A Taxonomy of Dependencies in Agile Software Development
Diane E. Strode
Sid L. Huff
School of Information Management
Victoria University of Wellington
Wellington, New Zealand
Email: diane.strode@alumni.unimelb.edu.au
Email: sid.huff@vuw.ac.nz
Abstract
Dependencies in a software project can contribute to unsatisfactory progress if they constrain or block the flow
of work. Various studies highlight the importance of dependencies in the organisation of work; however
dependencies in agile software development projects have not previously been a research focus. Drawing on
three case studies of agile software projects, and the IS literature, this paper develops an initial taxonomy of
agile software project dependencies. Three distinct categories of dependency are found: task, resource, and
knowledge dependencies. This paper contributes to theory by providing a taxonomy of dependency types
occurring in the area of agile software development. Practitioners can use this taxonomy as sensitising device
to ensure they consider dependencies they might face that could hinder their projects, enabling them to take
appropriate and timely mitigating action.
Keywords
Agile software development, Dependency analysis, Dependency Taxonomy, Software project dependencies.
INTRODUCTION
Dependencies in a software project can contribute to unsatisfactory progress if they constrain or block the flow
of work. Unsatisfactory progress can, in turn, contribute to late delivery of software, or even project failure. In
this paper we propose that constraints in software projects can be attributed to dependencies that are not
managed or organised appropriately. Furthermore, we define dependency as a situation that occurs when the
progress of one action relies upon the timely output of a previous action or the presence of a specific thing.
Various ISD (information systems development) reference literatures highlight the importance of dependencies,
including organisation studies, IS project management, and software engineering. However, dependencies
occurring in co-located agile software development projects have not previously been studied.
Agile software development came to prominence in the late 1990s and is now well-accepted (West and Grant
2010). Agile software development is achieved by adopting one or more agile methods such as Scrum or
Extreme Programming (Dyba and Dingsoyr 2008). These methods differ significantly from traditional
approaches to software development because they involve short iterations of development, close customer and
team interaction to achieve shared understanding, working software as a focus of communication, and an
acceptance of change within the development project, as opposed to attempting to control and reduce change
(Beck et al. 2001). Another notable characteristic of this class of system development methodologies is their
focus on work practices such as pair programming, daily stand-up meetings, and using story wallboards, rather
than modelling methods or documentation.
Software development projects typically evolve in an environment of multiple dependencies (Grinter 1996;
Wagstrom and Herbsleb 2006). It is therefore likely that projects using an agile approach also involve
dependencies. The same types of dependency may occur in agile and non-agile projects, or they may differ in
nature and relative importance. In this study the focus is on understanding the nature of dependencies in typical
agile software development projects. Therefore, this paper addresses the research question: What dependencies
occur in agile software development projects?
The paper is organised as follows. Literature on dependencies in work practice is briefly reviewed to determine
how dependencies are defined, and why previous research does not adequately explain dependencies in agile
projects. The multi-case study research method used to address the research question is described, including the
rationale for selecting cases, and the data collection and analysis procedures. Findings are presented in the form
of a taxonomy supported with evidence from the cases and the empirical research literature. The paper discusses
the contributions of this taxonomy to ISD theory, and its practical utility. Then the paper concludes and
discusses how the taxonomy can be used in future work.
23rd Australasian Conference on Information Systems A taxonomy of dependencies in ASD
3-5 Dec 2012, Geelong Strode & Huff
2
THE CONCEPT OF DEPENDENCY
Dependencies are considered important in various domains relevant to software development. Spanning these
domains is an interdisciplinary theory of coordination developed by Malone and Crowston (1994). Their
Coordination Theory focuses on dependency as a fundamental element in coordination. Malone and Crowston’s
Coordination Theory is based on the tenet that “coordination is the managing of dependencies between
activities” (Malone and Crowston 1994, p. 90). Later, Malone et al. (1999) proposed that a dependency belongs
to one of three fundamental types: fit, flow, or sharing. In this conceptualisation, resources and activities interact
to form dependencies. A fit dependency occurs when multiple activities produce a single resource. A flow
dependency occurs when one activity produces a resource used by another activity, and a sharing dependency
occurs when two or more activities use a single resource.
Pooled, sequential, reciprocal, and team interdependencies have been a focus in organisation studies. As
interdependency can be conceived of as two distinct dependencies; in organisation studies the two terms are
treated as equivalent. Staudenmeyer (1997) synthesised the research on interdependencies in this field and found
that most theorists adopt Thompson’s (1967) basic definitions. Thompson conceived four types of
interdependency related to workflow: pooled, sequential, reciprocal, and team. In pooled workflow, work enters
a work unit and actors perform work activities independently; work does not flow between them. Sequential
workflow occurs when work enters a unit, passes between actors in a single direction and then passes out of the
work unit. In the case of reciprocal workflow, work enters the work unit, and passes back and forth between
actors. In team workflow, work enters the unit and actors diagnose, problem-solve, and collaborate as a group,
working concurrently to deal with the work.
IS project management, and project management in general, focuses on dependencies between tasks, using this
information to reduce project timeframes and/or costs. In planning a project, tasks and their dependencies are
identified so that tasks can be carried out in a sequence that minimises project delays. Furthermore, tasks that
are independent of other tasks can be carried out simultaneously. Traditional project planning methods such as
PERT and Critical Path Modelling use this idea (Kerzner 2003).
Software engineering is concerned with the development of large software systems. Consequently, studies of
dependencies in this domain involve large-scale projects, many of which are distributed in nature. Dependencies
in software development projects, and coordination mechanisms for managing them, were the focus of Grinter’s
(1996) work. She noted that “developers must manage a cadre of dependencies simultaneously if they are to
build any working systems at all” (Grinter 1996, p. 50). In her study of three software development
organisations, she found the following dependencies: vendor, customer, lifecycle, “big picture”, testing, parallel
development, change, expertise, integration, historical, configuration management, and interface. Dependencies
in globally distributed software development were investigated by Espinosa, Slaughter, Kraut, & Herbsleb
(2007) within a single European telecommunications firm. They found technical, process, and temporal
dependencies were the main types of dependency.
Each of these research domains acknowledges the importance of dependencies in organisational and project
work arrangements, but each views dependency from a different perspective. Coordination theory is a general
analytical framework and does not discuss dependencies in any particular domain. Dependency categories from
organisation theory were not considered appropriate for our study because they focus on routine work, as
opposed to non-routine, time-bounded project work. Although the team workflow arrangement appears to
coincide with how work is conducted in agile projects, this conceptualisation does not provide for detailed
insight into the agile project context. IS project management focuses on instances of tasks rather than generic
dependencies occurring in projects; therefore it offers no means of exploring or explaining dependencies in agile
software development projects. Finally, in software engineering the focus is on large, distributed projects.
Dependencies in these contexts are likely to be of a different nature to those of small and co-located projects,
which are the environments where agile methods are normally adopted. For these reasons - the importance of
dependencies in managing and organising work, and the lack of a suitable framework in the existing literature to
explain dependency in agile software development projects - we chose to carry out an in-depth exploratory
study of dependencies in this context.
RESEARCH DESIGN
A multi-case study research approach was selected to explore the dependencies in ongoing software
development projects. This approach is a well-accepted way to investigate phenomena in natural system
development contexts where events cannot be controlled and where it is important to capture the detail in a
situation (Eisenhardt and Graebner 2007; Pare 2004; Yin 2003). To ensure accepted standards for validity and
reliability, we followed guidelines developed by Dubé and Paré (2003) for carrying out rigorous exploratory
positivist case study research in the field of information systems.
23rd Australasian Conference on Information Systems A taxonomy of dependencies in ASD
3-5 Dec 2012, Geelong Strode & Huff
3
Note that the findings reported in this paper form part of a larger study reported in Strode, Huff, Hope and Link
(2012).
Case selection followed a replication strategy, a tactic recommended in case study design (Miles and Huberman
1994; Yin 2003) which involves selecting cases that are similar, and therefore likely to provide similar results
(literal replications), or selecting cases that are dissimilar and therefore likely to provide contrasting results for
predictable reasons (theoretical replications). The study consisted of three literal replications. Each project was a
typical case selected because it was expected to show normal or average characteristics (Eisenhardt and
Graebner 2007; Pare 2004). Case sites used the agile method Scrum, or Scrum with some additional practices
from Extreme Programming, with a team size between 2 and 10. Ten is the maximum team size recommended
for effective use of these methods (Beck 2000; Schwaber and Beedle 2002). All projects were required to have
co-located teams. For practical reasons all projects were located in Wellington, New Zealand. No greenfield
projects were located (i.e. a project without constraints imposed by prior work), therefore each project involved
the replacement or extensive upgrading of an existing computerised system. Eisenhardt and Graebner (2007)
recommend selecting cases that vary in some dimensions because this supports the development of theoretical
concepts accounting for a wider range of contexts. Therefore projects were selected from different types of
organisation using different types of development contract. Table 1 provides details concerning the three
selected projects, which were code-named Land, Storm, and Silver.
Table 1. Organisation, project, and data collection summary
Case name Land Storm Silver
Organisation type Government Commercial service
provider Commercial software
development firm
Organisation size 2000 in NZ 200 in Australasia, Asia
and Europe 20 in NZ
Project purpose To improve the
organisations interactions
with the public
To migrate a critical
legacy system to a modern
technology platform
To provide a replacement
reporting system for an
external client
Contractual basis In-house development Independent contractors
working on the client site Development for external
client
Development
methodology Scrum Scrum and XP Scrum
Team size 6 10 5
Interviews 2 5 4
Roles of
interviewees 1 Project manager
1 Software developer 1 Project manager
2 Software developers
1 Tester
1 Domain expert
1 Development manager
1 Scrum coach
2 Software developers
The primary data collection method was semi-structured interview. An interview schedule appropriate for
collecting data on dependencies in software development projects was developed based on suggestions by
Crowston (1991) for identifying coordination mechanisms and dependencies, McChesney and Gallagher (2004)
for software project profiles, and Spradley (1979) for interviewing in natural situations. In each project, the first
interview was conducted with a senior team member who could provide details on the project, its purpose,
background, history, and issues. Following this interview, and depending on team size, up to four other project
team members in a variety of roles were interviewed for 1 to 1½ hours (see Table 1 for roles).
Data analysis was a two-step process. The first step was to prepare a full description of each case using a pre-
defined framework. This description included details of the organisation, the project, the technologies, the team,
the development method, and any problems in the project. The description was sent to one project participant for
verification, and any factual errors found in the description were then corrected. The second step was within-
case analysis. A general inductive coding approach following the guidelines of Miles and Huberman (1994) and
Thomas (2006) was used. Heuristics provided by Crowston and Osborne (2003) for analysing dependencies and
coordination mechanisms in a situation were followed:
Dependency-focused analysis. Identify dependencies, and then search for coordination mechanisms. In
other words, look for dependencies and then ask which activities manage those dependencies. Failure
to find such activities might suggest potentially problematic unmanaged dependencies.
23rd Australasian Conference on Information Systems A taxonomy of dependencies in ASD
3-5 Dec 2012, Geelong Strode & Huff
4
Activity-focused analysis. Identify coordination mechanisms, and then search for dependencies. In
other words, identify activities in the process that appear to be coordination activities, and then ask
what dependencies those activities manage. This approach asks directly whether all observed
coordination activities are necessary. (Crowston and Osborn 2003, p. 352)
Each case was analysed with dependency-focused and activity-focused analysis. Once instances of dependencies
were identified they were grouped into similar types and given a unique code name (e.g., Expertise). In
performing analyses, codes identified in the first case were used as starter codes for the second case, and codes
from the second case acted as starter codes for the third case. When new types of dependency emerged during
analyses they were added to the list of codes. In a final step, dependency types were grouped into higher-level
categories based on their commonalities. Thus there were three levels of analysis: instances of dependency,
types of dependency, and high-level dependencies.
DEPENDENCY TAXONOMY
We present our findings in the form of a taxonomy of dependencies. In organisation studies, taxonomies are
“classification systems that categorize phenomena into mutually exclusive and exhaustive sets with a series of
discrete decision rules” (Doty and Glick 1994, p. 232). In IS, Gregor (2006) classifies taxonomies as analytic
theories defining ‘what is’ in a bounded situation. Such theories describe, analyse and summarise “salient
attributes of phenomena and relationships among phenomena. The relationships specified are classificatory,
compositional, or associative, not explicitly causal (Gregor 2006, p. 623).
The following sections of this paper develop the dependency taxonomy. Each dependency type is defined along
with supporting evidence from the cases. When dependencies could conceivably be categorised into more than
one dependency type, then decision rules are developed to aid in classification. These rules are described at the
end of this section. Note that Williams (2010) provides a useful resource describing the details of the agile
practices occurring in the examples below.
Requirement Dependencies
A requirement dependency is a situation where domain knowledge or a requirement is not known and must be
located or identified, and this affects progress. Requirements are a critical input to software development
projects as they define the basic needs the software under development should address. In agile software
development projects, requirements are acquired, elaborated, and implemented in small increments as
development progresses. This is usually achieved by interaction between the team and suitable knowledgeable
stakeholders (i.e., end-users, clients, customers, or their proxies). Requirement dependencies were found in each
case. That is, each project presented a situation where a requirement was not known, and this lack of knowledge
affected or had the potential to affect, project progress. This situation occurred when information from suitable
stakeholders was not readily available either during iteration planning, or during development. For example,
Silver had problems communicating with their client, and the project team was not always able to get required
requirements information in a timely manner (pertinent sections of quotes are underlined): “It sometimes
changed our priorities…so we have sometimes, once or twice, taken stories out of the sprint because we
couldn’t get the information and sometimes it was relatively high … priority stories, that we could not
implement in a subsequent sprint…because they did not come back to us.” [Silver, Development Manager]. In
the most complex project, Storm, involving the replacement of a critical and complex mainframe-based system,
it was decided to integrate a domain specialist into the team. This specialist was located with the team in the
same room and so that he could be readily consulted on requirements: "We have a person on our team, who is
one of the gurus, and he sits with us, and we annoy him constantly to get stuff [i.e. information on requirements]
like that”. [Storm, Developer]. Prior research by Crowston and Kammerer (1998) into problems in the
requirements development process in large-scale software projects has also identified requirement dependencies.
Expertise Dependencies
Historically, expertise has been recognised an important factor influencing the success of software projects
(Brooks 1995; Curtis et al. 1988; Faraj and Sproull 2000), it is also acknowledged in agile software
development (e.g. (Beck 2000; Cockburn 2002). Expertise dependencies were found in all of the case projects.
An expertise dependency is defined as a situation where technical or task information is known only by a
particular person or group, and its absence affects project progress. Expertise dependencies tended to show how
expertise was acquired, and this was taken as a reflection of the importance of gaining and sharing expertise
among the team, as without such expertise the project might not have progressed so smoothly.
In Silver, for example, the project team as a whole developed expertise about how the software system worked
by testing the current system version just prior to its presentation to their client: "...we had…a day and a half
23rd Australasian Conference on Information Systems A taxonomy of dependencies in ASD
3-5 Dec 2012, Geelong Strode & Huff
5
when development would stop…, and everyone would test the thing to destruction effectively, and the knowledge
of how it worked at that point would be picked up." [Silver, Development Manager]. In Storm, expertise was
required for many parts of this complex project. The project team were all in a single project room, and were
able to acquire their needed expertise by asking anyone in the room, or ensuring expertise was shared by calling
an informal meeting: "…we can just yell out over our shoulder and grab someone, and also if they come to a
complex design decision then they should bring all of the team to the table so that everyone hears the design
decision that is made." [Storm, Developer]. In Land, a small project consisting of a project team of three
developers and three business people, an understanding of who had what expertise was gained at weekly sprint
planning meetings: “… in terms of who to ask within the business specific questions,…it was in the weekly
meetings, I figured out that Brian was doing this, Mary was doing this, and the other Mary had a different role
entirely.” [Land, Developer]. In Land, there were traditional role divisions in the team (analyst, developer,
designer) with very little shared expertise. Team members tended to pass tasks over to those with the needed
expertise: “Sam waited. He would do the first line of testing. So he would always do a initial user acceptance
testing to verify that everything was OK. Graeme would wait for me to complete the work so he could apply his
styling.” [Land, Project Manager].
Faraj and Sproull (2000) identified dimensions of expertise in software development: technical expertise
(knowledge about a specialised technical area), design expertise (knowledge about software design principles
and architecture), and domain expertise (knowledge about the application domain area and client operations).
However, in our conceptualisation of expertise, domain knowledge is considered a form of requirements
knowledge rather than expertise.
Task Allocation Dependencies
A task allocation dependency occurs when who is doing what, and when, is not known, and this affects project
progress. In traditional projects, tasks are allocated to developers by someone not directly involved in
development, such as a project manager, whereas in agile software development project team members allocate
tasks to themselves. For example: “As each day comes, you are meant to go grab the next highest priority one
[task] off the board, but generally we aren’t quite that strict about it, we all know, since we are in a team of four
people or five people, what each person is going to be best tackling. And you just go ‘yes’ I will do that, and no
one argues.” [Storm, Developer]. In agile projects using Scrum, stories (high-level requirements) are developed
in a sprint planning session. When a story is due for development it is decomposed into individual tasks. Stories
and tasks under development in a sprint (or iteration) are displayed on a publically visible wallboard. When a
project team member selects a task to work on they attach their avatar or name to the task. This means that all
project team members can readily see who is doing what and approximately when.
An example from Storm indicates that knowing what other people are doing can be useful: “…just if you look at
how you would do it with an online system it is like, you can’t tell what other people are working on as easily as
looking up on a wall." [Storm, Developer]. A display of task allocations is useful information because each
individual might at times need to know the relationship of their task to other tasks. Other tasks might precede,
follow, or be concurrent with their task. This enables them to monitor progress, and better manage their work, as
well as helping others complete their tasks. For example: “So a developer, if he wants his story to be Done,… if
they see a couple of test tasks hanging on there for a good couple of days, they may just say ‘[Sam] do you want
me to do these? You look pretty busy there,’ and they’ll go off and do them." [Storm, Developer].
Teamwork theory provides an explanation for this task allocation dependency. Based on a literature review,
Salas, et al. (2005) proposed five components contributing to effective teams. Two are pertinent here:
performance monitoring and backup behaviour. Mutual performance monitoring is the ability to keep track of
fellow team members’ work while performing your own. Monitoring leads to backup behaviour: a team member
willingly providing resources or task-related effort to another when a workload distribution problem is
recognised. Evidence for the task allocation dependency was found in each project.
Historical Dependencies
A historical dependency occurs when knowledge about past decisions is needed, and if such knowledge is not
readily available, project progress is affected. Grinter (1996) defined historical dependencies in terms of the
need to mine organisational memory or old code versions for previous decisions, when studying large-scale
software development projects. These dependencies tend to occur when existing poorly documented systems
need replacement, which was exactly the situation in Storm. In that project, an existing complex system was to
be completely redeveloped. The old system was largely undocumented, and had been extensively enhanced over
15 years. The project team needed to know what decisions had been made in the past, and why, so they could
decide which algorithms in the old system needed to be reproduced and which parts could be omitted from the
23rd Australasian Conference on Information Systems A taxonomy of dependencies in ASD
3-5 Dec 2012, Geelong Strode & Huff
6
new system. The project team addressed this problem in part, by bringing domain experts who had developed
the original system, into the team. They also sent their own team members to reside temporarily with other
project teams who had expertise in the functions of the old system. This comment reflects the situation: "…we
have a good ear of [Walter] who … used to be one of the Delphi programmers, and also I think he was heavily
involved in the VMS for a while, so he’s got a great history,…he understands why a lot of stuff is there.."
[Storm, Developer].
Activity Dependencies
We define an activity dependency as a situation wherein an activity cannot proceed until another activity is
complete, and this affects project progress. Activity dependencies are central to both organisation studies,
Coordination Theory, and project management planning, as discussed previously in the literature review on
dependencies. (Note that the concepts of task and activity are not clearly distinguished in the literature. We take
the view that a task is an activity that has a goal). Activity dependencies were found in all projects. The Storm
project team made efforts to reduce dependencies during breakdown sessions: “… we are getting much better at
doing, in our weekly breakdowns or bi-weekly breakdowns, is prioritising things so there is minimal blockage
happening for everyone." [Storm, Tester]. In Silver, dependencies sometimes appeared unexpectedly during
development: "…it became a discovery process. If ... we were ignorant of the possibility of these dependencies,
until we found that somebody would be working on a story at,…the top of the board that affected or was
required by, a story below it...occasionally we started off trying to work on the second story and then found out
‘hold on, I can’t complete this because it requires something that you are working on’." [Silver, Developer].
Business Process Dependencies
A business process dependency occurs when an existing business process causes activities to be carried out in a
certain order, and this affects project progress. System integration is acknowledged as a non-trivial aspect of IS
(Hasselbring 2000). Fitting new systems with existing systems can involve integrating technical systems and
business processes. It is sometimes difficult to tease out the boundary between the technical system and the
business process when an existing business process is embodied within an IT system. We identified business
process dependencies only in project Land. In this project, it was the existing business process embodied within
an existing technical system that the project team needed to accommodate in their development decisions. In
Land, a portion of the existing organisational web site was replaced and additional functions incorporated to
improve a service to the public. The new system needed to integrate seamlessly with the existing system, and
this constrained the development to follow a particular sequence. The developer explained: "…are translated
onto what you did online. The flow the user was taken through. So there was a certain dependency inherent in
the process, ... you were choosing something to apply for, then you had to provide some details, then you had to
pay. If you break it down like that…that naturally ordered the [development] tasks.” [Land, Developer].
Entity dependencies
An entity dependency occurs when a resource (person, place, or thing) is not available, and this affects project
progress. Entities are things, objects, or artefacts. In an IS project, entities include physical things such as
people, servers, and documents. When Crowston and Osborn (2003) explored the idea of dependencies proposed
in Coordination Theory they argued that all dependencies involved relationships between resources and
activities. Such dependencies occur in most projects because they rely on the timely presence of certain things.
In Land, Storm, and Silver, waiting for the IT operations group was a common issue: "…the main people we
annoy with that are the operations group, …, the people who look after the servers; and we suddenly go 'oh by
the way in two weeks we want to release this new thing to you' and they go 'well I’m not sure I can be ready in
two weeks' and you go" [rolls his eyes]. [Storm, Project Manager]; “…essentially system administration. I
would have to occasionally wait on them to do something for me. Like I needed something installed on a
server.” [Land, Developer]. IS project management recommends that projects be well-resourced to minimise
problems with acquiring needed resources, in a timely manner (Kerzner 2003).
Technical Dependencies
A technical dependency results when a technical aspect of development (such as when one software component
must interact with another software component) affects project progress. Software development is rife with
technical dependencies, and a large body of research focuses on this problem (Cataldo et al. 2009). In project
Land, no technical dependencies were noted, which we attribute to the simple nature of the project - only a
single developer was needed to create the system programs. The other two projects both encountered technical
dependencies. These projects, Storm and Silver, were more complex technically and involved more developers
than Land. In Storm, the team foresaw a technical dependency between modules and addressed it by waiting
23rd Australasian Conference on Information Systems A taxonomy of dependencies in ASD
3-5 Dec 2012, Geelong Strode & Huff
7
until various modules were complete so they could be integrated and deployed together, even though they knew
there was no apparent value to the end-user in this work: "...we should be able to include a whole bunch of our
modules and the [Vole] modules, and just make one application that you deploy onto the desktop, and doing
that, helping ourselves by not having to deploy two applications, more than actually getting through work that
gives the user [value], or give us more things migrated....” [Storm, Tester]. In Silver, a developer noted how
continuous integration and automated testing affected code interdependencies: “…working in a team requires a
different discipline to working alone, … because you are interacting with other peoples’ code. So having these
tests in place, which basically made sure that the behaviour, or the functionality of the code, doesn’t change. So
that if someone comes along and makes a modification, that they think in their world is quite normal but breaks
the way that you were expecting to use that code, then there is a little pop up. So yes, continuous integration is a
really useful tool” [Silver, Developer].
Once dependency types were identified, they were further categorised based on their similarities. Requirement,
expertise, historical, and task allocation were categorised as knowledge dependencies because they involve
forms of knowledge needed by project participants before they are able to perform project tasks. Activity and
business process dependencies were categorised as task dependencies as these dependencies involve the
performance of actions by one group of actors before other project actors can begin their required work. Entity
and technical dependencies are resource dependencies because both involve the necessary availability of people
or things, including software components (technical things), which are a form of resource. Table 2 shows the
dependencies found in the projects, and Figure 1 presents the complete dependency taxonomy. The next section
describes the classification rules used in allocating dependency instances to dependency types.
Table 2. Dependencies identified in projects
Dependency Land Storm Silver
Knowledge Requirement
Expertise
Task allocation
Historical -
Task Activity
Business process - -
Resource Entity
Technical -
Classification Decision Rules
Classification decisions were necessary when coding data into categories, and we applied the following decision
rules. Allocation of evidential data to the entity, expertise, or requirement dependency involved specialisation
logic; a requirement dependency is a specialised form of expertise dependency; and an expertise dependency is
a specialised form of entity dependency. For example, if a person has particular requirements knowledge then
this could be coded as 1) an entity dependency because a person is involved, or 2) an expertise dependency
because the person has particular expertise, or 3) a requirements dependency because the person has particular
expertise about requirements. In this example, following these decision rules, the dependency would be coded as
a requirements dependency even though the dependency involves both expertise and an entity. Further, an
historical dependency is a specialised type of expertise dependency. Another decision rule concerns entity and
technical dependencies. In our schema, a technical dependency is a specialised type of entity dependency.
DISCUSSION
Agile software development is fundamentally different from other approaches to software development. Yet,
agile projects are influenced by the same environmental characteristics as non-agile projects. Consequently this
taxonomy contains many concepts familiar from prior research such as expertise, technical, activity, and entity
dependencies. Historical and business process dependencies identified in these agile projects would also be
likely to occur in non-agile projects when replacement systems and high levels of integration with existing
systems are project characteristics. While identifying these similarities, the taxonomy also draws attention to
differences between agile and traditional approaches. In particular the need for a continuous supply of
requirements into agile project sprints, which is not necessary in projects organised into traditional phases.
Another difference is in the task allocation concept. Although this is seen as a key factor in generic teamwork
23rd Australasian Conference on Information Systems A taxonomy of dependencies in ASD
3-5 Dec 2012, Geelong Strode & Huff
8
research, participants in a project knowing who is working on what, is seldom a focus in traditional software
projects where a central knowledgeable figure allocates tasks.
TaxonomyofAgileSoftwareProjectDependencies
Adependencyiscreatedwhentheprogressofoneactionreliesuponthetimelyoutputofapreviousaction,orthepresenceof
somespecificthing.Dependenciesleadtopotentialoractualconstraintsonprojects.Potentialconstraintsarethosethatare
currentlyorganisedormanagedwell,causingnoproblemsintheprogressionofaproject.Actualconstraintsarebottlenecksor
pointsinaprojectthatstakeholdersareawareof,buthavenoimmediatemeanstocircumvent.
Knowledgedependency
Aknowledgedependencyoccurswhenaformofinformationisrequiredinorderforaprojecttoprogress.Therearefourformsof
knowledgedependency:
Requirement‐asituationwheredomainknowledgeorarequirementisnotknownandmustbelocatedoridentifiedandthis
affectsprojectprogress
Expertise‐asituationwheretechnicalortaskinformationisknownonlybyaparticularpersonorgroupandthisaffectsproject
progress
Taskallocation‐asituationwherewhoisdoingwhat,andwhen,isnotknownandthisaffectsprojectprogress
Historical‐asituationwhereknowledgeaboutpastdecisionsisneededandthisaffectsproject
Taskdependency
Ataskdependencyoccurswhenataskmustbecompletedbeforeanothertaskcanproceedandthisaffectsprojectprogress.There
aretwoformsoftaskdependency:
Activity‐asituationwhereanactivitycannotproceeduntilanotheractivityiscompleteandthisaffectsprojectprogress
Businessprocess‐asituationwhereanexistingbusinessprocesscausesactivitiestobecarriedoutinacertainorderandthisaffects
projectprogress
Resourcedependency
Aresourcedependencyoccurswhenanobjectisrequiredforaprojecttoprogress.Therearetwoformsofresourcedependency:
Entity‐asituationwherearesource(person,placeorthing)isnotavailableandthisaffectsprojectprogress
Technical‐asituationwhereatechnicalaspectofdevelopmentaffectsprogress,suchaswhenonesoftwarecomponentmust
interactwithanothersoftwarecomponent,anditspresenceorabsenceaffectsprojectprogress
Figure 1: A taxonomy of dependencies in agile software development projects
The paper contributes to the IS literature by developing a taxonomy of dependencies in agile software
development. We identify dependency types, and propose that, in addition to the traditional ISD project
management focus on identifying and managing task and resource in projects, knowledge in the form of
expertise, requirements, historical, and task allocation should also be included because it too had the potential to
affect project progress in the agile projects in this study. The paper makes a contribution to ISD practice
because this taxonomy provides a sensitising device for project stakeholders, a way for them to ensure they
consider dependencies they might face that could hinder their projects, and thus enable them to devise
appropriate actions to address those dependencies.
This study has limitations. Case study research is limited in its ability to generalize beyond the specific cases
studied, and we make no claim that this taxonomy is applicable in all agile software development contexts, but
only to those identified in this study. However, following the guidance of Seddon and Scheepers (2012) we have
attempted to improve the applicability of our findings to settings beyond these cases by drawing on supporting
evidence from extant literature. Further, Gregor (2006) notes that taxonomy should be complete and exhaustive
and we cannot make this claim; therefore this taxonomy is currently tentative. Further cases would strengthen
the validity of the findings, and we argue for further research to verify our taxonomy. Limitations particular to
this study include the selection of cases. Different cases in different contexts might have led us to find different
dependencies. Furthermore, we might not have captured all dependency types in the projects in the study
because interviews might not draw out all dependencies when participants recall not only recent events, but
events occurring many months prior to the interview.
CONCLUSION
This paper has presented a taxonomy of dependencies based on evidence from three typical cases of small, co-
located, agile software development projects, and relevant literature. Although some concepts in this taxonomy
are widely recognized in prior literature, this paper offers a different perspective on them, that of agile software
development, which is not currently available in the ISD literature. Furthermore, this tentative taxonomy makes
23rd Australasian Conference on Information Systems A taxonomy of dependencies in ASD
3-5 Dec 2012, Geelong Strode & Huff
9
a beginning at defining key dependency types that have the potential to contribute to project delay, and
ultimately to unsatisfactory project progress.
Future work includes verifying the taxonomy with additional evidence. In addition, investigating the relative
importance of dependency types would be valuable, for some dependencies might be more critical in certain
types of project, or at certain times during a project. Further research could assess the applicability of this
taxonomy in contexts such as non-agile software development projects, large-scale, and distributed software
projects. This would contribute to a better understanding of the types of dependency in software projects,
providing a sound basis for selecting effective mechanisms for managing them.
Another area for future work is in improving our understanding of what and how agile practices address
particular dependencies in a situation. We propose that many agile practices, such as iterations, regular and ad
hoc meetings, and many others, are designed to effectively manage dependencies in software development. The
taxonomy presented in this paper is a starting point for research into this aspect of agile software development.
REFERENCES
Beck, K. 2000. Extreme Programming Explained: Embrace Change. Boston: Addison-Wesley.
Beck, K., Beedle, M., van Bennekum, A., Cockburn, A., Cunningham, W., Fowler, M., . . . Thomas, D. 2001.
"Manifesto for Agile Software Development. ." Retrieved 1 January 2012, from
http://www.agilemanifesto.org
Brooks, F. 1995. The Mythical Man Month: Essays on Software Engineering. Reading, MA: Addison-Wesley.
Cataldo, M., Mockus, A., Roberts, J., and Herbsleb, J.D. 2009. "Software Dependencies, Work Dependencies,
and Their Impact on Failures," IEEE Transactions on Software Engineering (35:6), pp. 864-878.
Cockburn, A. 2002. Agile Software Development. Boston: Addison-Wesley.
Crowston, K. 1991. "Towards a Coordination Cookbook: Recipes for Multi-Agent Action," in: Alfred P. Sloan
School of Management. Cambridge, Mass: Massachusetts Institute of Technology, p. 352.
Crowston, K., and Kammerer, E.E. 1998. "Coordination and Collective Mind in Software Requirements
Development," IBM Systems Journal (37:2), 27 October 2008.
Crowston, K., and Osborn, C.S. 2003. "A Coordination Theory Approach to Process Description and Redesign,"
in Organizing Business Knowledge: The MIT Process Handbook, T.W. Malone, K. Crowston and G.A.
Herman (eds.). Cambridge, Massachusetts: The MIT Press, pp. 335-370.
Curtis, B., Krasner, H., and Iscoe, N. 1988. "A Field Study of the Software Design Process for Large Systems,"
Communications of the ACM (31:11), pp. 1268-1287.
Doty, D.H., and Glick, W.H. 1994. "Typologies as a Unique Form of Theory Building: Toward Improved
Understanding and Modeling," The Academy of Management Review (19:2), pp. 230-251.
Dube, L., and Pare, G. 2003. "Rigor in Information Systems Positivist Case Research: Current Practice, Trends,
and Recommendations," MIS Quarterly (27:4), December, pp. 597-635.
Dyba, T., and Dingsoyr, T. 2008. "Empirical Studies of Agile Software Development: A Systematic Review,"
Information and Software Technology (50:9-10), pp. 833-859.
Eisenhardt, K.M., and Graebner, M.E. 2007. "Theory Building from Cases: Opportunities and Challenges,"
Academy of Management Journal (50:1), pp. 25-32.
Espinosa, A.J., Slaughter, S.A., Kraut, R.E., and Herbsleb, J.D. 2007. "Team Knowledge and Coordination in
Geographically Distributed Software Development," Journal of Management Information Systems
(24:1), pp. 135-169.
Faraj, S., and Sproull, L. 2000. "Coordinating Expertise in Software Development Teams," Management
Science (46:12), pp. 1554-1568.
Gregor, S. 2006. "The Nature of Theory in Information Systems," MIS Quarterly (30:3), pp. 611-642.
Grinter, R.E. 1996. "Understanding Dependencies: A Study of the Coordination Challenges in Software
Development," in: Information and Computer Science. Irvine: University of California, p. 130.
Hasselbring, W. 2000. "Information System Integration," Communications of the ACM (43:6), pp. 33-38.
Kerzner, H. 2003. Project Management: A Systems Approach to Planning, Scheduling, and Controlling, (8 ed.).
Hoboken, New Jersey: John Wiley & Sons.
23rd Australasian Conference on Information Systems A taxonomy of dependencies in ASD
3-5 Dec 2012, Geelong Strode & Huff
10
Malone, T.W., and Crowston, K. 1994. "The Interdisciplinary Study of Coordination," ACM Computing Surveys
(26:1), pp. 87-119.
Malone, T.W., Crowston, K., Lee, J., Pentland, B., Dellarocas, C., Wyner, G., . . . O'Donnell, E. 1999. "Tools
for Inventing Organizations: Toward a Handbook of Organizational Processes," Management Science
(45:3), pp. 425-443.
McChesney, I.R., and Gallagher, S. 2004. "Communication and Coordination Practices in Software Engineering
Projects," Information and Software Technology (46:7), pp. 473-489.
Miles, M.B., and Huberman, A.M. 1994. Qualitative Data Analysis, (2 ed.). Thousand Oaks: Sage.
Pare, G. 2004. "Investigating Information Systems with Positivist Case Study Research," Communications of the
Association for Information Systems (13:1), pp. 233-264.
Salas, E., Sims, D.E., and Burke, C.S. 2005. "Is There a 'Big Five" in Teamwork?," Small Group Research
(36:5), pp. 555-599.
Schwaber, K., and Beedle, M. 2002. Agile Software Development with Scrum. Upper Saddle River, New Jersey:
Prentice Hall.
Seddon, P.B., and Scheepers, R. 2012. "Towards the Improved Treatment of Generalization of Knowledge
Claims in Is Research: Drawing General Conclusions from Samples," European Journal of Information
Systems (21), pp. 6-21.
Spradley, J.P. 1979. The Ethnographic Interview. New York: Holt, Rinehart and Winston.
Staudenmayer, N. 1997. "Interdependency: Conceptual, Practical, and Empirical Issues." Massachusetts
Institute of Technology.
Strode, D.E., Huff, S.L., Hope, B., & Link, S. 2012. "Coordination in co-located agile software development
projects," The Journal of Systems and Software (85:6), pp. 1222-1238.
Thomas, D.R. 2006. "A General Inductive Approach for Analyzing Qualitative Evaluation Data," American
Journal of Evaluation (27:2), pp. 237-246.
Thompson, J.D. 1967. Organization in Action. Chicago: McGraw-Hill.
Wagstrom, P., and Herbsleb, J.D. 2006. "Dependency Forecasting in the Distributed Agile Organization,"
Communications of the ACM (49:10), pp. 55-56.
West, D., and Grant, T. 2010. "Agile Development: Mainstream Adoption Has Changed Agility." Forrester
Research Inc., pp. 1-20.
Williams, L. 2010. "Agile Software Development Methodologies and Practices," in Advances in Computers,
M.V. Zelkowitz (ed.). Amsterdam: Elsevier, pp. 1-44.
Yin, R.K. 2003. Case Study Research, (3 ed.). Thousand Oaks: Sage.
ACKNOWLEDGEMENTS
We are grateful to the case study research participants and also to Professor Gordon Hunter, Siva Dorairaj, and
Kevin Carillo for comments on early versions of this paper.
COPYRIGHT
D. E. Strode and S. L. Huff © 2012. The authors assign to ACIS and educational and non-profit institutions a
non-exclusive licence to use this document for personal use and in courses of instruction provided that the
article is used in full and this copyright statement is reproduced. The authors also grant a non-exclusive licence
to ACIS to publish this document in full in the Conference Papers and Proceedings. Those documents may be
published on the World Wide Web, CD-ROM, in printed form, and on mirror sites on the World Wide Web.
Any other usage is prohibited without the express permission of the authors.