China's large public buildings (LPBs) often become problematic after only a few years' operation, leading to shortened building lifespans. Lacking architectural programming was identified by the industry regulators as a contributing factor to this. Despite a policy shift on the government side since 2007, little evaluation of the actual situation has been made. To raise awareness and attention to this pressing issue from the building industry, its regulators and the general public, a questionnaire survey focusing on the top-tier sector of professional practice in programming LPBs was carried out in Shanghai, China in 2009. The objectives were to evaluate current trends and pressing issues, identify major challenges and opportunities, and make recommendations for improvement. This paper presents a six-part analysis of the survey's findings from 57 professionals and clients who shared their hands-on experience on various programming issues and provided first-hand data of 90 LPBs developed in the 2000s. This pioneering study revealed significant gaps between the real and best practices as well as the mental reluctance and skill mismatch in delivering quality programming services. Given the persisting nature of identified problems, more research work should be done to catalyze a paradigmatic shift among industry players.
Content may be subject to copyright.
www.elsevier.com/locate/foar
Available online at www.sciencedirect.com
RESEARCH ARTICLE
Professional pr actice in progr amming large
public buildings in China: A questionnaire survey
Ying Deng
a,
n
, S.W. Poon
b
a
Department of Civil Engineering, The University of Hong Kong, Hong Kong, China
b
Department of Real Estate and Construction, The University of Hong Kong, Hong Kong, China
Received 18 February 2013; received in revised form 7 April 2013; accepted 8 April 2013
KEYWORDS
Architectural pro-
gramming;
The early stages;
Large public building
(LPB);
Questionnaire survey;
China
Abstract
China's large public buildings (LPBs) often become problematic after only a few years'
operation, leading to shortened building lifespans. Lacking architectural programming was
identied by the industry regulators as a contributing factor to this. Despite a policy shift on the
government side since 2007, little evaluation of the actual situation has been made. To raise
awareness and attention to this pressing issue from the building industry, its regulators and the
general public, a questionnaire survey focusing on the top-tier sector of professional practice in
programming LPBs was carried out in Shanghai, China in 2009. The objectives were to evaluate
current trends and pressing issues, identify major challenges and opportunities, and make
recommendations for improvement. This paper presents a six-part analysis of the survey's
ndings from 57 professionals and clients who shared their hands-on experience on various
programming issues and provided rst-hand data of 90 LPBs developed in the 2000s. This
pioneering study revealed signicant gaps between the real and best practices as well as the
mental reluctance and skill mismatch in delivering quality programming services. Given the
persisting nature of identied problems, more research work should be done to catalyze a
paradigmatic shift among industry players.
& 2013. Higher Education Press Limited Company. Production and hosting by Elsevier B.V. All
rights reserved.
1. Introduction
1.1. Poor programming leads to short-lived
buildings
In the wake of the late 2000s' global economic slowdown,
China's stimulus program has triggered a signicant upsurge
in the construction sector. With a total expenditure of US$1
2095-2635 & 2013. Higher Education Press Limited Company. Production and hosting by Elsevier B.V. All rights reserved.
http://dx.doi.org/10.1016/j.foar.2013.04.002
n
Corresponding author. Tel.: +852 2241 5896.
E-mail address: ydeng@hku.hk (Y. Deng).
Peer review under responsibility of Southeast University.
Frontiers of Architectural Research (2013) 2, 222 233
trillion, China overtook the United States as the world's
biggest construction market in 2010 (Betts et al., 2011).
Despite an annual average of new construction up to
2 billion m
2
or an equivalent of 40% of the world's total, a
building's life span was only averaged about 35 years in
China, lagging far behind 74 years in the United States and
132 years in the United Kingdom, according to the Ministry
of Housing and Urban-Rural Development (MoHURD) (Qiu,
2010). This ephemerality phenomenon not only exist
among those jerry-built residential buildings but already
extend to many large public buildings (LPBs).
China's Ministry of Construction et al. (2007) denes LPBs
as the buildings, each with a oor area of 20,000 m
2
or
above, which are used for any single or combined purposes
of ofce, commerce, tourism, science, education, culture,
health, communications, and transportation. A root cause
for their shortened lifespans, as pointed out by MoHURD
(2008) (the successor of the Ministry of Construction after
2007), was a lack of rigorous architectural programming as
the critical rst step of the early stages. Driven by the
mindset to aunt economic ascendancy through huge
expenditure on image building, quite a number of LPBs
across the country were overdesigned in form but under-
designed in substance. As a result, many so-called landmarks
easily become underuse, energy-intensive or even unsafe to
use after only a few years in operation (Architecture We ekly,
2008; Qiu, 2010). Despite exorbitant initial costs mainly on
fancy facades and excessive decoration, less consideration was
shown to fundamental building performance issues of spatial
and functional integrity, user comfort, adaptability, economy,
safety, energy efciency, locality, and sustainability. The
ignorance at the early stages may start a vicious cycle of
frequent revamping, deconstruction and reconstruction after
a building is occupied. This may explain why poor program-
ming leads to short-lived buildings.
Just as a house built on an inadequate foundation will not
last long, a building based on an incomplete program is
seldom viable. In practice, this has been well received
among the developed economies but not in China by far.
Following the pioneering paper Architectural Program-
ming: Important Steps Before Design Can Begin (Peña and
Good, 1967), the signicance of architectural programming
has been generally realized by the industry and well
researched by the academia in North America and Europe.
For instance, extensive programming efforts must be made
before undertaking and commissioning architectural design
for large and complex building projects in most states of the
United States. This has in turn encourage large American
design practices to foster strong in-house capacities and
close ties with professional programmers (Preiser, 1993).
Similar regulatory mechanisms and codes of practice have
been implemented long in the United Kingdom although
laden with many practical problems (Blyth and Worthington,
2010; Kamara and Anumba, 2001). By contrast, there was a
long interval before the term architectural programming
was translated into Chinese in the 1990s. Except for the rst
domestic publication on architectural programming by
Zhuang (2000), related overseas literature in its original or
translated versions was rare in China in the meantime.
Domestic professional institutions also lacked focused
efforts to promote this emerging concept and benchmark
best practices, lagging behind their overseas counterparts
such as American Institute of Architects, Royal Institute of
British Architects and Australian Institute of Architects.
1.2. Police shift
As a good public building has to serve good to the public (Nasar,
1999), it becomes an imperative for China's building industry to
increase the number of quality built products rather than the
volume of new construction alone. The international focus on
building sustainability, in particular, energy and economic
resources management, has put on a new challenge on the
building industry besides the traditional emphasis on quality,
safety and environment. To curb the proliferation of proble-
matic LPBs, a range of regulatory changes were jointly initiated
in 2007 by the Ministry of Construction and four other related
state ministries (2007). A tougher control was imposed over the
number, scale and quality of LPBs. Moreover, MoHURD (2008)
updated The provisions of schematic design tendering for
construction projects, calling for substantial rectication in
the following aspects of the entire design tendering process:
(1) The inclusion of detailed expert reports concerning a
building's functional performance, energy efciency,
construction and operational costs in the design bidding
documents.
(2) The involvement of interdisciplinary experts in the design
review process.
(3) A tougher control over the launching of international
design competitions to avoid unnecessary pursuit of
signature architecture.
(4) The inclusion of public consultation to enhance the
transparency in the decision-making process.
Table 1 summarizes the best practice at the early stages
of LPBs advocated in the above two government instruc-
tions. Despite a good starting point for a long overdue
correction, little research has been carried out to probe
Table 1 Highlighted issues by MoHURD (2008) and
Ministry of Construction of PRC (2007).
Issues at the
early stages
The best practice
Client's program The client shall seek experts' advice,
clarify project requirements, and
determine critical technical and
economic parameters.
Schematic design The schematic design shall conform to
approved master plan, detailed
regulatory plan of the specic site,
and urban design of the site.
Format of design
competition
Domestic rather than international
design competitions shall be the rst
choice for clients.
Review of design
competition
Open and transparent procedures
shall be devised for the process, while
the requirements and accountability
of jury shall be claried.
223A questionnaire survey on programming large public buildings in China
into the real professional practice in programming LPBs and
to map out the actual situation at large. Built upon such
evidence-based ndings, specic coping strategies with
operational guidelines can be formulated for consideration
by the government regulators.
1.3. Aim and objectives
The main thrust of this paper was to raise awareness and
attention to this pressing issue by stakeholders of the
building industry and the general public who are bonded
by their common interests in LPBs. To this end, a ques-
tionnaire survey on the professional practice in program-
ming LPBs developed in the 2000s was conducted in
Shanghai, China in 2009. Specic objectives of this explora-
tive study were to evaluate the current trends and issues;
identify related challenges and opportunities; and promote
the needed consensus on formulating a way forward among
the government regulators, professionals and scholars.
Given the time, physical and nancial constraints, it was
deemed realistic to keep clarity and focus by starting with
representative individuals and organizations in the top-tier
sector of LPBs, i.e., those with signicant impacts on the
local and national scales. This was based on a simple
rationale: if the professional practice sampled from the
specic high-end stratus with more regulated clients and
better qualied professionals is problematic as against the
best practice, it will be more condent to predicate more
problems in the rest strata and infer the magnitude of the
issue at large.
2. Research framework
The rest of this paper is structured in three parts. The
research framework is rst introduced in terms of its
theoretical background, method and design, selection cri-
teria, and data collection. This is followed by a six-part
presentation of the survey's major ndings. Finally, conclu-
sions are drawn and recommendations made to the industry
and its regulators.
2.1. Theoretical background
A building's lifecycle can be mainly phased into the early
stages and the later stages as shown in Table 2. Although
research ndings continue to prove well-informed early
stages lead to well-performed buildings, the input at the
early stages remains signicantly lower than that at the
later stages in practice (Barrett and Stanley, 1999; Best and
Valence, 1999; Smith et al., 2001; Smith, 2003; Vanston,
2003). As an initial step towards a building's lifecycle and an
integral component of the early stages, the process of
programming (brieng) allows all stakeholders to assess
opportunities and constraints, investigate and communicate
requirements, and develop a program statement as the
guidance of a proper design solution and as a constant
yardstick against the built product (Hershberger, 1999;
Kumlin, 1995; Peña and Parshall, 2001). A program is a set
of documents that explicitly claries the objectives, exist-
ing contexts, philosophies and functional requirements of a
project to facilitate design decision making (Preiser, 1993).
An important attribute of a program is that it never remains
Table 2 The phasing of a building project's lifecycle.
Sources: complied from (Austen and Neale, 1984; Best and Valence, 1999; Bowen et al., 1997; Carmichael, 2006; Cherry, 1998;
Cherry and Petronis, 2005; Cleland and Ireland, 2007; Hershberger, 1999; Ryd, 2004).
No. of sub-
stages
The early stages The later stages
Three Brief and design Construction planning Construction
Pre-design Design Post-design
Feasibility Pre-construction Construction
Programming Designing Building (execution)
Pre-project
(brieng)
Project (design and construction) Post-project (review )
Appraisal Implementation Operation
Four Programming Design Construction Occupancy
Appraisal Design Construction Operation
Five Program
development
Preliminary
design
Production Construction Post-occupancy
Concept Brieng Planning Production Evaluation
Preparation Design Pre-construction Construction Management
Concept Development Implementation Termination Operation, maintenance
Concept Denition Production Operation Divestment
Brieng Designing Tendering Constructing Commissioning
Planning Programming Design Construction Occupancy
Six Programming Schematic
design
Design
development
Construction
documents
Construction Occupancy
Y. Deng, S.W. Poon224
static but is subjected to constant validation by the client
organization and its understanding of external demand (Best
and Valence, 1999).
A large and complex building project may also include the
preliminary/schematic design phase (Table 2). According to
MoHURD (2008), an open or invited architectural competi-
tion is compulsory for any LPBP in China, unless otherwise
specied. As a key approach to procuring quality building
products, design competitions can be categorized into
several basic formats and developed into more combined
options (Table 3). As an important vehicle between the
competition sponsor (usually the client) and the competi-
tors, a competition program serves as an important vehicle
to clarify the client's requirements, de ne terms of refer-
ence for the competitors, and provide yardsticks for the
jury's evaluation of the competition entries (American
Institute of Architects, 1988; RAIA, 2003).
2.2. Research method and design
The method of questionnaire survey, due to its extensive
use in programming research worldwide [e.g., (Bowen
et al., 1997; Brown, 2001; Kelly et al., 2005; Preiser,
1993; Shen and Chung, 2006)], was employed for this
experimental study in China. Based on these previous
studies, three interrelated common issues were identied.
Firstly, intensive client involvement in establishing a good
program holds the key to the quality of design service
(Barrett and Baldry, 2003), but the issue of a client
organization is often ignored or oversimplied (Boyd and
Chinyio, 2006). Secondly, organizational issues rather than
methodological issues arising from the client organization
might exert greater impacts on the outcome of a project,
but were largely ignored in the programming process
(Farbstein, in Preiser, 1993, p. 384). Finally, for a large
and complicated project, it is difcult to determine the
components of its programming team in practice (Kumlin,
1995). These formed part of the focal issues considered in
the survey. The questionnaire was structured in six parts
containing 26 questionsamong which 14 (54%) are closed
ended, 10 (38%) are semi-closed ended, and the rest two
(8%) open-ended (Table 4).
2.3. Sampling techniques
A few sampling techniques, i.e., cluster sampling, stratied
sampling, convenience sampling and snowball sampling
were used in combination (Groves, 2002), to better focus
on the target group and yield more valid and accurate
results in a timely and cost-effective manner.
(1) Cluster sampling was employed to determine Shanghai
as the initial survey base for several reasons. Normally,
an international metropolis has a better chance than
other less internationalized cities to attract and accom-
modate major developments. Shanghai ts the prole
due to its reputation as one of the most developed
markets for LPBs in China and its global perspective and
all-inclusive capacity to attract diversied resources.
(2) There were several reasons to use stratied sampling.
Among others the construction of major building ag-
ships led by Expo 2010 served as a big boost for an inux
of domestic and overseas industrial players into the city
since 2001. This would facilitate the selection and
liaising of respondents of different natures. A number
of high-prole international design competitions were
launched by several well-established local developers
between 2004 and 2007. The shortlisted design agencies
were invited mainly for their extensive experience and
track record in handling large and complex building
projects in China and overseas. The highly strict screen-
ing processes of design tendering indicated that the
clients and designers selected from a large pool of
qualied candidates at the local, regional and interna-
tional levels would be representative of the top-tier
players in LPBs as the targeted subgroup. Hence, this
group of respondents were considered as the most
suitable stratus for this explorative study.
(3) As convenience sampling is most useful for pilot testing
(Fink, 1995), the rst author's work experience in both
the professional and government sectors of Shanghai
between 2003 and 2007 offered another bonus in the
process of liaising with the target respondents.
(4) Snowballing sampling were used when some initially
approached respondents agreed to refer more potential
respondents whom they considered capable of answer-
ing the questionnaire due to their job nature and work
experience.
2.4. Selection criteria
Three major criteria were set out for selecting respondents
as follows:
(1) The inclusion of client organizations. Unlike some
previous surveys aiming solely at professional consul-
tants such as architects, key client members as the
driving force of the early stages were also included. The
inclusion of design consultants of various nature and
their clients allowed pressing issues highlighted in the
two government documents mentioned earlier to be
explored more completely.
(2) The capacity of design agencies. Due to the highly
selective nature of the procurement processes for major
Table 3 Categorization of design competition.
Sources: American Institute of Architects, 1988 ; Nasar,
1999; RAIA, 2003.
Aspects of consideration Types of
competition
Eligibility of competitors Open
Limited/selected
Scope of the competition International
National
Regional
Objective of the competition Idea
Project
Scale and complexity of the
project
One-stage
Two-stage
225A questionnaire survey on programming large public buildings in China
LPBs, design contracts are usually awarded to a limited
number of large and interdisciplinary practices experi-
enced in handling sophisticated design tasks. It hence
made sense to seek respondents from these agencies.
(3) The capacity of respondents. To ensure the validity and
accuracy of rst-hand data, preference was given to those
potential respondents with both decision-making autho-
rities and enriched experience at the early stages of LPBs.
2.5. Data collection
The questionnaire sheets were prepared in Chinese and English
versions to suit different needs. In January 2009, the hard-
copies of 70 questionnaire sheets were distributed to each
available respondent in Shanghai. Subsequently, 30 electronic
copies were emailed to other intended respondents who were
previously unavailable in Shanghai. Altogether 100 question-
naire sheets were sent to potential respondents in 11 qualied
large agencies, including three Shanghai-based public clients
and eight large desig n practices. Among the three local
clients, one was from the government sector and the other
two from the business sector. All were actively involved in a
number of high-prole LPBs including major building agships
for Expo 2010. Among the eight large design practices, ve
were based in Beijing and Shang hai and listed on The Top 60
Chinese Design Firms for 2008 (ERN, 2009b), with one ranked
in the top ve and two in top 20. The three overseas rms
were also ranked among The Top 500 US-based Des ign Firms
for 2008 (ERN, 2009a). All eight rms had extensive experi-
ence in designing major LPBs in major Chinese cities. By the
end of March 2009, 65 replies (65% response rate) in hardcopy
or electronic version were returned, among which 57 were
regarded as valid and the rest eight were incomplete. Follow-
up enquires for more detailed explanations or clarications to
the completed questionnaires were made afterwards.
3. Major ndings
In line with the framework set out above, major ndings are
reported in six parts below.
3.1. Proles of respondents
Each of the 57 respondents was involved in at least one LPBP
between 2003 and 2009. R e spondents' proles were studi ed in
Table 4 The questionnaire survey framework.
Aspect of concern Scope of inquiry
Part 1 (Q17)
Length of experience in the industry.
Occupation/specialty.
Educational level.
Recent involvement in LPBs.
Channels for programming education/training.
Respondent prole
Part 2 (Q814)
The demand of programming services.
The supply of programming services.
The prospect of programming services.
Major consequences of poorly-conducted programming.
The output of programming literature.
The provision of programming education.
Programming performance
Part 3 (Q1518) Whether do respondents agree the following statements:
Programming should be added as a link between planning and design.
Programming is critical along the project cycle.
Programming has not yet gained enough attention it deserves.
An additional fee for the programming service shall be charged.
Awareness on programming
Part 4 (Q1920)
Key factors inuencing the outcome of a design competition.
Typical problems in a client's program.
Design competition and its programs
Part 5 (Q2125)
Programming methods.
Programming benets (short-term, long-term).
Formation of a program
Part 6 (Q26)
Project prole.
[location, type, scale, attribute (regular or event-led), length of formation period].
Client prole (ownership, experience, organization).
Competition format (scope, stage).
Frequency of signicant program changes.
Communication approaches.
Fee issue of programming services.
Programming cases
Y. Deng, S.W. Poon226
veaspectsasspecied in Ta ble 4 . Figure 1 showsthat74%
respondents held senior positions at the time of the survey. Six
respondents (11%) claimed to have been handling 50 to over 100
LPBs. Figure 2 indicates the distribution of respondents by
occupation or speciality. Figure 3 demonstrates that 66%
received certain type of programming-related education or
training, while 34% never did. In terms of the source, 16%
received programming-related education from school education
while 23% obtained the knowledge from vocational training.
3.2. Professional practice in programming LPBs
P art 2 examines the supply-demand trends and the academic
and educational provision in architectural programming. Most
respondents (89%) agreed that the demand for programming
services was on the rise and the future market would be
promising. However, 58% thought that there was a lack of
quality professional services. Almost unanimously, 95% and 96%
considered that the provision of related literature and educa-
tion was insufcient. To further understand the impacts of
programming on the later stages, respondents were asked to
rank ve possible consequences closely tied to the program-
ming process. Figure 4 ranks them by number of votes each
problem received. The result showed major design revision
ranking in the rst place, followed by outstanding cost
overrun, serious operational problem, serious cooperation
problems and serious construction delay.
3.3. Awareness on programming
To investigate the awareness on programming among different
industrial players, opinions were sought r egarding the value,
status and fee of programming. As listed below, the four
statements were given for the correspondents' evaluation.
0
10
20
30
40
50
Client organization Design agency In total
Number of respondents
Senior position Non-senior position
Figure 1 Distribution of respondents by position.
Engineer
5%
Architect
30%
Programmer
3%
Project manager
12%
Urban planner
12%
Design manager
13%
Landscape
architect
4%
Client member
14%
Other
2%
Regulatory agency
officer
5%
Figure 2 Respondents distribution by job title/specialty.
Self-teaching
2%
Vocationa
l
training
23%
Lecture
3%
Designated
training
p
rogram
6%
School
education
16%
Never learnt
34%
Project
experience
11%
Consultation
3%
Reference
materials
2%
Figure 3 Distribution of programming learning channel (person-time).
227A questionnaire survey on programming large public buildings in China
Detailed results illustrated in Figure 5 indicated that 87% of
respondents supported all four statements as a whole.
Traditionally speaking, the whole project
cycle in the Mainland China can be
roughly phased into planning, design,
construction and occupancy. Do you
think programming should be added as
a connection link between planning
and design?
Strongly agree
Agree
Neutral
Disagree
Strongly
disagree
Do you think the process of programming
is critically important to the whole
project cycle?
Strongly agree
Agree
Neutral
Disagree
Strongly
disagree
Do you think programming is still
undervalued in the Mainland China's
construction industry?
Strongly agree
Agree
Neutral
Disagree
Strongly
disagree
Do you think there should be a separate
fee for the programming service
provided by professionals besides the
routine billing system?
Strongly agree
Agree
Neutral
Disagree
Strongly
disagree
3.4. Design competition and its program
This part includes the following two questions for respon-
dents to rank:
An open design competition is compulsory for a large-
scale public building as stipulated by the relevant law.
According to your own experience, how will the following
factors affect the competition outcome? Please rank
the applicable items in number by order of priority
(e.g., 1-most important, 10-least important).
Project/client prestige
Remuneration/prize money
Jury composition
Length of the tendering time
Design review process
Program quality
Other
A competition program serves as both the primary vehicle
for a design competition and the fundamental criteria for
evaluating competition entries. Have you encountered, or
have been given feedback on, any of the following problems
in a competition program for a large-scale public building
project? Please rank the applicable items in number by order
of priority (e.g., 1-most important, 10-least important).
Lack of site suitability or adequacy
Ignorant of, or in conict with regulatory planning
requirements
Too generic or too trivial in project requirements
Lack of priority, clarity or consistency in the occu-
pancy requirements
0
20
40
60
Major design
revision
Outstanding
cost overrun
Serious
operational
problem
Serious
cooperation
problem
Serious
construction
delay
Others
Number of votes
Figure 4 Ranking of programming-related consequences.
0
5
10
15
20
25
30
35
40
Number of votes
Added as a link
21 27 7 2 0
Viewed as critical
30 25 2 0 0
Still undervalued
15 34 6 2 0
Billed separately
24 23 7 3 0
Strongly agree Agree Neutral Disagree
Strongly
disagree
Figure 5 Awareness of programming.
Y. Deng, S.W. Poon228
Only a space list, lack of specicity of the client's
idiographic values and objectives
Unachievable budget or inadequate cost estimation
Unachievable project schedule
Insufcient required gross oor area (GFA) resulted
from miscalculation or inconsideration of net-to-gross
area ratios of different building types
Other
For the rst question, accordingly to the number of votes
illustrated in Figure 6, the rst-choice ranking is as follows:
1 Program quality
2 Project/client prestige
3 Jury composition
3 Design review process
4 Remuneration/prize reward
5 Bidding time
For the second question, by order of the rst-choice,
eight most frequent problems are:
1 Too generic or too trivial in project requirements.
2 Lack of priority, clarity or consistency in the occupancy
requirements.
3 Lack of site suitability or adequacy.
4 Ignorant of, or in conict with regulatory planning
requirements.
5 Only a space list, lack of the client's idiographic values
and objectives.
6 Unachievable budget or inadequate cost estimation.
7 Insufcient gross oor area by the client resulted from
miscalculation or inconsideration of net-to-gross area
ratios of different building types.
8 Unachievable project schedule.
3.5. Formation of the program
When asked whether the professionals should provide
assistance to their clients at the programming stage, an
overwhelming majority (91%) responded positively. Among
the three given reasons, 81% respondents agreed that by
doing so, it could realize the objective to better determine
the client's requirements to assure design efciency and
quality; while 53% considered this could build up a long-
term reciprocal relationship with the client and help win
the trust and respect from the client, thus having greater
say in the process of design decision making. With regard
to the issue of programming methods, the ranking of six
given choices by order of popularity is shown in Figure 7.
Study visit was on the top while literature search
ranked at the bottom. About 2% respondents chose their
own ways including external consultations of governmental
or professional agencies, market analysis, multiple-scheme
comparison and selection.
Interestingly, both similar and contradictory results were
recorded in this survey and the Preiser's (1993). In both
cases, literature search was ranked the lowest in actual
usage. The insufcient provisions in research and education
0
2
4
6
8
10
12
14
16
18
Number of votes
Program quality
17 6 9 5 8 6
Project/client prestige
15 5 8 3 9 7 4
Jury composition
12 10 5 16 8 3
Design review process
12 9 9 8 7 7
Remueration/prize reward
4796 9123
Bidding time
31311115 7
1st 2nd 3rd 4th 5th 6th 7th
Figure 6 Ranking of factors affecting the outcome of a design competition.
229A questionnaire survey on programming large public buildings in China
in China partially explained its unpopularity in this survey.
Furthermore, study visit to similar projects ranked the
most popular method in this survey but the least popular in
Preiser's (1993). A possible explanation for this is that, in
China, such visits are normally arranged by the clients and
their designers together after the awarding of design
contracts. These eld trips can provide good opportunities
for the clients to get a feel of those built products of similar
nature by seeing, walking around and listening to the
opinions from the current users and facility managers or
even the original consultants and project managers. In turn,
the designers are also able to better understand their
clients' requirements and preference with the presence of
real built products. The mutually benecial nature of this
method may also help strengthen the client-designer rela-
tionship at the early stages.
3.6. Programming cases
To identify pressing challenges faced by the current prac-
tices, the questions in the last part of the survey were
designed to draw out information on LPBs with respondents'
own inputs. The 90 projects provided by respondents were
mainly developed between 2000 and 2009. They were
located in 25 mega- and medium-cities, among which 65%
came from four municipalitiesBeijing, Tianjin, Shanghai
and Chongqing. Many projects were high-prole on local,
national or international scales. About one third of the 90
projects were led by various events including the Beijing
2008 Olympics and the Shanghai 2010 Expo. New construc-
tion, conversion and extension accounted for 79%, 12% and
9% respectively. Those with a total oor area of 50,000 m
2
or above accounted for 74%. Sixteen types of LPBs were
recorded, among which 56% were mixed-use, ranging from
two to four combinations of the basic types in the ofcial
denition of LPBs. Among the 90 projects, government and
corporation clients accounted for 97% in the 90 projects.
Half of the LPBs were developed by rst-time clients, while
47% were either developed by either experienced or reg-
ular/repeated clients (Figure 8). With regard to organiza-
tional structure, 81% clients were single-headed and 19%
multiple-headed. Eight-eight projects (98%) were procured
through design competitions, among which 64% were invited
competitions. International and domestic competitions
almost equaled each other in the 88 cases.
In terms of the billing issue of programming, about 30% of
the 90 programming services were billed, either as part of
the design service or as a separate consulting service. This
was in sharp contrast with the result that 82% respondents
supported the institutionalization of billing the program-
ming service separately. The division indicated that pro-
gramming was still undervalued by the market. In terms of
the composition of the programming team, Figure 9 reects
the ranking of its members by frequency of presence.
Results show that Client representative (78%) came in
the rst place, while Architect (76%) scored much higher
than other professionals such as urban planner, Building
economist and Engineer. Worth noting is that User repre-
sentative ranked fairly low at a 14% presence rate.
4. Discussions and conclusions
This explorative questionnaire survey revealed some sig-
nicant gaps between the best and real practices in
programming LPBs. The results are summarized in Table 5.
Furthermore, the following three ndings also deserve due
attention from the industry as well as its regulators.
(1) Fee issue. Seventy percent of programming services were
not paid in the 90 LPBs under survey; suggesting much
fewer clients were willing to pay the bill, no matter how
insignicant the amount can be. This reality check posed an
0
20
40
60
Study visit to
similar
projects
Client
interview
Data
analysis
Site Survey User survey
Literature
search
Others
Number of votes
Figure 7 Frequency of programming methods in use.
First-time
50%
Experienced
16%
Regular or repeated
+Experienced
1%
Unidentified
1%
First-time+Experienced
1%
Regular or repeated
31%
Figure 8 Distribution of the 90 surveyed LPBs by nature of clients.
Y. Deng, S.W. Poon230
interesting contrast to another nding that most respon-
dents acknowledged the signicanceofprogramming.
(2) User participation. The result showed that user repre-
sentatives were much less involved in the programming
process than eight out of 14 identied types of partici-
pants. Coupled with the lack of post-occupation evalua-
tion mechanism, this might partially explain why a
signicant portion of LPBs, according to the MoHURD's
report (2008), did not function well beyond only a few
years of operations.
(3) Demand-supply mismatch. The survey also revealed a
shortage of well-trained professionals to provide quality
programming services. Although perceived as a growth
area by most respondents, conventional wisdom still
holds that it would not necessarily attract monetary
rewards
in practice. A fundamental reason was that that there
appeared no real incentive to encourage the profes-
sionals to enhance their performances given the current
non-protable nature of programming services.
Despite the imposing of tougher regulations from the
government side since 2007, feedback from a predominant
majority of respondents in 2009 suggested that the industry
still reacted with skepticism about the feasibility of the
Table 5 Comparison between the best and real practices.
Issues in the
early stages
The best practice The real practice
Client's program The client shall seek experts' advice, clarify project
requirements, and determine critical technical and
economic parameters.
The top two ranked problems in a competition
program:
Too generic or too trivial in project
requirements.
Lack of priority, clarity or consistency in the
occupancy requirements.
Schematic
design
The schematic design shall conform to approved master
plan, detailed regulatory plan of the specic site, and
urban design of the site.
The 3rd and 4th ranked problems of competition
programs:
Lack of site suitability/adequacy.
Ignorant of, or in conict with regulatory
planning requirements.
Format of
design
competition
Domestic rather than international competitions shall be
the rst choice for clients.
Actual ratio between international and domestic
competitions was 48%: 51%.
For highest prole design competitions,
international competitions have become a
norm.
Review of design
competition
entries
Open and transparent procedures shall be devised for the
process, while the requirements and accountability of
jury shall be claried.
There was a lack of a clearly-dened review
procedure and evaluation criteria in the
competition program.
0
20
40
60
80
Client representative
Architect
Urban planner
Building economist
Project manager
Engineer
External programmer
Design manager
User representative
Landscape architect
Contractor/ Subcontractor
Broker
Leasing consultant
Government officer
Unidentified
Types of participants
Times of presence
Figure 9 Ranking of programming team members by frequency of presence in the 90 surveyed LPBs.
231A questionnaire survey on programming large public buildings in China
advocated best practice. According to the survey's results,
programming services for LPBs were underpaid and under-
valued among the surveyed top-tier industry players. There
appeared virtually no incentive to challenge the conven-
tional wisdom that the designing process, rather than the
programming process, would more easily bring a sense of
achievement and more concrete rewards to both the clients
and professionals. This would certainly discourage the
clients from giving more considerations to the user require-
ments or prevent the professionals from investing more in
providing quality programming services. Although it was not
the intention of this small-scale survey to cover all issues of
programming LPBs in China, an important message conveyed
here is that an effective mechanism for catalyzing a
mentality shift among industry players has to be worked
out apart from a policy shift from the government sector.
Given the multidimensional impacts of programming on
the long-term performances of LPBs and the capacity short-
falls in delivering quality programming services among pro-
fessionals, it becomes imperative to develop a concrete
package of implementation tools to translate the desirable
aims into clearly measurable rules and regulations. In view of
the persisting nature of the problems identied, more
broader-scale work needs to be carried out to help the
government regulators to better understand the real picture
of professional practice and to formulate effective incentives
and action plans to develop the industry's related capacities.
Such research will facilitate the comparison between the
current practices in China and international best practices
and the identication of the most concentrated problem
areas. Based on these accumulative studies, specic bench-
marks and measures in delivering quality programming
services can be set out for trial implementation in major
cities under pilot programs to check and improve feasibility
and efciency by the government regulators. This would
eventually accelerate the desired paradigmatic shift in the
whole industry. By then, professionals and clients will be
more willing to invest time and efforts in better programming
towards more responsible and sustainable LPBs.
Acknowledgements
The authors are deeply grateful for the generous support
and invaluable inspiration for this survey from respondents
and referees amid their extremely busy agendas.
References
American Institute of Architects.1988. Handbook of architectural
design competitions, 15th ed.. Washington, DC: American
Institute of Architects.
Architecture Weekly, 17 March, 2008. F4, for arts or for luxury?
Architecture Weekly, p. 4. Available from: http://www.arch
weekly.com.
Austen, A.D., Neale, R.H. (Eds.), 1984. International Labour Ofce,
Geneva.
Barrett, P., Baldry, D., 2003. Facilities Management: Towards Best
Practice, 2nd ed. Blackwell Science, Oxford, UK; Malden, MA.
Barrett, P., Stanley, C., 1999. Better Construction Brieng. Black-
well Science, Oxford.
Best, R., Valence, G.D. (Eds.), 1999. John Wiley, London; New York
Arnold.
Betts, M., Robinson, G., Blake, N., Burton, C., & Godden, D., 2011.
Global Construction 2020. Global Construction Perspectives and
Oxford Economics, London.
Blyth, A., Worthington, J., 2010. Managing the Brief for Better
Design, 2nd ed. Routledge, New York, NY.
Bowen, P.A., Pearl, R.G., Nkado, R.N., Edwards, P.J., 1997. The
Effectiveness of the Brieng Process in the Attainment of Client
Objectives for Construction Projects in South Africa. Paper
Presented at the COBRA'97, RICS Research Conference, Univer-
sity of Portsmouth.
Boyd, D., Chinyio, E., 2006. Understanding the Construction Client.
Blackwell, Oxford, Malden, MA.
Brown, S.A., 2001. Communication in the Design Process. Spon
Press, London.
Carmichael, D.G., 2006. Project Planning, and Control. Taylor &
Francis, London; New York.
Cherry, E., 1998. Programming for Design: From Theory to Practice.
John Wiley, New York.
Cherry, E., Petronis, J., 29 November, 2005. Architectural Program-
ming. Available from: http://www.wbdg.org/design/dd_arch
programming.php (accessed 20.10.07.).
Cleland, D.I., Ireland, L.R., 2007. Project Management: Strategic
Design and Implementation. McGraw-Hill, New York.
ERN, 2009a. The top 500 US-based design rms for 2008. Available
from McGraw-Hill Companies, Inc. http://enr.construction.
com (accessed 07.06.09.).
ERN, 2009b. The Top 500 US-based Design Firms for 2008. Available
from McGraw-Hill Companies, Inc. http://enr.construction.
com (accessed 07.06.09.).
Fink, A. (Ed.), How to Sample in Surveys, vol. 6. Thousand Oaks,
Calif.: Sage Publications.
Groves, R.M. (Ed.), Wiley, New York.
Hershberger, R., 1999. Architectural Programming and Predesign
Manager. McGraw-Hill, New York.
Kamara, J.M., Anumba, C.J., 2001. A Critical Appraisal of the
Brieng Process in Construction. Journal of Construction
Research 2 (1), 1324.
Kelly, J., Hunter, K., Shen, G., Yu, A., 2005. Brieng from
a facilities management perspective. Facilities 23 (7/8),
356367.
Kumlin, R.R., 1995. Architectural Programming: Creative Techni-
ques for Design Professionals. McGraw-Hill, New York .
Ministry of Construction of PRC, National Development and Reform
Commission of PRC, Ministry of Finance of PRC, Ministry of
Supervision of PRC, National Audit Ofce of PRC, 2007. Several
Opinions on Enhancing the Administration of Large-Scale Public
Building Project Construction. Ministry of Construction of the
People's Republic of China. Available from: http://www.gov.cn/
gzdt/2007-01/11/content_492868.htm.
Ministry of Housing and Urban-Rural Development of PRC, 2008.
Administrative Measures of Architectural Schematic Design
Tendering for Building Projects, Beijing, p. 63. Available from:
http://www.mohurd.gov.cn/zcfg/jswj/jzsc/200804/
t20080402_158921.htm.
Nasar, J.L., 1999. Design by Competition: Making Design Competi-
tion Work. Cambridge University Press, Cambridge; New York.
Peña, W.M., Parshall, S., 2001. Problem Seeking: an Architectural
Programming Primer, 4th ed. Wiley, New York.
Peña, W.M., Good, L.V., 1967. Architectural programming: impor-
tant steps before design can begin. Junior College Journal: The
Magazine for Junior College Education, American Association of
Junior Colleges, 3437.
Preiser, W.F.E. (Ed.), Van Nostrand Reinhold, New York.
Qiu, B.-X., 2010. Outlook of China's six elds with the biggest
potential for energy-conservation. Paper Presented at the the
Sixth International Conference on Green Building and Building
Energy-Conservation, Beijing http://www.cin.gov.cn/ldjh/
jsbd/201004/t20100408200306.htm.
Y. Deng, S.W. Poon232
RAIA, 2003. Guidelines for Architectural Design Competitions. Available
from: http://www.architecture.com.au/ (accessed 19.11.10.).
Ryd, N., 2004. The design brief as carrier of client information
during the construction process. Design Studies 25 (3), 231249
http://dx.doi.org/10.1016/j.destud.2003.10.003.
Shen, G.Q.P., Chung, J.K.H., 2006. A critical investigation of the
brieng process in Hong Kong's construction industry. Facilities
24 (13/14), 510522.
Smith, J., Love, P.E.D., Wyatt, R., 2001. To build or not to build?
Assessing the strategic needs of construction industry clients and
their stakeholders. Structural Survey 19 (2), 121132.
Smith, N.J. (Ed.), Thomas Telford, London.
Vanston, J.H., 2003. Better Forecasts, Better Plans, Better Results.
Research-Technology Management, 4758.
Zhuang, W.M., 2000. Guide to Architectural Programming, 1st ed.
Water Power Press, Beijing, China.
233A questionnaire survey on programming large public buildings in China
... In other word, architectural programming means the inquiry, observation, ques- (Ma, 2015). That is to say, architectural programming is the process of describing the real condition, gathering the information, client's requirements, uncover the design problem, analysis, synthesis the relevant data of project which clarifies the objectives, to facilitate the design decision making (Goldman & Peatross, 1992;Palmer 1981;Preiser, 1993;Faatz, 2009;Deng & Poon, 2013;Sanoff, 1992;Van der Voordt & Van Wegen, 2005;Hussanian & Juaim, 2013). The architectural programming phase presented in various methodologies (White, 1972;Kumlin, 1995;Pena & Parshall, 2001;Li & Xu, 2011;Neiler, 2015). ...
... Architectural programming goal is aimed directly at design; to provide accurate and reliable data building vocabulary can be directly used for the design (Kumlin, 1995;Cherry & Petronis, 2009, cited by Hussanian & Juaim, 2013Hershberger, 1999;Pena & Parshall, 2001;Ma, 2015;Deng & Poon, 2013). Indeed, the process of architectural programming works to increase the quality of the buildings and development as well as a proper design. ...
... In other words, urban programming means the inquiry, observation, questionnaire, investigation, interview, discussions (Ma, 2015). That is to say, it is the process of describing the real condition, gathering the information, client's requirements, uncover the design problem, analysis, synthesis of the relevant data of project which clarifies the objectives, to facilitate the design decision making (Deng & Poon, 2013;Van der Voordt & Van Wegen, 2005;Hassanain & Juaim, 2013). ...
Article
Full-text available
La regulación urbana normativa es una regulación técnica e higiénica que se refiere esencialmente a los derechos de construcción en el suelo. Concebida según una visión puramente cuantitativa, constituye una reglamentación rígida que se impone como una restricción carente de sentido. Sus disfunciones y fracasos han provocado su rechazo y la aparición de una nueva tendencia: el proyecto urbano. Este concepto se nutrió de los debates teóricos sobre los centros históricos en Italia en torno a los años sesenta. Siguiendo el ejemplo de las ciudades argelinas, Annaba ha sido testigo de la aparición de varios proyectos emblemáticos en los últimos años. Para saber si el enfoque seguido es el de un proyecto urbano, en este trabajo se ha realizado una comparación de la gestión urbana entre Annaba y tres ciudades europeas. Este estudio permite redefinir las herramientas de planificación urbana existentes para poner en marcha otras más innovadoras y eficaces.
... Fragmented into many specialties, intense competition, tight budget and less time, the industry proved to be a resilient one. Yet, many developers, project managers, structural engineers and architects are having over designed buildings (Deng & Poon, 2013). This may be attributed to the lack of innovation, resistance to new systems and technologies, little research and development, lack of skilled resources and shortage of intelligent systems to support project stakeholders. ...
Thesis
Full-text available
Efforts have been made to minimize the cost of affordable housing through modular construction, prefabrication, economies of scale and low cost materials. However, there is a gap in the literature regarding the integration of the varying sizes of the units with design optimization to mutually benefit developers and potential residents of affordable homes. This research introduces an optimization model to integrate optimization with ranges of units’ dimensions. The model proposed exploits the variations in the reinforced concrete cost versus area through applying several scenarios. Available options are tailored to optimize the reinforced concrete floor cost of housing units through varying the dimensions of the rooms. In addition to this objective, the thesis investigates the sensitivity of selected parameters on the model output. Through these objectives, the model is able to optimize housing units within a specified budget to result in layouts with varying areas where the model would recommend the layout with the least reinforced concrete cost per m2 within the budget range. In addition, it optimizes housing units within a specified area range to result in layouts with varying cost where the model would recommend the layout with the least reinforced concrete cost per m2 in the selected area range. The model has been applied on 2 case studies where it showed promising results. The research was able to optimize the cost for a given area or increase the area for a given cost. For example, it was able to decrease the cost by 15% for the same area. These percentages are based on the selected examples. Different savings may be achieved with other layouts. However, this is dependent largely on the initial design and dimensions of the unit.
Article
Given the exemplary of public buildings, energy efficiency in these buildings is an essential element in the response of societies to the challenges of climate change, economic development, and energy security. Although there is a lot of literature about different policies to promote energy efficiency in buildings and particularly in tertiary buildings, insufficient attention has been given to promote it through the building authorization process. This work attempts to establish a new method for achieving energy efficiency in the public buildings by integrating this aspect into the monitoring and controlling processes that delivers this kind of buildings in Morocco; specifically, the delegated project management, through the analysis of the process, and the identification of priority policies or actions. Through surveys with experts, we proposed to analyse the authorization process, to model it, and to highlight the different policies by which Energy Efficiency can be integrated or improved in this process. Our original contribution is to explore a new method to reach energy efficiency in the public buildings without any additional technical actions, but rather with an optimal approach.
Book
Project management is widely used in the construction industry and is central to planning and controlling time, costs and resources. This book enables readers to perform more effectively, to understand project planning and control procedures and to gain an insight into the associated skills. Numerous case examples from diverse industries and exercises support and illustrate important concepts. The result is a new perspective for project managers: planning can be shown to be a systems synthesis or an inverse problem, which provides a way to reach a satisfactory solution, avoiding the time-consuming or impractical search for the optimal solution.
Article
Data and experience from numerous case studies are reviewed and summarized. The author arrives by evaluation at the conclusion that the effects of imperfections in a road construction and major wearing by extreme traffic volume can be quantified in terms of impact on long-term performance by existing theories. Of great importance for the behavior of a road is Yound's modulus of the subsurface, the loosely layed base course, and the bond quality between bituminous layers.
Article
An important aspect of life cycle management in software development is project planning and control. There are five elements: project planning, project monitoring, reporting, collection of statistics and replanning. The project should be broken down into packages, each of which is given an estimate of man days to complete, and slotted into a network. Progress should be monitored to compare with the schedule, and revisions made as necessary. Automated systems can be helpful.
Article
The pre-design stage of construction projects has become a focal point in design management research in the last decade, as it is primarily the source of problems such as rework, change orders, and contractual claims. In particular, it is widely acknowledged that client briefing is an intractable problem which many projects encounter. Primarily this is because little attention is given to assessing the needs of the client, stakeholders and those of the design team. With this in mind, this paper presents a soft system approach known as strategic needs analysis (SNA) to assist clients, stakeholders and their design teams in determining their strategic needs for a given project. The rationale for using a SNA approach during the early stages of the project development process and in relation to the strategic environment of the client organization is presented and discussed. The SNA process is described and applied to two case study projects. It is concluded that SNA can improve the strategic decision-making process of a project, as clients are able to identify their strategic needs and thus improve the effectiveness of the briefing process.