ArticlePDF Available

Applying Earned Schedule to Critical Path Analysis and More

Authors:
  • Earned Schedule

Abstract and Figures

Earned Schedule is a fairly new method for analyzing schedule performance; it is a derived application of Earned Value Management (EVM) data. Created three years ago, the method has propagated to several countries and been used for various types of work spanning a large range of project sizes. During this period of infancy, a misperception may have emerged that ES is only applicable to the total project and thus is limited for schedule performance analysis. As has been shown in the article, "Connecting Earned Value to the Schedule," ES can be used for much more. It facilitates the ability to identify constraints, impediments, and the possibility of rework at the task level [1]. This information is very useful for management purposes, but it does not provide performance indicators below the project level. This paper describes how ES can be applied to sub-levels of the project. Using this capability, the project manager can analyze schedule performance at virtually any level desired – control accounts, work packages, and critical path activities. During presentations about Earned Schedule (ES) I am sometimes asked, "Can Earned Schedule be used to analyze the critical path?" My response is always, "Certainly, simply treat the critical path as the project." I notice then that the person doesn't say anything else, but has the look of someone who didn't have his question answered. This question is asked often enough …with the same result …that it is apparent a more complete response is needed. Hopefully this paper will satisfy all those who have voiced the question in the past, as well as those who are seeking a way to use ES as a "drill-down" tool. In this paper, it is assumed the reader has good understanding of Earned Value Management (EVM) and that Earned Schedule is being used as one of the project management tools. Although it is likely the reader has a working knowledge of ES, a review of the concept, the time-based indicators and the forecasting calculation is needed to establish a common foundation for the remainder of the paper. Earned Schedule The ES idea is simple: identify the time at which the amount of earned value (EV) accrued should have been earned [2]. By determining this time, time-based indicators can be formed to provide schedule variance and performance efficiency management information.
Content may be subject to copyright.
Fall 2006
26
T
he
Measurable News
Applying Earned Schedule
to Critical Path Analysis and More
By Walt Lipke, Retired Deputy Chief, Software Division, Tinker Air Force Base
Abstract
Earned Schedule is a fairly new method for analyzing schedule performance; it is a derived applica-
tion of Earned Value Management (EVM) data. Created three years ago, the method has propagated
to several countries and been used for various types of work spanning a large range of project sizes.
During this period of infancy, a misperception may have emerged that ES is only applicable to the
total project and thus is limited for schedule performance analysis. As has been shown in the article,
“Connecting Earned Value to the Schedule,” ES can be used for much more. It facilitates the ability
to identify constraints, impediments, and the possibility of rework at the task level [1]. This informa-
tion is very useful for management purposes, but it does not provide performance indicators below the
project level. This paper describes how ES can be applied to sub-levels of the project. Using this capa-
bility, the project manager can analyze schedule performance at virtually any level desired – control
accounts, work packages, and critical path activities.
During presentations about Earned Schedule
(ES) I am sometimes asked, “Can Earned
Schedule be used to analyze the critical
path?” My response is always, “Certainly,
simply treat the critical path as the project.” I notice then
that the person doesn’t say anything else, but has the look
of someone who didn’t have his question answered. This
question is asked often enough …with the same result
…that it is apparent a more complete response is needed.
Hopefully this paper will satisfy all those who have
voiced the question in the past, as well as those who are
seeking a way to use ES as a “drill-down” tool.
In this paper, it is assumed the reader has good
understanding of Earned Value Management (EVM) and
that Earned Schedule is being used as one of the project
management tools. Although it is likely the reader has a
working knowledge of ES, a review of the concept, the
time-based indicators and the forecasting calculation is
needed to establish a common foundation for the remain-
der of the paper.
Earned Schedule
The ES idea is simple: identify the time at which the
amount of earned value (EV) accrued should have been
earned [2]. By determining this time, time-based indica-
tors can be formed to provide schedule variance and per-
formance efficiency management information.
Figure 1, Earned Schedule Concept, illustrates how the
ES measure is obtained. Projecting the cumulative EV
onto the project management baseline (PMB), as shown
by the diagram, determines where planned value (PV)
equals the EV accrued. This intersection point identi-
fies the time that amount of EV should have been earned
in accordance with the schedule. The vertical line from
the point on the PMB to the time axis determines the
“earned” portion of the schedule. The duration from the
beginning of the project to the intersection of the time
axis is the amount of earned schedule (ES).
With ES determined, time based indicators can be cre-
ated. It is now possible to compare where the project is
time-wise with where it should be in accordance with the
PMB. “Actual time,” denoted AT, is the duration at which
the EV accrued is recorded. The time-based indicators
are easily formulated from the two measures, ES and AT.
Schedule Variance becomes SV(t) = ES – AT, and Sched-
ule Performance Index is SPI(t) = ES / AT.
The graphic and the box in the lower right of figure 1
portray how ES is calculated. While ES could be deter-
mined graphically as described previously, the concept
becomes much more useful when facilitated as a calcula-
tion. As observed from the figure, all of the PV through
May has been earned. However, only a portion of June
has been completed with respect to the baseline. Thus the
duration of the completed portion of the planned schedule
is in excess of 5 months. The EV accrued appears at the
end of July, making actual time equal to 7 months. The
method of calculation to determine the portion of June to
credit to ES is a linear interpolation. The amount of EV
extending past the cumulative PV for May divided by the
incremental amount of PV planned for June determines
the fraction of the June schedule that has been earned.
The creation of ES and the derivative time-based
schedule performance efficiency, i.e. SPI(t), facilitates
forecasting the duration of the project and its completion
Fall 2006 27
T
he
Measurable News
date. Two formulas are presently in use; one is termed
the “short form” and the other the “long form.” The short
form is IEAC(t) = PD / SPI(t), where IEAC(t) is the In-
dependent Estimate at Completion (time) and PD is the
planned duration for the project [3]. The long form is not
needed in the subsequent discussion and, consequently, is
not stated.
Why the Question?
In the previous discussion of the concept, it is established
that the determination of ES requires the Project Man-
agement Baseline (PMB), and is a cumulative measure.
It is the cumulative “earned” portion of the schedule.
The cumulative nature of ES is, also, emphasized in the
seminal paper, “Schedule is Different” [2]. And, the in-
structions for using the ES calculator also stress that the
complete PMB of the project must be entered to expect
correctly calculated results [4].
My conjecture is the emphasis of these statements
could cause the misunderstanding that the method is only
applicable to the total project. With the repeated overtures
to use the project PMB along with the statements that ES
is a cumulative measure, it is a reasonable deduction.
However, ES is not limited to only the total project. It
is much more applicable. I intend to dispel the perception
of the limitation and show how the ES method can be ap-
plied at any level of interest within a project, including
work packages, control accounts, and critical path activi-
ties. In other words, the capability is available for “drill-
down” schedule analysis by applying the ES method to
the project EVM data.
What’s the Trick?
To broaden the applicability of ES to detailed schedule
performance analysis is not difficult. All that is required
is to view the subject of the analysis as if it is the total
project. This response is very similar to my answer, earli-
er in the paper, to the question concerning applying ES to
analyze the critical path. It should be. But, just as it was
for the persons who posed the question during my pre-
sentations, the answer is incomplete. Thus, the question
becomes, “How do I make a portion of a project appear
like a total project?”
To answer this question, let us view Table 1, Project
Plan and Performance Measures by Task. The table de-
picts the time-phased plan, earned value (EV), and actual
costs (AC) for each of ten tasks comprising the notional
project. The time-phased plan, the performance baseline,
is created from the planned value (PV) amounts. All
amounts are in units of cost and are periodic, not to be
understood as cumulative. The diamond symbol indicates
the initiation of the task. At project completion, the sum
of the periodic EV amounts for each task equals the sum
of its PV quantities.
To construct the PMB, first sum the periodic PV
amounts across all tasks by performance period (PP).
Then, finalize the PMB by creating the cumulative quan-
tities by PP. This is accomplished by adding, successive-
ly, the periodic PV determined from the summing across
tasks. For example, add the total periodic PV in period
two to period one to obtain the cumulative PV for pe-
riod two; then for period three add its periodic PV to the
cumulative PV for period two. This process is repeated
through period ten. The resultant cumulative values for
periods one through ten is the PMB. This is the project
performance baseline from which ES for the total project
is determined.
To analyze tasks (work packages), control accounts
or critical path a performance baseline must be created
specific to the analysis area; i.e., if a cost account is to
FIGURE 1. EARNED SCHEDULE CONCEPT
Fall 2006
28
T
he
Measurable News
be analyzed, its comprising tasks must be segregated
and grouped. Then the process for creating the project
PMB is applied to this set of tasks to create a PMB for
the cost account, PMBa. Having PMBa allows ES to be
calculated specifically for the cost account. In turn, the
determination of ES facilitates the calculations of SPI(t)
and IEAC(t) for the specific evaluation of cost account
performance.
Critical Path Example
With the methods in place, the process for applying ES
to critical path analysis can be described. As discussed in
the previous section of the paper, segregate and group the
critical path tasks, and create a PMB representing them,
PMBc. For this example, the critical path for the notional
project includes tasks one, four, eight, and ten (1-4-8-10).
Table 2, Performance Baselines and Earned Value Mea-
sures, aggregates the data for both the total project and
the critical path.
The project management baselines for the total proj-
ect (PMB) and critical path (PMBc) are their respective
PVcum rows. The PVper rows represent the summation
of the planned values of the representative tasks for the
specific performance period. As described previously,
the PVcum is obtained from the PVper values. For ex-
ample the calculation for PVcum for period three of the
Project Data
  Performance Period 
Task Nr Measure
0 1 2 3 4 5 6 7 8 9 10 11 12
PV
5 5 5
1 EV
456
AC
557
PV
10
2 EV
7 3
AC
10 5
PV
10 10 10
3 EV
8 13 9
AC
10 15 10
PV
5 5
4 EV
3 4 3
AC
5 5 5
PV
5 5 5
5 EV
5 3 5 2
AC
5 5 5 2
PV
5 5
6 EV
6 4
AC
5 5
PV
10 10 10 10 10
7 EV
8 9 7 13 8 5
AC
10 10 10 15 10 5
PV
5 10 5
8 EV
12 8
AC
15 12
PV
5 5 5
9 EV
4533
AC
5653
PV
5 5
10 EV
10
AC
14
TABLE 1. PROJECT PLAN AND PERFORMANCE MEASURES BY TASK.
Fall 2006 29
T
he
Measurable News
total project is determined by adding PVper for period
three to PVcum of period two: PVcum(3) = PVcum(2) +
PVper(3). Using the values from the Table 2, the calcula-
tion can be performed: PVcum(3) = 10 + 35 = 45.
The remainder of Table 2 contains the performance
data, earned value (EV) and actual costs (AC) for the
total project and for the specific critical path tasks. The
accumulation of this information allows analysis and pre-
diction to occur for the total project and the critical path.
The EVM performance indicators and duration fore-
casts calculated from the Table 2 data are aggregated in
Table 3, Performance Indicators and Duration Forecasts.
The “p” and “c” appended to the indicators shown in the
table indicate period and cumulative, respectively.
From Table 2 it can be determined that the project
is planned to complete in 10 time periods, but actually
completes in 12. Similarly, Table 2 indicates the tasks
on the critical path completed at the planned time, 10
periods. For comparison purposes both SPI and SPI(t)
indicators are shown in Table 3. The familiar behavior of
the two indicators is seen for the critical path and total
project. The values for SPI(t) compare favorably to those
for SPI for the critical path which completes as planned.
However for the total project, the values for the two in-
dicators are significantly different. The corresponding
values for SPI(t)c and SPIc noticeably begin departing in
period eight, and conclude as expected for late finishing
projects; at project completion, SPI(t)c is a valid number
(0.8333) truly depicting the actual schedule performance
efficiency, while SPIc illogically equals 1.0.
By inspection of Table 2, it is obvious the critical path
changed during project execution. Knowing this begs the
TABLE 2. PERFORMANCE BASELINES AND EARNED VALUE MEASURES.
�� Performance Period ��
Measure 0 1 2 3 4 5 6 7 8 9 10 11 12
0 0
0000000000000
PVper
0 5 5 35 30 40 30 20 5 10 5 0 0
PVcum
0 5 10 45 75 115 145 165 170 180 185 185 185
Total
0000000000000
Project EVper
0 0 4 16 43 27 18 31 16 9 15 3 3
EVcum
0 0 4 20 63 90 108 139 155 164 179 182 185
0000000000000
ACper
0 0 5 20 52 35 20 37 22 10 20 5 3
ACcum
0 0 5 25 77 112 132 169 191 201 221 226 229
0
0000000000000
PVper
0 5 5 5 5 5 5 10 5 5 5 0 0
PVcum
0 5 10 15 20 25 30 40 45 50 55 55 55
Critical
0000000000000
Path EVper
0 0 4 8 10 3 0 12 8 0 10 0 0
1-4-8-10 EVcum
0 0 4 12 22 25 25 37 45 45 55 55 55
0000000000000
ACper
0 0 5 10 12 5 0 15 12 0 14 0 0
ACcum
0 0 5 15 27 32 32 47 59 59 73 73 73
0 0
0000000000000
TABLE 3. PERFORMANCE INDICATORS AND DURATION FORECASTS
�� Performance Period ��
Indicator 0 1 2 3 4 5 6 7 8 9 10 11 12
CPIp
xxx xxx 0.8000 0.8000 0.8269 0.7714 0.9000 0.8378 0.7273 0.9000 0.7500 0.6000 1.0000
CPIc
xxx xxx 0.8000 0.8000 0.8182 0.8036 0.8182 0.8225 0.8115 0.8159 0.8100 0.8053 0.8079
Total SPI(t)p
xxx 0.0000 0.8000 1.4857 1.3143 0.7750 0.4500 0.9750 0.7000 0.4500 1.9500 0.5000 0.6000
Project SPI(t)c
xxx 0.0000 0.4000 0.7619 0.9000 0.8750 0.8042 0.8286 0.8125 0.7722 0.8900 0.8545 0.8333
SPIp
xxx 0.0000 0.8000 0.4571 1.4333 0.6750 0.6000 1.5500 3.2000 0.9000 3.0000 xxx xxx
SPIc
xxx 0.0000 0.4000 0.4444 0.8400 0.7826 0.7448 0.8424 0.9118 0.9111 0.9676 0.9838 1.0000
IEAC(t)
xxx xxx 25.00 13.13 11.11 11.43 12.44 12.07 12.31 12.95 11.24 11.70 12.00
CPIp
xxx xxx 0.8000 0.8000 0.8333 0.6000 xxx 0.8000 0.6667 xxx 0.7143
CPIc
xxx xxx 0.8000 0.8000 0.8148 0.7813 0.7813 0.7872 0.7627 0.7627 0.7534
Critical Path SPI(t)p
xxx 0.0000 0.8000 1.6000 2.0000 0.6000 0.0000 1.7000 1.3000 0.0000 2.0000
1-4-8-10 SPI(t)c
xxx 0.0000 0.4000 0.8000 1.1000 1.0000 0.8333 0.9571 1.0000 0.8889 1.0000
SPIp
xxx 0.0000 0.8000 1.6000 2.0000 0.6000 0.0000 1.2000 1.6000 0.0000 2.0000
SPIc
xxx 0.0000 0.4000 0.8000 1.1000 1.0000 0.8333 0.9250 1.0000 0.9000 1.0000
IEAC(t)
xxx xxx 25.00 12.50 9.09 10.00 12.00 10.45 10.00 11.25 10.00 xxx xxx
Fall 2006
30
T
he
Measurable News
question, “Does the simultaneous application of ES to
both the critical path and total project provide advance
warning of this condition?” If the answer is “Yes,” then
applying ES has been shown to yield analysis advantages
to project managers.
One significant implication of a response of “Yes” is
detailed schedule performance information can be ob-
tained solely from the EVM data …without the laborious
bottom-up analysis performed by skilled schedulers.
Another point is detailed schedule analysis takes time
and considerable effort by sometimes several people, of-
tentimes becoming a distraction to those performing proj-
ect work. For any size, but especially for larger projects,
performing a detailed schedule analysis involving several
subcontractors in the time-frame the ES schedule forecasting
calculations can be made is virtually impossible.
The time advantage offered by IEAC(t) does not mean
to imply that detailed bottom-up schedule analysis should
never be performed. Certainly, just as the final cost esti-
mate obtained from IEAC is not relied on solely at criti-
cal points without a detailed cost analysis, a bottom-up
schedule estimation should be performed for confirmation
of the ES forecast.
By reviewing and comparing the IEAC(t) numbers
for the total project and critical path we can answer the
question posed a few paragraphs earlier. The answer is
“Yes,” it can be observed that the critical path is likely
to have changed. From examining Table 3 it is seen very
early, beginning with period 3, that the forecast duration
for the total project is always greater than the forecast for
the critical path. It is reasonably clear that the critical path
changed early in the project execution from tasks 1-4-8-
10. From this example, it may be said that ES can provide
advance warning that the critical path has changed.
Without going into the detail, the project duration fore-
casting method from ES can further be used to identify
the longest duration path; i.e., the changed critical path.
By forecasting duration for each task and inserting the
forecasts into the network structure of the schedule, the
actual critical path can be determined as well as condi-
tions for float. With some technical ingenuity, this analy-
sis could be completely automated.
Summary
The Earned Schedule analysis method is demonstrated in
this paper to be applicable to more than the total project.
Segregating and grouping EVM data for a specific por-
tion of the project is the technique by which ES is made
applicable to the total project and any sub-level desired.
Specifically, the technique is shown to be capable of ana-
lyzing the schedule performance for the critical path. By
employing the same techniques to analyze critical path,
schedule performance by individual tasks can be evalu-
ated, which then allows identification of the longest dura-
tion path for the project (actual critical path) along with
schedule float.
References
1. Lipke, Walt. “Connecting Earned Value to the
Schedule,” CrossTalk, June 2005: On-line (http://www.
stsc.hill.af.mil/crosstalk/2005/06/0506Lipke.html).
2. Lipke, Walt. “Schedule is Different,” The Measurable
News, March 2003: 10–15.
3. Henderson, Kym. “Further Developments in Earned
Schedule,” The Measurable News, Spring 2004: 15–22.
4. http://www.earnedschedule.com/Calculator.shtml
About the Author
Walt Lipke recently retired as the deputy chief of the
Software Division at the Oklahoma City Air Logistics
Center. The division employs approximately 600 people,
primarily electronics engineers. He has over 35 years of
experience in the development, maintenance, and man-
agement of software for automated testing of avionics and
jet engines as well as automation of industrial processes.
During his tenure, the division achieved several software
process improvement milestones:
1993 — first Air Force activity to achieve Level 2 of
the Software Engineering Institute’s Capability Ma-
turity Model® (CMM®)
1996 — first software activity in federal service to
achieve CMM® Level 4 distinction
1998division achieved ISO 9001/TickIT registration
1999 — division received the SEI/IEEE Award for
Software Process Achievement
Mr. Lipke has published several articles and presented
at conferences, internationally, on the benefits of software
process improvement and the application of earned value
management and statistical methods to software proj-
ects. He is the creator of the technique Earned Schedule
(Copyright© 2003 Lipke), which extracts schedule infor-
mation from earned value data. Mr. Lipke is a graduate
of the USA DoD course for Program Managers. He is a
professional engineer with a master’s degree in physics,
and is a member of the physics honor society, ΣΠΣ. Lipke
achieved distinguished academic honors with the selec-
tion to ΦΚΦ.
... Efficiency needed from "time now" to achieve a Cost Target Note. Adapted from (Defense Acquisition University, 2017); (Henderson, 2004); (Lipke, 2003(Lipke, , 2006; (Lipke & Henderson, 2006). ...
... Schedule Performance Parameters Note. (Defense Acquisition University, 2017); (Lipke & Henderson, 2006); (Lipke, 2006); (Henderson, 2004); (Lipke, 2003). ...
... Note. (Defense Acquisition University, 2017); (Lipke & Henderson, 2006); (Lipke, 2006); (Henderson, 2004); (Lipke, 2003 Combining Concepts for Greater Insights Lipke (2006) discusses the application of the ES method to critical path analysis, which applies the ES method to a group of segregated tasks comprising a program in addition to the program aggregate. Applying this approach to a flight test program could provide valuable insights that would otherwise be missing. ...
... Efficiency needed from "time now" to achieve a Cost Target Note. Adapted from (Defense Acquisition University, 2017); (Henderson, 2004); (Lipke, 2003(Lipke, , 2006; (Lipke & Henderson, 2006). ...
... Schedule Performance Parameters Note. (Defense Acquisition University, 2017); (Lipke & Henderson, 2006); (Lipke, 2006); (Henderson, 2004); (Lipke, 2003). ...
... Note. (Defense Acquisition University, 2017); (Lipke & Henderson, 2006); (Lipke, 2006); (Henderson, 2004); (Lipke, 2003 Combining Concepts for Greater Insights Lipke (2006) discusses the application of the ES method to critical path analysis, which applies the ES method to a group of segregated tasks comprising a program in addition to the program aggregate. Applying this approach to a flight test program could provide valuable insights that would otherwise be missing. ...
... The earned schedule (ES) is the actual progress expressed (or valued) in time units [13][14][15][16][17]. It is the equivalent of the earned value that is expressed in other units. ...
Article
Full-text available
Successful project management depends on ensuring the project’s objectives. Within these objectives, technical success is associated with achieving the expectations of the project baseline. The baseline of the project is made up of the definition of the scope (WBS), time (schedule) and costs (S curve) of the project. Directly, the project is expected to be technically successful if it manages to deliver its full scope on schedule and without associated cost overruns. Baseline performance management is how project managers track and control the progress of deliverables, timelines and associated costs. In a traditional approach, for waterfall-type projects that use the critical path paradigm, the baseline performance management tool par excellence is earned value management (EVM). Earned value management, in practice, works well when project costs are monitored and controlled; however, applying this approach to measure the status of the schedule presents serious inconsistencies. Over the last several decades, different variations of the original earned value have been developed to overcome some of these inconsistencies when used to measure project schedule status. Within these variations, we have the critical path earned value; the work in progress earned value; the critical path earned value and the work in progress; the earned schedule; and the critical path earned schedule. Each of these proposals tries to address some weakness of the original earned value management applied to time monitoring and control, for example, considering critical tasks as a focus on monitoring the progress of the schedule, solving the problem of task recognition late finishers, reporting schedule variances in time units and measuring adherence to the project’s schedule (P factor). Due to the exposed situation, it is necessary to determine which alternative of the versions of the original earned value is the most appropriate for the management of the project schedule, considering that there are several evaluation criteria that must be considered. In the present research, a systematic review and comparison of EVM and its variations for measuring project baseline schedule performance are performed to determine the most suitable methods for monitoring and controlling the project baseline schedule. For this purpose, the analytic hierarchy process (AHP) is used, and five comparison criteria are considered: schedule variation focused on critical tasks, recognition and measurement of the delay of tasks that finish late, schedule variation in time units, measurement of schedule adherence (P factor) and software support and development. The result of the AHP performed for comparing the methods shows that the best method for monitoring and controlling the project baseline schedule is the critical path earned schedule because it behaves adequately in comparison with the other methods for the evaluated comparison categories.
... Assessing performance for milestone achievement is similar to the ES application to critical path (CP) analysis. [Lipke, 2006] To analyze performance for the CP, its performance baseline is required. From the schedule and the estimated values of cost and duration for the tasks comprising the CP, the associated PMB can be created. ...
Article
Full-text available
The application of Earned Value Management (EVM) provides insight to a project’s performance, thereby providing management information useful for project control. Many projects, especially those that are large, establish milestones in their schedules. Milestones are used to assess progress, usually by evaluation of product characteristics, at an interim point significant to the project. Although EVM plays a role, the method is not focused on milestone achievement. To address this perceived void, this paper introduces an Earned Schedule method for determining, in process, the achievability of a specific milestone.
... This concern has also been raised by other authors and has led to a discussion summarized in articles such as Book (2006aBook ( , 2006b, Jacob (2006) and Lipke (2006). Although it is recognized that, at higher WBS levels, effects (delays) of non-performing activities can be neutralized by well performing activities (ahead of schedule), which might result in masking potential problems, it is the only approach that can be taken by practitioners. ...
Article
Monitoring the performance of projects in progress and controlling their expected outcome by taking corrective actions is a crucial task for any project manager. Project control systems are in use to quantify the project performance at a certain moment in time, and allow the project manager to predict the expected outcome if no action is taken. Consequently, these systems serve as mechanism that provide warning signals that tell the project manager when it is time to take corrective actions to bring the expected project outcome back on track. In order to trust these generated warning signals, the project manager has to set limits on the provide performance metrics that serve as thresholds for these actions. This paper gives an overview of different approaches discussed in the literature to control projects using such actions thresholds. First and foremost, the paper discusses three classes of actions thresholds,ranging from very easy-to-use rules-of-thumb to more advanced statistical project control methodologies. Each of these tools have been the subject to research studies, each of which aim at showing their power to predict project problems during its progress. In addition, the paper will emphasize the fundamental different between statistical project control using tolerance limits and statistical process control for projects. Finally, three different quality metrics to evaluate the performance of such control methods are presented and discussed.
... Depending upon the individual work item durations applied the example project's critical path may switch from one pathway of work items to another. The critical pathway for the remainder of a project yet-to-be completed may not be the critical pathway that has prevailed up to the stage of the project so far completed [13] and can in some cases become a shorter path and no longer "the longest path" [16], and may not necessarily be best estimated by the earned schedule method [8,20]. However, for whatever duration assumptions that are made for individual work items in a particular case, one pathway will always constitute the critical path (or longest path) for that case. ...
Article
Formation damage issues typically arise at different recovery stages of unconventional oil/gas and geothermal energy in various petroleum and hydrological geosystems. A lack of understanding of the potentially induced damage in those geosystems is associated with downside risks and negative economic consequences. As a comprehensive review and analysis building upon our previous work (Yuan and Wood, 2018), this paper aims to raise more awareness of the mechanically, chemically, biologically and thermally induced damage issues associated with oil/gas and geothermal energy recovery in unconventional shale, coal-bed methane, geothermal reservoirs, and deepwater oilfields. It does so by integrating state-of-the-art modelling, laboratory experiments and field examples. Potential formation damage issues are discussed in the context of each specific geosystems to answer why, where and when damage occurs, its extent and impacts, and how to control, prevent and take advantages of such issues. Moreover, an integrated risk and opportunity assessment and management framework is presented with the objective of improving the outcomes of energy extraction projects in practice.
... The longest duration is determined by applying ES forecasting to each remaining serial path. This methodology has been described in the literature for comparison of planned CP performance to the total project [Lipke, 2006]. Fundamentally, the remaining Planned Value (PV) for the serial path examined is used as the Performance Measurement Baseline (PMB). ...
Article
Full-text available
مدیریت ارزش کسب شده یکی از قویترین و پرکاربرد ترین تکنیک های مدیریت پروژه است که در سال های اخیر از سوی کارشناسان و مدیران پروژه مورد توجه بسیاری قرار گرفته است. یکی از مفاهیم توسعه ای مدیریت ارزش کسب شده، زمان بندی کسب شده میباشد که شاخص عملکردی زمان پروژه را از دقت و صحت بالایی برخوردار کرده است. از دیگر کاربردهای ES میتوان به پیشبینی زمان اتمام پروژه اشاره کرد. در تحقیقات بسیاری نشان داده شده است که پیشبینی زمان اتمام پروژه با استفاده از ES از سایر روش های موجود برتری قابل توجهی داشته و اغلب نتایج بهتری را ارائه میکند. با وجود کاربرد وسیع مدیریت ارزش کسب شده در مدیریت پروژه، اخیرا تحقیقاتی توسط ماریو ونهوک صورت گرفته است که بکارگیری این روش در تمامی پروژه ها را با تردید مواجه کرده است. در این تحقیقات نشان داده شده است که توپولوژی شبکه بر کارایی این تکنیک به شدت موثر است، بدین نحو که نتایج حاصله از این تکنیک تنها در شبکه های سری از صحت خوبی بهره مند میباشد و در شبکه های موازی دچار تردید هستند. حال آنکه بسیاری از پروژه ها توامان از ارتباطات موازی و سری استفاده میکنند. در این مقاله سعی بر آن است تا با بکارگیری روش طولانی ترین مسیر، زمان پیشبینی شده اتمام پروژه در شبکه های با توپولوژی موازی را بر مبنای اطلاعات سیستم مدیریت ارزش کسب شده و بدون افزودن حجم قابل توجه به محاسبات، بهبود بخشید. علاوه بر این، انتظار میرود مدل پیشنهادی اشکال وارده را برطرف نموده و بتواند به عنوان راه حلی مناسب برای استفاده مدیریت ارزش کسب شده در شبکه های موازی بکارگرفته شود.
Article
Earned duration metrics improve project-duration-performance monitoring and forecasting compared to earned schedule metrics because they depend only on time-based variables. In projects with multiple-parallel paths of work items and with work items varying significantly in individual durations, earned duration metrics sometimes fail to provide reliable project-duration monitoring and forecasts. Calculating earned duration using information for the critical-path work items only, provides a way of overcoming distortions in earned duration caused by non-critical-path work items. Weighting the work items used in an earned duration calculation, according to their individual-planned durations, places more emphasis on the longer-duration work items, which often constitute the more-crucial work items in terms of uncertainty and performance. Two new earned duration formulations are derived and evaluated. The analysis is performed using deterministic, stochastic and fuzzy models related to work breakdown progress diagrams that illustrate the quality and reliability of the information that can be derived from these new formulations.
Article
Full-text available
Recent research indicates cost and schedule forecasting from EVM data is improved when the performance factor, PF = 1, is used. This paper uses a small set of real data to examine the research finding, to either confirm or refute. As well, the application of PF = 1 is employed in statistical forecasting; results are tested and compared to the index method. Observations from the research and this study are made referencing historical studies. Further research is encouraged on these topics, but with some precaution when real data is used.
Article
Full-text available
For project cost, analysts can predict the final value with some confidence using the Independent Estimate at Completion (IEAC) formulas from Earned Value Management (EVM). 1 The formulas provide a means to understand the financial health of a project without having to reassess the cost value for each of the unfinished tasks. Earned value analysts cannot assess the health of schedule performance in the same manner. EVM does not provide IEAC-like formulas by which to predict the final duration of a project. Many who are knowledgeable of earned value express the opinion that schedule information derived from EVM is of little value. This paper discusses the problem and develops a methodology for calculating the predicted project duration using EVM data. The methodology uses the concept of Earned Schedule and introduces an additional measure required for the calculation.
Article
Full-text available