Applications of Experimental Design and Response Surface Method in Probabilistic Geothermal Resource Assessment – Preliminary Results

Conference Paper

Applications of Experimental Design and Response Surface Method in Probabilistic Geothermal Resource Assessment – Preliminary Results

Abstract and Figures

Resource estimates in geothermal green-fields involve significant inherent uncertainty due to poorly constrained subsurface parameters and multiple potential development scenarios. There is also limited published information on probabilistic resource assessments of geothermal prospects. This paper explores the applications of a systematic experimental design (ED) and response surface method (RSM) approach to generate probabilistic resource results. ED and RSM have been successfully used in uncertainty analysis and resource evaluation of petroleum fields. These techniques have also been used in a number of field management strategy assessments of geothermal brown-fields. This work presents the preliminary results of a study to extend the geothermal applications of ED and RSM to geothermal green-field resource assessments. ED and RSM are applied to a simple geothermal process model and used to estimate the amount of electrical generating capacity from this synthetic geothermal system. A response variable (electrical generating capacity) as a function of the main uncertain parameters was derived from the simulation runs. This response function serves as the proxy model in Monte-Carlo probabilistic analysis. For this preliminary study, distributions used for the main uncertain parameters are assumed. The probabilistic results from the proxy model are compared with the probabilistic results from the mass in-place volumetric reserves method. The results provide a preliminary understanding of the potential strengths and weaknesses of the ED and RSM methodologies as applied to geothermal resource assessment. Future work will focus on refining the appropriate workflow, understanding the distribution of uncertain parameters, and exploring the ED and RSM levels of complexity applicable to an actual green-field numerical model.
Content may be subject to copyright.
PROCEEDINGS, Thirty-Ninth Workshop on Geothermal Reservoir Engineering
Stanford University, Stanford, California, February 24-26, 2014
SGP-TR-202
1
Applications of Experimental Design and Response Surface Method in Probabilistic
Geothermal Resource Assessment Preliminary Results
Jaime J. Quinao* and Sadiq J. Zarrouk
Department of Engineering Science, University of Auckland, Private Bag 92019, Auckland 1142, New Zealand
*jaime.quinao@mightyriver.co.nz
Keywords: Experimental design, response surface method, proxy models, uncertainty analysis, probabilistic resource assessment,
reservoir simulation,
ABSTRACT
Resource estimates in geothermal green-fields involve significant inherent uncertainty due to poorly constrained subsurface
parameters and multiple potential development scenarios. There is also limited published information on probabilistic resource
assessments of geothermal prospects. This paper explores the applications of a systematic experimental design (ED) and response
surface method (RSM) approach to generate probabilistic resource results.
ED and RSM have been successfully used in uncertainty analysis and resource evaluation of petroleum fields. These techniques
have also been used in a number of field management strategy assessments of geothermal brown-fields. This work presents the
preliminary results of a study to extend the geothermal applications of ED and RSM to geothermal green-field resource
assessments.
ED and RSM are applied to a simple geothermal process model and used to estimate the amount of electrical generating capacity
from this synthetic geothermal system. A response variable (electrical generating capacity) as a function of the main uncertain
parameters was derived from the simulation runs. This response function serves as the proxy model in Monte-Carlo probabilistic
analysis. For this preliminary study, distributions used for the main uncertain parameters are assumed. The probabilistic results
from the proxy model are compared with the probabilistic results from the mass in-place volumetric reserves method.
The results provide a preliminary understanding of the potential strengths and weaknesses of the ED and RSM methodologies as
applied to geothermal resource assessment. Future work will focus on refining the appropriate workflow, understanding the
distribution of uncertain parameters, and exploring the ED and RSM levels of complexity applicable to an actual green-field
numerical model.
1. INTRODUCTION
Probabilistic assessment of undeveloped geothermal resources has been necessary to accommodate the uncertainties in both the
subsurface parameters and the development scenario to be implemented. The geothermal industry has done this mainly through
Monte Carlo simulations of the parameters in the volumetric stored heat or mass in-place estimation methodologies (Grant and
Mahon, 1995; Parini et al., 1995; Parini and Riedel, 2000; Sanyal and Sarmiento, 2005; Williams et al., 2008; AGRCC, 2010; Garg
and Combs, 2010; Onur et al., 2010). The Monte Carlo simulation is applied to the parameters of the volumetric stored heat
equation where the parameters are allowed to vary over a range of values and within a defined probability distribution
(AGRCC, 2010). The range of parameter values ideally covers the range of uncertainty for that particular variable. This is strongly
influenced by the geothermal experts doing the estimate as shown by the review of geothermal resource estimation methodology
by Zarrouk and Simiyu (2013).
An example of a power capacity estimate based on volumetric stored heat equation is shown below (Zarrouk and Simiyu, 2013):

 (1)
where is the power capacity in MWe, is the theoretical available heat in both the reservoir rock and fluid, is the recovery
factor that represents the fraction of recoverable heat from the system, is the conversion efficiency, is the project life, and is
the power plant load factor. The theoretical available heat, , is described by the following expression (AGRCC, 2010):
 (2)
where the product of area and height, Ah, is the resource volume, is the porosity representing the fluid-filled fraction of the
volume, is the density of the rock, is the heat capacity of the rock,  is the difference between the initial and final rock
temperature,  and  are the initial steam and liquid densities, and are the steam and liquid saturations,  and  are the
change in steam and liquid enthalpies.
The probabilistic resource assessment would be a Monte Carlo simulation of equation (1) where the parameters are randomly
sampled within their defined probability distribution range. The result is a probability density function (PDF) or a cumulative
distribution function of the power capacity (AGRCC, 2010). In this assessment, the most debated parameter is the recovery factor,
.
Quinao and Zarrouk
2
Parini and Riedel (2000) investigated the recovery factor using numerical simulation. In their approach, was based on the ratio
of total steam produced in 30 years to the original reservoir mass in-place. The use of numerical simulation to investigate the
relationship between the physics of the reservoir and the recovery factor is an improved probabilistic assessment based on the
volumetric method (equation 1).
The use of numerical simulation models for probabilistic resource assessment has never been a popular option due to the resources
required to build reservoir models and the perceived weakness of a model without production history calibration. However, use of
numerical simulations for the final resource assessment, the delineation stage as defined by AGRCC (2010), before a major
investment decision is madeadditional drilling, power plant construction, etc.is slowly gaining ground. Grant (2000) argued for
the superiority of numerical simulations in evaluating the size of a geothermal development. Similar to volumetric stored heat or
mass in place estimates, the main concern with a resource assessment using numerical simulation is that it is deterministic even
though the parameters that are used to build the model still have large uncertainties. In a recent geothermal development in New
Zealand, Clearwater, et al. (2011) used a reservoir model as part of the resource evaluation process prior to the installation of a
power station and production history calibration.
Probabilistic resource assessment using numerical simulation has been applied in geothermal reservoirs with concepts similar to ED
and RSM. Parini and Riedel’s (2000) recovery factor in their probabilistic capacity equation is essentially a response surface or
proxy model for the numerical simulation. Acuña et al., (2002) built and calibrated alternative full-field reservoir simulation models
to evaluate field strategies. The most-likely, pessimistic, and optimistic model responses were represented by a polynomial
approximation model, a similar concept to the response surface proxy models, to enable a probabilistic Monte Carlo simulation.
In both cases, varying the factors in the model is either done one factor at a time or by multiple parameter variations but without a
suggestion of how these combinations are done. In the work flow by Acuña et. al., (2002), the variations are done by trial and error.
A systematically designed experiment through ED and RSM can improve this process by modifying parameters simultaneously and
running the minimum number of reservoir simulations required to generate a response surface model. Since the design is known, it
can be independently verified. The basis for the response surface or the proxy model that results from the analysis is also verifiable.
This will address the concerns raised by AGRCC (2010) and Atkinson (2012) in regards to the independent verification of the
results and analysis performed.
This work provides a preliminary result of the study to apply experimental design and response surface methods to reservoir
simulation models and use the resulting proxy model to provide a probabilistic resource assessment.
2. EXPERIMENTAL DESIGN AND RESPONSE SURFACE METHODOLOGY
One of the earliest works on the application of experimental design methodology in oil and gas reservoir simulations
(Damsleth et al., 1992) demonstrated that information can be maximized from a minimum number of simulation runs through a
“recipe” of combining parameter settings. Also, the work verified the possibility of substituting a response surface for the reservoir
simulation in a probabilistic Monte Carlo analysis. The response surface is a polynomial describing the relationship between the
simulation output and the investigated parameters. In the geothermal industry, an ED workflow was described
by Hoang et al. (2005). ED and RSM frameworks and workflows for reservoir simulations in the oil and gas industries are also
described by other authors (Friedmann et al., 2003; White and Royer, 2003; Yeten et al., 2005; Amudo et al., 2008). From these
works, a generalized workflow applied in this study is shown below.
Figure 1. Experimental design workflow applicable to probabilistic resource assessment.
2.1 Experimental Design
To illustrate the ED concept, let us take for example a reservoir simulation where the response, say power capacity, to three
parametersA, B, and Care being investigated. These parameters will have a low setting (minimum) and a high setting
(maximum). These settings are known as levels and the simplest design used in this work has two levels, low and high. These
designs belong to a group of designs known as factorial experiments (Walpole et. al., 2012) where is the number of parameters
being investigated. In ED and RSM, the parameter levels are more conveniently dealt with using dimensionless coded variables,
i.e., -1 for low, 0 for middle, and +1 for high settings (Anderson and Whitcomb, 2000; Myers and Montgomery, 2002). Their
Quinao and Zarrouk
3
combinations are the design points or simulation runs required by the design. A two-level, three-parameter complete factorial
design requires 23 or 8 simulation runs. This is shown in Figure 2.
Figure 2. Design points and the parameter combinations for each run on a full factorial design.
In contrast, the one-factor-at-a-time (OFAT) sensitivity analysis for the same number of levels and parameters is illustrated in
Figure 3 where a parameter is varied while the rest of the parameters are held constant. At least runs are required, where is
the number of parameters.
Figure 3. Design points and the parameter combinations for each run with OFAT sensitivity analysis.
If there are 10 parameters at two levels, a full factorial design will be 210 or 1,024 experiments; if the design is done at three levels
(low, mid, and high), the total number of experiments will be close to 60,000. A simulation run in a full-field geothermal reservoir
model can range from a few minutes to a few hours dependent on the complexity of the model. With more design parameters and
levels, the required number of runs becomes prohibitively time consuming.
ED maximizes the information that can be gathered from a minimal number of simulation runs by effectively choosing a number of
design points (simulations) out of the complete factorial design. Some of these runs are fractions (1/2, 1/4, 1/8) of the full factorial
design; these are known as fractional factorial designs (Walpole et al., 2012). Other designs are effective in screening out
insignificant factors and identifying the key parameters that affect the simulation result. From the aforementioned oil and gas
workflows, the most commonly used screening design is the Plackett-Burman experimental design. Doing a screening design is
useful when a higher level or a more complex design may be required at a later stage. Examples of more complex designs are the
Central Composite Design (CCD), and Box-Behnken design (Myers and Montgomery, 2002).
2.2 Response Surface Proxy Models
The term response surface and proxy models are interchangeably used in this work to define the polynomial approximation of
the simulation results, , and the parameters tested, , , and . Equation 3 shows an example of a first-order polynomial
approximation, also known as a main effects model (Myers and Montgomery, 2002), of the simulations from the design described
in Figure 2. In this equation, the values are the coefficients of the tested parameters.
(3)
Details regarding the higher-order polynomial models and the experimental designs that produce them are discussed by Myers and
Montgomery (2002), and Anderson and Whitcomb (2005).
The aim of our ED and RSM study is to approximate the correct form of this function good enough to serve as a substitute for the
geothermal reservoir simulation in the Monte Carlo probabilistic analysis.
2.3 Implementing the ED and RSM Workflow
In studying this technique, the preliminary approach was to find and use currently existing software packages that are accessible to
industry specialists. As expected, we did not find software packages that can link the experimental design to the geothermal
reservoir simulation code TOUGH2 (Pruess, et al., 1999)
Although no single integrated package performed the ED method, software packages existed for specific parts of the workflow. We
used PetraSim for the TOUGH2 reservoir simulation interface, PyTOUGH for results extraction, (Croucher, 2011), Minitab
for the statistics for both experimental design and response surface models, and @Risk for the Monte Carlo simulation. The
software packages used do not affect the validity of the workflow since commercial software packages may be replaced by open-
source codes like PyTOUGH to pre-process and post-process the simulation runs, and R (R Core Team, 2013) to handle the
statistical analysis, i.e., design the experiments, analyze results, fit the response polynomial, and perform Monte Carlo simulation.
Quinao and Zarrouk
4
In this work, the scope was limited to a low-level screening design. A two-level Plackett-Burman experimental design was used to
test six likely key parameters affecting the power capacity of an idealized geothermal model. The reservoir simulation model,
parameters, and probability distribution of parameter uncertainties are based on the model described by Parini and Riedel (2000).
3. CASE STUDY NUMERICAL MODEL OF A GEOTHERMAL GREEN-FIELD
The ED and RSM workflow was applied to provide a probabilistic resource assessment of a green geothermal field described by
Parini and Riedel (2000).
3.1 Objective of the Assessment
The objective of the assessment answers the basic question: What is this model for? The significance of the parameters being
investigated is based on this objective. This assessment aims to identify the key parameters that affect the estimate of the power
capacity of the idealized geothermal resource normalized to 30 years of project life. It also aims to derive a proxy model to the
reservoir simulation in the probabilistic Monte Carlo simulation.
3.2 Likely Key Parameters
Six parameters were investigated out of the ten parameters used in the reference model (Parini and Riedel, 2000): reservoir
temperature, matrix porosity, fracture permeability, average fracture spacing, well feedzone depth, and boundary conditions. The
parameters were chosen mainly based on ease and consistency of manually implementing the parameter changes to the reservoir
simulation models. For example, parameters that change the physical size of the model like areal extent and reservoir thickness
were not selected. Note that the range of parameter values will also limit the results to within the values identified. A reservoir
management team’s experience and expert opinion should ideally guide the range of these values. For this study, the range of
values was adopted from the reference model. The parameters are summarized in Table 1 showing a list of quantitative and
qualitative/categorical variables.
Table 1. Reference model parameters chosen for the Experimental Design.
Parameter
Low
Mid
High
Reservoir Temperature, °C
250
265
280
Matrix porosity
0.05
0.08
0.1
Fracture permeability, mD
10
60
100
Average fracture spacing (3D)
2 (approx. single porosity)
30
100
Well feedzone depth
Shallow (1350 m)
--
Deep (1900 m)
Boundary conditions
Close
--
Open (150°C lateral recharge)
3.3 Experimental Design: Plackett-Burman
A screening design based on the chosen six parameters was implemented. A two-level (high and low) Plackett-Burman design was
chosen to identify the main parameters that affect the response, 30-yr power capacity.
The experimental design generated from Minitab is shown in Figure 4. In the design table, the standard order column is an
experimental design idea to do the experiments in a random order (run order) and avoid run-dependent effects. This is mainly
useful when running physical experiments. In numerical simulation experiments, the run order may not be as important.
From the design table in Figure 4, the first row describes one reservoir simulation model where reservoir temperature is set at the
high setting (+), matrix porosity is set at the high setting (+), fracture permeability is set at the high setting (+), fracture spacing is
set at the low setting (-), well feed zone depths are at the high setting (deep), and boundary condition is set at the high setting
(open). Each row is a reservoir simulation model for a total of 12 model runs. In contrast, a full factorial design at two levels will
require 26 or 64 simulation runs.
Figure 4. Plackett-Burman design for six parameters with a total number of 12 experiments.
3.4 Numerical Simulation Models
3.4.1 Model Description
The numerical simulation models were built using the reference model (Parini and Riedel, 2000) as the basic structure and
Petrasimas the user interface for the TOUGH2 geothermal reservoir simulator. The Equation of State (EOS) module used was
Quinao and Zarrouk
5
EOS1, which is the module for non-isothermal water. A three-dimensional dual-porosity formulation was used with three (3)
multiple interacting continua (MINC) layers. The fracture part of the MINC layers was assigned a volume fraction of 0.05. In the
material properties, fractures were assumed to have 90% porosity. Other generic model details are summarized in Table 2.
Table 2. General model parameters in all the numerical model runs.
Model parameter
Value
Unit
Reservoir volume
10.26
km3
Number of blocks
1440
blocks
Initial reservoir pressure
Psaturation + 10
bars
Rock density
2600
kg/m3
Rock wet heat conductivity
2.2
W/m-C
Rock heat capacity
1
kJ/kg-C
Relative Permeability
Grant’s curves
Residual liquid saturation
0.3
Residual gas saturation
0.05
Capillary pressure function
Linear function
CPmax CP(1)
1.0E6
A CP(2)
0.25
B CP(3)
0.4
Production wells
15
wells
Deep injection wells
5
wells
Total mass production
555
kg/s
Total injection rate
~416
kg/s
Steam usage rate
7
kg/kW
Power capacity years
30
years
3.4.2 Model Geometry
The surface area of the model is 9 km2 (3 km by 3 km) divided into 12 along the x and y model dimensions. The reservoir thickness
is 1.14 km divided into 10 layers with thinner upper layers to capture the two-phase changes. The outermost lateral blocks are thin
blocks used to implement fixed states. There are 1440 blocks in this simple reservoir model. The surface area was divided into four
(4) main regions to represent a development strategy (Figure 5):
1. 20% - A: No drilling/no access, e.g., national park, inaccessible terrain, etc.
2. 50% - B: Production area
3. 20% - C: Production-injection buffer, and
4. 10% - D: Deep injection
Five deep injection wells were used and 15 production wells were distributed around the production area using a 500 m radius well
spacing. The shallow wells tap the reservoir at -350 m above sea level (ASL) while the deep wells tap the reservoir at -900 m ASL.
In the simulation runs that have “open” boundary condition settings, a fixed state at -590 m asl is implemented as thin blocks
around the four lateral sides of the model, providing recharge to the reservoir at 150°C and constant initial reservoir pressure in the
thin blocks.
Figure 5. Model geometry showing the modeled reservoir volume, the production wells in sector B, the injection wells (D),
an injection buffer area (C), and an inaccessible area (A). The surface elevation (not shown) is at 1000 m ASL and the
modeled reservoir thickness is from 100 m ASL down to -1040 m ASL.
A total of 12 numerical models were created based on the ED settings in Figure 4 and the generic model parameters in Table 2.
Once a reservoir simulation model is set-up, it is run to at least 10,000 simulated years to approximate a “natural state,” without
Quinao and Zarrouk
6
production and injection. This is done to let the pressure profile settle to a natural hydrostatic gradient (see Figure 5) and is used as
the initial condition for the production run.
3.4.2 Reservoir Simulation Runs: Limits and Cut-offs
The reservoir simulations were run by equally distributing the total mass production into the 15 wells and 75% of the mass
produced into the 5 deep injection wells. The enthalpy of the re-injected fluid is based on an 8 barg separation pressure adopted
from the reference model (Parini and Riedel, 2000). The simulations were performed until the first production well was unable to
flow. The simulations are therefore a conservative run where it is terminated once the total mass production cannot be support by
all 15 production wells. Once the simulation ends, a script using PyTOUGH is used to efficiently extract the results from the
simulation output file. The generation is estimated using the total steam produced by all the wells at the 8 barg separation pressure
and applying the steam usage rate in Table 2. The total generation is normalized to 30 years and this value is recorded as the
response for that simulation run.
To determine when a well is unable to flow, wellbore simulation runs were done to create the plot of the minimum well bottom-
hole pressure, Pmin, versus discharge enthalpy (Figure 6). The wells modelled have a 13 3/8” production casing and a 10 ¾”
production liner. Initially, a 10 kg/s flow was assumed as the minimum mass flow (Parini and Riedel, 2000) but as shown in Figure
6, the Pmin showed large variations with the pressure drop correlation used. These variations are small at higher flow rates, hence
the decision to increase the assigned well flow from 10 to 37 kg/s at a wellhead pressure of 10 barg.
The evolution of pressure at the well feed zone depth and the changing well discharge enthalpy of the 15 production wells were
compared to the Pmin vs discharge enthalpy line. In Figure 6, a well starts to the right of this line and gradually moves down with
pressure decline and will either track farther to the right as the enthalpy increases or track to the left as it decreases. Either way,
once any of the 15 producers intersects the cut-off line, the total steam produced is calculated only up to that simulation time. At the
moment, this is done in a spread sheet and should ideally be coupled with the reservoir model.
Figure 6. Cut-off based on the minimum bottom-hole pressure required for a well to flow at a certain enthalpy. On the left
plot, the limit for shallow wells is shown by the green diamonds and the limit for deep wells is shown by the green triangles.
On the right, the plot shows a variation in minimum bottom-hole pressure with pressure drop correlation at low mass flow
rates.
3.5 Simulation Results and Fitting a Response Surface Proxy Model
After creating 12 reservoir numerical models, performing the simulations, and calculating the responses (30-year power capacity),
the results are summarized in Table 3.
Table 3. Designed simulation runs and 30-yr power capacity results.
Std
Order
Temperature
Porosity
Permeability
Frac Spacing
Well Depth
Boundary
Power
Capacity, MWe
6
+1
+1
+1
-1
deep
Open
53
11
-1
+1
-1
-1
shallow
Open
65
3
-1
+1
+1
-1
deep
Closed
59
5
1
+1
-1
+1
deep
Closed
129
9
-1
-1
-1
+1
deep
Open
48
7
-1
+1
+1
+1
shallow
Open
213
12
-1
-1
-1
-1
shallow
Closed
39
2
+1
+1
-1
+1
shallow
Closed
125
8
-1
-1
+1
+1
deep
Closed
89
1
+1
-1
+1
-1
shallow
Closed
255
4
+1
-1
+1
+1
shallow
Open
361
10
+1
-1
-1
-1
deep
Open
97
The Plackett-Burman design response was analyzed in Minitab™ to approximate the response surface or the proxy model of the
numerical simulations done. The regression analysis output is shown in Figure 7.
500000 1000000 1500000 2000000 2500000 3000000
0
2000000
4000000
6000000
8000000
10000000
12000000
14000000
16000000
18000000
20000000
0
20
40
60
80
100
120
140
160
180
200
500 1000 1500 2000 2500 3000
Bottomhole pressure, b(a)
Discharge enthalpy, J/kg
Well flow cut-off
Deep Shallow
P5 P12
P1 P3
NCG content: 1% of total mass
0
20
40
60
80
100
120
140
160
180
200
500 1000 1500 2000 2500 3000
Bottomhole pressure, b (a)
Discharge enthalpy, kJ/kg
Deep well
Correlation 1
Correlation 2
Correlation 3
NCG content: 1% of total mass
Quinao and Zarrouk
7
Figure 7. Summary table of the polynomial fit between the response and the parameters.
The reservoir numerical simulations are approximated by a first-order proxy model using all the coded (-1, +1) parameters to
generate the response (Power Capacity). This is shown in Equation 4.
 (4)
where A is reservoir temperature, B is matrix porosity, C is fracture permeability, D is average fracture spacing, E is well feed zone
depth, and F is boundary condition. This means a response may be estimated by replacing the variables with their coded value. The
polynomial coefficients were taken from the “Coef” column in Figure 7. Note that the ED chosen at the start of the analysis,
Plackett-Burman, limits the proxy model to a first-order polynomial because this design analyzes main effects only.
3.6 Analysis of the Main Effects and Response Surface
To screen out the main effects, the p-values (P) in the results table (see Figure 7) were checked to verify the parameters that are
statistically significant. The significance was set at a 95% confidence level so the p-values were compared to α-level of 0.05. All p-
values less than or equal to the α-level are significant while all p-values greater than the α-level are insignificant.
The regression model contained three significant parameters that affect the 30-yr power capacity estimate of the numerical
simulation: (1) well feed zone depth, (2) fracture permeability, and (3) reservoir temperature. The absolute values in the “Effects”
column show the relative strength of a parameter’s effect on the response. Well feed zone depth has the greatest effect (-97.28),
followed by fracture permeability (87.76), and reservoir temperature (84.49). From the sign of the effects, we can additionally infer
that using just deep production wells in the strategy results in lower power capacity, while finding high permeability (100 mD) and
high reservoir temperature (280°C) results in higher power capacity.
Figure 8. Pareto Chart and the Normal Plot of the effects showing the three significant parameters based on a 95%
confidence level (α = 0.05).
Fracture spacing does not meet the 95% interval but, as shown in Figure 7, has a p-value almost close to the required α level
of <0.05. Also, based on their p-values, porosity and boundary conditions are not significant. While α = 0.05 is typical of this type
of analysis, this shows that selecting a lower confidence level, for example α = 0.1, would have included fracture spacing as a
significant parameter and could be employed in such circumstances.
The validity of the regression and of the proxy model is verified by the plots of the residuals shown in Figure 9. The plots show that
the errors are normally distributed and are independent of each other. It should be noted here that numerical simulation experiments
do not have a random error or measurement error (Sacks, et. al., 1989; Myers and Montgomery, 2002) and the error is mainly from
fitting the wrong proxy polynomial or the choice of parameters to include in polynomial fitting.
Quinao and Zarrouk
8
Figure 9. Residual plots showing residuals on a normal plot, residuals and fits, histogram of the residuals, and residuals
versus the order simulations were performed.
3.7 Refitting the Response Surface with Only the Significant Parameters
Keeping the full response equation might be a good idea for the particular purpose of approximating the reservoir simulation
response to the tested parameters (Myers and Montgomery, 2002). Refitting the proxy model to the significant parameters
simplifies the model to the main effects terms. Also, if a more detailed design like CCD or Box-Behnken is required in the analysis,
the workflow suggests applying the design to the significant parameters. A similar issue about keeping the full model or refitting
was discussed by Anderson and Whitcomb (2005). To compare, we refitted the model using only the significant terms, the
response polynomial of coded parameters becomes:
 (5)
3.8 Monte Carlo Simulation on the Reservoir Simulation Proxy Model
To provide a probabilistic resource assessment of the 30-yr power capacity of the system being investigated, we ran a Monte Carlo
simulation using @Risk on the proxy model shown in equations 4 and 5. The probability distributions of the polynomial
variables were applied to the coded low, mid, and high values. Around 100,000 iterations were done, randomly sampling the
probability distribution functions of the parameters. The result is a probability distribution function of the power capacity covering
the full range of possible outcomes.
Using both the refitted (Equation 5) and the full proxy model (Equation 4), the cumulative distribution function for the 30-year
power capacity of the resource is shown in Figure 10. Note that the P50 values are almost the same while the power capacity range,
standard deviation, is larger when more factors are included in the proxy model and smaller when refitted to the significant few.
Figure 10. Cumulative distribution functions with P10, P50, and P90 indicated.
100500-50-100
99
90
50
10
1
Residual
Percent
3002001000
100
50
0
-50
Fitted Value
Residual
806040200-20-40-60
4
3
2
1
0
Residual
Frequency
16151413121110987654321
100
50
0
-50
Observation Order
Residual
Normal Probability Plot Versus Fits
Histogram Versus Order
Residual Plots for MW@30yr
Quinao and Zarrouk
9
4. DISCUSSION
The concept of approximating the reservoir simulation runs with response surface models and the proxy models’ ability to provide
a probabilistic resource assessment has been demonstrated. The main strengths of the methodology are as follows:
Recorded simultaneous parameter variations to generate the different reservoir simulation models;
Use of proxy polynomial that approximates the reservoir simulation runs in probabilistic Monte Carlo analysis;
4.1 Choice of Experimental Design
The choice and the implementation of an experimental design type is an important decision. In this work, Plackett-Burman, a
screening design, was chosen to approximate the response surface because it was commonly used in literature as a simple design to
implement and was viewed as a good starting point in exploring this technique. Due to the characteristics of this design, it is useful
for identifying significant main effects but not significant interactions between parameters as shown by the lack of interaction
variables in the full proxy model in equation 4. In future assessments, experimental designs appropriate to geothermal numerical
simulations will be explored. For example, a screening design that analyzes interactions, e.g., fractional factorial designs, may be
tested (Amudo, et al., 2008).
A center point was added into the set of 12 Plackett-Burman simulation runs to test the effect of adding mid-value runs to this
design. Due to the two categorical parameters, well feed zone depth and boundary conditions, the center point run ended up being
four additional simulation runs. The full proxy model coefficients were different but the statistically significant parameters were the
same. In addition, a curvature parameter and a lack-of-fit parameter were found to be insignificant. The probabilistic responses
plotted with the original results are shown in Figure 11.
Figure 11. Cumulative distribution functions of the response with the PB design + center points.
4.2 The Tested Parameters and the Significant Few
The design table provides a list of the required parameter settings for all the simulation runs done, making it independently
verifiable. With a pre-determined pattern by which the parameter settings will be combined, the resource assessment team’s focus
shifts to the list of likely parameters and the uncertainty in each parameter. The choice to do six parameters out of 10 in the
Parini and Riedel (2000) reference model was based on ease in building the simulation models and not through a rigorous
uncertainty framing exercise. While there may be hundreds of uncertain parameters in a geothermal green-field, the final list of
parameters that are built into the ED and RSM workflow should be determined by an integrated team of experts that will narrow
down the list based on the objective of the assessment, e.g., power capacity, total years of production for a X-MW
development, etc.
It was also observed that a parameter’s range size may influence its significance in the model approximation process. This work did
not have the freedom to set the parameter uncertainty ranges because these values were adopted from the reference model. Fracture
spacing, the fourth parameter with the strongest effect on the response, will possibly be significant if the high setting of the
uncertainty range was investigated up to 300 m. However, parameters with very strong effects on the response were still found
significant even within a narrow range of parameter values (reservoir temperature at 250-280°C) while parameters with very weak
effects on the response were still insignificant even with a wide range of investigated values (boundary conditions at fully closed
and fully open).
The three parameters that were found to be significantly affecting the 30-yr power capacity of the reservoir model being assessed
make good sense. When evaluating the size of a geothermal development, the usual questions to answer are: (1) How hot is the
resource? (2) Is there enough permeability for the geothermal fluid to flow? (3) How can we bring the fluid to the surface?
Quinao and Zarrouk
10
4.3 The Proxy Models and the Volumetric Stored-heat/Mass in Place
The probabilistic resource assessment based on ED and RSM proxy models were compared with the probabilistic resource
assessments based on volumetric stored heat and combined volumetric/numerical simulation methods. The parameters that were
varied were limited to the parameters chosen in the ED and RSM workflow, i.e., reservoir area and thickness were kept constant.
Table 4. Parameters used in the volumetric stored heat and the volumetric/numerical simulation probabilistic analyses.
Parameters
Low
Mid
High
Distribution
Common to both
Area, km2
--
9
--
N.A.
Thickness, km
--
1.14
--
N.A.
Average porosity
0.05
0.08
0.1
Triangular
Reservoir Temperature, °C
250
265
280
Triangular
Reject Temperature, °C
--
175.36
--
N.A.
Rock heat capacity, J/kg
--
1000
--
N.A.
Rock density, kg/m3
--
2600
--
N.A.
Plant load factor
--
0.85
--
N.A.
Project life, years
--
30
--
N.A.
Stored
heat
Recovery factor, stored-heat1
0.1
0.15
0.5
Triangular
Conv. efficiency (stored heat)2
--
0.12
--
N.A.
Vol/
numerical
Recovery factor,
(volumetric/numerical)3
0.205
0.468
0.75
Triangular
Steam usage rate, kg steam/kW
--
7.5
--
N.A.
1The stored heat recovery factor parameter range was based on the review done by Zarrouk and Simiyu (2013). 2Conversion
efficiency is based on review by Zarrouk and Moon (2013). 3Mass in place recovery factor was parameterized by Parini and
Riedel (2000) but no proxy polynomial was published so this range was estimated from the main effects plot between parameters
and % recovery.
The results of the different probabilistic resource assessments are shown in Figure 12.
Figure 12. ED and RSM, stored heat, and volumetric/numerical cumulative distribution functions.
The comparison showed in Figure 12 should be limited to a simple illustration of the different probabilistic assessment results and
how similar methods(1) volumetric stored heat with volumetric/numerical simulation and (2) ED/RSM proxy model and
volumetric/numerical simulationresult in different estimates due to different assumptions in the methodologies. The volumetric
stored heat had the lowest power capacity range due to the lower range of thermal recovery factors and is probably due to the lower
conversion efficiency used. The other two methods have recharge components providing them access to a larger fluid volume.
Although the ED and RSM proxy model was based on the volumetric and numerical simulation model, the implementations of the
numerical simulations were different. The simplification done by estimating the mass in place recovery factors from the published
main effects plots (Parini and Riedel, 2000) and assigning a triangular probability distribution to the parameter was a large
assumption.
Quinao and Zarrouk
11
5. CONCLUSION
A probabilistic resource assessment methodology based on numerical simulations was demonstrated using an experimental design
and response surface method (ED and RSM) workflow. The strength of the workflow lies in the experimental design’s ability to be
independently verified because the parameter settings and combinations are recorded in the design table. The response surface or
proxy model is a good approximation of the relationship between the response and the tested parameters generated from reservoir
numerical simulations. There are existing commercial software packages that can be used to implement the ED workflow in
geothermal reservoir simulation though the process is still manual and inefficient. In this scenario, resource assessment specialists
can focus more on refining the list of parameters and the range and distribution of parameter uncertainties because the design
pattern is available.
6. NEXT PHASE
In the next stage of the study the ED and RSM workflow will be improved and tested on a large numerical model of a geothermal
green-field and will transition out of the commercial software packages into available open-source codes. Appropriate experimental
designs will be explored. A response surface method (RSM) experimental design, with quadratic proxy models, will be tested to
evaluate the possible optimization of controllable parameters e.g. the impact of well depths and the impact of well spacing. Also, a
more efficient way of implementing the workflow, e.g., building the numerical simulation runs through PyTOUGH
(O’Sullivan et al., 2013), will be explored.
7. ACKNOWLEDGMENT
The authors would like to thank Mighty River Power Ltd. for supporting the work and allowing us full use of software licenses
during this part of the study. The authors would also like to thank Lutfhie Sirad-Azwar for valuable discussions on process
modeling and Peter Franz for invaluable assistance with PyTOUGH.
REFERENCES
Acuña, J., Parini, M., and Urmeneta, N.: Using a Large Reservoir Model in the Probabilistic Assessment of Field Management
Studies, Proceedings, 27th Workshop on Geothermal Reservoir Engineering, Stanford University, Stanford, CA (2002).
Amudo, C., Graf, T., Dandekar, R., and Randle, J.M.: The Pains and Gains of Experimental Design and Response Surface
Applications in Reservoir Simulation Studies, paper SPE 118709, presented at the 2009 SPE Reservoir Simulation
Symposium, The Woodlands, Texas, February 2-4.
Anderson, M., and Whitcomb, P.: DOE Simplified: Practical Tools for Effective Experimentation, Productivity, Inc., Portland
(2000).
Anderson, M., and Whitcomb, P.: RSM Simplified: Optimizing Processes Using Response Surface Methods for Design of
Experiments, Productivity, Inc., New York (2005).
Atkinson, P.: Proved Geothermal Reserves Framework and Methodology, Proceedings, New Zealand Geothermal Workshop,
Auckland (2012).
Australian Geothermal Reporting Code Committee (AGRCC): Geothermal Lexicon for Resources and Reserves Definition and
Reporting, 2nd ed., Adelaide (2010).
Clearwater, J., Burnell, J., and Sirad-Azwar, L.: Modelling the Ngatamariki Geothermal System, Proceedings, New Zealand
Geothermal Workshop, Auckland (2011).
Croucher, A.: PyTOUGH: A Python Scripting Library for Automating TOUGH2 Simulations, Proceedings, New Zealand
Geothermal Workshop, Auckland (2011).
Damsleth, E., Hage, A., and Volden, R.: Maximum Information at Minimum Cost: A North Sea Field Development Study With an
Experimental Design, JPT, (December 1992), 1350-1356.
Friedmann, F., Chawathé, A., and Larue, D.K.: Assessing Uncertainty in Channelized Reservoirs Using Experimental Designs, SPE
Reservoir Evaluation and Engineering (August 2003), 264-274.
Garg, S.: Appropriate Use of the USGS Volumetric “Heat In Place” Method and Monte Carlo Calculations, Proceedings, 35th
Workshop on Geothermal Reservoir Engineering, Stanford University, Stanford, CA (2010).
Garg, S., and Combs, J.: A Reexamination of USGS Volumetric “Heat In Place” Method, Proceedings, 36th Workshop on
Geothermal Reservoir Engineering, Stanford University, Stanford, CA (2011).
Grant, M., and Mahon, T.: A Probabilistic Approach to Field Proving and Station Sizing, Geothermal Resources Council
Transactions, 19, (1995).
Grant, M.: Geothermal Resource Proving Criteria, Proceedings, World Geothermal Congress, Kyushu-Tohoku (2000).
Hoang, V., Alamsyah, O., and Roberts, J.: Darajat Geothermal Field Performance-A Probabilistic Forecast, Proceedings, World
Geothermal Congress, Antalya (2005).
Myers, R., and Montgomery, D.: Response Surface Methodology-Process and Product Optimization Using Designed Experiments,
2nd ed., John Wiley & Sons, Inc., New York City (2002).
Onur, M., Sarak, H., and Türeyen, İ.: Probabilistic Resource Estimation of Stored and Recoverable Thermal Energy for Geothermal
Systems by Volumetric Methods, Proceedings, World Geothermal Congress, Bali (2010).
Quinao and Zarrouk
12
O'Sullivan, J., Dempsey, D., Croucher, A.E., Yeh, A. and O'Sullivan, M.J.: Controlling Complex Geothermal Simulations Using
PyTOUGH, Proceedings, 38th Workshop on Geothermal Reservoir Engineering, Stanford University, Stanford, CA (2013).
Parini, M., Pisani, P., Monterrosa, M.: Resource Assessment at the Berlin Geothermal Field (El Salvador), Proceedings, World
Geothermal Congress, Firenze (1995).
Parini, M., and Riedel, K.: Combining Probabilistic Volumetric and Numerical Simulation Approaches to Improve Estimates of
Geothermal Resource Capacity, Proceedings, World Geothermal Congress, Kyushu-Tohoku (2000).
Pruess, K., Oldenburg, C., and Moridis, G.: TOUGH2 User’s Guide, Version 2.0, Report LBNL-43134, Lawrence Berkeley
National Laboratory, University of California, Berkeley, CA (1999).
R Core Team: R: A Language and Environment for Statistical Computing. R Foundation for Statistical Computing, Vienna, ISBN
3-900051-07-0, http://www.R-project.org/ (2013).
Sacks, J., Schiller, S., and Welch, W.: Design for Computer Experiments, Technometrics, 31, (February 1989) 41-47.
Sanyal, S., and Sarmiento, Z.: Booking Geothermal Energy Reserves. GRC Transactions, 29, (2005) 467-474.
Walpole, R., Myers, R., Myers, S., Ye, K.: Probability & Statistics for Engineers and Scientists, 9th ed., Prentice Hall, Boston
(2012).
White, C., and Royer, S.: Experimental Design as Framework for Reservoir Studies, paper SPE 79676, presented at the 2003 SPE
Reservoir Simulation Symposium, Houston, February 2-5.
Williams, C.., Reed, M., and Mariner, R.: A Review of the Methods Applied by the U.S. Geological Survey in the Assessment of
Identified Geothermal Resources, U.S. Geological Survey Open-File Report 2008-1296, 27p. (2008).
Yeten, B., Castellini, A., Guyaguler, B., and Chen, W.H.: A Comparison on Experimental Design and Response Surface
Methodologies, paper SPE 93347, presented at the 2005 SPE Reservoir Simulation Symposium, Houston, January 31
February 2.
Zarrouk, S., and Moon, H.: Efficiency of Geothermal Power Plants: A worldwide review, Geothermics, 51, (2013) 142-153.
Zarrouk, S., and Simiyu, F.: A Review of Geothermal Resource Estimation Methodology, Proceedings, New Zealand Geothermal
Workshop, Rotorua (2013).
... A residual graph was used to verify the effectiveness of the regression model (Quinao and Zarrouk, 2014). The polynomial model was evaluated based on the goodness of fit. ...
Article
Full-text available
It is crucial for financial providers, investment groups, resource developers, and exploration companies to rate new geothermal projects in terms of resources and reserves. In general, the existing volumetric method is constrained by limited information when projects are at the early stage of development. The main objective of this study is to estimate the probabilistic potential thermal energy of the M research area in the Maichen Sag, a geothermal prospect in South China, through stochastic methodologies. The probabilistic assessment methodology provides a way to embody the uncertainty and risk in geothermal projects and to quantify the power potential in a probable range. In this study, proxy numerical models were built by combining the Experimental Design (ED) and Response Surface Methodology (RSM) with the Monte Carlo Simulation technique. An improved workflow for combined ED-RSM that uses two-level Full Factorial and Box–Behnken designs was proposed. For comparative analysis, the typical volumetric technique was also implemented in this study. The ED-RSM results show that the M area has P10, P50, and P90 reserves of 5.7 × 1014 J, 5.3 × 1014 J, and 5 × 1014 J, respectively, and these numbers from the typical volumetric method are 1.5 × 1015 J, 9 × 1014 J, and 5.1 × 1014 J, respectively. In this study, the operability, applicability, and accessibility of ED-RSM in the assessment of geothermal potential and its ability to provide a reliable output are demonstrated.
... The stochastic method had been utilized in quantifying the uncertainty of subsurface properties [7]. Application of experimental design and response surface method was established in a preliminary result of geothermal resource assessment [8]. The location of a wellbore in the geothermal area had been optimized by experimental design [9]. ...
Article
Full-text available
The number of geothermal wells (production, injection, make-up) should be calculated carefully to get the optimum values for the technical aspect of power plant development. However, the method for calculating the number of wells has been used is a deterministic approach that involves only a single value for every parameter. Since the result of this method is a single value, it cannot capture the uncertainties of the field parameters. Therefore, this paper proposed the newest method that applied 2-level full factorial design of experiment approach with the help from Minitab software to cover the uncertainties of the field parameters and to produce the probabilistic number of wells in combination with Monte Carlo Simulation. The proposed method has been successfully used to calculate the number of wells in the case study of Karaha-Talaga Bodas field. Based on the study, the most significant factors for determining the number of production and injection wells are the fluid enthalpy and total mass flow rate, whereas for the make-up wells number are the decline rate and make-up well capacity. 5 production wells, 1 injection well, and 4 make-up wells are the minimum requirement number of wells that should be drilled for generating 30 MW power plant capacity in 30 years.
... Resource assessment using a numerical model coupled with the heat stored method has been done by several researchers [5,6,7,8,9,10]. On the other side, experimental design has been done by numerous researchers [11,12,13,4]. Both methods used widely to determine the resources of the geothermal field. ...
Article
Full-text available
A successful geothermal field size assessment requires integrative data analysis of all aspects to determine the optimum capacity to be installed. Nowadays, numerical simulation becomes a powerful tool in a geothermal resource assessment process. However, this method involves significant uncertainty of subsurface information as an input. Then a study of resource assessment methods, such as heat stored and experimental design, needs inputs coming from the result/output of reservoir numerical. The calculation of both methods based on a range of reservoir parameter values can be carried out using stochastic methods (Monte Carlo Simulation). It applies a probabilistic method of resource assessment to capture uncertainties. A sophisticated numerical reservoir model of Ciwidey-Patuha Geothermal Field, West Java-Indonesia in the natural state condition was used as a case study to determine the generating potential of the reservoir.
... This method is commonly used for resource assessment in the oil and gas industries [3], yet there are still very few applications in the geothermal industry and stimulation methods. Although there are authors starting to use this method for resource assessment in geothermal fields such as Quinao and Zarrouk [4], Riswan [5] and Quinao and Zarrouk [6]. In this study, the experimental design will be applied to assess the uncertainty parameters of hydraulic fracturing stimulation in a water-dominated reservoir where in this case, Wairakei geothermal field. ...
... During the simplest simulation, used in this work, each factor has two levels -low and high ones. These experimental simulations belong to a group of designs known as 2 í µí±˜ factorial experiments (designs), where í µí±˜ is the number of parameters being studied (Quinao & Zarrouk, 2014). The full factorial design provides for the taking into account of all combinations of factors at levels studied, creating 2 í µí±˜ combinations of factorial design conditions and is (Walpole, Myers, Myers, & Ye, 2012). ...
Article
Uncertainty quantification of power (MWe) prediction from a geothermal numerical model is time-consuming. Existing techniques and workflows are still being tested. Our study focuses on using the Experimental Design (ED) and Response Surface Methodology (RSM) framework as an alternative method to facilitate probabilistic MWe estimation. This study involves two types of Experimental Design: the two-level Full Factorial and Plackett Burman, and the investigation is divided into two parts. The first part investigated the difference in the prediction of the Wairakei geothermal field power potential using the polynomial model built from the 64 simulation runs based on the two-level Full Factorial design and the 12 simulation runs based on the Plackett-Burman configuration. The second section compared the MWe predictions using the Plackett-Burman design and the volumetric stored heat method. The simulated MWe potential of Wairakei for 50 years is comparable for both the two-level Full Factorial and Plackett-Burman designs, indicating the latter as a practical design for building a proxy model of a numerical model. Furthermore, the MWe prediction of the polynomial model created based on the ED Framework closely resembles the actual production capacity of Wairakei compared to the volumetric stored heat method. The results based on the proxy modelling further indicate that the 353 MWe production generation could be sustainable at least for another 40 years. https://authors.elsevier.com/c/1f3GZ1LQRpx6uZ
Article
Estimating power potential (MWe) with higher accuracy remains a necessity and a challenge confronting the geothermal industry. Reservoir models can predict MWe capacity probabilistically for resource management and decision-making use, but the process remains laborious to implement. This work involves applying the Experimental Design (ED) and Response Surface Methodology (RSM) framework to a calibrated natural-state reservoir model for predicting MWe probabilistically, quantifying uncertainties in the prediction and identifying the key driving factors. This study has chosen six uncertain parameters and implemented the Plackett-Burman design to build twelve versions of the Leyte reservoir model for uncertainty quantification. These uncertain parameters are permeability in the x, y and z-direction, porosity, reinjection enthalpy (RI Enthalpy), and the fraction of reinjection (% RI). Results revealed that all of these parameters except RI Enthalpy are significant predictors of MWe and that the Leyte Geothermal Production Field (LGPF) has an indicative capacity of 670 MWe (P90), 730 MWe (P50) and 790 MWe (P10) if it operates for 50 years. https://authors.elsevier.com/c/1ezSp1LQRpx6sH
Article
Full-text available
Modeling reserves of geothermal reservoirs in Gujarat and Maharashtra in India are in nascent stage. Prognosis of reserve estimate for these shallow prospects is attempted for the irst time. Genetic-based Monte Carlo Modeling was used to carry out the systematic investigation. Input parameters required for the model are area of the thermal reservoir, speciic heat of the rock, speciic heat of reservoir water and average annual surface temperature. Range of values for each parameter were collected using geophysical and logging surveys. Gravity and Magnetic surveys were utilized to have a range of values for prospect closure area, porosity logs were utilized for porosity ranges for reservoirs. Temperature probes were carried out in 19 locations, 17 in Gujarat and 2 in Maharashtra. Speciic heat of water was collected from the reports of abandoned hydrocarbon wells. The distribution of values for each parameter was found to be triangular or log normal. The modeling algorithm then deined a relationship between input and output parameters. Genetic-based steps such as random population creation, encoding, crossover, mutations and decoding were performed to assign probability to likely outcome of reserve. The last step of the model involved analyzing the results of the calculation and providing a probability distribution function for each result. Heat capacities of places like Shirdi, Saputara and Harsani were found to be highly encouraging.
Article
Numerical reservoir modelling is the most reliable geothermal resource assessment tool for quantifying power production at a sustainable level, but it does not mesh well with the Monte Carlo method for quantifying uncertainties. Building proxy numerical models using Experimental Design (ED) and Response Surface Methodology (RSM) workflows may provide a solution. The present study attempts to improve existing approaches through the use of the two-level and three-level Full Factorial and Box-Behnken designs. The improved workflow yields consistent results for both the Ohaaki and Rotorua geothermal fields suggesting that probabilistic MWe output distribution is between P90 to P10 of the widely used volumetric method. https://authors.elsevier.com/c/1bP7q1LQRpqe7E
Conference Paper
Full-text available
Resource assessment plays an important role in the financing, development and operation of a geothermal power project. There are several simple (volumetric and areal) resource assessment methods used in the industry to quantify the resource potential predominantly of green field projects. On the other hand, a more complicated numerical representation of geothermal reservoirs is used to model dynamic changes in the field and make predictions of future capacity. However, there is a need to develop a more robust approach with a lower level of uncertainty in the predictions compared to the existing techniques. A hybrid approach of response surface methodology and reservoir simulation provides an alternative method for probabilistic resource assessments. A probability distribution of production potential is generated by first determining the significant reservoir model parameters using Experimental Design (ED). A Box-Behnken response surface model design is then applied to determine the number of simulation runs required to run the experiment at three parameter levels (low, medium and high). The power potential calculated from the reservoir model runs is then used to create a polynomial (proxy) model and a Monte Carlo simulation is then applied to the proxy model to generate a probabilistic distribution of the potential power output. The method was tested successfully to the calibrated natural state model of the Rotorua Geothermal Field. At a 95% confidence interval, the model shows that the Rotorua geothermal system has an average potential to produce: P10 between 148 and 153 MWe, P50 between 147 and 153 MWe and P90 between 146 and 151 MWe for at least 30 years. This approach offers a new perspective on geothermal resource assessment, highlights the importance of developing numerical models even for a geothermal prospect at the early due diligence stage and provides a systematic way of handling the uncertain reservoir model parameters.
Article
Full-text available
Performance forecasts can either significantly overestimate or underestimate a subsurface resource capacity due to uncertainties associated with the collected data and the evaluation process. We applied a process developed around the Experiment Design methodology to capture relevant uncertainties existing in the Darajat's field static model construction, the dynamic simulation model building, calibration, and forecasting. This process systematically identifies, ranks, and quantifies key parameters affecting field performance. It generates a full range of probabilistic field generating capacity distributions that can provide a better platform for the economic evaluations, development planning, and decision making than relying on a single deterministic projection. The ranking of the reservoir and geologic parameters' uncertainty and the projected performance distribution provide a framework for the field operator to explore different expansion alternatives as well as to develop an effective risk management plan to mitigate the potential shortfalls.
Article
Full-text available
The great expansion of geothermal development, and in the number of geothermal developers, during the 1990s, led to the need to formally define geothermal reserves. Such definition occurs at a project milestone, such as bank finance approval, or to enable an oil company to add reserves to its assets, or when a project is sold; as well as the more obvious traditional need to size a power station. At the same time technology and experience has grown rapidly. The development of reservoir simulation has been spurred by both software development and practical experience. It is now the case that reservoir simulation provides in most cases a reliable and proven technology for resource assessment, and is clearly superior to lumped-parameter estimates such as stored heat, and the cost of reservoir simulation is now reasonable. The superiority is so clear that it is difficult to justify the use of any other method to provide an estimate to the reserves available from a geothermal resource. Possible exceptions include small projects using only part of a resource.
Book
RSM Simplified keeps formulas to a minimum and makes liberal use of figures, charts, graphs and checklists. It offers many relevant examples, with amusing sidebars and do-it-yourself exercises that will lead readers to the peak potential for their product quality and process efficiency. The authors, Mark J. Anderson and Patrick J. Whitcomb, are principals of Stat-Ease, a provider of DOE training, consulting, and software. They both are professional chemical engineers. Anderson has more of a business background while Whitcomb specializes in statistics. Incorporated into this book is the more advanced Design-Expert, version 7 software for Windows, with a 180-day trial, so the reader can do the complex statistical computations, generate the necessary graphics (2D and 3D maps) and perform the numerical optimization.
Article
For the probabilistic assessment of exploitation strategies of a geothermal reservoir, alternative numerical simulation models are constructed (most likely, pessimistic and optimistic), in order to represent the uncertainty range of key reservoir properties affecting field performance. While each of these models is calibrated to the initial state and field historical behavior, they significantly diverge in the prediction of future reservoir performance. The entire set of models is used to evaluate some exploitation strategies. However, some uncertain parameters, although not directly related to reservoir properties, can also affect to some extent overall field behavior. Therefore a complete coupling of the reservoir simulation models with a probabilistic evaluation would lead to an unreasonably high number of model runs, making it computationally impractical. To overcome this problem, polynomial approximation functions have been developed for the predicted reservoir performance, based on specially designed model runs and on the recognized relationship between well deliverability and cumulative steam production. The polynomial expressions are incorporated into a complex economic model that allows the combined evaluation of the complete range of uncertainties potentially affecting a given project, without the need of specific, time consuming reservoir modeling runs.
Article
Confidence in estimates of geothermal resource electricity generation capacity can be improved by a probabilistic approach that combines numerical reservoir simulation with the classic volumetric estimation based on fluid mass in place. A simplified reservoir simulation model is used to examine the sensitivity of resource performance to changes in the assumptions concerning key reservoir parameters. In particular, this process establishes the expected variability of the volumetric recovery factor with respect to the likely variations in resource thermodynamic and hydraulic characteristics. Recovery factor is defined as the fraction of fluid in place that can be produced as usable steam over the life of the project. In typical volumetric estimates, the recovery factor is treated as an independent variable and is chosen somewhat arbitrarily based on experience with other geothermal fields. The important innovation in this method is a more systematic approach establishing the dependence of recovery factor on certain key reservoir parameters. Probability distributions are assigned to account for the uncertainty in reservoir parameters that affect recovery factor and the volumetric estimation of fluid mass in place. Monte Carlo simulation is then used to assess the probability of occurrence of a given electricity generating capacity based on steam recovery and mass in place. This approach treats recovery factor as a dependent variable. The outcome of this capacity estimation is therefore explicitly linked to the key thermodynamic and hydraulic characteristics of the resource and to their uncertainty level, rather than to volumetric parameters alone. This method is particularly suited to capacity estimates in the early exploration stages of a geothermal prospect, when only a few deep wells have been drilled and numerical reservoir simulation is not well constrained. It provides a more coherent approach to the estimation of both proven reserves and upside potential, with both being defined in terms of the required confidence level needed for making investment decisions.