meetings
(see Figure 5); and (3) Integrating RFIs, change orders and punch list information in the BIM
models. Throughout the construction period, the project team must continuously update the
BIM model so that it reflects the most up-to-date information which later on can be used by
the facility managers for building operations and maintenance.
The advances in smartphone and tablets technology have allowed contractors and
subcontractors to frequently use BIM models at the jobsite for information extraction and
coordination. Some of the notable BIM apps include BIMX®, Bentley Navigator®, Buzzsaw®,
etc. Recently the Autodesk® has started a Cloud-based service, The Autodesk 360©, which
allows users to share BIM models in a web environment and perform various tasks in the
field such as walk-throughs, clash detection and preparing digital RFIs (Rubenstone, 2012).
Figure 5 Trade coordination meeting using BIM in a job trailer
(Courtesy of: Holder Construction Company, Atlanta, GA)
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 21
BIM in the Post construction Phase
A building information model contains complete information about a facility as it evolves
through planning, design and construction. This information can be leveraged for
downstream use by facility managers thereby making operations and maintenance of a
facility more efficient. Research suggests that 85% of the lifecycle cost of a facility occurs
after construction is completed and approximately $10 billion are annually lost in the U.S.
alone due to inadequate information access and interoperability issues during operations
and maintenance phases (Newton, 2004). The use of BIM for facility management (FM) can
significantly help to prevent these loses.
The fundamental benefit of a BIM model is that it provides information about a building and
its spaces, systems and components. The overall goal is to transfer these data into facility
management operations. In this manner information about building systems and equipment
can be accessed by simply clicking on an object in a BIM model. For example, the
information that is extracted for a piece of equipment such as a VAV box are location, name,
model number, product type, operation and maintenance manuals, commissioning
information and performance data. This makes it very simple for a maintenance worker to
access the required information vital to different systems in the building as shown in Figure 6
(Philips and Azhar, 2011).
(a) A HVAC Model
(b) Data of HVAC Equipment
Figure 6 Illustration of use of BIM in facility operations
Following are some additional applications of BIM for facility operations and management:
(1) Maintenance work order management; (2) Emergency service request management; (3)
Space planning and management; (4) Inventory management and inspections; (5) Move
management; and (6) Real estate portfolio management.
BIM Benefits for Project Stakeholders
Before discussing benefits of BIM for project owners, designers, constructors and facility
managers, it is useful to summarize BIM applications for these stakeholders. Table 2
provides this summary. The individual benefits of BIM for each stakeholder are discussed in
the following sections.
Project Owners
Owners can achieve significant benefits on projects where BIM technology and processes
are applied. Eastman et al. (2011) and Reddy (2011) summarized the following benefits of
BIM for project owners: (1) Early design assessment to ensure project requirements are met;
(2) Operations simulation to evaluate building performance and maintainability; (3) Low
financial risk because of reliable cost estimates and reduced number of change orders; (4)
Better marketing of project by making effective use of 3D renderings and walk-though
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 22
animations; and (5) Complete information about building and its systems in a single file. Due
to these and other tangible and intangible benefits of BIM, large project owners in the USA
(such as the General Services Administration (GSA), the U.S. Army Corp of Engineers
(USACE), etc.) are increasingly requiring designers and contractors to utilize BIM in all
projects (Ku and Taiebat, 2011).
BIM Application
Owners
Designers
Constructors
Facility
Managers
Visualization
x
x
x
x
Options analysis
x
x
x
Sustainability analyses
x
x
Quantity Survey
x
x
Cost Estimation
x
x
x
Site Logistics
x
x
Phasing and 4D scheduling
x
x
Constructability analysis
x
x
Building performance analysis
x
x
x
x
Building management
x
x
Table 2 BIM applications for project stakeholders
Project Designers
The project architects and engineers can take advantage of BIM in schematic and detailed
design; and construction detailing phases as summarized in Table 1. Following are some of
the main benefits of BIM for project designers: (1) Better design by rigorously analyzing
digital models and visual simulations and receiving more valuable input from project owners;
(2) Early incorporation of sustainability features in building design to predicts its
environmental performance; (3) Better code compliance via visual and analytical checks; (4)
Early forensic analysis to graphically assess potential failures, leaks, evacuation plans and
so forth; and (5) Quick production of shop or fabrication drawings (Kymel, 2008).
The early design and preconstruction stages of a building are the most critical phases to
make decisions on its sustainability features (Azhar et al., 2009). Traditional Computer-Aided
Design (CAD) planning environments typically lack the capability to perform sustainability
analyses in the early stages of design development. Building performance analyses are
typically performed after the architectural design and construction documents have been
produced. This failure to analyze sustainability continually during the design process results
in an inefficient process of retroactive modification to the design to achieve a set of
performance criteria (Schueter and Thessling, 2008). To assess building performance in the
early design and preconstruction phases realistically, access to a comprehensive set of data
regarding a building’s form, materials, context and systems is required. Since BIM allows for
multi-disciplinary information to be superimposed within one model, it creates an opportunity
for sustainability measures to be incorporated throughout the design process (Autodesk,
2008). Azhar et al. (2011) found that information for up to 17 LEED® (Leadership in Energy
and Environmental Design, a green building rating system used in the USA) credits can be
obtained in the design phase by performing BIM-based sustainability analyses. It means a
building information model can be used as a by-product for LEED® analysis thereby saving
substantial time and resources.
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 23
Project Constructors
In the United States general contractors are the early adopters of BIM among all
stakeholders (Azhar et al., 2008a). The contractors and subcontractors can use BIM for the
following applications (Hardin, 2009): (1) Quantity takeoff and cost estimation; (2) Early
identification of design errors through clash detections; (3) Construction planning and
constructability analysis; (4) Onsite verification, guidance and tracking of construction
activities; (5) Offsite prefabrication and modularization; (6) Site safety planning; (7) Value
engineering and implementation of lean construction concepts; and (8) Better
communication with project owner, designer, subcontractors and workers on site. Through
these applications constructors can achieve the following benefits: (1) High profitability; (2)
Better customer service; (3) Cost and schedule compression; (4) Better production quality;
(5) More informed decision making; and (6) Better safety planning and management.
Case Study 3
This case study illustrates the use of BIM by general contractor (GC) to minimize design
errors via clash detections. The project is a $35 million academic building at the campus of
Emory University, Atlanta, Georgia, USA. The architectural model was developed by the
project architect. The GC acquired 2D structural and MEP systems drawings from project
engineers and converted them into 3D BIM models. By integrating all “single” BIM models
and through clash detections in the preconstruction phase, the GC was able to rough save
$259,000 as illustrated in Figure 7.
(a) Integrated BIM model
(b) Cost and time savings via clash detections
Figure 7 Use of BIM in the project preconstruction stage
(Courtesy of: Holder Construction Company, Atlanta, GA)
Facility Managers
In the past, facility managers have been handed over the building with boxes and piles of
owner’s manuals and warranties. The use of BIM provides two major benefits: (1) The same
critical information is present in a single electronic file; and (2) the facility managers do not
have to sift through the piles of information to gather data. As mentioned by Reddy (2011),
“with the BIM database, any information about an equipment is just one-click away.” The
facility managers can click on any equipment or fixture to obtain information on product,
warranties, life cycle of the product, maintenance checks, replacement cost, installation and
repair procedures, and even place order for a replacement online (Jordani, 2010). The
advances in smart phones and tablet devices (such as iPhone® and iPAD®) and Augmented
Reality (AR) has made it possible to obtain complete information about a building component
by just pointing the device towards it. Joyce (2012) reported an AR-based system,
InfoSPOT®, developed at the Georgia Institute of Technology, Atlanta, Georgia which allows
facility managers to obtain quick “on the spot” information about an equipment using their
smartphones.
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 24
Risks and Barriers to Implementing BIM
Besides numerous benefits of BIM for project stakeholders there are many risks and barriers
to implement BIM. In other words, BIM is not a panacea for every project and every firm. The
BIM related risks can be divided into two broad categories: (1) Technology-related risks; and
(2) Process-related risks. Following sections present brief discussion on each category.
Technology-related Risks
The first technology-related risk is lack of BIM standards for model integration and
management by multidisciplinary teams. Integrating multidisciplinary information in a single
BIM model requires multiuser access to the BIM model. This requires establishment of
protocols in the project programming phase to ensure consistency in information context and
formatting styles. At the moment, since there are no standard protocols available, each firm
adopts its own standards. This could create inconsistencies in the model, which if not
properly detected, could lead to inaccurate and inconsistent BIM model. The project team
should perform frequent “model audits” to ensure avoidance of any such issues (Weygant,
2011).
The interoperability issues, though significantly reduced during the last 5 years, still pose
considerable risk. Interoperability is the ability to exchange data between applications to
facilitate automation and avoidance of data re-entry. The introduction of Industry Foundation
Classes (IFC) and XML Schemas has significantly helped to solve interoperability issues
(Smith and Tardif, 2009). However, both of these approaches have their inherent limitations.
The users must research interoperability while selecting BIM software applications.
When project team members other than the owner and architect/engineer contribute data
that are integrated into the building information model, licensing issues can arise. For
example, equipment and material vendors offer designs associated with their products for
the convenience of the lead designer in hopes of inducing the designer to specify the
vendor’s equipment. While this practice might be good for business, licensing issues can
arise if the designs were not produced by a designer licensed in the location of the project
(Thompson and Miner, 2007).
Process-related Risks
The process-related risks include legal, contractual and organizational risks. The first risk is
the lack of determination of ownership of the BIM data and the need to protect it through
copyright laws and other legal channels. For example, if the owner is paying for the design,
then the owner may feel entitled to own it, but if team members are providing proprietary
information for use on the project, their proprietary information needs to be protected as well.
Thus, there is no simple answer to the question of data ownership; it requires a unique
response for every project depending on the participants’ needs. The goal is to avoid
inhibitions or disincentives that discourage participants from fully realizing the model’s
potential (Thompson, 2001). To prevent disagreement over copyright issues, the best
solution is to set forth in the contract documents ownership rights and responsibilities
(Rosenberg, 2007).
Another contractual issue to address is who will control the entry of data into the model and
be responsible for any inaccuracies. Taking responsibility for updating building information
model data and ensuring its accuracy entails a great deal of risk. Requests for complicated
indemnities by BIM users and the offer of limited warranties and disclaimers of liability by
designers are essential negotiation points that need to be resolved before BIM technology is
used. It also requires more time spent inputting and reviewing BIM data, which is a new cost
in the design and project administration process. Although these new costs may be
dramatically offset by efficiency and schedule gains, they are still a cost that someone on the
project team will incur. Thus, before BIM technology can be fully used, not only must the
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 25
risks of its use be identified and allocated, but the cost of its implementation must be paid for
as well (Thompson and Miner, 2007).
The integrated concept of BIM blurs the level of responsibility so much that risk and liability
are likely to be enhanced. Consider the scenario in which the owner of the building files suit
over a perceived design error. The architect, engineers, and other contributors to the BIM
process look to each other in an effort to try to determine who had responsibility for the
matter raised. If disagreement ensues, the lead professional not only will be responsible as a
matter of law to the claimant but may have difficulty proving fault with others such as the
engineers (Rosenberg, 2007).
One of the most effective ways to deal with such risks is to have collaborative, integrated
project delivery contracts in which the risks of using BIM are shared among the project
participants along with the rewards. Recently, the American Institute of Architects released
an exhibit on BIM to help project participants define their BIM development plan for
integrated project delivery (Building Design and Construction, 2008). This exhibit may assist
project participants in defining model management arrangements, as well as authorship,
ownership, and level-of-development requirements, at various project phases.
Based on a survey of 31 contracting firms in the United States, Ku and Taiebat (2011) found
the following barriers to BIM implementation:
1. Learning curve and lack of skilled personnel
2. High cost to implementation
3. Reluctance of other stakeholders (e.g. architect, engineer, contractor)
4. Lack of collaborative work processes and modeling standards
5. Interoperability
6. Lack of legal/contractual agreements
They indicated that the advances in BIM technology, adoption of IPD and similar project
delivery systems, requirement of BIM model by project owners, and introduction of fresh
graduates with BIM knowledge in the project teams will ultimately help to avoid these
barriers.
Authors’ Analysis and Conclusions
BIM has changed the way the buildings are designed, constructed and operated. The use of
BIM has led to improved profitability, reduced costs, better time management and improved
customer-client relationships. BIM represents a new paradigm within AEC, one that
encourages integration of the roles of all stakeholders on a project. This integration has
brought greater efficiency and harmony among players who all too often in the past saw
themselves as adversaries.
The successful implementation of BIM had allowed project stakeholders to re-engineer and
streamline their processes to take full advantage of BIM. BIM has allowed implementing
manufacturing concepts such as lean design and modularization into construction. The
reemergence of modular construction as a “new” trend can be tied to the rise of BIM, as
reported in the SmartMarket report of 2011 published by the McGraw-Hill Construction
(SmartMarket Report, 2011). BIM is helping to make the fabrication of increasingly complex
building assemblies and subassemblies economically and technologically feasible.
The way the BIM movement is progressing, it is not very far that BIM will completely replace
CAD systems. As the market continues to adopt BIM as a standard, BIM will continue to
flourish. The advances in smartphone and tablet technologies will allow users to instantly
use BIM models for communications and quick decision-making. As the use of Cloud
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 26
technology is growing, it would be easier for project stakeholders to quickly access BIM
model virtually everywhere. The developments in augmented reality and similar virtual
technologies will allow project owners and facility managers to more efficiently operate their
buildings.
However, there are several technological and managerial challenges ahead. The
technological challenges can be broadly classified into three categories (Azhar, 2011): (1)
The need for well-defined transactional construction process models to eliminate data
interoperability issues; (2) The requirement that digital design data be computable; and (3)
The need for well-developed practical strategies for the purposeful exchange and integration
of meaningful information among the building information model components.
The management challenges cluster around the implementation and use of BIM. Right now,
there is no clear consensus on how to implement or use BIM. Unlike many other
construction practices, there is no single BIM document providing instruction on its
application and use (Associated General Contractors of America 2005). Furthermore, little
progress has been made in establishing model BIM contract documents (Post, 2009).
Several software firms are cashing in on the buzz” of BIM and have programs to address
certain quantitative aspects of it, but they do not treat the process as a whole. There is a
need to standardize the BIM process and to define the guidelines for its implementation.
Another contentious issue among the AEC industry stakeholders (i.e., owners, designers,
and constructors) is who should develop and operate the building information models and
how the developmental and operational costs should be distributed.
To optimize BIM performance, either companies or vendors, or both, will have to find a way
to lessen the learning curve of BIM trainees. Software vendors have a larger hurdle of
producing a quality product that customers will find reliable and manageable and that will
meet the expectations set by the advertisements. Additionally, the industry will have to
develop acceptable processes and policies that promote BIM use and govern today’s issues
of ownership and risk management (Post, 2009).
Researchers and practitioners have to develop suitable solutions to overcome these
challenges and other associated risks. As a number of researchers, practitioners, software
vendors, and professional organizations are working hard to resolve these challenges, the
future of BIM is exciting and promising.
Acknowledgements
The authors would like to express their gratitude to Holder Construction Company, Atlanta,
Georgia, USA for providing necessary data and photos. The first author of this paper is also
indebted to School of Property, Construction and Project Management for providing travel
funds to visit RMIT University and discuss BIM benefits and implementation challenges with
Australian colleagues.
References
Associated General Contractors of America (2005) The Contractor’s Guide to BIM, 1st ed,
AGC Research Foundation, Las Vegas, NV
Autodesk, Inc. (2008) Improving Building Industry Results through Integrated Project
Delivery and Building Information Modeling
online at http://images.autodesk.com/adsk/files/bim_and_ipd_whitepaper.pdf
Azhar, S., Behringer, A., Sattineni, A. and Mqsood, T. (2012) BIM for Facilitating
Construction Safety Planning and Management at Jobsites’, Accepted for publication in the
Proceedings of the CIB-W099 International Conference: Modelling and Building Safety,
Singapore, September 10-11, 2012
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 27
Azhar, S. (2011) Building Information Modeling (BIM): Trends, Benefits, Risks and
Challenges for the AEC Industry’, ASCE Journal of Leadership and Management in
Engineering, 11 (3), 241-252
Azhar, S., Carlton, W. A., Olsen, D, and Ahmad, I. (2011) ‘Building Information Modeling for
Sustainable Design and LEED® Rating Analysis’, Journal of Automation in Construction
(Special Issue on Building Information Modeling and Changing Construction Practices), 20
(2), 217-224
Azhar, S., and Richter, S. (2009) Building Information Modeling (BIM): Case Studies and
Return-on-Investment Analysis’, Proceedings of the Fifth International Conference on
Construction in the 21st Century (CITC-V), Istanbul, Turkey, 1378-1386
Azhar, S., Hein, M., and Sketo, B. (2008a) Building Information Modeling: Benefits, Risks
and Challenges’, Proceedings of the 44th ASC National Conference, Auburn, AL, April 2-5
Azhar, S., Nadeem, A., Mok, J.Y.N., and Leung, B.H.Y. (2008b) Building Information
Modeling (BIM): A New Paradigm for Visual Interactive Modeling and Simulation for
Construction Projects’, Proceedings of the First International Conference on Construction in
Developing Countries (ICCIDC-I), Karachi, Pakistan, August 4-5
Azhar, S., Brown, J., and Farooqui, R. (2009) BIM-based Sustainability Analysis: An
Evaluation of Building Performance Analysis Software’, Proceedings of the 45th Annual ASC
Conference, Gainesville, FL, April 1-4, 2009
Berlo, L.V. and Laat, R.D. (2011) Integration of BIM and GIS: The Development of the City
GML GeoBIM Extension’, Advances in 3D Geo-Information Sciences, Kolbe, T. H., König, G.
and Nagel, C. (Eds.), Springer
Building Design and Construction (2008) New AIA Documents include BIM Agreement and
Two New IPD Contracts, online at http://www.bdcnetwork.com/article/CA6600255.html
Carmona, J. and Irwin, K. (2007) ‘BIM: Who, What, How and Why’, Building Operating
Management, October 2007
CICRP (2009) BIM Project Execution Planning Guide, Ver 1.0, The Computer Integrated
Construction Research Group, The Pennsylvania State University, PA
CRC Construction Innovation (2007) Adopting BIM for Facilities Management: Solutions for
Managing the Sydney Opera House, Cooperative Research Center for Construction
Innovation, Brisbane, Australia
Eastman, C, Teicholz, P., Sacks, R. and Liston, K. (2011) BIM Handbook: A Guide to
Building Information Modeling for Owners, Managers, Designers, Engineers and
Contractors, 2nd ed., NY: John Wiley and Sons
Glick, S. and Guggemos, A. (2009) ‘IPD and BIM: Benefits and Opportunities for Regulatory
Agencies’. Proceedings of the 45th ASC National Conference, Gainesville, Florida, April 2-4
Hardin, B. (2009) BIM and Construction Management, Indianapolis: Wiley Publishing, IN
Isikdag, U., Underwood, J. and Aouad, G. (2008) An investigation into the applicability of
building information models in geospatial environment in support of site selection and fire
response management processes’, Advanced engineering informatics, 22, 504-519
Jordani, M. (2010) ‘BIM and FM: The Portal to Lifecycle Facility Management’, Journal for
Building Information Modeling, Spring 2010, 13-16
Joyce, E. (2012) Augmented Reality for Facilities Management Edges Closer to Real-World
Applications’, Engineering News Record, April 9, 2012
Ku, K. and Taiebat, M. (2011) BIM Experiences and Expectations: The Constructor’s
Perspective’, International Journal of Construction Education and Research, 7 (3), 175-197
Kymmell, W. (2008) Building Information Modeling: Planning and Managing Projects with 4D
CAD and Simulations, USA:McGraw Hill Construction
Australasian Journal of Construction Economics and Building
Azhar, S et al. (2012) ‘Building information modeling (BIM): now and beyond’, Australasian Journal of Construction
Economics and Building, 12 (4) 15-28 28
McGraw-Hill Construction (2008) Building Information Modeling: Transforming Design and
Construction to Achieve Greater Industry Productivity, McGraw-Hill Construction, New York
NBIMS (2010) National Building Information Modeling Standard, online at
http://www.wbdg.org/pdfs/NBIMSv1_p1.pdf
Newton, R. S. (2004) Inadequate Interoperability in Construction Wastes 415.8 Billion’,
AECNews.com, 13, Article 342
Philips, S. and Azhar, S. (2011) Role of BIM for Facility Management in Academic
Institutions’, Proceedings of the 6th International Conference on Construction in the 21st
Century (CITC-VI), Kuala Lumpur, Malaysia, July 5-7, 950-957
Post, N. (2009) Building Team Members See Progress and Problems’, Engineering News-
Record, 22 (12), 28
Reddy, K. P. (2011) BIM for Building Owners and Developers, NJ: John Wiley and Sons
Rosenburg, T.L. (2007) Building Information Modeling, online at
http://www.ralaw.com/resources/documents/Building%20Information%20Modeling%20-
%20Rosenberg.pdf
Rubenstone, J. (2012) Autodesk Steers Users Toward the Cloud With Expanded
Subscription-based Services’, Engineering News Record, April 16, 2012
Schueter, A. and Thessling, F. (2008) Building Information Model based energy/exergy
performance assessment in early design stages’, Automation in Construction, 18 (2), 153-
163
SmartMarket Report (2011) Prefabrication and modularization: Increasing productivity in the
construction industry’, online at
http://www.modular.org/htmlPage.aspx?name=McGrawHill_Prefabrication, accessed April
16, 2012
Smith, D.K., and Tardif, M. (2009) Building Information Modeling: A Strategic Implementation
Guide for Architects, Engineers, Constructors, and Real Estate Asset Managers, NJ: John
Wiley and Sons
Stine, J.D. (2011) Design Integration Using Autodesk Revit® 2012, Mission, KS: SDC
Publications
Thompson, D.B. (2001) e-Construction: Don’t Get Soaked by the Next wave’, The
Construction Law Briefing Paper, online at http://www.minnlaw.com/Articles/68553.pdf
Thompson, D.B. and Miner, R.G. (2007) Building Information Modeling - BIM: Contractual
Risks are Changing with Technology, online at http://www.aepronet.org/ge/no35.html
Weygant, R.S. (2011) BIM Content Development: Standards, Strategies and Best Practices,
NJ: John Wiley and Sons
... This has been supported by the collaborative working of the design team. BIM is a process supported by various tools, technologies and contracts involving the generation and management of digital representations of physical and functional characteristics of spaces (Azhar et al. 2012). From an Operational perspective, BIM embeds essential product and asset data and a three-dimensional computer model that can effectively manage information throughout a project's life cycle (Parn et al. 2016). ...
... From a technological point of view, BIM modeling is a building infor-mation model that provides a simulation of the project in 3D models of the various components of the project with information for all needs related to the planning, design, construction or operation of the project [10]. ...
Article
Full-text available
This article explores the development of Augmented Reality (AR) models for railway projects, as illustrated in Fig. 1, with particular emphasis on interoperability between different systems and platforms. The historical development of Building In- formation Modeling (BIM) is traced from its origins in computer-aided de- sign (CAD) to its recent applications in diverse fields. Significant milestones and the evolution of BIM into project lifecycle management are highlighted. Fundamental aspects such as Level of Development (LOD) and Industry Foundation Classes (IFC) file types are reviewed. The integration of BIM with machine learning and AR has enormous po- tential to improve asset management and decision-making in railway projects. The importance of interoperability when integrating AR into railway projects using BIM methodology, highlighting tools and models that ensure seamless operation across various platforms and software systems, is discussed. Stan- dards such as ISO 19650 and ISO 16739 are fundamental in this context. Studies that demonstrate the advantages of BIM in railway projects, in- cluding cost control, error detection and better maintenance planning, are reviewed. The challenges and opportunities associated with integrating BIM into rail are discussed, including the importance of technological advances in promoting increasingly efficient, collaborative and sustainable maintenance projects. This research is important for advancing the study and development of integration and compatibility with new technologies, specifically in the con-text of the use of BIM methodologies in railways, particularly in locomotives and carriages, and the application of AR, making a significant contribution to the fields of computer engineering, maintenance engineering and others. Graphical abstract
Article
Full-text available
With the digital transformation of the construction industry, construction management built by BIM and AR/VR technologies has gradually become a crucial mean to enhance efficiency, reduce costs and promote environmental protection. This paper discusses the application of BIM combined with AR/VR in construction management, and demonstrates its advantages in project visualisation, collaborative communication and safety management through literature analysis. The combined technology can significantly improve the transparency and precision of project management, help managers better control construction progress and costs, optimise resource allocation, and reduce rework. At the same time, the introduction of AR/VR improves worker training, decreases the risk of accidents and promotes the intelligent and green development of construction management. Although the technology still faces problems such as data compatibility, applying BIM and AR/VR in construction management is promising with the integration of new technologies such as artificial intelligence.
Article
This study investigates the reliability of monodiscipline IFC/BIM models in public construction projects of educational facilities through advanced clash detection and quantitative analysis. Data were collected from BIM models of two kindergartens and a school in Vilnius, Lithuania, representing different design disciplines. A mixed-methods approach was employed to analyse the number, types, and geometric characteristics of detected clashes. The research introduces innovative metrics, such as the Relative Quality Coefficient (RQC), Relative Uncertainty Coefficient (RUC), and Modified Relative Quality Coefficient (MRQC), to assess model quality and reliability quantitatively. The findings reveal a direct relationship between model complexity, clash detection precision, and the number of identified clashes, underscoring the importance of enhanced quality control measures in IFC/BIM models for public procurement. The study concludes that the implementation of these novel metrics can enhance the reliability of IFC/BIM models, thereby optimizing the design and construction process.
Article
Full-text available
The Industrial Revolution 4.0 in the 21st century has necessitated a shift in learning experiences and self-development to adapt to evolving learning mindsets and digital literacy demands. Teachers are encouraged to reduce administrative workloads that are not aligned with the digital age and focus on adopting digital-based learning models and media that suit modern student needs. This study aimed to implement and analyze the impact of case-based projects integrated with Building Information Modeling (BIM) software on civil engineering students’ understanding of interior building design. This mixed-methods research utilized a sequential explanatory design. A sample of 60 civil engineering students was selected through random sampling. Quantitative data were analyzed using path analysis, while qualitative data were examined through data reduction, data display, and conclusion drawing/verification analysis. The findings indicate that the case-based project approach, integrated with BIM software, was effectively applied and positively impacted students’ skills in learning BIM. Students showed improved abilities to analyze, explore, and synthesize information through hands-on experience with real-world case-based projects. This study contributes a novel educational model by integrating technology with learning methods through case-based projects in BIM software. This innovation supports students in enhancing their analytical and problem-solving skills and aligns with the requirements of the Industrial Revolution 4.0
Article
Full-text available
The need for technology in the world of construction is very important, good use of technology can facilitate the completion of the construction process. One of the developments in digital technology that has had a significant impact in accelerating infrastructure development is Building Information Modeling (BIM). The BIM software used is Autodesk Revit. This research aims to model the structure of the Hibatullah Kasiman Islamic boarding school dormitory building using Autodesk Revit software to calculate work volume and cost estimates, then carry out comparative analysis with conventional methods. Structural modeling includes concrete work and reinforcement in foundations, sloofs, columns and beams. The research results showed that the volume of concrete work using Autodesk Revit software was 861.84 m³, and the estimated cost of concrete work was IDR 1,159,002,226.60, while the volume of reinforcement was 123089.27 kg, and the estimated cost of reinforcement was IDR 2,144,978,024.97. The difference between the volume and estimated cost of concrete work using Autodesk Revit and conventional software was found to be 4.48%, while the difference between the volume and estimated cost of reinforcement was 10.69%. Calculations using Autodesk Revit software are fewer and cheaper than conventional ones, conventional volumes calculated are still rough and less detailed, there are many discrepancies in values with those in the drawings, and more estimates are made to anticipate material shortages at the time. work in the field.
Article
The built environment requires extraction and consumption of enormous quantities of raw materials, water, and energy. While these materials remain in use for several years or decades, growing global populations and aging infrastructure are driving widespread generation of one of the largest and most challenging waste streams to manage. There is growing interest from communities in integrating circular economy (CE) strategies in the context of construction & demolition (C&D) material management. Many approaches for doing so focus on small-scale CE applications like individual products, materials, or projects. However, greater understanding is needed at the city-scale given communities’ complex position at the frontlines of local development, resource consumption, and waste management. This study summarizes the development of an evaluative framework for community-based C&D circularity at a city or regional level. The framework expands upon a mixed methods approach called the Circularity Assessment Protocol (CAP), which integrates aspects of urban metabolism, geospatial analysis, and qualitative research methods to examine plastic waste management in communities. To advance convergent CE research, here, we aim to adapt the CAP framework to C&D. We describe our adaptation of the CAP to C&D through a conceptual review describing research, methods, and strategies related to seven elements of a local CE context: C&D Analytics, Building Material and Design, Community, Use, Collection, End-of-Cycle, and C&D Emissions. This work describes a novel yet preliminary conceptualization for developing a baseline understanding of circular C&D material management and a holistic examination of barriers, affordances, and opportunities for improving city-wide circularity.
Article
Este trabalho tem como objetivo investigar o planejamento e gerenciamento de obras, abordando práticas eficientes e sustentáveis aplicadas ao setor da construção civil. A pesquisa utilizou uma metodologia de revisão bibliográfica e estudo de caso comparativo, analisando artigos de bases de dados acadêmicos que tratam da implementação de metodologias como Lean Construction e Building Information Modeling (BIM). A análise focou em como essas abordagens podem otimizar o uso de recursos, reduzir custos e prazos, além de melhorar a eficiência dos projetos de construção. Os resultados mostraram que a aplicação do Lean Construction pode reduzir desperdícios e aumentar a produtividade, enquanto o uso do BIM facilita a comunicação e a visualização dos projetos, impactando positivamente o gerenciamento de obras. A comparação entre os casos estudados revela que, embora ambos os métodos tenham benefícios comprovados, a integração de ambas as ferramentas é ainda mais vantajosa para projetos complexos. Conclui-se que a adoção conjunta de BIM e Lean Construction no planejamento de obras públicas e privadas é uma estratégia eficaz para promover a sustentabilidade e a eficiência, além de mitigar os riscos associados a atrasos e falhas na execução dos projetos.
Chapter
Full-text available
Executive SummaryIntroductionTypes of Construction FirmsInformation Contractors Want from BIMProcesses to Develop a Contractor Building Information ModelReduction of Design Errors Using Clash DetectionQuantity Takeoff and Cost EstimatingConstruction Analysis and PlanningIntegration with Cost and Schedule Control and Other Management FunctionsUse for Offsite FabricationUse of BIM Onsite: Verification, Guidance, and Tracking of Construction ActivitiesImplications for Contract and Organizational ChangesBIM Implementation
Conference Paper
Full-text available
The Architecture, Engineering and Construction (AEC) industries have long sought techniques to decrease project cost, increase productivity and quality, and reduce project delivery time. Building Information Modeling (BIM) offers the potential to achieve these objectives. BIM represents the development and use of computer-generated n-dimensional (n-D) models to simulate the planning, design, construction and operation of a facility. It helps architects, engineers and constructors to visualize what is to be built in simulated environment and to identify potential design, construction or operational issues. BIM represents a new paradigm within AEC, one that encourages integration of the roles of all stakeholders on a project. It has the potential to bring about great efficiency as well as harmony among players who all too often in the past saw themselves as adversaries. In this paper, the benefits of Building Information Modeling (BIM) for the AEC industries are discussed with the help of two case studies. These case studies illustrate the various tangible and intangible benefits achieved by all stakeholders by implementing BIM in their projects. At the end, light is thrown on various BIM related risks and future challenges for the AEC industries.
Book
The optimal approach to design, build, operate, and maintain buildings. With this strategic guide to building information modeling (BIM), you'll learn how to implement this new technology as part of a comprehensive systems approach to the design, construction, management, operation, maintenance, and use of buildings. The authors, among the leading experts and pioneers in BIM, show you how BIM supports more streamlined, integrated, and efficient business processes throughout the life cycle of buildings, from their initial conception through their eventual retirement or reuse. The result is better quality buildings, lower construction and operating costs, shorter project turnaround times, and a higher quality of building information to support better business decisions. Moreover, they set forth a plan for incorporating BIM into every organization's existing workflows, enabling you to take full advantage of all the benefits that BIM offers. Everything you need to implement a BIM approach is set forth in detail, including: The business case for BIM, demonstrating how it can improve collaboration, facilitate better design and construction, optimize workflow, and help reduce risk. Guidance for meeting the challenges of BIM such as an entrenched business culture, the proliferation of BIM tools, and the uneven rates of BIM adoption The "big picture" view showing how your organization can work with business partners and fit into the building life cycle in a BIM-enabled industry. Throughout the book, sample documents and figures help you better understand the principles of BIM and how it works in practice. In addition, first-hand accounts show you exactly how adopters of BIM have gained a competitive edge. Architects, engineers, constructors, building owners, and facility managers can turn to this book to realize the full potential of BIM and radically improve the way buildings are designed, built, operated, and maintained.
Chapter
BIM Implementation FundamentalsBusiness Operations and BIMMarketing/Business DevelopmentHuman ResourcesFinanceInformation TechnologyOperationsWorkflow VisualizationEndnotes
Article
Building information modeling (BIM) is one of the most promising recent developments in the architecture, engineering, and construction (AEC) industry. With BIM technology, an accurate virtual model of a building is digitally constructed. This model, known as a building information model, can be used for planning, design, construction, and operation of the facility. It helps architects, engineers, and constructors visualize what is to be built in a simulated environment to identify any potential design, construction, or operational issues. BIM represents a new paradigm within AEC, one that encourages integration of the roles of all stakeholders on a project. In this paper, current trends, benefits, possible risks, and future challenges of BIM for the AEC industry are discussed. The findings of this study provide useful information for AEC industry practitioners considering implementing BIM technology in their projects.