ArticlePDF Available

Abstract and Figures

The effect of the construction of the 4th subway line of Budapest (Metro4) on the potential surfaces of the gravity field has been investigated from the aspects of monitoring vertical deformation. In the study mass loss due to the excavation of the two tunnels and of the stations has been considered. Practically, the effect of the mass loss on leveling measurements was determined at a level 1 m above the ground, roughly simulating common instrument heights. The indirect effect of the actual deformations of the physical surface on the leveling was not considered, so in the investigation a rigid Earth has been assumed. In the study, different arrangements of the leveling lines and of the excavations were examined, furthermore, the steepness of the leveling line and the density of the leveling points were analyzed. According to the results, under certain arrangements of the leveling line, the effect can reach the 0.05 mm order of magnitude, which is equivalent to the accuracy of the precise leveling.
Content may be subject to copyright.
Ŕ periodica polytechnica
Civil Engineering
58/2 (2014) 131136
doi: 10.3311/PPci.7489
http://periodicapolytechnica.org/ci
Creative Commons Attribution
RESEARCH ARTICLE
Variations of the gravity field due to
excavations of the Budapest Metro4
subway line
Csaba Éget˝
o/Nikolett Rehány /Lóránt Földváry
Received 2013-04-25, revised 2013-06-10, accepted 2013-07-11
Abstract
The eect of the construction of the 4th subway line of Bu-
dapest (Metro4) on the potential surfaces of the gravity field has
been investigated from the aspects of monitoring vertical defor-
mation. In the study mass loss due to the excavation of the two
tunnels and of the stations has been considered. Practically, the
eect of the mass loss on leveling measurements was determined
at a level 1m above the ground, roughly simulating common in-
strument heights. The indirect eect of the actual deformations
of the physical surface on the leveling was not considered, so in
the investigation a rigid Earth has been assumed. In the study,
dierent arrangements of the leveling lines and of the excava-
tions were examined, furthermore, the steepness of the leveling
line and the density of the leveling points were analyzed. Ac-
cording to the results, under certain arrangements of the level-
ing line, the eect can reach the 0.05mm order of magnitude,
which is equivalent to the accuracy of the precise leveling.
Keywords
temporal variations of gravity ·deformation of potential sur-
faces ·precise leveling ·virtual veritcal motion ·prism mod-
elling
Csaba Éget˝
o
Department of Geodesy and Surveying, Budapest University of Technology and
Economics, uegyetem rkp. 3., H-1111 Budapest, Hungary
e-mail: ecsaba@agt.bme.hu
Nikolett Rehány
Faculty of Civil Engineering, Budapest University of Technology and
Economics, uegyetem rkp. 3., H-1111 Budapest, Hungary
Lóránt Földváry
Department of Geodesy and Surveying, Budapest University of Technology and
Economics, uegyetem rkp. 3., H-1111 Budapest, Hungary
1 Introduction
Temporal variations of gravity field are of central interest in
geodesy and geophysics, since it reflects the mass redistributions
on the surface and within the planet Earth, providing a unique
tool for investigating its interior [14], [8]. Nowadays there is
an urge of such analyses in global and regional scales due to
the obvious signs of a climate change [11]. The state-of-the-
art gravity satellites turn to be very ecient tools for that [9],
[16], [12], [10]. As the knowledge of the temporal gravity in
global and regional scales improves notably, there is a demand
for the local gravity variations as well, since satellites are in-
sensitive for the temporal varying gravity in local scales. Thus,
it can only be determined independently by terrestrial measure-
ment techniques e.g. [3] to provide the short frequency part of
the spatial wavelength spectrum [15].
In the present study temporal variation of a local gravity fea-
ture due to a technogenic mass redistribution eect is modeled
and analyzed. In case of a huge industrial project, notable redis-
tribution of soil occurs due to the earthworks. It does aect the
gravity field [1]. As so, it also has an eect on the local hori-
zontal and vertical directions. As surveying instruments are set
up with respect to the horizontal or vertical, it does aect the ac-
companying surveying measurements. In the present study cer-
tain geodetic aspects of an actual surveying engineering applica-
tion is considered. The excavation of various layers of soil dur-
ing the construction of the new subway line of Budapest, Metro4
is investigated from the aspect of its eect on the simultaneously
performed vertical deformation measurements.
2 Theoretical Background and Formulation
2.1 The classical formulae of modelling
In case of excavating tunnels, deformations on the surface are
expected to be accompanied. Furthermore, the removal of a no-
table amount of soil changes the structure of the gravity field
too. Therefore, observed height variation, dH consists of two
components [1], [13]:
dh =dH +dN (1)
Variations of the gravity field due to excavations of the Budapest Metro4 subway line 1312014 58 2
where dh refers to the actual surface deformation, and dN is
change of the geoid undulation due to the mass loss. (Generally,
in this study the dierential symbol, drefers to change in time
and not in space.) The change of the geoid undulation does af-
fect the height measurements, but has no eect on the neighbor-
ing structures, buildings. Such a height dierence involved to
the geometrical leveling is rather the consequence of theoretical
looseness than actual vertical displacement, thus the confusion
of the two should be avoided.
Change of the geoid undulation by time, dN in Eq. (1) is usu-
ally interpreted as (cf. [2] and [17]):
dN =R
4πgZ Z dg ·S(ψ)dσ+R
4πgZ Z 2g
Rdh ·S(ψ)dσ
(2)
The terms on the right hand side of Eq. (2) refers to two inde-
pendent sources of mass variations:
1 deformation of the equipotential surface due to the mass loss
corresponding to the tunnelling,
2 deformation of the equipotential surface due to the actual ver-
tical displacement of the physical surface.
For every infinitely small area, dσ=cosϕdϕdλthe spherical
distance from the point of interest, Pis computed as
cosψ=cosθcosθP+sinθsinθPcos(λλP) (3)
Eq. (2) describes the temporal variation of geoid undulation as
a function of that of the gravity anomaly, dg, weighted by the
Stokes function, S(ψ). Considering a mass anomaly model, dm
as known input data, Eq. (2) can be solved by using the Newto-
nian gravitational law,
dg =kZdm
r2(4)
A more direct approach to obtain temporal variations of geoid
undulation from a mass variation model is to derive geoid un-
dulation variations from Newtonian potential using the Bruns’
equation.
dN =1
˜γkZdm
r(5)
In Eq. (5) ˜γrefers to the mean normal gravity between the point
and the reference ellipsoid along the plumb line. Note that
Eq. (5) is analogue with the first term of the right hand side of
Eq. (2).
In the followings a single height dierence between stations A
and Bwith repeated levelling measurements performed at time
tand t1is considered (c.f. Fig. 1). Temporal variation of geoid
undulation between the two stations can be defined as the dier-
ence of the temporal changes in each point
dNAB =dNB(t1t0)dNA(t1t0) (6)
The measured vertical displacement is interpreted as temporal
change of the height dierence
dHAB =HAB (t1)HAB (t0)(7)
Fig. 1. Visualization of the apperent vertical displacements due to the tem-
poral variation of gravity field
Then the relationship between change of geoid undulation and
observed vertical displacement can be derived from equations
above as follows (c.f. equation 212.5 of [1], on page 31):
dHAB =dNAB
˜gB(t1)˜gB(t0)
˜gB(t1)HAB (t0).(8)
In Eq. (8) ˜gBrefers to the mean gravity between levels of Aand
Balong the plumb line through point B. This is approximately
equal to the gravity at the half of the HAB height dierence.
2.2 Elaborating the formulation
In the present case, height of the benchmarks on the test re-
gion is available after the tunneling, after the excavation has
been performed. However, according to [1], HAB (t0)in Eq. (8)
refers to the original height dierence, before the deformation
takes place. As so, a modified version of Eq. (8) is derived:
dHAB =dNAB
˜gB(t1)˜gB(t0)
˜gB(t1)(HAB (t1)+dNAB)(9)
For details of the derivation see [5].
In the present study eect of the excavation on the level sur-
faces was estimated based on equations Eq. (5)- Eq. (9)). The
integral of equation Eq. (5) was approximated by a summation
over mass elements. A preceding study has already been pre-
sented by [4], where the non-deformational eects due to the
tunneling were investigated in a regular grid, and not along lev-
eling lines as it is to be presented here. In this study the eect of
the actual surface deformation on the gravity field, i.e. second
term of the right hand side of Eq. (2) has been neglected. The
eect due to actual surface deformations has been analyzed and
discussed by [6].
3 Data and Calculations
The calculations have made use of the following available
data:
1 longitudinal sections and cross sections of the tunnels pro-
vided by the DBR Metro Project Directorate
2 soil density along the tunnels provided by the Geovil Ltd
3 gravity anomaly data in the vicinity of the tunnels provided
by the Hungarian Geological and Geophysical Institute
Per. Pol. Civil Eng.132 Csaba Éget˝o /Nikolett Rehány /Lóránt Földváry
4 horizontal trace of the leveling lines provided by the Consor-
tium of the Soldata Ltd and Hungeod Ltd
The top view of the tunnels and the location of the surrounding
gravimetric data are displayed on Fig. 2. The used coordinates
are the local stereographic coordinates (BÖV, equivalent to Bu-
dapest Municipal Projection system).
Fig. 2. The tunnel (solid black line interrupted at the stations) and the gravi-
metric points (grey stars) with main structures of Budapest in the background.
The axis are local stereographic coordinates in m.
First a 3D geometry model of the tunnels and of the stations
was determined based on the longitudinal sections. The corre-
sponding mass model of the excavated soil has been derived by
using the soil density data, and the eect of the excavation on
geoid undulation was determined by Eq. (5). The resolution of
the mass model was 30cm, i.e. the masses were concentrated
into cubes with 30 cm long edges. Then the adequate formulas
of rectangular prisms (c.f. [7]) were simplified to simple point
masses, and Eq. (5) was used. The accuracy loss due to this sim-
plification was verified by [4], and it was found to cause negli-
gible dierence. In case of the stations, the exact rectangular
prism formula was used. The mass removals due to excavation
in the tunnels and in the stations were added, and the result is
considered to be an estimate of the eect of the excavation with-
out any displacements assumed to occur.
Subsequently, gravity value was interpolated from the neigh-
boring gravity data to each point of evaluation, and for every
single height dierences of the leveling line the eect of the tun-
neling on the every single height measurements was determined
by Eq. (8).
The eect of the excavation was evaluated at the points of ac-
tual vertical control leveling lines on the south-east part of the
subway line, c.f. Fig. 3 (note that the interruptions of the tun-
nels refer to the presence of stations). To the known heights of
the benchmarks 1 m has been added to simulate a typical instru-
ment height. Altogether there were 40 leveling lines involved in
the analysis. Among them, only some typical features are to be
presented in the following section.
4 Results
Generally, the eect of the excavation on the measurements
along the leveling lines is varying between 0 and 0.01mm.
Though it does not seem to be much, it is important to note
that eect of this theoretical error is in the same magnitude than
that of the precision of the precise level instruments. As so, it is
detected in the measurements. Furthermore, it could be detected
that under certain conditions it accumulates along the leveling
line. The accumulation of the error depends on the orientation
of the line, the distance of the instrument and the sta, and the
height dierence.
4.1 Dependence on the relative orientation
The orientation of the leveling line relatively to the orienta-
tion of the tunnels makes notable impact on the result. The two
extremes of the orientation is when the tunnel and the leveling
line are parallel to each other and when they are perpendicularly
cross each other. There was no good example for the perpen-
dicular crossing (c.f. Fig. 3), but as an example, a nice example
for that is adopted from [4] on a dierent part of the same sub-
way line. The perpendicular crossing with very short distances
between the instrument and the stais displayed in Fig. 4. The
figure shows the longitudinal section of the leveling line. The
ordinate is the distance from the midpoint of the two tunnels,
and the abscissa is the estimated error in µm. The horizontal
location of the tunnels is displayed by the two circles close to
the zero value of the ordinate. From the figure at the crossing a
sudden change of sign can obviously be detected. Due to that,
when the line is processed, the dierent sign of the error neutral-
izes the eect. So practically the closure error is compensated.
On the other hand, in cases, when the leveling line runs par-
allel to the tunnels, the error eect becomes similar for every
single height dierences. Thus the error is accumulating along
the line. For such an example in Fig. 5 and Fig. 6 the line no.
34 is presented. Fig. 5 shows the horizontal arrangement of the
line, which is parallel to the tunnels, passing through at the up-
per left corner. The abscissa and the ordinate refer to the V
coordinates in meter. On Fig. 6 the error estimate is shown along
with the longitudinal section of the leveling line. The zero or-
dinate refers to the starting point. The error on the abscissa is
displayed in µm.
As it can be seen, the error has consequently the same sign,
aecting all the measurements in the same extent. On Fig. 6 also
the back and forth errors are displayed. It is obvious that this er-
ror cannot be eliminated by averaging back- and forth measure-
ments. As so, in such a case the error remains in the adjusted
heights even in case of a thorough processing.
4.2 Dependence on the height difference
In the cases of the tested leveling lines, with the exception of
line no.14, the height dierence between the first and the last
point is only 1-2 m. The last section of the line no. 14 climbs up
to a hill, resulting in a 13 m height dierence along the line, cf.
Fig. 7 and Fig. 8. On Fig. 7 and Fig. 8 the axes are the same as
in the case of Fig. 5 and Fig. 6, respectively.
According to Fig. 8, the dependence of the error on the height
Variations of the gravity field due to excavations of the Budapest Metro4 subway line 1332014 58 2
Fig. 3. The location of the vertical control lines (thin lines) with respect to the tunnels (thick parallel lines).
Fig. 4. An example on the eect of perpendicularly crossing the tunnels.
Per. Pol. Civil Eng.134 Csaba Éget˝o /Nikolett Rehány /Lóránt Földváry
Fig. 5. Top view of the levelling line no. 34. dashed line: leveling line.
symbol ’o’: place of sta, symbol ’x’: assumed place of the instrument. The
two tunnels are marked by thin lines on the upper left part of the figure.
dierence is obvious. Where the steep part comes, the error
suddenly increases with an order of magnitude. The result is
not surprising at all, as in Eq. (9) height dierence appears as a
multiplier.
Fig. 6. The estimated error for every single height dierences along level-
ling line no. 34 in µm. The error along the back- and forth levelling is deter-
mined independently, then the mean error was derived. At the bottom sta- and
instrument places are shown in the same manner as in Fig. 5.
4.3 Dependence on instrument-staff distance
Oddly, the dependence of the error on the distance of the level
instrument and the leveling stacannot be demonstrated from
real measured data, like in the present case. Although it is obvi-
ous: measuring with short distances means a finer resolution of
the level surfaces, than long ones. Thus with shorter distances
the error can be decreased.
The reason it could not be demonstrated is a very practical
one: in case of an actual work, short distances are used only in
case of large height dierences. So it is used for steep fields,
such as line no 14 on Fig. 6. However, in this case the unlike
eect of the height dierence suppresses the eect of the short
distances.
5 Conclusions
Basically, the eect of the excavation on the measurements
along the leveling lines was found to have theoretical impor-
tance in most cases. Still, in such cases, when the leveling line
Fig. 7. Top view of the levelling line no. 14. dashed line: leveling line.
symbol ’o’: place of sta, symbol ’x’: assumed place of the instrument. The
two tunnels are marked by thin lines on the bottom of the figure.
Fig. 8. The estimated error for every single height dierences along levelling
line no. 34 demonstrating a very steep levelling line at its final section. The error
along the back- and forth levelling is determined independently, then the mean
error was derived. At the bottom sta- and instrument places are shown in the
same manner as in Fig. 7.
Variations of the gravity field due to excavations of the Budapest Metro4 subway line 1352014 58 2
was running parallel to the tunnels, the cumulative error reached
the precision of precise leveling. Even though precise leveling
measurements are subsequently processed, dropping the random
errors out, in case of parallel orientation the error remains in the
adjusted results and becomes systematic.
Further relevance of the study is that Metro4 is just a subway
line. There are several other constructions resulting in huge ex-
cavations, removal of notable masses. It is important to keep in
mind that redistribution of mass does aect the gravity field. In
case of a large construction there is always a demand for sur-
veying control measurements in order to detect actual deforma-
tions. Thus it is worth to conclude that surveying control mea-
surements are infected by the temporal variation of the gravity
field as well, and that the two cannot be separated from the mea-
surement, only by theoretical considerations. It remains the case
as long surveying methods make use of the gravity field for ad-
justing the direction of the horizontal and the vertical.
Finally, it is worth to note that this study was considering ap-
parent deformations only. In reality, there are always real de-
formations as well. The actual deformations occur much closer
to the instrument than the tunnels are, it is just 1-1.5 m below
the instrument. These deformations also have their impact on
the gravity field. It means that real deformations have two ef-
fects on the control measurements: a direct eect, as they are
the deformations to be detected, and an indirect eect, as they
alter the gravity field. Even though these close-to-instrument
deformations can be small in magnitude, as the gravity vanishes
with square distance, they can aect the measurements in larger
extent. As a complementary research to the present study, it is
essential to quantify the magnitude of the indirect eect of real
deformations.
References
1Biró P,Time variation of height and gravity, Wichmann Verlag; Karlsruhe,
1983.
2Biró P, Thong NC, Weisz E,Modelling of secular variations in gravity and
in geoidal undulations, Periodica Polytechnica Separatum, 30(1-2), (1986),
23–26.
3Csapó G, Laky S, Éget˝
o C, Ultmann Z, Tóth G, Völgyesi L,Test mea-
surements by Eötvös torsion balance and gravimeters, Periodica Polytech-
nica Civil Engineering, 53(2), (2009), 75–80, DOI 10.3311/pp.ci.2009-2.03.
4Éget˝
o C, Földváry L,The eect of the Metro 4 tunnel system on the gravity
field (in Hungarian), Geomatika, XIV(1), (2011), 17–26.
5Éget˝
o C, Földváry L,Numerical accuracy analysis of modeling excavation
induced gravity field variations, Proceedings in Global Virtual Conference:
The 1st International Global Virtual Conference, 1(1), (2013), 549–554.
6Éget˝
o C, Földváry L, Huszák T,The eect of tunnelling on repeated pre-
cise levelling measurements for vertical deformation control of the Metro4
project, Journal of Geodetic Science, 3(2), (2013), 95–102.
7Holstein H,Gravimagnetic anomaly formulas for polyhedra of spatially lin-
ear media, Geophysics, 68(1), (2003), 157–167, DOI 10.1190/1.1543203.
8Paterson NR, Reeves CV,Applications of gravity and magnetic sur-
veys:The state-of-the-art in 1985, Geophysics, 50(1), (1985), 2558–2594,
DOI 10.1190/1.1441884.
9Rummel R, Balmino G, Johannessen J, Visser P, Woodworth P,Ded-
icated gravity field missions - principles and aims, Journal of Geodynamics,
33(1), (2002), 3–20, DOI 10.1016/S0264-3707(01)00050-3.
10 Schmidt M, Fengler M, Mayer-Gürr T, Eicker A, Kusche J, Sanchez
L, Han S-C,Regional gravity modeling in terms of spherical base functions,
Journal of Geodesy, 81(1), (2008), 17–38, DOI 10.1007/s00190-006-0101-5.
11 Sideris MG (ed.), Observing our Changing Earth, Series: International
Association of Geodesy Symposia, Vol. 133, Springer Verlag, 2008, DOI
10.1007/978-3-540-85426-5.
12 Somodi B, Földváry L,Application of numerical integration techniques for
orbit determination of state-of-the-art LEO satellites, Periodica Polytechnica
Civil Engineering, 55(2), (2011), 99–106, DOI 10.3311/pp.ci.2011-2.02.
13 Thong NC,Determination of true surface movement with spherical har-
monic expansion of the variation in geopotential (in Hungarian), Geodézia
és Kartográfia, 37(4), (1985), 261–265.
14 Torge W,Geodesy, Valter de Gruyten; Berlin, New York, 2001, DOI
10.1515/9783110879957.
15 Sz˝ucs E,Validation of GOCE time-wise gravity field models using GPS-
levelling, gravity, vertical deflections and gravity gradient measurements in
Hungary, Periodica Polytechnica Civil Engineering, 56(1), (2012), 3–11,
DOI 10.3311/pp.ci.2012-1.01.
16 Wahr J, Swenson S, Zlotnicki V, Velicogna I,Time-variable gravity from
GRACE: First results., Geophysical Research Letters, 31, (2004), 01–04,
DOI 10.1029/2004GL019779.
17 Weiss E,Modelling of true vertical surface movements (in Hungarian),
Geodézia és Kartográfia, 37(2), (1985), 101–105.
Per. Pol. Civil Eng.136 Csaba Éget˝o /Nikolett Rehány /Lóránt Földváry
... The method of performing geodetic works when observing subsidence and deformations of engineering structures is well studied and reflected in the works of Uzbek and foreign scientists geodesists [1,2,4], as well as in the relevant regulatory documents [7,8]. According to most recent investigations, the precise observation of the subsidence (vertical monitoring) is very critical not only from the precision of the observation technology, but also from the variations of the environment, such as temporal variations of the reference horizontal level, or the geoid [9,10]. ...
... 10) 0-in other cases, When с i ∈ (0,1), and с i = 0 if Н i is not an extreme among all previous values, in the opposite case с i = 1[5], i.e.0 ≤ [с] ≤ n -1(11)Comment 1. If the elevations (subsidence) of all points are equal, (H 1 = H 2 =...H n-1 = H n or S 1 =S 2 =...=S n-1 =S n ), then [c] = 0, if they change monotonically or their oscillations alternate, systematically increasing or decreasing, then [с] = n -1. ...
Article
Full-text available
To improve the quality of construction and increase the durability of engineering structures under construction, complex geodetic works should be performed, including geodetic observations of deformations of structures. These observations are carried out during the construction of buildings and structures and their operation, mainly before the period of deformation stabilization. In this regard, a reliable statistical definition of deformations close to the limit is necessary, based on the data of geodetic observations. The research helps to improve the definition of deformations of structures using the Fischer’s F-test and the Foster-Stuart test, based on analysis of the measurements of horizontal and vertical monitoring of industrial structures. According to the results, the magnitude of the subsidence plays a more significant role from than its absolute value, thus the value of the deformation intensity is of primary importance in justifying observation periodicity.
Article
Full-text available
Classical numerical integration methods have been tested for determining the orbit of most recent Low Earth Orbiter (hereafter LEO) satellites. In general, numerical integration techniques for orbit determination are commonly used to fill the gap between two discrete, observed epochs. In this study orbits have been determined using the EGM96 gravity model by the Euler, Runge-Kutta, Bulirsch-Stoer and Adams-Moulton numerical integration techniques among others. This analysis is performed for a LEO, the GOCE, and for medium altitude satellite, one GPS satellite. The orbits are integrated under different assumptions on the roughness of the force model, considering effects of the ellipticity, high order gravity and non-static Earth generated accelerations on the orbit.
Article
Full-text available
After more than 40 years of interruption new field observations have been made by an E-54 type torsion balance (TB)in the Csepel-island. These TB measurements were accompanied by a detailed gravimetric survey of each station with LCR gravimeters. Both vertical (VG) and horizontal (HG) gravity gradients were determined at each TB station for VG interpolation and reliability tests. Vertical gradient of gravity cannot be measured directly by the Eötvös TB. However, we successfully interpolated VG differences in the network of TB measurements following the idea originally due to Haalck. Reliability tests by comparing HG and VG gravimetric and TB measurements were also performed. Our recent paper discusses first results of these TB and gravimetric measurements which are scheduled to be continued in the future as well.
Article
Full-text available
The effect of the construction of the 4th subway line of Budapest (Metro4) on the potential surfaces of the gravity field has been simulated, using the prism modelling technique. In the study mass loss due to the excavation of the two tunnels and of the stations has been considered. Mass variations deform the level surfaces; as so, the vertical reference surface of the levelling measurements is changing by time. In this study, the effect of the mass loss on levelling measurements was determined at a level 1 m above the ground, roughly simulating common instrument heights. Subsequently, the effect of the actual deformations of the surface on the levelling measurements has also been determined. According to the results, under certain arrangements of the levelling line with respect to the position of the excavations, the error due to the change of the vertical reference is in the 1μm order of magnitude, thus negligible.
Article
Full-text available
1] The GRACE satellite mission is mapping the Earth's gravity field at monthly intervals. The solutions can be used to determine monthly changes in the distribution of water on land and in the ocean. Most GRACE studies to-date have focussed on producing maps of mass variability, with little discussion of the errors in those maps. Error estimates, though, are necessary if GRACE is to be used as a diagnostic tool for assessing and improving hydrology and ocean models. Furthermore, only with error estimates can it be decided whether some feature of the data is real, and how accurately that feature is determined by GRACE. Here, we describe a method of constructing error estimates for GRACE mass values. The errors depend on latitude and smoothing radius. Once the errors are adjusted for these factors, we find they are normally-distributed. This allows us to assign confidence levels to GRACE mass estimates.
Article
Full-text available
1] Eleven monthly GRACE gravity field solutions are now available for analyses. We show those fields can be used to recover monthly changes in water storage, both on land and in the ocean, to accuracies of 1.5 cm of water thickness when smoothed over 1000 km. The amplitude of the annually varying signal can be determined to 1.0 cm. Results are 30% better for a 1500 km smoothing radius, and 40% worse for a 750 km radius. We estimate the annually varying component of water storage for three large drainage basins (the Mississippi, the Amazon, and a region draining into the Bay of Bengal), to accuracies of 1.0– 1.5 cm.
Article
With the advantage of satellite gravity gradiometry, (SGG) high standard global gravity determination could attain in the static part of the gravitational field. This paper presents the validation of the first and second generation GOCE-only models using terrestrial data sets in Hungary. GOCE global geopotential models (GGM) are consistent models with global coverage in sense that GGMs have been compiled utilizing measurements refer to short time period. Besides GOCE-based GGMs satellite only GRACE models were evaluated to assess the improvements by GOCE observations with respect to GRACE in gravity field determination. EGM2008 as the state-of-the-art model and SRTM3 elevation model were applied to provide that measurements involving Hungarian data sets and model derived gravity field functionals have almost the same spectral content. Results with GPS-levelling and gravity data support that there is an improvement in the determination of medium-wavelength parts of the gravitational field with GOCE models. Although vertical deflections characterize the short-wave part of the gravity field, they are also capable to sense the advancement of SGG observations. Our experiences show that torsion balance measurements depict the fine structure of the gravity field, and hence they are not adequate in low-degree GGM validation.
Article
Formulas for the gravity potential, field, and field gradient tensor are derived for a polyhedral target body of a spatially linear density medium. The formulas also define the magnetic potential and field in the case of a medium of spatially linear magnetization. This work generalizes existing solutions for the gravity field of a polyhedral target of linearly varying density. The formulas are analyzed for singularities and for numerical error growth. Error growth with increasing target distance is found to be higher than in the corresponding uniform polyhedral case. Examination of the error sources reveals that some error reduction is possible. On this basis, new algorithms of improved error control over existing algorithms are proposed for the linear medium. Computational results confirm the expected improvement.
Article
Methods of quantitatively interpreting anomalies in terms of models of causative bodies are adapting rapidly to the burgeoning availability of computing power, from large, powerful machines to inexpensive and field-portable microcomputers. Geologic interpretation, or the identification of physical property distributions in terms of realistic geologic models and processes, is still relatively neglected. Research into the relationships between physical rock properties - particulary magnetite distribution - and geology is gaining momentum, but research still lags behind the requirements of the conscientious geophysical interpreter.-from Authors