Stage 1 metro construction for the city of Izmir, which has the third highest population in Turkey, has been successfully completed. It included a 2.75 km tunnel excavated by tunnel-boring machine (TBM) using the earth pressure balance (EPB) method in soft ground conditions with shallow overburden. This paper revisits the surface settlement values predicted by the empirical approach, adds numerical analysis, describes the geotechnical instrumentation for field performance and then compares the observed deformations with empirically and numerically predicted ground deformations. INTRODUCTION With a population of 3.5 million, Izmir is the third biggest metropolis and one of the most historically significant cities in Turkey. The total length of planned rail transport in the Izmir Bay area is 45 km, according to the transportation master plan. The Yapi Merkezi – AdTranz Consortium has successfully completed Stage 1 of metro construction for Izmir Metropolitan under a design-and-build turnkey contract. With a total length of 11.5 km, the alignment's peak capacity will be 45,000 passengers per hour per direction in 2010. Total contract value was US$600m. The project includes 2.75 km of tunnels excavated by tunnel-boring machine (TBM) using the earth pressure balance (EPB) method. Yapi Merkezi subcontracted construction of the TBM tunnels to YAPTAG JV (Yapi Merkezi – Wayss & Freytag AG Joint Venture). Of the 10 stations on the project route, four are underground, and three are connected by TBM twin tunnels. The TBM tunnel alignment is situated in soft ground with shallow overburden, and crosses populated and historic built environment. The bore diameter of the completed TBM tunnels is 6.56 m. This paper compares the tunnelling-induced, observed ground deformations with values predicted by empirical methods and numerical analysis. It also describes the geotechnical instrumentation used for field performance and, finally, compares the observed deformations with empirically and numerically predicted deformations. PROJECT ALIGNMENT AND BUILT-ENVIRONMENT The 11.5-km-long project alignment was divided into its major elements: 1.7 km of mined tunnels, 1.4 km of TBM twin tunnels, 1.1 km of cut-and-cover tunnels, and the remainder was surface works. Konak, Cankaya and Basmane stations were constructed using the cut-and-cover method. Each station is approximately 200 m long, with excavation depths of 17 m, 20 m and 16 m respectively. These underground stations were connected by EPB-type TBM twin tunnels. Four
Figures - uploaded by
Ahmet UnlutepeAuthor contentAll figure content in this area was uploaded by Ahmet Unlutepe
Content may be subject to copyright.