Article

Developing a risk assessment model for PPP projects in China — A fuzzy synthetic evaluation approach

Department of Construction Management, Tsinghua University, Beijing, China
Automation in Construction (Impact Factor: 1.81). 11/2010; 19(7):929-943. DOI: 10.1016/j.autcon.2010.06.006

ABSTRACT

Earlier research works on PPP showed that an objective, reliable, and practical risk assessment model for PPP projects is essential to the successful implementation of PPP projects. However, actual empirical research studies in this research area are rather limited. This paper reports the second stage of a funded research study, which aims to develop a fuzzy synthetic evaluation model for assessing the risk level of a particular critical risk group (CRG) and the overall risk level associated with PPP projects in China. At the first research stage, thirty-four risk factors were identified through a comprehensive literature review and 3 new risk factors were proposed during a two-round Delphi questionnaire survey. The most critical 17 risk factors were selected through the calculation of normalized values. The correlation of these 17 critical risk factors (CRFs) was further analyzed via factor analysis and 6 CRGs were formulated, namely: (1) Macroeconomic Risk; (2) Construction and Operation Risk; (3) Government Maturity Risk; (4) Market Environment Risk; (5) Economic Viability Risk; and (6) Government Intervention. On the basis of the research works conducted at the first research stage, the weightings for each of the 17 critical risk factors (CRFs) and 6 CRGs were determined through the two-round Delphi questionnaire survey. A set of knowledge-based fuzzy inference rules was then established to set up the membership function for the 17 CRFs and 6 CRGs. The empirical research findings showed that the overall risk level of PPP highway projects is between “moderate risk” and “high risk”. Hence it could be construed that investment in PPP highway projects in China may be considered as risky. In fact, the Delphi survey respondents perceived that “Government Intervention” is the most CRG; with “Government Maturity Risk” being the second; “Economic Viability Risk” the third; “Market Environment Risk” the fourth; “Construction and Operation Risk” the fifth; and “Macroeconomic Risk” the last. These findings revealed that government intervention and corruption may be the major hurdles to the success of PPP highway projects in China. These may be caused by inadequate law and supervision system and poor public decision-making process. Although the fuzzy synthetic evaluation model was primarily developed for PPP projects in general, the research method could be replicated in a specific type of PPP project, such as water treatment projects and hospital projects, to produce similar models for inter-type comparisons. By doing so, it provides an opportunity for practitioners to assess the risk level of different types of PPP projects based on objective evidence rather than subjective judgment. The most CRG for different types of PPP projects could be identified and both precautionary and remedial actions could be taken as soon as possible. Such an extension would provide a deeper understanding of managing different types of PPP projects.

  • Source
    • "As a multi-criteria evaluation model, the proposed risk assessment model requires three basic elements (Mu et al., 2014; Xu et al., 2010b): (1) A set of basic criteria/factors C ¼ {c 1 , c 2 , … c m }, where m is the number of criteria/factors; (2) A set of alternatives E ¼ {e1, e2, … en}, where n is the number of alternatives; and (3) An evaluation matrix R ¼ (r ij ) mÂn , where r ij denotes the degree to which the alternative e j satisfies the criterion c i . "
    [Show abstract] [Hide abstract]
    ABSTRACT: In recent years, green building has attracted wide attention from both academia and industry. As green building projects are inevitably plagued with risks, this study attempted to assess the risks in green building projects in Singapore. Categorizing a list of 28 risk factors into 11 groups, the study performed a questionnaire survey and received 31 responses from project managers in Singapore. A risk assessment model was developed using the fuzzy synthetic evaluation approach. Using the proposed model, the likelihood of occurrence, magnitude of impact and risk criticality of each risk factor, group and the overall risk were calculated. “Inaccurate cost estimation” was the top risk factor, and “cost overrun risk” was the most critical risk group. The overall risk criticality was high, implying risk management was still necessary for green construction in Singapore. The proposed risk assessment model is reliable and practical for professionals in the green building industry, and can be applied in risk assessment in other countries. As few studies focused on risks in green projects, this study expands the knowledge and literature.
    Full-text · Article · Dec 2015 · Journal of Cleaner Production
  • Source
    • "Therefore, the data are appropriate to be further analyzed. Normally, an evaluation model is developed from a hierarchical framework (Xu et al. 2010). Therefore, to hierarchize the framework of measurement items of corruption, factor analysis was conducted utilizing SPSS 17.0. "
    [Show abstract] [Hide abstract]
    ABSTRACT: Corruption has been identified as the greatest obstacle to economic and social development. Public construction projects, in particular, face high corruption risk as public construction sector has been consecutively deemed as the most corrupt one. Despite considerable efforts have been undertaken to measure corruption at a nation level, few researchers focus on the measurement of corruption in construction projects. This paper develops a fuzzy measurement model for the potential corruption in public construction projects in China. Through semistructured interviews with 14 experts, and then a questionnaire survey with 188 respondents, 24 measurement items of corruption were identified and further categorized into five constructs. The fuzzy set theory was then adopted to quantify each measurement item, construct, and the overall corruption level. This model can facilitate in evaluating, revealing, and monitoring corruption in public construction projects. Although this paper focuses on measuring corruption in public construction projects in China, similar research methods can be applied in other countries around the world and thus contribute to the global body of knowledge of corruption.
    Full-text · Article · Sep 2015 · Journal of Professional Issues in Engineering Education and Practice
  • Source
    • "Moreover, the validity of the indicators was improved by applying PPP data from Australia (Jin, 2010), Tehran (Heravi and Hajihosseini, 2012), and India (Singh and Kalidindi, 2006), which have extensive PPP experiences. Table 3 lists a summary form of indicators adapted from Bing et al. (2005a), Hwang et al. (2013), Chou et al. (2012), Ke et al. (2010), Chan et al. (2011), Jin (2010), Xu et al. (2010) "
    [Show abstract] [Hide abstract]
    ABSTRACT: Public-private partnerships (PPPs) are an effective and established strategy for procuring infrastructure. Although numerous countries have implemented PPPs for infrastructure development in recent years, not all projects have been successful. Most PPP failures result from inappropriate risk allocation and a lack of information on success factors in specific countries. For this study, we compared the categories of key drivers, critical success factors (CSFs), and preferred risk allocation in PPPs established in Taiwan, Singapore, China, the United Kingdom, and Indonesia. Mean value analysis, confirmatory factor analysis, and dimensional importance were used to analyze and compare these categories. Data on PPPs in Taiwan, Singapore, China, and the United Kingdom were obtained through comprehensive literature reviews. Data for Indonesia were obtained through structured surveys distributed to PPP practitioners and academicians. Considering Indonesia as the baseline, the results revealed that Indonesia and Taiwan exhibit several similar indicators of key drivers. Furthermore, comparisons with several countries revealed that Indonesian CSFs are most similar to those of China. Regarding risk allocation preference, the analytical results indicated that Singapore exhibits the most similarity with Indonesia. This study provides useful information for people seeking to invest in PPP projects, enabling them to enhance their understanding of key drivers, CSFs, and risk allocation in the researched countries. Based on our findings, international investors can apply investment strategies by considering the similarities and differences in each country.
    Full-text · Article · Jul 2015 · International Journal of Project Management
Show more